Upload
dinhnhan
View
220
Download
0
Embed Size (px)
Citation preview
Granite (Building Stone) Quarry of M/s KKJ Group International (India) Pvt. Ltd.,Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam,
Kerala
PRE-FEASIBILITY REPORT
&
ENVIRONMENTAL MANAGEMENT
PLAN
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
CHAPTER 1
1.1 INTRODUCTION
Quarry lease for extraction of Granite as building stone (minor mineral) over an area of
2.07.66 hectares in Block no. 1, Sy. No. 125/2-9,2-1,2-8,2,126/1-1,1-2,1,2-3,2-4,9,4
at Village- Veliyanoor, Taluk- Meenachil, District- Kottayam, Kerala. Has been granted
to M/s KKJ Group International (India) Pvt. Ltd., by department of Mines and Geology
Kerala vide its order no. 412/2010-11/5408/M3/2010 dated 04/10/2010 for a period of
12 years. Consent to operate to produce 1400 tons of Granite per day from the area
has been granted by Pollution control board of Kerala vide its consent no.
PCB/KTM/ICO/R/1039/2012 dated 27/07/2012 with validity upto 31/12/2014. As per
notification of MoEF Environmental clearance is mandatory to operate the quarry,
therefore for obtaining clearance from MoEF the proposal is prepared and submitted to
SEIAA/SEAC, Kerala for consideration and approval please.
M/s KKJ Group International (India) Pvt. Ltd., a company registered under the
company Act 1956 having its registered office at “Ashiana Towers, KKJ Town Ship,
Perumpadavom P.O, Elanji, Ernakulum (Dist), Kerala, India-686665.
The entire land of proposed quarry site is private/patta land owned by the proponent
(copy of the sale deed is enclosed as annexure-1). The estimated project cost is 3.0
crore, life of the mine with proposed rate of production of 70000 tons per year will be 8
years. The applicant has obtained quarry lease for said period from the department of
Mines and Geology, government of Kerala. Consent to operate from Pollution control
Board
1.2 PROJECT DESCRIPTION:
Project proponent: M/s KKJ Group International (India) Pvt. Ltd.,
Mailing address: Ashiana Towers,
KKJ Township,
Perumpadavom P.O,
Elanji,
Ernakulum (Dist),
Kerala, India- 686665.
Proposed project: Granite stone quarry
Area : 2.07.66 Ha
Survey nos : 125/2-9, 2-1, 2-8, 2,126/1-
1, 1-2, 1, 2- 3, 2-4, 9, 4
Village : Veliyanoor
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Taluk : Meenachil
District : Kottayam
State : Kerala.
Type of land : Private, waste land
1.3 SALIENT FEATURES OF THE STUDY AREA
Project Location; The proposed area lies between:
Latitude: 09o 50’49.91’’N
09o 50’53.55’’N,
09o 50’58.68’’N,
09o 50’47.88’’N, and
Longitude: 076o37’43.44’’ E
076o37’34.94’’ E
076o37’37.63’’ E
076o37’42.94’’ E
The area falls in toposheet no. 58 C/14 of Survey of India and is approachable from
pala. The nearest town Thodupuza is 9.5 km. Location map is enclosed as plate no.2 in
quarry plan.
Table C - 1: Salient features of the proposed mine
Particulars Details
Quarry permit area Proposed : 2.07.66 ha
Toposheet no 58 C/14
Latitude and longitude.
Latitude: 09o 50’49.91’’N
09o 50’53.55’’N,
09o 50’58.68’’N,
09o 50’47.88’’N, and
Longitude: 076o37’43.44’’ E
076o37’34.94’’ E
076o37’37.63’’ E
076o37’42.94’’ E
The co-ordinates of boundary pillers are as under:
Pillar Coordinate
Easting Northing BP
67084’29.0274” 108092’20.9869” 1
67084’25.1639” 108092’12.7830” 2
67084’09.8585” 108091’99.5935” 3
67084’20.6628” 108091’60.2599” 4
67083’74.8230” 108091’52.8082” 5
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
67083’76.9907” 108091’32.9022” 6
67083’88.8626” 108091’15.7098” 7
67083’78.0927” 108091’00.1785 8
67083’75.9733” 108091’04.0823” 9
67083’40.1112” 108090’84.6049” 10
67083’47.8139” 108090’62.9330” 11
67083’82.9444” 108090’56.0421” 12
67083’93.2850” 108090’72.1961” 13
67084’02.9489” 108090’77.1645” 14
67084’14.4791” 108090’72.1824” 15
67084’28.9607” 108090’18.6356” 16
67084’36.1934” 108090’23.4706” 17
67084’76.1869” 108089’29.6067” 18
67084’98.7174” 108089’65.8788” 19
67085’28.0017” 108089’26.7465” 20
67085’61.3530” 108089’01.6212” 21
67085’92.3915” 108088’90.0223” 22
67086’07.4827” 108089’52.4234” 23
67085’12.6840” 108089’87.5715” 24
67085’09.4901” 108089’82.6108” 25
67084’59.6374” 108090’39.1429” 26
67084’74.2981” 108091’36.1397” 26
67084’62.6272” 108090’95.5065” 27
67084’53.6882” 108091’54.9054” 29
67084’40.8909” 108091’70.8814” 30
67084’30.7451” 108091’94.7224” 31
Elevation
Maximum 85 RL
Minimum 15 RL
Ground level 10 RL
Maximum Production 70,000 TPA
Ultimate pit depth 0 RL
Life of mine 8 years
Man power 20 persons
Estimated project cost. 3.0 crores
Land use (exsisting)
Particulars Area in Ha
Quarry pit
Magazine
Road 0.00
Undisturbed area 2.0766
Total 2.0766
Width of access road to
the quarry. 7.0 m
Nearest habitation/town. Veliyanoor Village -2.6Km - WSW
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Kuninji Village-2.2 km-ESE
Nearest highway. State Highway (40) - 1Km- WSW
National Highway (49) - 20 Km- N
Nearest airport. Kochi-41 km-NNW
Nearest railway line. Piravam Road is the nearest Railway Station at 31 kms.
Nearest dispensary, and
hospital Deva matha Hospital- 4.2 km- WNW
Water source Ground & Surface water
Education facility
Marygiri CMI CBSE Public School- 4.1 Km - WNW
Santhigiri Collge - 2.7 Km – NE
College of Engineering &Technology - 3.0 km - W
Fire station Thodupuzha
Ambulance Thodupuzha
Police station Thodupuzha
Church/temple/mosque St. Antony church- 2.34 km- E
Electrical installation like
transformer/HT line. Power Line near Mine lease area
Nearest water bodies Mining lease area
Seismic zone Zone No.-III
Nearest Forest boundary None within 10 km radius from Mine Lease Area
Nearest Archeological
features None within 10 km radius from Mine Lease Area
Nearest Ecological
sensitive zones None within 10 km radius from Mine Lease Area
1.4 NEED OF THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY
Raw material which is hard and compact in nature, having high compresive strength,
and occurs in planty is the basic requirment of construction industries. The area in
hundreds of square kilometers in and around Idukki is covered with Granite. Fine and
meddium grained granite free from hair crecks/joints and good looking in colour is
generally used as dimension stone for making tiles, ornamental and monumental work.
Off coloured and jointed granite is used as road metal, and building materials.there is
no other rock which can be used as building material and road metals in Idukki and
nearby districts. The project will help in development of infrastructure of the nearby
area by meeting the requirement of raw material for the road and construction
projects. Employment will be generated for the local workers, and government will get
royalty on the mined out material.
1.4.1 End use (Domestic or export market)
The grainte of this area is off coloured, medium to coarse grained, it can not be used as
dimension stone, it can only be used to make rubbles and agreegate which can be
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
used in road making and for construction work therefore entire material produced from
the said area will be used in domestic market only.
1.5 PHYSIOGRAPHY AND DRAINAGE
Topographically the proposed area is hilly terrain, having heighest elevation of 85 RL
and the lowest elevation is of 15 RL.The drainage of the area is controlled by seasonal
channels along the hill slope towards North. The contour map/ Surface map of the
proposed area is enclosed as plate no.3 in quarry plan.
1.6 LEASE AREA
The entire proposed lease area is private land owned by the applicant.
The surface plan of the proposed quarry lease area showing all the features on the
ground is enclosed as plate no 3 of quarry plan.
1.7 GEOLOGY
1.7.1 Regional
Crystalline rock of Precambrian period sedimentry rocks of Tertiary and quaternary
period are noticed.The sedimentry formation occurs in the coastal plains.
1.7.2 Local
Granite rock is exposed in the entire proposed area, no other rock unit is seen. The
granite is compact, mediam grained composed of quartz,hornbland and
feldspar.Granite is exposed at places, whereas in Western part of the area it is covered
with soil varies in thickness from 1.0 to 2 meters and the soil is brownish in colour it is
fine to medium grained.
1.8 RESERVES
The entire lease area is covered with crystalline reock granite, the area is hilly tarrain
therefore reserve have been estimated by cross sectional area method.
V=A x D
Tonnage=V x 2.6
2.6 is bulk density of the granite.
1.8.1 GEOLOGICAL RESERVES
Proved reserves : 1763521 tones
Probable reserve : 1061066 tones
Total Geological reserve : 2824587 tones
Less reserve trapped
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
i) in 7.5m Barreir zone : 718819 tones
ii) to maintain the pit
slope and below the UPD. : 1567717 tonnes
Mineable reserve : 538051 tones
1.9 MINING
The area is hilly terrain; Granite occurs in the entire proposed area, it is working
quarry. Granite being low cost rock opencast mechanized mining is the best choice,
therefore it is being worked by open cast mining method and the same procedure will
be continued, proper benches of 5M height and width will be formed to maintain the pit
slope of 450.
The details have been furnished in Quarry plan.
The blasted material after sizing will be transported by road for the end use by
contractors.
1.9.1 Drilling and blasting
Granite is compact rock, at places it is fractured also. Production from the fractured
zone will be obtained with the help of excavator, whereas from compact zone the
production will be obtained by drilling and blasting.
Drilling will be done by jack hammer with the help of air compressor.
About 30 to 50 hole will be blasted in one blast.
Number of blasts per day will be 2 blasts of 40 holes each.
Requirement of explosives is 735 kg per month.
Details of excavation during ensuing plan period and generation of waste is tabulated
as under
Table C - 2: Details of excavation during ensuing plan period
S.
No. Year
ROM
(tones)
Graded ore 95%
(tones) Waste (tones)
1 First Year 53176 50517.2 2658.8
2 Second Year 70415 66894.25 3520.75
3 Third Year 71860 68267 3593
4 Fourth Year 69258 65795.1 3462.9
5 Fifth Year 69623 66141.85 3481.15
Total 334332 317615.4 16716.6
1.9.2 Extent of Mechanization
Following machineries are proposed to be deployed at the quarry site.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Table C - 3: Details of machineries used for excavation
S.
No. Machine type Capacity Requirement
1 Excavator 0.9M3 1
2 JCB 1
3 Rock breaker 1
4 Compressor 100cfm. 3
5 Jack hammer 2.5 m length 2
6 Tippers 10 tones 4
1.9.3 Employment potential
Details of man power required for proposed mining project as tabulated below to
achieve maximum production capacity of 70,000 TPA
Table C - 4: Details of Manpower Required
S. No. Designation No. of persons
1. Mine manager/ permit manager 1
2. Mining engineer(part time) 1
3. Mine Mate 1
4. Operators 6
5. Clerk 1
6. Helper and workers 10
Total 20
1.9.4 Generation of top soil and waste and its disposal
17125 M3 of Top soil and 26902 tons of waste will be generated during life of the mine,
it will be kept in the area earmarked for the same. The waste will be used to backfill
the part of quarry pit, and soil will be spread over the back filled area; the reclaimed
area will be used for Rubber plantation.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
CHAPTER-2
DESCRIPTION OF ENVIRONMENT
2.1 BASELINE ENVIRONMENT
Baseline environmental status in and around the proposed project depicts the existing
environmental conditions of air, water, noise, biological and socio-economic
environment.
Field monitoring studies was carried out by M/s. CEG Test House & Research Centre
Pvt. Ltd. having its head office at B-11(G) CEG Tower, Malviya Industrial Area, Jaipur,
CEGTH & RC is well equipped NABL accredited and BIS recognized laboratory,
Registration No. NABL-T-1601, to evaluate the baseline status of the project site.
2.2 CLIMATIC CONDITIONS
2.2.1 Temperature
The temperature normally ranges from 280C to 32oC on the plains but drops to about
20oC in highlands. The highlands of Kerala, enjoys a cool and invigorating climate the
year round. Owing to its diversity in geographical features, the climatic conditions in
Kerala is diverse.
2.2.2 Relative Humidity
In general the relative humidity in the area is observed to be high due to its proximity
to the sea. During the summer it varies from 35% to 95%, during monsoon it varies
from 20% to 90% and during the winter it varies from 80% to 90%.
2.2.3 Rainfall
There are two monsoons in Kerala; they are the south-west monsoon and the north-
east monsoon. The south-west monsoon starts in June and ends in September and
northeast monsoon commence from October and ends in November. The average
rainfall is around 3000 mm per year.
2.3 AMBIENT AIR QUALITY MONITORING
The prime objective of baseline air quality monitoring is to assess existing air quality of
the area. This will also be useful in assessing the conformity to standards of the
ambient air quality as per standards during the mine operations. The Monitoring studies
for one day (24 hourly) were carried out to evaluate the baseline status of the project
site.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
2.3.1 Methodology adopted for Air Quality Monitoring
The baseline status of the air quality in the study area has been assessed through a
scientifically designed ambient air quality monitoring network. The design of monitoring
network in the air quality surveillance program has been based on the following
considerations:
Meteorological conditions on synoptic scale;
Topography of the study area;
Representatives of regional background air quality for obtaining baseline status;
and
Representatives of likely impact areas.
Ambient Air Quality Monitoring (AAQM) stations were set up at two locations with due
consideration to the above mentioned points.
Table C - 5: Ambient Air Quality Monitoring Locations
Station Codes Name of the
Location Distance from Mine
[Km] Direction
AAQ-1 Mine lease Area - -
AAQ-2 Veliyanoor Village 2.6 Km WSW
2.3.2 Instruments used for Sampling
Respirable dust samplers (RDS) with gaseous attachments were used for monitoring of
PM10, SO2 and NOx, and fine particulate matter was used for monitoring of PM2.5.
2.3.3 Sampling and Analytical Techniques
Sampling and analysis was done as per guidelines issued by CPCB/MoEF. The
techniques used for ambient air quality monitoring and technical protocols are given in
Table C - 6.
Table C - 6: Techniques used for Ambient Air Quality Monitoring
S. No. Parameter Technique/Method Technical Protocol
1. Respirable Particulate
Matter (PM 10)
Respirable Dust Sampler
(Gravimetric method) IS-5182 (Part-23)
2. Respirable Particulate
Matter (PM 2.5)
Fine Particulate Sampler
(Gravimetric method) CPCB Method
3. Sulphur Dioxide (SO2) Modified West and Gaeke IS-5182 (Part-2)
4. Oxides of Nitrogen
(NOx) Jacob & Hochheiser IS-5182 (Part-6)
2.3.4 Presentation of Results
The analysis results are presented in Table C – 7. These are compared with the
standards prescribed by Central Pollution Control Board (CPCB).
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Table C - 7: Ambient Air quality Monitoring Results
Name of
Location
Parameters
PM10
(µg/m3)
PM2.5
(µg/m3)
SO2
(µg/m3)
NOx
(µg/m3)
CO
(mg /m3 )
Mine lease Area
58.2 19.6 5.7 7.8 BDL (<0.5)
Veliyanoor
Village 55.3 21.2 6.1 9.6 BDL (<0.5)
Standards 100 60 80 80 4
BDL- Below Detection Limit
2.3.5 Conclusion
The ambient air quality monitoring result obtained are well within the Prescribe
standards (NAAQS). The detail analysis reports are enclosed as Annexure 15.
2.4 WATER ENVIRONMENT
2.4.0 Hydrology
The study area is situated in hilly terrain, in general water level is sallow during both
the monsoon period in valley and topographically low land area during the course of
mining activities we are not going the below the general ground level. Therefore the
Hydrology of the area is not going too affected in to mining operation.
2.4.1 Water Quality Monitoring
Water quality Monitoring of ground water resources within 5 km radius of the study area
have been studied for assessing the water environment to evaluate anticipated impacts
of the proposed mine. It also assists to identify critical issues in a view to suggest
appropriate mitigation measures for implementation.
2.4.2 Methodology
Reconnaissance survey was undertaken and monitoring locations were finalized based on
the following aspects:
Drainage pattern of the regional area;
Location of residential areas representing different activities/likely impact areas and
Areas representing the existing baseline environment.
Water samples in the study area were collected from ground water sources and
analyzed for physical and chemical characteristics as per the procedures specified in
'Standard Methods for the Examination of Water and wastewater' published by American
Public Health Association (APHA) & BIS.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
2.4.3 Water Sampling Locations
Two ground water samples were collected as grab samples and analyzed for various
parameters. The details of the sampling locations are given in the Table C - 8.
Table C - 8: Water Sampling Location
Location
Code Location
Distance from the
project boundary
(km)
Direction
GW-1 Near Mine lease
Area --- --
GW-2 Veliyanoor Village 2.6 Km WSW
2.4.4 Presentation of Results
The results of water samples are presented in Table C - 9. These are compared with
the standards for drinking water as per IS: 10500:2012
Table C - 9: Results of Water Quality Analysis
S.
No Parameter Unit
Test Results
Limits as per IS-
10500-2012
Desirab
le Limit
Permissibl
e Limit Near Lease
Area
Mannakad
Village
1. pH (at 25 °C) - 7.3 6.8 6.5 – 8.5 No
relaxation
2. Colour Hazen < 1 < 1 5 15
3. Odour - Agreeable Agreeable Agreeable
4. Taste - Agreeable Agreeable Agreeable
5. Turbidity NTU <1 <1 1 5
6. Total Dissolved
Solids mg/l 156 148 500 2000
7. Alkalinity as
CaCO3 mg/l 26.4 15.1 200 600
8. Total Hardness
(as CaCO3) mg/l 48.4 36.5 200 600
9. Chlorides (as Cl) mg/l 17.6 14.8 250 1000
10. Sulphate (as SO4) mg/l 14.8 9.7 200 400
11. Nitrate (as NO3) mg/l 2.6 0.9 45 No
relaxation
12. Fluorides (as F) mg/l < 0.2 < 0.2 1 1.5
13. Calcium (as Ca) mg/l 18.6 14.3 75 200
14. Magnesium (as
Mg) mg/l 7.4 5.6 30 100
15. Iron (as Fe) mg/l 0.21 0.16 0.3 No
relaxation
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
16. Boron (as B) mg/l BDL
(<0.005)
BDL
(<0.005) 0.5 1
17. Chromium (as Cr) mg/l BDL
(<0.005)
BDL
(<0.005) 0.05
No
relaxation
18. Zinc (as Zn) mg/l BDL
(<0.005)
BDL(<0.005
) 5 15
19. Aluminium (as Al) mg/l BDL(<0.01) BDL(<0.01) 0.03 0.2
20. Copper (as Cu) mg/l BDL
(<0.005)
BDL
(<0.005) 0.05 1.5
21. Manganese (as
Mn) mg/l
BDL
(<0.005)
BDL
(<0.005) 0.1 0.3
22. Arsenic ( as As) mg/l BDL
(<0.005)
BDL
(<0.005) 0.01 0.05
23. Lead (as Pb) mg/l BDL
(<0.005)
BDL
(<0.005) 0.01
No
relaxation
24. Selenium (as Se) mg/l BDL
(<0.005)
BDL
(<0.005) 0.01
No
relaxation
25. Cadmium (as Cd) mg/l BDL
(<0.001)
BDL
(<0.001) 0.003
No
relaxation
26. Mercury (as Hg) mg/l BDL
(<0.001)
BDL
(<0.001) 0.001
No
relaxation
27. Mineral oil mg/l BDL(<0.05) BDL(<0.05) 0.5 No
relaxation
28. Total Coliform Absent/
100ml Absent Absent
Absent/
100ml
Absent/
100ml
29. E. Coli Absent/
100ml Absent Absent
Absent/
100ml
Absent/
100ml
BDL - Below Detection Limit
2.4.5 Conclusion
The Water quality monitoring at two locations shows that all the parameters were found
within permissible limit.
The analysis reports of the water samples are enclosed as Annexure 15.
2.5 NOISE ENVIRONMENT
The main objective of noise monitoring in the study area is to establish the baseline
noise levels and assess the impact of the total noise expected to be generated during
the project operations around the project site.
2.5.1 Identification of Sampling Locations
Noise at different noise generating sources has been identified based on the residential,
industrial and commercial activities in the area.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
The noise monitoring has been conducted for determination of noise levels at two
locations. The noise levels at each location were recorded for 24-hrs. The environment
setting of each noise monitoring location is given in Table C – 10
Table C – 10: Details of Noise Monitoring Locations
S.NO Station
Code
Name of the
Location
Distance from Mine
[Km] Direction
1 NQ-1 Mine lease Area … …
2 NQ-2 Veliyanoor Village 2.6 Km WSW
2.5.2 Method of Monitoring
Sound Pressure Levels (SPL) measurements were recorded at two locations. The
readings were taken for one minute interval by used sound level meter with data logger
for 24-hrs. The day noise levels have been monitored during 6 am to 10 pm and night
noise levels during 10 pm to 6 am.
2.5.3 Presentation of Results
The statistical analysis is done for measured noise levels at two locations in the study
area. The parameters Lday and Lnight were computed and results are given in Table C -11
Table C - 11: Results of Ambient Noise Monitoring
S.
No. Name of the Location
Noise Level dB (A)
Day
Equivalent
(Lday)
Night
Equivalent
(Lnight)
Ldn
1 Near Boundary of Mine
Lease Area 43.3 34.5 43.7
2 Veliyanoor Village 46.3 32.8 45.4
2.5.4 Observations of Results
The daytime (Lday) noise levels at all the locations are observed to be in the range of 43.3
dB (A) to 46.3 dB (A) and night time (Lnight) noise levels are observed to be in the range
of 32.8 dB (A) to 34.5 dB (A). It is observed that the noise levels are well within the
limits accordance to the prescribed limits.
The Noise monitoring reports are enclosed as Annexure 15.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
2.6 ECOLOGICAL STUDIES
2.6.1 Flora
Study of biological environment is one of the important needs for conservation of
Environmental quality. We were carried out a detailed enumeration of species.
Occurrences of flora at various locations were observed and typical plant species were
collected. The visual observations of plants were recorded with a view to obtaining
some idea about the relative density of certain species and their predominance.
Primary survey for flora and fauna studies have been conducted in and around
proposed mine.
2.6.2 Objectives of Ecological Studies
The present study was undertaken with the following objectives:
To assess the nature and distribution of vegetation in and around the project site;
To assess the distribution of animal life spectra;
To understand the productivity of the water bodies;
To assess the biodiversity and to understand the resource potential; and
To ascertain migratory routes of fauna and possibility of breeding grounds.
2.6.3 Methodology Adopted for the Survey
To achieve the above objectives a detailed study of the area was undertaken in 5 km
radius around proposed mine area. The different methods adopted were as follows:
Generation of primary data by undertaking systematic ecological studies in the
area;
Discussion with local people so as to elicit information about local plants, animals
and their uses; and
Gathering data for ethno biology.
The present report gives the review of published secondary data and the results of field
sampling conducted.
The primary data was generated through;
Preparing a general checklist of all plants encountered in the study area. This would
indicate the diversity for wild and cultivated plants.
Determining the bird population of migratory and local birds by taking 10 random
readings at different locations, and
Observing mammals, amphibians and reptiles, noting their calls, droppings,
burrows, pugmarks and other signs.
2.6.4 Flora observed in study area
The topography, climate and nature of soil is mainly responsible for the growth of flora,
which are important for making the environment of the area suitable for the survival of
living beings.
The most prominent varieties of flora found in the area.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Table C - 12: List of trees observed in the study area
S.No. Botanical Name Local Name Family
1 Hevea Brasiliensis Rubber Euphorbiaceae
2 Ailanthus excelsa Pongiliam Simaroubaceae
3 Tectona grandis Teak Verbinaceae
4 Artocarpus heterophyllus Jack Fruite Moraceae
5 Magnifera indica Mango Anacardiaceae
6 Arecacatechu Arecanut Arecaceae
7 Cocus nucifera Coconut Arecaceae
Table C - 13: List of Shrubs and Herbs observed in the study area
S.No. Botanical Name Local Name Family
1 Lantana camera Kongini verbenaceae
2 Clerodendrum infortunatum Paragu verbenaceae
3 Chromoleena odorata Assam pacha Asteraceae
4 Alternanthera sessilis Ponamgani Amaranthaceae
5 Spermacoce latifolia Pachapall Rublaceae
Table C - 14: List of Climbers observed in the Study Area
S. No. Botanical Name Local Name Family
1 Mikania micranth vayara Asteraceae
Table C - 15: List of Grass observed in the Study Area
S.No. Botanical Name Local Name Family
1 Cynodon dectylon Doobhi Grass Poaceae
2.6.5 Conclusion from the floral Study:
There are no flora species existing at site which are in the red listed category, endemic
or scheduled species category.
2.6.6 Fauna observed in the Study Area
The most common species of animals like Cow, Dog, buffalo etc. observed in the study
area. There is no schedule I species of animals observed within the study area.
2.7 SOCIO-ECONOMIC ENVIRONMENT
To study the socio-economic aspects of people in the study area around proposed
mine, the required data has been collected from various secondary sources and
supplemented by the primary data generated through the process of a limited door to
door socio-economic survey.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
2.7.1 Methodology Adopted for the Study
Review of secondary data, such as District Census Statistical Handbooks-2011 and the
records of National Informatics Center data, for the parameters of demography,
occupational structure of people within the general study area of 5 km radius around the
project site.
2.7.2 Review of Demographic and Socio-Economic Profile – 2011
The sociological aspects of this study include human settlements, demography, social
such as Scheduled castes and Scheduled Tribes and literacy levels besides
infrastructure facilities available in the study area.
The Demographic details of Meenachil taluk in which the proposed mine site located are
tabulated below.
Table C - 16: Demography details of study area (Thodupuzha Taluk)
Total Number of House Holds : 72996
S. No. Population Persons Males Females
1 Total 406,471 201,743 204,728
2 In the age group 0-6 years 36,489 18,627 17,862
3 Scheduled Castes (SC) 19,749 9,783 9,966
4 Scheduled Tribes (ST) 9,213 4,668 4,545
5 Literates 360,100 179,328 180,772
6 Illiterate 46,371 22,415 23,956
7 Total Worker 161,032 114,825 46,207
8 Main Worker 132,173 100,805 31,368
9 Main Worker - Cultivator 14,530 13,076 1,454
10 Main Worker - Agricultural Labourers 9,427 7,435 1,992
11 Main Worker - Household Industries 2,205 1,605 600
12 Main Worker - Other 106,011 78,689 27,322
13 Marginal Worker 28,859 14,020 14,839
14 Marginal Worker - Cultivator 2,337 1,460 877
15 Marginal Worker - Agriculture Labourers 3,832 2,285 1,547
16 Marginal Worker - Household Industries 1,085 359 726
17 Marginal Workers - Other 21,605 9,916 11,689
18 Non Worker 245,439 86,918 158,521
Source: Census data-2011, http://www.censusindia.gov.in/
The mining activity in the lease area will thus give direct employment to about 20
persons engaged in mining/extraction of Granite (Building stone); loading of material
into tractor trolleys and trucks. Thus, for transportation of material about two drivers
and equal number of helpers shall be engaged. Moreover, the mine will generate
direct/indirect employment for more than 100 workers.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
2.7.3 Occupational structure in the Study area
In the initial stages, the shift of resources occurs away from the, primary sector
(agriculture, forestry, fishery, dairy, poultry, mining etc.) to the manufacturing sector or
the secondary sector. These two sectors are the commodity producing sectors and their
activities are required to be supported by the appropriate and adequate development of
the service sector, or the tertiary sector.
Occupational structure of the workforce will be indicative of the economic activity. Any
change in occupational structure would be indicative of the changing nature economically.
The occupational structure has been worked out for categories of occupational available in
the project site, which includes cultivators, agricultural labor, and household industry
workers etc.
2.7.4 Health Status
Health of the people is not only a desirable goal, but is also essential investment in human
resources. As per the National Health Policy (1983) primary health center has been
accepted as a main instrument for achieving this goal.
For the development and strengthening of rural health infrastructure through a three tier
system, such as sub centers, primary health centers (PHC) and community health centers
have been established.
2.7.5 Socio Economic Survey
Following salient observations were recorded.
Educational facilities are available for all the villages in the form of primary and
middle schools. In some of the villages it is extended up to high schools. For
higher studies students have to avail this facility from the nearest town.
Primary health centers and sub-centers are available to the rural people. During
emergencies people have to move to the nearest town places.
Communication facilities are available in the villages.
Most of the villages having good infrastructural facilities like primary schools,
transportation, post office, telecommunication, power, banking facilities etc.
2.7.6 Awareness and opinion about the project
The respondents from almost of all the villages are aware about this project
activity.
The respondents have mixed view about the project. Most of the respondents have
opinion that due to proposed project activity, economy of the villages will be
improved.
As regards the respondents from the nearby villages also shown favorable opinion
about activity that it may lead to increase in infrastructural facilities, job
opportunities and business opportunities in the project area.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
2.7.7 Civic Amenities
Infrastructure resources are base of the villages with reference to education, drinking
water resources, post and telegraph, communications and supply. The infrastructure
amenities available in the area denote the economic wellbeing of the region.
Table C – 17: Civic Amenities available in the study area
S. No. Amenities Distance
in Km
Direction w.r.t.
ML Area
1. Marygiri CMI CBSE Public High
School 4.1 WNW
2. Santhigiri College 2.7 NE
3. Deva Matha Hospital 4.2 WNW
4. College of Engg. & Technology 3.0 W
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
CHAPTER 3
ENVIRONMENTAL MANAGEMENT PLAN
3.1 INTRODUCTION
The EMP is required to ensure sustainable development in the study area of 5 Km
radius of the proposed mining site; hence it needs to be an environmental conservation
management plan for the proposed activity.
The EMP aims at controlling pollution at the source level to the possible extent with the
available and affordable technology.
Environmental management for the proposed mining activity is discussed for the
environmental impact pertains to the operational phase. Even though reversible in
nature - all the impacts will be visible only during operational phase. It is planned to
take corrective measures to ensure that these effects are kept to bare minimum. The
EMP will therefore, be initiated during planning stage itself.
The environmental management plan consists of a set of mitigation, management,
monitoring and institutional measures to be taken during implementation and operation
of the project, to eliminate adverse environmental impacts or reduce them to
acceptable levels. The present environmental management plan addresses the
components of environment which are likely to be affected by the different operations
in the mine
3.2 OBJECTIVE OF EMP
The main objectives of Environmental Management Plan are:
Overall conservation of environment.
Minimization of waste generation and pollution.
Judicious use of natural resources and water.
Safety, welfare and good health of the work men and populace.
Ensure effective operation of all control measures.
Vigilance against probable disasters and accidents.
Monitoring of cumulative and long time impacts.
Ensure effective operation of all control measures.
Environmental Management Plan (EMP) aims at the preservation of ecological system
by considering in-built pollution abatement facilities at the proposed site. Some of the
major criteria governing the environmental measures will be adopted, and the same is
described in ensuring paragraphs.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
3.3 POLLUTION CONTROL MEASURES
3.3.1 Air Environment
The proposed mining operations are not anticipated to raise the concentration of the
pollutants beyond prescribed limits. However, the following measures would be adopted
to mitigate the pollution levels in ambient air. Dust particles generated during mining
activities when become airborne lead to increase in particulates level in the ambient air.
The major source of dust generation is the transport of material by trucks and tractor
trolleys. Adequate control measures shall be taken during mining operations as well as
transportation of minerals
3.3.1.1 PREVENTION AND CONTROL OF DUST POLLUTION
The main pollutant in air is Particulate Matter (PM10), which is generated due to
various mining activities. However, to reduce the impact of dust pollution the following
steps are being taken during various mining activities.
a. During Transport operation
All the haulage roads in the area are being kept wide, leveled, compacted and
properly maintained and water is sprayed regularly during the shift operation to
prevent generation of fugitive dust due to movement of vehicles.
b. Plantation work :
In order to reduce spread of air pollution in the surroundings, green belt is being
developed around the mines office, mine approach road, etc. to control dust
pollution.
c. Monitoring of air pollution
Periodic air quality survey is being carried out to monitor the quality and for timely
corrective actions.
Lying of haul roads as per the standards to avoid or eliminate air – borne dust.
Watering of haul roads and other roads at regular intervals
Spraying of water on permanent transport roads at required frequencies.
Provision of green belt by vegetation for trapping dust.
Greenbelt development along the haul roads and along the boundaries of the
lease area.
Wet drilling will be followed so that the dust emission to atmosphere is
minimized.
Proper blasting pattern will be followed for effective rock fragmentation and
generation of minimal fine dust to open atmosphere.
The extracted mineral would be transported from the mine to the end user by
adopting following measures so as to minimize dust emissions.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Speed of the vehicles would be maintained within the prescribed limits.
Trucks would not be over loaded and would be maintained to the body level.
3.3.2 Noise Environment
The Noise is the environmental attribute associated with the quarry activities and
operational of machinery. The quarrying operation will be restricted to only day time, to
attenuate noise various measures shall be taken. Drilling by Jack hammer-compressor
combination shall be adopted. The compressor shall be located where men are not
exposed to noise generated by the compressors.
Following control measures will be taken to keep the ambient noise levels well within
limits:
Use of Personal Protective Equipments (PPE) i.e., earmuffs and earplugs by workers,
working in high noise areas.
The greenbelt with species of rich canopy in the lease area at suitable places and
along the roads will further attenuate the noise levels.
Conducting periodical medical checkup of all workers for any noise related health
problems
Proper training to personnel to create awareness about adverse noise level effects.
Planned noise monitoring at suitable locations in the mine and outside location for
proper effective remedial actions.
Minimum use of horns and speed limit of 10 kmph
Timely maintenance of vehicles and their silencers to minimize vibration and Sound.
The greenbelt, which is being provided, will act as noise attenuator. With the noise
abatement measures (as indicated above), it is expected that the noise levels will be
maintained in compliance with standards.
3.3.3 Water Environment
3.3.3.1 Surface Water
The major source of surface water pollution due to mining is insignificant, however the
following measures will be undertaken to prevent water pollution.
Drainage around the mining area would be undertaken so that rain water does
not enter the mining pits.
Plantation will be under taken as per green belt development plan.
Before onset of monsoon, drains are cut along to the quarry faces to divert the surface
run off. Garland drain is provided at the quarry top to regulate monsoon water and
direct the same to the settling ponds/quarry pit to contain the quarry wash off and to
avoid the same joining to the adjoining surface water bodies/water courses. To arrest
the silt if any carried by monsoon run-off will be contained the settling pond from
where the clear water will be let out to the natural water course.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
3.3.3.2 Ground Water
There would not be any adverse effect on the ground water quality. The rock formation
does not contain any harmful element, which could percolate into the ground and
pollute the ground water. Hence, no control measures are required.
However, regular monitoring of quality in the existing tube wells in the vicinity would
be carried out both with reference to area and times intervals to study the
hydrodynamics of the strata.
3.3.4 Land Environment
Any mining activity may alter the land use pattern in the lease area. In order to
minimize the adverse effects, the following suggestions have been made. Degradation
of land is not a very significant adverse impact of hilly terrain mining due creation of
access roads, mining operations, transportation of mined material. In order to prevent
the environmental degradation of leased mine area and its surroundings, the following
measures shall be taken;
Minimal damage to the flora standing around the lease area.
Operations during daylight only.
No foreign material should be allowed to remain/spill in lease area and
catchments area, or no pits/pockets will be allowed to be filled with such
material,
Movement of the vehicles on the road will be increased; however, non-metaled
road leading to mining area will be sprinkled with water at regular intervals.
3.3.4.1 Plantation and Soil Conservation
The main objective of the green belt is to provide a barrier between the source of
pollution and the surrounding areas. The green belt helps to capture the fugitive
emission and to attenuate the noise generated apart from improving the aesthetics.
Development of green belt and other forms of greenery shall also prevent soil erosion
and washing away of topsoil besides helping in stabilizing the functional ecosystem and
further to make the climate more conducive and to restore water balance. While
making choice of plant species for cultivation in green belts, weightage has to be given
to the natural factor of bio-climate. The environmental condition of the study area is
suitable for rubber plantation. Therefore the proponent has decided to plant the rubber
trees in the area which will serve the purpose of green belt development as well as it
will have commercial value also.
The entire top soil so excavated will be reused for rubber plantation. Grass will also be
grown to stabilize the soil cover to prevent from the erosion during monsoon season.
3.3.4.2 Post mining land use
As the mining lease area is hilly terrain and it belongs to private individuals, the mined
out land will be used for commercial plantation. Top soil will be used to spread over all
the benches and grass will be grown to stabilize the soil cover and rubber plantation
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
will be done. Thus mined out area would be reclaimed by plantation during the mining
period.
3.3.5 Biological Environment
The mining activity will have insignificant effect on the existing flora and fauna. Data
have been collected during site visit It was found that the mining activity will not have
any significant impact on the biological environment of the region.
3.3.5.1 Mitigation of Impacts on Biological Environment
It is required to establish a stable ecosystem with both ecological and economic
returns, minimization of soil erosion and dust pollution enhances the beauty of the
area. To achieve this it is planned to increase plantation activities. The basic objectives
of plantations are as follows.
Improvement of Soil quality
Quick vegetative cover to check soil erosion
Conservation of biological diversity
3.3.6 Occupational Health and Safety Measures
Occupational health and safety (OHS) is a cross-disciplinary area concerned with
protecting the safety, health and welfare of people engaged in work or employment.
The goal of all occupational health and safety programs is to foster a safe work
environment.
To control and minimize the risks at workplace, The Project proponent implements
Health, Safety and Environment Policy with the following objectives:
To prevent hazards
To provide safe and healthy environment to all the employees.
The company, therefore, adopts the policy set below for the purpose of creating and
maintaining safe and healthy environment.
3.3.6.1 Occupational health hazards at mine site:
Mining activity experiences risk of a number of hazards. Some examples of such
hazards are as under:
Exposure to dust
Noise exposure;
Physical Hazards;
Vehicular movements and other related issues.
These mainly impact on those working within the mine, although health hazards can
also impact on local communities.
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
3.3.6.2 Implementation of Occupational Health and Safety
Measures
Occupational Health & Safety measures result in improving the conditions under which
workers are employed and work. It improves not only their physical efficiency, but also
provides protection to their life. Management will consider the following safety
measures:
To depute dedicated safety team
Inspection and maintenance of equipments and accessories
Pre placement and periodic health check up
Removal of unsafe conditions and prevention of unsafe acts
Detailed analysis of each and every incident
To provide standard PPEs and ensure its uses
Medical facilities & first aid boxes will be established in the mine premises.
Besides, following points are also taken care of during mine operation for assuring
safety of workers:
Health Awareness Programmes and camps are organized and will be done in
future too.
The mine workers are provided all necessary PPE, especially dust masks for their
safe guard from dust, Ear Plugs/Ear Muffs for noise and measures for other
hazards.
The fresh employees when taken are thoroughly medically examined under
initial medical examination and thereafter during continuation of employment;
the periodic medical examination will be conducted.
3.3.6.3 The Occupational Health Surveillance Programme:
A team of qualified doctors and nurses give visit periodical visit for health check up
of all the workers, team and its records is maintained properly.
3.4 ENVIRONMENTAL MONITORING PROGRAMME
The following routine monitoring programme as given below shall be implemented at
site. Besides this monitoring, compliances to all environmental clearances conditions
and consents from KSPCB/MoEF will be monitored and reported periodically.
Table C - 18: Environmental Monitoring Programme
S.
No
Potential
Impact
Action to be
Followed
Parameters
for
Monitoring
Frequency
of
Monitoring
Location
1 Air Emission
Ambient air quality
at the boundary of
mine and also near
the habitations.
PM10, PM2.5,
SO2, NOx, ,CO Half yearly
One
location at
the
boundary
of Project
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Site.
Exhaust from
vehicles will be
minimized by using
of fuel efficient
vehicles and well
maintained vehicles
having PUC
certificate.
Vehicle logs to
be maintained -
Vehicle trips to be
minimized to the
extent possible
Vehicle logs Daily
records Main gate
2 Noise
Noise generated
from various mining
operation like
drilling/blasting/
vehicular to be
optimized and
monitored
Noise level
recording; Leq
(day), Leq
(night)
Half yearly
(Noise level
in dB (A) for
day and
night time.
Two
locations
one at the
boundary
of mine
and other
at the
nearby
habitations.
Generation of
vehicular noise
Maintain
record of
vehicles
Periodic
during
operation
phase
-
5 Water quality
Monitoring of
surface water
quality & ground
water quality.
Comprehensive
monitoring as
per standard
methods.
Half yearly
Two
locations
one at the
project site
and
another at
the nearby
habitations.
7
Emergency
preparedness,
such as fire
fighting
Fire protection and
safety measure to
take care of fire and
explosion hazards,
to be assessed and
steps taken for their
prevention.
Mock drill
records, on
site emergency
plan,
evacuation
plan
Periodic
during
operation
phase
-
8
Maintenance
of Flora and
fauna
Vegetation,
greenbelt/green
cover development
No. of plants,
species
Periodic
during
operation
phase
-
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
9 Waste
Management
Implement waste
management plan
that identifies and
characterizes every
waste arising
associated with
proposed activities
and which identifies
the procedures for
collection, handling
& disposal of each
waste arising.
Record of solid
waste
generation,
treatment and
disposal
Periodic
during
operation
phase
-
10 Soil quality Maintenance of good
soil quality
Physio-
chemical
parameters
and metals
Periodic
monitoring
Plantation
area
11 Health
Employees and
migrant labour
health check up
All relevant
parameters
Regular
check ups -
3.5 SOCIO-ECONOMIC ENVIRONMENT /CORPORATE SOCIAL
RESPONSIBILITY
This project operation will provide livelihood to the poorest section of the society. The
overall impact of mining of Granite (Building stone) on the socio-economics of the area
shall be a very positive one, as not only it will generate employment opportunities for
local population at mine site but also in associated activity like for transportation of
mined out material, etc. It will also give a good boost to the general economy of the
area.
About 20 persons shall be employed at mine site. And approximately 100 people are to
be benefited directly or indirectly by the project.
The project proponent as corporate social responsibility agrees to provide free of cost
Granite (Building stone) for social projects as Panchayat Bhawan, schools in the area
besides carrying out extensive tree plantation.
The proposed mining activity is expected to provide stimulus to socio-economic
activities in the region and thereby accelerate further development processes.
3.6 COST PROVISION FOR ENVIRONMENTAL MEASURES
It is proposed to invest a capital cost of Rs. 12.8 lakhs on pollution control, treatment
and monitoring systems with recurring amount of Rs.1.40 lakhs per annum. The break-
up of the investment is given in the following Table C - 19
Granite (Building Stone) Quarry of M/s. KKJ Group International (India) Pvt. Ltd., Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam, Kerala
PRE FEASIBILITY REPORT
M/S Overseas Min-Tech Consultants, Jaipur
Table C - 19: Cost Provision for Environmental Measures
3.7 CONCLUSION
As discussed, it is safe to say that the proposed project is not likely to cause any
significant impact on the ecology of the area, as adequate preventive measures has
been adopted to contain the various pollutants within permissible limits. Green belt
development around the area is been developed and also be taken up as an effective
pollution mitigate technique, as well as to control the pollutants released from the
premises of M/s. KKJ Group International (India) Pvt. Ltd. and will develop the green
belt as per the programme to improve aesthetic beauty of the area.
S.
No Title
Recurring
Cost
Rs. in Lakhs
Capital Cost
Rs. in Lakhs
1. Monitoring of Air, Water , Noise etc. 0.20 --
2. Air Pollution Control- Management of
Haulage Roads including Sprinkling 1.0 0.5
3. Green belt development 0.2 0.8
4. Disposal and spreading of top soil and mine
waste -- 9.5
5. Occupational Health Measures Provision of
PPE and other Miscellaneous expenditure -- 2.0
Total 1.40 12.8
Granite (Building Stone) Quarry of M/s KKJ Group International (India) Pvt. Ltd.,Located at Vill- Veliyanoor, Taluk- Meenachil, Dist- Kottayam,
Kerala
ANNEXURES
e
EJ
Ee6
"s(o5
r.) Erca P
^t9ca8il o;l 3.z
' FllOE
'-5
I ca 'ql'aI crt i-13co E lF,
s-e ',3
'I : li\+ -,P
tE
!-1,e;-96t€
e
ce
s
aE?
tiF
e
E
a
€
@
lRiltt I lL
r i:1!g{:*r!s!!
* pEEe | \ \1 lElE i \"\
_:ffiE',.:ff"r:,":
| nl BIS] $f'''"{';*'"s- idl i U $ rY 1 d
-a S E RSt-€f-e*Tf E ,ffiied:Artlrl(rlo0l r.i6s
.ionlui d.p _. i r._LI:{g *{<€{:r'''nintEEt!
ie-=FiEeEPlle.o
E
I
'I-t.P,
-(l-{\0
t<:
<-a
?
t.l.Itlileil9t-t:fNI l'. ?r
il€ll.,l{o-t:
t"
!:+F
i,r3
b
III
I
lr-1 lo,.lrol6rlI o;ll'4Ir8
I
I-
i
I
aF i- - ---j:1--:-i: 1€ "Lst6 ii*? *sic i
E ;E;; i
{
\ lc\d\
I-----I E l;.i
? do.
+#s*r -".",,-I | &oroetsEa
il?tfTE+'l iD
i'f$itr
.ee r iii tl q Yiiit:iri;;;li?ilr r. r. -i \.LLl-i I s-gd i -J
a:tei-:
8
'4 ieTi i-j 5
d tY-t Ys
!
24.<ci{
e6.
6loaariiG l{nesni t.ijd,gl.to'l€6) !i
{i_r.:Tle : 9oul t9Al -cs - l+
digi:{B
."
<'iissd,si................-6--rr"t.u.e$ . .. -, """'** !1 ],1 i9^":-11:'|1-:j.-_i-t{l:u*,
....lr\.|.0..'.r.s.rm.....ddrojlo1.....fb.*o.o...rflt.w.a.....fx.c;l;z,.d]gl...rs)ooa*n.r,tr*
€$qo*aln)€* (U4*.4ae€'ode*(Dt.
€<ltgE' cq]€a
A=*6 ^riqGg€q<.ca
o:cudrqo..Ja .,
<iiG-dtsgF+ilArcil(.
-F
\CI
a
Aeso
tTalt-ltt6i t :tr.sl e-ir2'{l ?| 13lr_lr € la-l'r 131 0- *rL€_ la- tr2si 3-Strsl ,-6l>a I .,
4o '479t ,{43€, sc31. i t6
39ja1o3:6q
,r" s450, e9-13 5so:. '43gq: oo
Y"{bo
se6 (rlcdai+lbkrt6e#,
gc'lr' o-<':g5 c-1.}" -::.€16!.".' fba
A '.-rtl ':tl n6..
gd,.,.1.'Ato."i --t 6I0JGJ '
€I€
VELIYNN!!IOR i.p'N ca,ti dit 334 . ..
o'd6)o6rd.n.,ld , 1f 'lsott Land [email protected],500/1m 19610 2s r02011GPE@Govt ol'(d.t
I
./tt"
,,/tz
./,,
.'/ l2
tal2
coerrec4rd a,anaei
^,.,^,4. JH l(,KJ- @#-r.ro,i"^+J -ncrtdk:nJ^.e*.,*"o. --..(.1n.dlr. ),e!t ' L+1..',..,-tr'r.."ia --r.6) &3 6 -:J o.'{).utaroasa, W6,5rBodora'o6q cdd.. nn e.e4d.s-t*.asrtt2 a-tl)J )z-1 a t "S7J^m
sO ep>JonmJorofiFs CII<O a4arv
poo(dooBrsld
ctloc6a;a$dDri.
gE
2 3 4 5
t2lt'4t16t30
zL
2-{t2-3t.>3
+3g
t-lz-Ja-Ll
_? -/a-a3d
3-r?
o'3'7 '3oo -98'3oo '\o '97s .]o '6oo.3l .34
o,18'41o'2o'z-3o'3a'4oo' lt tlo6'o2'75o,t4'oSo , o?'o7o.oz,Y3
"1aeJ4>
?tla taiu' t'f
VELIYANNOOR
PIN CODE:686 634
.6Daoc6rr; (r)(n.xA 8Land Revenue 14.50C/100 1S/610 29102011GPEOCov1 ofX.6la
&5rDd6l
clcru{latrv1|,l..........,n"go
G)6113GolO
'".,,*............................-Cfl -..4J
@(noilboS6,1d
6)a," ^b.
o 46'.4VO 3Qt+4a3651o2t 16
O g5 szo0364o G4;OQ
o 4(,s4O 5o Y'5
o 1.3 : -s-s
o 62 4,2
o 3? cjd
1.'dk.
l/
h
inw or&
VTLLAGE OFFICEVELIYANNOOR
PIN COoEi 686 634
l-l
I
e-7
{l-lt-\{rg
&-7
os,eoro -.rua.......4._9.5_o_......-.ti_trrJ...e),ba. g-.Id\ c.)\.\'a"\ "rb le*lcjr; oo€' artr" e.fu1q
^J,""."i***.*"",.S*&lHf*Pf ilgl?sffi$3fr g3a,y*"e,s*!^--difl
I ^tf
I at4
rd_3
t23r23
,./l& s_
,att&s-
FILE No. - PCB/KTM/QR/9312oo9
KERALA STATE POLLUTION CONTROL BOARD
CONSENT TO OPERATE
UNDER
. RENEWAL
Air (Prevention & control of Pollution) Act, 1981
dt'
Environment (Protection) Act' 1986
TO
_/ ytr. K.K.l Group rnternational (Inlii)tq"...,.rl
Ashiana Towers, K.K.J TownshlpPerumpadavom P.O, Elanji (via)
Ernakulam - 686 665
consent No: PCB/KT /rco/RJ Lo39 | 201'2
Datedt 27 .O7 '2OL2valid up to: 31.12.2014
1, GENERAL
1J
)
I
Name and address ofestablishment
Communication
Up to 31.12.2014
M/s. K.K.J Group International (India)Pvt Ltd (QuarrY)
Ashiana Towers, K.K.J TownshiPPerumpadavom P.O, Elanji (via)Ernakulam - 686 665
Telephone: 0485 - 2258002, 2258339225A609
Sri. Joy Varghese (Director)Koottumalil (H)PerumPadavom, Elanji P.O
MoovattuPuzha
@J-4 1tA-q
3
4 Occupier details
5 Survey Number
2.0766 Hectares
Veliyannoor
Meenachil
Kottayam
Veliyannoor
RED
SMALL
{ 45,000/-
? 85.5 lakhs
100 lit/daY
15,000/-
Granite Rubbles (Boulders) - 1400 T/daY
Jack Hammer 90 HP
6 Extent of land
!8
Village
Taluk
9
10
1I
District
Panchayath
CategorY
!2 Scale
13 Fee remitted/Fee SIab
L4 Capital Investment15 Water consumPtlon
16 PRODUCTS
Machinery
2. GEI{ERAL CONDITIOI{S :.i :.:''
2.1. This consent is granted based on the particulars and affidavit submitted by the
applicant, certificate issued by the Village Officer and subject to the power of the
Board to review and make variations in all or any of the condltions as pe' sectlon
21(6) of the Ad.
2.2. This consent is unless withdrawn earlier and subject to condition no.1 shall be valid
for a period as mentloned under condltlon no.1.1 of this consent order'
2.3, This consent is valid only along with valid mining permit, Explosive License, D&O
license and other essential licenses/permits/environmental clearances'
2.4. No change or alteration or expansion of the quarry is to be made without the prior
Dermission of the Board. Any change in the particulars furnished in the application
and /or in the identity of the occupler/authorized agent is to be intimated to the
Board forthwith.
2.5, Application for renewal of consent is to be submitted on or before 31 10 2014'
2.6. Protection fencing shall be constructed and malntained along deep cutting edges of
quarry to prevent accidents.
2,7, Quarry shall be conducted only at the area earmarked in the approved site plan'
3,1. Raw materials and products shall be transported with proper cover and / or after
wettlnq to prevent spreading of dt-lst
3.2. (i) The suspended particulate matter level at the boundary of the premises shall not
exceed 200 microgram per cubic metre.
(ii) The Respirable Particulate Matter level at the boundary of the premises shall not
exceed 100 microgram/cubic metre.
3.3'Thesound|evelmeasuredlmoutsidetheboundaryofthepremisessha||notexceed55dBlAl Leq.
9
o
4. OTHER CONDITIOI{S
4.1. All the quarrying activities shall be stopped at 1O0m distance from residential
buildings, place of worshlps, public bLlildinqs' publlc road' river/lake and any railway
line or bridges.
4.2. Bench mining shall be practlced and necessary protection measures shall be taken to
prevent accidents due to flyin9 rock p'eces
4.3. Proper audio signals like siren shall be made before and after each blasting period to
avold accidents'
4.4. Appropriate protecllve me'rsures shall be taken during blasting operation to avolo
flying a stone outside of quarry premises'
4.5, In case of using electric detonators' maximum simultaneous
to 10 bore holes or delay detonators shall be used'
4.6. The quarry shall be operated between 6am to 6pm only'
blasting shall be limited
4.7. Jhe quarry shall not De operated in the absence of any of the essential
license/permit/consent f rom the competent author'ties'
4.8. The applicant shall obtain necessary environmental clearance as directed by Hon'ble
Supreme Court in t A No 12-13 of 2011 in S L P(C)No 19628-19629 of 2009'
I hr)Ptiy'Lr L'-r3 ijA PrtN
j -,ri : il- -ir_ i r'
sr6"err*e & sEAL oF
ISSUING AUTHORITYOAIEt 27 .O7 .2072
OFFICE SEALa
copy to: r. rhe cdief Environmental Engineer'Ernakyam.
2. st9( file.
GD * *' t 1l,)l,"ti*'1,?,':""1,"1r
( I n d i a ) ? v t' L td'Ashrana Towerc . KKJ Township. Peftrmpadavom PO . Elanji. Ernaklrlam (Dist )
Kerala.India - 686665. Tel: +91 -485-22 5E002 2259339-44 Fax:+91-485 2259086E-marl kkjgrcup@vsnl nel Webs(e w\,!4r.kkjgroup com
( ,\t1\ttn! ! \)tu;t I a[ ntrrt$uttnt]n'.\ ut.nl
Exlract of the Mirutes of the Meetine of the Board of Directors of theComDanv, held al 11.30 AM, on Saturdav, l4th of.tuly, 2007, at it!Rceistered Oftice. at l0/2tl0A. Ashiana Tolvers. KKJ Townshin.P(rrumDadavom P.O, Elanii. Ernakrlrm I)islrict. Kerala - 686 665.
"RESOLVED that Mr. Joy Varghese, Director ofthe Company be and is here
by authorized to sign and execute all agreements, underraking , applications ,
returns,papers,receipts,all documents relating to excise,customs,sales tax, incomctax, impod and export, Kerala Water Authority, application to small scalc
industrial dcparlments, Electricity Board and all other Document(s) includingagreement relating to the purchasc, as also salc of company's products whichrequire authentication in the name and on behalf of the Company and to do all orany of the acts,deeds,matters and things as may be considered expedient and
necessary on behalfofthe Company."
*RESOLVED Further that the Dircctor be and is hereby authorized tc appear
and act on bchalf of and represent thc Company in all matters before CcntralGovemment, State Govemmcnt and similar other authorities, public bodicspublic offers, Iocal self govemment bodies and all Govemment ollicers and tosign and execute all applications,returns,objections, documents, agreements, and
papcrs that may be required for and on behalf of the Company and in relation toany matter in which it is interested or may be concemed in any way."
*RESOLVED lurther that the Director be and is here by authorized tonegotiate and act as the representative for purchase landed propeties and appcar
before the Sub Registrar Office,Village Office,Thasildar,s Ofhce and rclated
o ices and to sign all documents rclating to Patta, l'handapper, etc."
"RESOL\ED Further that the Director be and is here by authorized to sub-
delegate all or any powers hereby confened to other officer(s),Consultant(s),legaladviser(s) or auditor(s),of the Company as he may think fit".
"Tme certified extract ofthc minutcs" M-f)irector
t)ro,, r ... r' ,rq.li{ir::r'i
GD K K J G rou"p,"t r#l 1,1,,"t""#
l ( t ndi a ) p v t. L td.Ashiana Towe.s, KKJ Township, Perumpadavom PO , Etanii, Ernakutam (Drst )
Kerala, lndia' 686665- Tet +91 4a5-2258002, 2259339-44 Fax +91-485-2259086E-mail: [email protected], Web{e: wwwkkjgrosp.com
gnu!Cotpotdtc Offe: n'.o lo\ 20551, :Apan, L.:.,s.L. Ii[ +971 6 7J385N[a.t +971.6 7t8s50s L "ui[: ab!iss@.'nitur.s.nct.ae
Minutes of the of thheld at I on Tu
^t lID naT
P.O. Elrnii. Ernakulam District. Kerata - 686 665.
of the Borof Ma
I
The Board has discussed, evaluated and reviewed, the actions initiated by thg company tomeet the Corporate Social Responsibility (CSR) and expressed satisfaction on, variousphilanthfopic activities ca[ied out, through our group Charitable Trust, [ts KKJFoundations.. Since our group has entered into, the metal crushins activities in aslccessful manner, it is better to design an effective community welfare plen, directly bythe company for the benelit of the downtrodden settled in the nearby areas of ourfactory.. The Chairman, therefore, has presenred a Community pension plan (Cpp) to thedeserving local community at the Swiss Tech plant at Kolady, as a monthly monetarybenefit, as per the merit of the applicant and at the discretion of the board as well. Theboard felt it very appropriate, and has agreed to implement the same, within the framework of the proceduml system decided by the management and the following r€solutionis passed
"RESOLVED that approval of the Board be and hereby accorded to implement aCommunity Pension Plan ( CPP ) for the deserving local community, ai monthlyMonetary Benefit Scheme, at the Swiss Tech Plant at Kolady, not directly related to thenormal business of the company, but to adhere to the Corporate Social Responsibilitycommitments voluntarily and the pension plan shall, automatically cease to exist at therccommendation ofthe Operational Head ofthe Swiss Tech plant Sitc at Kolady. ano arthe Iinal discretion of the Board of Directors ofthe comoanv"
Tt,. c-^El..'l ,-',' l-^-'l' { f:. r"r^^le
ension Plan and
ffi ,t.,1t(t L,ltnrin4 t|rtr.nol dtj trNnn,or :\dnrttd.nt tL'i!rt).ra@t hfnrndut{ )h,tkt!, ( i6r idldt, l?,Iu6 &u4,',ltq d li\1p.d t , t,14o"' nt !f,i:11,t.i, .\t n @;8o|^li&la.n8'l\|li!nIll||Lt1d'If]jni|r'l|lf$tn|nntnJll||4':||nt';i.:ua.||'ia^
Addtass : 532' t(d"o!|ttlll7
ll.ntt
olerru 't i1r, &Elot'old
pc'6r .
Lt*"1-,isr
ulltJftgi'*'-' om'-pe,._r.a .rk!_.Fad q^n'tM
For Mw'tlsPltL CodlieftY
'lol0irt old'xD_tr!€!
n|c. : |'t.rdlp'd
ffi,.,Jff* "-"''t"ffffffiffii"i.ifit .q.,-tt"-"t'"'"4*'
, \f,-'"t*
1-\
\'*
r \-r,L,
. ' ..\W. v-' '\x\a;\ /- .a\'
":F::li:iiSJ$8i$Slllsr;'^"t(
..-,' t.
^-1.lt'JB'.fj
')o
-f.l$loa ..anr'
E6.d.X& :Jtr.lEsdos/.: --[
A!. .r r l-l-9t:-..A*-.-
: d.ab't .: r'd/.f,...j I / .!|-
Annexure-10-Panoramic view of the site.jpg
Mine Boundary
Zone Limits 500meter
N
S
W E
200 meter
Key Plan Map of the Study Area
PREPARED BY:
CHECKED BY:
PROJECT NAME:
GRANITE (BUILDING STONE) QUARRY OF VELIYANOOR
Kiran Kumar Jadav
P.S. Soni
Survey of India Topo Sheets NoC43Q9
Coordinate SystemWGS_1984_UTM_Zone_43P
Geographical Coordinate systemGCS.WGS.1984
DatumD_WGS_1984
GD K KJ G roup,,t *:.1r,1,,",.i,x
| ( | n di a ) prr' r, td.
Ashrana ]owers KKJ Townsh,p Perumpadavom PO . Elanji ErnakLrlam (Dsr )Kerala lndia 686665. Te1 +91-485-2258002 2259339-44 Fat +91.485 2259086
E'mail [email protected] Websiie wwwkkjgroup com
q ^,t'
( otrt t ! tlf.fii : /r(),4rr\] .lr)rr t.
Extract of the Minutcs of the proceedinss of the Meetins of the Borrd of Direcaorsof the Comnanv. held at 10.30 AM. on Tucsdav 25th of March. 2014 Nt itsResistcrcd Office. at 10/280A. Ashiana Towcrs. KKJ Township. I'erumDldavomP,O. Ehnii. Ernakulam District. Kcralo - 686 665.
Corporate Pension Plan and Derformance of thc Koladv crushine Dl:rnt
The Board has discussed, evaluated and reviewed, the actions initiated by the company tomeet the Corporate Social Responsibility (CSR) and expressed satisfaction on, variousphilanthropic activities carried out, through our group Charitable Trust, M/s KKJF'oundations.. Since our group has entered into, thc metal crushing activities in a
successful manner, it is bctter to design an effective community welfare plan, direotly bythe company for the benefit of the downtrodden settled in thc nearby areas of ourl'actory.. The Chairman, thereforc, has presented a Community Pension Plan (CPI') to thedeserving local community at the Swiss Tech Plant at Kolady, as a monthly monetarybenefit, as per the merit ofthe applicant and at the discretion of the board as well. Theboard felt it very appropriate, and has agreed to implement the same, within the frame
work of thc procedural system decided by the management and the following resolutionis passed
"RESOLVED that approval of the Board be and hereby accorded to implement a
Community Pension Plan ( CPP ) for the deserving local oommunity, as monthlyMonetary Benclit Scheme, at the Swiss lech Plant at Kolady, not directly relatcd to the
normal business of the company, but to adhere !o the Corporate Social Responsibility
commitments voluntarily and thc pension plan shall, automatically cease to exist at the
recommendation ofthe Operational Head ofthe Swiss Tech Plant Site at Kolady, and at
the final discretion ofthe Board ofDi.ectors ofthe company"
f'- -[l'J -* luo-"l' { lt* r"'^^1*
Director