Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
PRE-FEASIBILITY REPORT
M/s. SRI.GANDRETI SEETHARAM
Mining Project: Category ‘B2’
Area: 1.54 Hectare
Sy No. 7
Sompuram Village, Vepada Mandal,
Vizianagaram District
Andhra Pradesh
Project Proponent
SRI GANDRETI SEETHARAM
S/o.Late Sanyasiappadu
L.Kota Village & Mandal
Vizianagaram District, Andhra Pradesh
ENVIRONMENT MANAGEMENT PLAN
FOR
M/s. SRI GANDRETI SEETHARAM
VILLAGE : Sompuram
TEHSIL : Vepada
DISTRICT : Andhra Pradesh
AREA : 1.54 Hectare
MINERAL : Road Metal & Building Stone
Sy No : 7
PRODUCTION CAPACITY : 41361.60 Cu.mt/year
APPLICANT
SRI GANDRETI SEETHARAM
S/o.Late Sanyasiappadu
L.Kota Village & Mandal
Vizianagaram District, Andhra Pradesh
Pre Feasibility Report
Page 3 of 15
INTRODUCTION
Nature is very kind on the human to provide all kind of materials on earth. All kinds of minerals
are available in their raw form in the earth . Mining operations disturb the terrestrial configuration
and natural beauty of the area. The magnitude of disturbance depends upon how the minerals are
extracted from the mining area and the environmental impact depends upon the location and size
of deposits and the methods adopted for its exploration. By adopting good mining practices it is
moving towards harmonious development where both the operational and environmental
aspects are accorded due weightage.
Every quarry lease holder shall take all possible precautions for the protection of environment and
control of pollution while conducting quarry operation. Under the mining operation this
management plan is required.
The proposed quarry lease area named Sri Gandreti Seetharam of road metal and building stone
over an extent of 1.54 Ha. Located at Sy.No.7, Sompuram Village, Vepadu Mandal, Vizianagaram
District, Andhra Pradesh state submitted an application for grant of quarry lease. The asst. director
of mines and geology Vizianagaram vide File No. 8295/Q/2017 dated. 06.03.2018 submitted
proposals on the application duly recommending for grant of quarry lease in favour of Sri Gandreti
Seetharam, S/o. Late Sanyasappadu.
After careful examination of proposals the asst. director of mines and geology, Vizianagaram is
decided in principle for grant of quarry lease for road metal and building stone for the applied mine
for a period of 10 years subject to submission of approved mining plan with a condition that the
approved mining plan shall reflect the restrictions to be adopted by the application while quarry
operations. For the same the deputy director of mines & geology, Visakhapatnam sent a notice vide
939/Q3V/2018 dated.29.03.2018.
The approved mining plan prepared as per guidelines issued in Form T in G.O.Ms. No.56, Industries
& Commerce (MII) Department dated. 30.04.2016 under Rule 7A of APMMC Rules’ 1966 and
progressive mine closure plan underRule 23(B) of MCDR 1988 for the first five years period and
accordingly submitted & got approved by Deputy Director of Mines & Geology vide Letter
No.919/MP/VZM/2018 dated. 05.05.2018.
Pre Feasibility Report
Page 4 of 15
NAME & ADDRESS OF SITE:
Sri. Gandreti Seetharam,
Sy.No.7, Sompuram Village,
Vepada Mandal, Vizianagaram District, A.P – 535579
NAME & ADDRESS OF LESSEE:
Sri. Gandreti Seetharam
S/o. Late Sanyasappadu,
L.Kota Village & Mandal,
Vizianagaram District, A.P – 535361
SALIENT FEATURES OF THE PROJECT:
Particulars Details
Name of the project Sri Gandreti Seetharam
Road Metal & Building Stone quarry
Location Sy.No.7, Sompuram Village, Vepadu Mandal, Vizianagaram
District, A.P.
Land use pattern Individual Owner
Mineral Road Metal & Building Stone
Mining Lease area 1.54 Hect.
Sy.No 7
Land Use Govt. Land
Lease Validity 10 Years
Production Capacity 41361.60 Cu.mt/year
Toposheet No. 65 N/4
Latitude& Longitude (1) 18°03'15.47"N, 83°07'18.16"E
(2) 18°03'14.57"N, 83°07'18.15"E
(3) 18°03'14.33”N, 83°07'16.47"E
(4) 18°03'11.02"N, 83°07'16.82"E
(5) 18°03'10.67"N, 83°07'13.50"E
Pre Feasibility Report
Page 5 of 15
(6) 18°03'14.99"N, 83°07'13.04"E
Topography Hilly area
Method of mining Open cast semi mechanized
Estimated project cost 10 Lakhs
EMP Cost 1.0 Lakh
Man Power Total : 25 NOs
Mines manager – 01
Mine Supervisor – 1 No
Skilled workers – 6 Nos
Semi Skilled Workers – 6 Nos
Un Skilled workers – 11 Nos
No of working days 300 days per annum
Water demand and supply 4 KLD
Nearest habitation/town Ramaswamipeta village at a distance of 1.25 km
Vizianagaram town located at 40kms
Mandal Head Quarters Vepada is located a t 11.54 kms via seethampeeta road.
Nearest Airport The nearest Airport is Visakhapatnam which is about 42
kms from mine site.
Nearest Connectivity The quarry lease area can be approached from sompuram
village road, stat transport bus services ply from
srungaavarapu kota, vepada & vizianagaram.
Nearest Railway Station The nearest Railway Station is Lakkavarapu kota which is
about 6.5 kms from mine site.
Port Facility Visakhapatnam port about 52 km
Power Supply Electricity is available in all the villages and in the nearby
agricultural lands for bore wells.
DETAILS OF THE AREA
The details of the lease area to be grant, ownership etc. is as below:
Pre Feasibility Report
Page 6 of 15
Whether area is recorded in forests : No
Existence of Public road : No public road passes
TOPO SHEET : Area falls in survey of India (65 N/4)
BOUNDARIES OF QUARRY :North – Hill
South – Hill & Water Body
East – Hill & Agricultural Lands
West – Hill & Agricultural Lands
No interlinked projects were associated with this project.
COORDINATES OF PROJECT AREA
S.No Latitude (N) Longitude (E)
1 18°03'15.47"N 83°07'18.16"E
2 18°03'14.57"N 83°07'18.15"E
3 18°03'14.33”N 83°07'16.47"E
4 18°03'11.02"N 83°07'16.82"E
5 18°03'10.67"N 83°07'13.50"E
6 18°03'14.99"N 83°07'13.04"E
Toposheet no. 65 N/4
District & State Tehsil Village Area in
hect.
Khasra
No.
Mineral
Name
Lease
Period
Vizianagaram
Andhra Pradesh
Vepada Sompuram 1.54 7 Building stone
and road metal
10Years
Pre Feasibility Report
TOPOMAP
Pre Feasibility Report
Village Map:
Pre Feasibility Report
Satellite Image/google image of the mining area:
of the mining area:
Pre Feasibility Report
TOPOGRAPHY:
The quarry lease applied area is located o a hillock with a maximum elevation of 50 m above ground
level within the quarry lease applied area with topo relief in NE direction. The lowest contour is 75 m
and the highest contour is 125 m in topo plan.
DRAINAGE:
Sub- Dendritic/Parallel Pattern in N-S direction
VEGETATION :
Sparse with tron bushes, areas around the barren rock land are cultivation lands.
CLIMATE:
The area is falling under tropical zone. The weather is hot and humid with a tropoical climate and
thereby no distinct seasons.
25 dec C in winter & 48 deg C in summer usually.
The wind direction is in SW to NE. The coolest months are December and January, when it is pleasant at
27 deg C to 30 deg C.
There is heavy monsoon rain at the end of summer with depression in the Bay of Bengal.
RAINFALL:
The average annual rainfall of the area is 1000mm
SOIL TYPE :
Heavy Soil
LAND USE PATTERNS :
Agriculture and Cultivated lands
Pre Feasibility Report
GEOLOGY AND EXPLORATION:
The eastern ghat mobile belt (EGMB) is more than 600 km in length form vizianagaram in the North to
Ongole in the South. This belt is more than 100 km in width in Northern part and tapers down to less
than 20 km in the south, it has broad actuated trend with westward convexity. The NNE-SSW trend in
the southern part of the belt changes NE-SW in the North. EGMB is divided into 3 longitudinal
zones viz.,
1. Western-Charnockitic Zone
2. Central – Khondalite Zone
3. Eastern – Migmatite Zone
While in the northern parts in Srikakulam, Vizianagaram & Visakhapatnam districts the central
Khondalite Zone occupies major part of the area. Whereas western Charnockite Zone occurs in the
Southern part. The rocks in this belt are represented High grade granulite facies of Metamorphism and
suffered by complex deformation. The stratigraphic succession of EGMB is as follows:
Recent Alluvium, Beach Sands, River Sand
Quarternary Laterite, Lateritic Soils
Upper Gondawana Sandstone with Interbedded Clays and Connglmorate
Easter Ghats Migmatitic Group
Super group
Charnokitic Derived Migmatites
Khondalite Derived Migmatites
Pre Cambrian Charnokite Group Hypersthene Gneiss
Pyroxene Gneiss
Khondalite Group Khondalite
Charnokitic/Gneissee
QUartzites
Intrusives Layered Anorthisites and associated mafics and chromiferrous ultra
mafics
Charnockite Group Charnockites with Mega Crystic K-Feldspar
Charnockite two pyroxene granulite/Amphiboites
Khondalite Group Calc-silicate-granulites
Pre Feasibility Report
Garnet-silliminite-quartz-biotite—Feldspar-Graphite Gneiss
(Khondalite)
Quartzite –Garnet –Silliminite
Granitoid Suite Granitoid with Mega Crystic K-Feldspar undifferentiated (with
migmatitic dia textite, Augen) Perferoblastic granite and Gniesses.
Granet – Biotite Homophanus Granie /Gniess Leptynite, Local
Charnockite Neosomes and Relics
In vizianagaram district the EGMB is represented by vide range of litho units viz: Charnockites,
Khondalites, two pyroxene granulites, Migmatites, Leptynite and Intrusive Porphyroblastic
Charnockites. Large enclaves of Acid Charnockites, Khondalites and Meta Basic rocks occur within
Migmatites, which are largely seen in the area lying between R.Vamsadhara and Coast line.
DETAILED DESCRIPTION OF GEOLOGY AND LEASE AREA:
The present area is occupies by Charnockites, charckites is a garnet bearing quartz plagioclase
pyroxene, grey in color (Graniulite) with typical platly “Granoblastic”texture. This rock type might have
been derived from high-grade granulite facies metamorphism of a pile of volcanic intrusive. Tis rock
type is formed in N-S direction and this type of material is being excavated for road metal & Building
stone during previous years.
The material excavated from this area will be crushed as chips and the chips will be supplied to the
road works & building constructions. Accessory minerals like biotite and opaque cannot be identified
megascopically.
Entire quarry lease applied area is covered with road metal & building stone which is rising upto 50 m
above ground level trending SE-NW, the length of the exposed body measured 140 m in the area with
an average width of 99 m.
The road metal & building stone can be extracted from the rock available n the quarry lease applied
area which is useful in civil constructions purposes.
Pre Feasibility Report
DETAILS OF PROSPECTING CARRIED OUT:
1 old pit is existing in the quarry lease applied area .
Pit No Grids Area in sq.mtrs Avg depth in meters
1 N50-200 TO E00-150 6597 22.00
FUTURE PROGRAM OF EXPLORATION WITH DUE JUSTICIATION TAKING INTO CONSIDERATION
THE FUTURE TENTATIVE EXCAVATION PROGRAMME PLANNED IN FIRST FIVE YEARS :
Year No. of Bore Holes
(Core//RC/DTH)
Grid
Interval
Total
Meterage
No. of Pits
dimensions and
volume
No of trenches,
dimensions and
volume
1st N.A - - N.A N.A
2nd N.A - - N.A N.A
3rd N.A - - N.A N.A
4th N.A - - N.A N.A
5th N.A - - N.A N.A
Reserves and resources as per UNFC. Detailed calculation of reserves shall be stated:
TOTAL GEOLOGICAL RESERVES
Sections Category Sectional Area in
sq.mtrs
Sections
influence in
meters
Volume
A-A1 Proved 3624.00 99.00 358776.00
B-B1 Proved 1034 50.00 51700.00
TOTAL GEOLOGICAL RESERVES 410476.00
RESERVES BLOCKED UNDER 7.5M BUFFER ZONE
Sections Category Sectional Area in
sq.mtrs
Sections
influence in
meters
Volume
A-A1 Proved 573.00 99.00 56727.00
B-B1 Proved 558.00 50.00 27900.00
TOTAL BLOCKED 84627.00
Pre Feasibility Report
RESERVES BLOCKED UNDER SAFETY SLOPES
Sections Category Sectional Area in
sq.mtrs
Sections
influence in
meters
Volume
A-A1 Proved 587.00 99.00 58113.00
B-B1 Proved 275.00 50.00 13750.00
TOTAL BLOCKED 71863.00
RESERVES AVAILABLE FOR MINING:
TOTAL GEOLOGICAL RESERVES
A Geological Reserves 410476.00 M3
B Reserves Blocked under 7.5m buffer zone 84627.00 M3
C Reserves blocked under safety slopes 71863.00 M3
D Total reserves blocked (B+C) 156490.00 M3
E Reserves available for quarrying (A-(B+C)) 253986.00 M3
Extraction of Market grade reserves @100%
recovery
253986.00 M3
Life of the mine 253986.00 M3/41361.60 M3
6.15 Years
PROJECT DESCRIPTION WITH PROCESS DETAILS:
METHOD OF MINING:
The road metal & building stone in the quarry lease applied area is exposed on the surface with sheet.
Hence, it is proposed to quarry the sheet by open cast semi mechanized method by developing the
multiple benches of 6m height and with of 6m with drilling and blasting. The development of benches
in the sheet rock will be maintained 60o safety slopes under rules and regulations as per MMR 1961.
DRILLING:
Drill holes of 6m depth will be drilled in a staggered pattern at 3mx4m interval:
Drill hole dia : 54 mm upto 3-6.25 m long
Pre Feasibility Report
Depth of inclination of drill hole : generally drilled vertically in an alignment
Explosive type : ANFO+Booster & Detonator Fuse
YEARWISE TENTATIVE EXCAVATION IN CUBIC METERS:
Year Pit
No
Total
tentative
excavation
Top
soil
OB/
SB/I
B
Rom from mineralized zone ROM
/WASTE
RATIO Clean ore Sub grade
ore
Mineral
rejects
M3 M3 M3 M3 M3 M3
1 2 3 4 5 6 7 8 9
1st 1 37548.00 Nil Nil 37548.00 Nil Nil 1:0
2nd 2 38388.00 Nil Nil 38388.00 Nil Nil 1:0
3rd 3 37968.00 Nil Nil 37968.00 Nil Nil 1:0
4th 4 46368.00 Nil Nil 46368.00 Nil Nil 1:0
5th 5 46536.00 Nil Nil 46536.00 Nil Nil 1:0
Total 206808.00 206808.00
Average 41361.60 41361.60
DUMP MANAGEMENT:
It is proposed to produce 206808.00 M3 of road metal and building stone aggregates during first 5 years
of plan period with an average annual production of 41361.60 M3. Multiple benches of 6m height and
6m width will be developed during the plan period as per MMR 1961.
STOCK YARD:
Temporary stocks will be maintained on day to day basis, entire ROM will be cleaed within days (i.e. 4
to 5 days).
QUARRYING PROGRAM FOR THE FIRST FIVE YEARS:
As per applicant purposed the quarry operations will start from south of the quarry lease area between
the grids N00-150 & E00-185 and between the RL 136-96 M to RL 55M. The excavation activity will be
Pre Feasibility Report
taken up in entire quarry lease applied area and advances northwards.
The volume calculations are made by the cross sectional area method discussed below:
YEAR ROAD METAL & BUILDING STONE
1st Mining from south of the quarry lease applied area covering the surface area of 447.00 M2
will be excavated producing 37458 M3 of road metal & building stone between the RL86-78
to RL70 and between the grids N00-100 to E00-150 covering sections A-A1, B-B1. The
workings advance northwards.
2nd The mining will contain due north of 1st year workings covering the surface area of 457.00
M2 will be excavated producing 38388 M3 of road metal & building stone between the
RL113-80m and between the grids N00-100 to E00-150 covering sections A-A1, B-B1. The
workings advance northwards.
3rd The mining will contain due north of 2nd year workings covering the surface area of 452.00
M2 will be excavated producing 37968.00 M3 of road metal & building stone between the
RL113-80m and between the grids N00-100 to E00-150 covering sections A-A1, B-B1. The
workings advance northwards.
4th The mining will contain due north of 3rd year workings covering the surface area of 552.00
M2 will be excavated producing 46368.00 M3 of road metal & building stone between the
RL70m to RL 55 m and between the grids N50-120 to E00-150 covering sections A-A1, B-
B1. The workings advance northwards.
5th The mining will contain due north of 4th year workings covering the surface area of 554.00
M2 will be excavated producing 46536.00 M3 of road metal & building stone between the
RL70m to RL 55 m and between the grids N00-70 to E00-150 covering sections A-A1, B-B1.
The workings advance northwards.
The year wise production proposed is shown in the following table:
YEAR WISE PRODUCTION FOR 5 YEARS
YEAR SECTIONAL
AREA IN
sq.mtrs
SECTIONAL
INFLUENCE
VOLUME RL’S
1 447.00 84.00 37548.00 RL 86-78 TO RL70
2 457.00 84.00 38388.00 RL113 TO RL80
Pre Feasibility Report
3 452.00 84.00 37968.00 RL 80 TO RL 55
4 552.00 84.00 46368.00 RL70 TO RL55
5 554.00 84.00 46536.00 RL70 TO RL 55
TOTAL 2465.00 206808.00
AVERAGE 492.40 41361.60
Quantum of Excavation: A total of 206808.00 m3 of road metal & building stone will be produced and
marketed during the first five years of plan period.
PRODUCTON SCHEDULE:
The production of road metal & building stone continuous throughout year except during monsoon.
That is 10 working months, 25 days per month are considered. The average production of 46536.80
cum.mtrs per year ( 300 days @ 155.12 cum.mtrs) can be easily achieved in a single shift with sufficient
men and machinery.
DRILLING AND BLASTING:
54 mm hammer drilling will be used for blasting holes in staggered pattern of 2 x 3m with depth of 6m.
each blast holes with 61 tons (24.40 cum.mtrs).
Proposed production per day @ 300 working
days per year
46536.80 cum mtrs
116342 tons max production
Drilling machine required with 54 mm drill rods.
Bench height 6.00 m
Spacing 3.00 m
Burden 4.00 m
Bulk density (insitu) 2.50
Depth of drilling 6.25 m
Yield per meter of drilling 3.00x4.00x6.25x2.50
187.50 tons (75 m3)
187.50 tons / 6.25 m
Pre Feasibility Report
30 tons ( 12 m3)
Rate of drilling 6m per hour
Drilling capacity per days with effective 6 hours 6x6= 36
Rate of production per day 1080 tons ( 432 m3)
Requirement of drilling per day for 155.12 m3 (
486.38 tons)
387.8 tons / 1080 tons
0.36 or say 1
No. of meters required 387.80 tons/30 tons
12.92 mtrs
No. of machines required per day considering 80%
availability
12.92/36 = 0.36 or say 1 machine
EXTENT OF MECHANIZATION:
S.No Machinery No’s
1 Excavator 1
2 Drilling Machines 1
3 Tractor with trailers 2
MINE DRAINAGE:
A Minimum and maximum depth of water table Shallow aquifers during monsoon period
and canal flows.
B Indicate maximum and minimum depth of
workings
RL 113-70 M to RL 55 m
C Quantity and Quality of water Portable
D Regional Drainage Pattern Sub-Dendritic
STOCKING OF MINERAL REJECTS / SUB GRADE MATERIAL AND DISPOSAL OF WASTE
Not applicable as no mineral rejects / sub grade material is anticipated.
USE OF MINERALS:
The rock quarried out will be utilized for construction of structures and for formation of roads. No
mineral rejects are anticipated.
PROCESSINGS OF ROM AND MINERAL REJECTS:
Pre Feasibility Report
The rock excavated in large sizes will be subjected to crushing and sizing to various sizes as suitable to
construction and road formation.
EMPLOYMENT:
S.No Category No. of Persons
1 Mines Manger 1
2 Mine supervisor 1
3 Skilled Workers 6
4 Semi skilled workers 6
5 Un skilled workers 11
PROGRESSIVE MINE CLOSURE PLAN
I Existing Land
Use Pattern
The quarry lease applied area is surrounded by barren lands and low level
hillocks comprising Road Metal & Building Stone of good quality. The
surrounding area of the quarry lease applied area are quarries for Road Metal
& Building Stone and beyond are agricultural lands
Ii Water Regime
The subject area is located on a hillock and the surrounding areas around are
agricultural lands.
The ground water occurs under confined conditions in both hard rock and
alluvium which are shallow in nature.
No impact on surface water or ground water is foreseen due to quarry
operations.
Iii Flora and Fauna
The whole area is occupied by scattered sparse vegetation of thorny trees and
small bushes. In the quarry lease applied area no wild animals are witnessed
as per the statements collected from the local population, since 50 years
Iv
Quality of Air,
Ambient Noise
Level and
Water
Air quality is good but at quarries it is filled with dust, due to haulage on the
road, blasting etc.
The noise generated mostly due to blasting, drilling, vehicular traffic
Road Metal & Building Stone quarrying will not affect water quality.
v Climatic The area is falling under tropical zone. The area is having Humid climate. The
Pre Feasibility Report
Conditions temperature recorded in this area is 25°C in winter and about 48°C in summer
seasons. The wind direction is in SW to NE. The average annual rainfall of the
area is 1000 mm.
Vi Human
Settlement
The nearest village Ramaswamipeta is situated 1.250Km due NE of the quarry
lease applied area, having approximately population of 400 No’s. Agriculture
and sheep breeding are important profession of the people living in the village
besides involving themselves in quarrying activity.
Vii
Public
Buildings,
Places &
Monuments
No public buildings, important places and monuments are seen in and around
the quarry lease applied area. The applicant will adopt the safety measures
while conducting the quarry operations as per the Regulations of
Metalliferrous Mines Regulation 1961
Viii Sanctuaries No bird or animal sanctuaries are existing in 10 Km radius
Ix Eco-Sensitive
Areas
No Eco Sensitive are existing in 10 Km radius
LANDSCAPE CHANGES:
During the first 5 years 6,438 M2 of the quarry lease applied area will be reduced by 18 M.
AIR QUALITY:
The project includes various quarrying operations involving
• Development of Benches
• Approach Roads
• Haul Roads
• Drilling
• Blasting
• Excavation and Transportation
These operations generally result in generation of dust and thereby pose health hazards. However,
adequate control measures will be provided at every stage of operation such as water sprinkling at
loading and unloading point and on haul roads before transportation to reduce the fugitive dust
emissions.
Pre Feasibility Report
Heavy Earth Moving Machinery like excavator, dumpers, dozer and other transport vehicles will
emit gaseous pollutants mainly CO and NOx.
The generation of dust is anticipated from various quarry activities i.e. drilling, blasting, loading,
haulage, unloading, and other activities related to quarry.
The increment in the fugitive emissions will be due to material handling and transportation
activity. These will be restricted to the lease area only by adopting water sprinkling, which will be
practiced at the quarry site to control air pollution load.
Ambient air quality standards promulgated by National Ambient Air Quality applicable to the
subject project are given below.
NAAQ STANDARDS
Pollutant Time Weighted Average
Concentration in
Ambient Air
Industrial, Residential,
Rural and Other Area
Sulphur Dioxide (SO2) Annual*
24 Hours**
50
80
Nitrogen Dioxide (NO2)
µg / M3
Annual*
24 Hours**
40
80
Particulate Matter (size
less than 10 µm ) or
PM10 µg / M3
Annual*
24 Hours**
60
100
Particulate Matter (size
less than 2.5 µm ) or
PM2.5 µg / M3
Annual*
24 Hours**
40
60
Dust levels will be higher within the active operational areas (quarry area) due to blasting and
transportation. However, in the buffer zone it is not likely to be affected by dust problems, when
proper dust suppression measures are taken.
Pre Feasibility Report
AIR QUALITY MANAGEMENT
The following measures will be adopted to mitigate air pollution generated due to the quarry
activities :
Water sprinkling while drilling
Rock breaker will be used for breaking over size boulders in order to reduce dust
and noise generation
Water spray on haulage roads & proper maintenance of haul roads will be done
Development of green belt around lease boundary, roads and other places will be
carried out to control the air pollution
Personal Protective Equipment like dust mask will be provided to all
employees working in the dusty areas
Proper maintenance of vehicles will be done to limit gaseous emissions
WATER QUALITY
Surface Water
There is no perennial surface water source in the quarry lease applied area. Ground water is the
source for the nearby habitation also.
Stone is non-toxic in nature. There will be no outside discharge of liquid effluent from the quarry
site.
GROUND WATER
Ground water pollution can take place only if the quarry rejects contain toxic substances, which
get leached by the precipitation water and percolate to the ground water table thus polluting
it. Any nearby wells or other sources of water can be rendered unfit for drinking and even for
industrial use.
This is not the case with this deposit as the stone or topsoil does not contain any harmful
ingredients. Moreover, stone constitutes of fairly inert and chemically non- reactive ingredients.
Water Pollution Control Measures
Pre Feasibility Report
No waste water will be generated during quarry operation
Garland drains all along the downstream boundary of the pit.
Rainwater falling in the quarry pit will flow based on the slope into the garland drain provided
with sedimentation pits.
Noise Levels
Noise generation is from operations at quarry development, excavation and transportation of
stone.
High noise levels will be confined to work zone areas only. Noise levels get diffused rapidly with
distance.
Noise impact is mainly restricted to the work zone areas. Hence, the noise levels impact due to the
quarry operations on community is insignificant.
Noise Control Measures
The following control measures will be adopted to keep the ambient noise levels well below the
limits.
Controlled blasting with proper spacing, burden, stemming and optimum charge / delay will be
maintained.
The blasting will be carried out during less human activity timings i.e. during lunch interval or
during change of shifts.
Proper maintenance, oiling and greasing of machines at regular intervals will be done.
Green belt and plantation will be developed wherever possible.
Vibration Levels
Ground vibration, fly rock, air blast, noise, dust and fumes are the effects of blasting on
environment. The seismic wave due to explosive energy in the ground can cause significant
damage to structures and disturbance to human occupants due to vibration.
The vibration/ Particle Velocity (Peak Particle Velocity) is measured in millimetre per second. The
standards for safe limit of PPV are established by Director General of Quarries Safety for safe level
Pre Feasibility Report
criteria through Circular No. 7 dated 29/8/1997. The safe level criteria PPV as mentioned in
Circular No. 7 of DGMS is presented below.
PERMISSIBLE PEAK PARTICLE VELOCITY (mm/s)
S.NO Type or Structure Dominant
<8Hz 8 - 25 Hz >25 Hz
A) Buildings / Structures not belonging to the owner
1. Domestic houses/ structures 5 10 15
2. Industrial Buildings 10 20 25
3. Objects of historical importance and 2 5 10
B) Buildings belonging to the owner with limited life span
1. Domestic houses/ structures 10 15 25
2. Industrial buildings 15 25 50
Blasting damage has been classified into four categories; and no appreciable damage occur when
PPV less than 17 mm / sec. So no effect is envisaged
EFFECT OF GROUND VIBRATION ON STRUCTURES
S.No. Category Description of Damage
1.
No
appreciable
damage
No formation of noticeable cracks
(PPV <17 mm / sec.)
Formation of fine cracks, fall of plaster, opening and lengthening
of old cracks, loosening of joints
2. Threshold Dislodging of loose objects, etc.
PPV – 17.75 mm / sec.)
3. Minor
Superficial not affecting the strength of structures – broken
windows. Hairline cracks in masonry around openings near
partition, broken windows. Fall of loose mortar etc. (PPV – 30
mm / sec).
4. Major
Formation of several large cracks, serious weakening of
structures, shifting of foundation, fall of masonry, ruptures of
opening vaults, etc. (PPV – 40 – 60 mm / sec)
Pre Feasibility Report
As the distance increases the PPV value is likely to reduce. The ground vibrations generated by
blasting during the quarry operations will be maintained well within standards prescribed by
DGMS by controlled blasting and optimum charge. Ground vibrations are not likely to affect the
structures in the vicinity of quarry lease area.
VIBRATIONS AND FLY ROCKS CONTROL MEASURES
The blasting operations will be carried out by drilling and blasting. The measures for abatement of
ground vibration, air blast and fly rocks are detailed below:
Blasting will be performed strictly as per the guidelines specified under MMR, 1961.
Proper design of blast with correct spacing, burden & optimum charge / delay
Supervision of drilling and blasting operations to ensure blast design geometry as per planning
Sub-drilling will be kept adequate to eliminate toe formation
Supervision of drilling and blasting operations to ensure blast design geometry
Sub-drilling will be kept just adequate to tear-off the bench bottom
Blasting operations will be carried out only during day time as per DGMS guidelines.
Proper warning signals will be used
Adequate safe distance from habitation as per standards from centre of blasting will be
maintained.
Drilling parameters like overburden, depth, diameter and spacing will be properly designed to
ensure proper blast.
Effective stemming of the explosives will be done in the drill holes.
Water Environment
The surface water environment will not be disturbed as the quarry is far off from the water
courses.
Acid Mine Drainage
No acids will be generated from Road Metal & Building Stone quarries
Surface Subsidence
No subsidence is anticipated in this regime as the basement rock is massive
Pre Feasibility Report
Socio Economics
The main occupation of villagers is agriculture and sheep raring. The commencement of quarrying
activity in this area improved the socio-economic status of the local people by creation of
employment and paying taxes to gram panchayath.
The quarrying in this area does not involve any hazardous methods. The quarrying will be Open
Cast Semi Mechanized Method. In this, the possibilities of small injuries is anticipated. The
applicant is providing First Aid facilities at quarry site.
Historical Monuments
No historical monuments exist within 5 Km radius
Bio-Diversity
No impact will happen to the Mankind, Flora and Fauna by the quarry operations, excepting minor
vibrations due to blasting, sound pollution and dust which will be under control and within the
permissible limits.
PROGRESSIVE RECLAMATION PLAN
The quarry lease applied area is part of hillock.
The pits will be utilized for water storage and water harvesting structure.
Year Pit No.
Mined out
area at the
beginning (Ha)
Additional area
proposed for
working in
the year (Ha)
Total Area (Ha)
Backfilling & Afforestation
in the year (Ha)
Mined out
area at the
end of the year (Ha)
1st 1 0.6597 0.5366 1.1963 - 1.1963
2nd 2 1.1963 (0.6500) (within the
pit in depth)
1.1963 - 1.1963
3rd 3 1.1963 (0.2689) (within the
pit
1.1963 - 1.1963
Pre Feasibility Report
in depth)
4th 4 1.1963 (0.2629) (within the
pit in depth)
1.1963 - 1.1963
5th 5 1.1963 (0.2787) (within the
pit in depth)
1.1963 - 1.1963
MINED OUT LAND
Land Use Pattern of the quarry area will be as follows :
CARE AND MAINTENANCE DURING TEMPORARY DISCONTINUANCE
The quarry workers are taken on contract basis on need based orders, the workers always get
Employment / Contract in similar quarries existing around. During monsoon these labour are busy
with agricultural activities.
Area M2 Hectares
Active Mine Area
Broken 6,597 0.6597
To be Broken (within the pit in depth)
5366 0.5366
TOTAL 11,963 1.1963
7.5 M Wide Safety Zone 3437 0.3437
Infrastructure (within the 7.5 M Buffer Zone)
(160) (0.016)
Roads (included in pit) (900) (0.090)
Dumps Existing Nil Nil
Proposed Nil Nil
TOTAL AREA UTILISED 11,963 1.1963
TOTAL MINE LEASE AREA 15,400 1.540
Pre Feasibility Report
ITEM DETAILS PROPOSED ACTUAL
Dump
Management
Area afforested (Ha)
1. No. of saplings planted
2. Cumulative no of plants
3. Cost including watch and care
during the year
Nil Nil
Area afforested
(ha) No. of
saplings
planted
Cumulative no
of plants Cost
including watch
and care during
the year
1. Area available for rehabilitation
(specify)
2. No of saplings planted in the
year
3. Cumulative no of plants
4. Any other method of
rehabilitation (specify)
5. Cost including watch and care
during the year
Plantation is
proposed all
along the
7.5 M Buffer
Zone
-
Reclamation
and
Rehabilitation
by backfilling
1. Void available for backfilling
(L x B x D) pit wise / stope wise
Void filled by waste / tailings
afforestation on the backfilled
area
2. Rehabilitation by making water
reservoir Any other means
(specify)
No back
filling is
proposed as
no
considerable
waste is
anticipated
to be
generated
-
Rehabilitation
of waste land
within lease
1. Area available (Ha)
2. Area rehabilitated
No
proposals
are made
-
Pre Feasibility Report
DETAILS OF AREA CONSIDERED FOR COMPUTATION OF FINANCIAL ASSURANCE
S.
N
o.
Head Area
put
on
use
at the
start
of
plan
(in
Ha.)
Additio
nal
require
ment
during
the plan
period
(in Ha.)
Total
(in
Ha.)
Area
consider
ed as
fully
reclaime
d and
rehabilit
ated
(in Ha.)
Net
area
consid
ered
for
calcula
tion (in
Ha.)
1 2 3 4 5 6 7
1 Area under
Mining
0.659
7
0.5366 1.196
3
- 1.1963
2 Storage for Top
Soil
Nil N.A. N.A. N.A.
3 Overburden /
Dump
Nil Nil Nil Nil
4 Mineral Storage Nil Nil Nil Nil
5 Infrastructure
(Workshop,
Administrative
Building etc.,)
Nil (0.016)
(within
the
7.5 M
BZ)
(0.01
6)
(withi
n the
7.5 M
BZ)
- (0.016)
(within
the
7.5 M
BZ)
6 Roads (0.09
0)
(inclu
ded
in pit)
Nil (0.09
0)
(inclu
ded
in pit)
- (0.090)
(includ
ed
in pit)
7 Railways Nil N.A. N.A. - N.A.
8 Green Belt Nil (0.075)
(within
the
7.5 M
BZ)
(0.07
5)
(withi
n the
7.5 M
BZ)
- (0.075)
(within
the
7.5 M
BZ)
9 Tailing Pond Nil N.A. N.A. - N.A.
10 Beneficiation
Plant
Nil - - - -
Pre Feasibility Report
11 Mineral
Separation Plant
Nil - - - -
12 Township Area Nil N.A. N.A. - N.A.
13 Oth
ers
Retai
ning
Wall
Nil Nil Nil - -
Fenci
ng
aroun
d the
pit in
lengt
h (M)
Nil (366 M) (366
M)
- (366
M)
GRAND TOTAL A B C =
(A +
B)
D E = (C-
D)
0.659
7
0.5366 1.196
3
- 1.1963