30
PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare Sy No. 7 Sompuram Village, Vepada Mandal, Vizianagaram District Andhra Pradesh Project Proponent SRI GANDRETI SEETHARAM S/o.Late Sanyasiappadu L.Kota Village & Mandal Vizianagaram District, Andhra Pradesh

PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

PRE-FEASIBILITY REPORT

M/s. SRI.GANDRETI SEETHARAM

Mining Project: Category ‘B2’

Area: 1.54 Hectare

Sy No. 7

Sompuram Village, Vepada Mandal,

Vizianagaram District

Andhra Pradesh

Project Proponent

SRI GANDRETI SEETHARAM

S/o.Late Sanyasiappadu

L.Kota Village & Mandal

Vizianagaram District, Andhra Pradesh

Page 2: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

ENVIRONMENT MANAGEMENT PLAN

FOR

M/s. SRI GANDRETI SEETHARAM

VILLAGE : Sompuram

TEHSIL : Vepada

DISTRICT : Andhra Pradesh

AREA : 1.54 Hectare

MINERAL : Road Metal & Building Stone

Sy No : 7

PRODUCTION CAPACITY : 41361.60 Cu.mt/year

APPLICANT

SRI GANDRETI SEETHARAM

S/o.Late Sanyasiappadu

L.Kota Village & Mandal

Vizianagaram District, Andhra Pradesh

Page 3: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Page 3 of 15

INTRODUCTION

Nature is very kind on the human to provide all kind of materials on earth. All kinds of minerals

are available in their raw form in the earth . Mining operations disturb the terrestrial configuration

and natural beauty of the area. The magnitude of disturbance depends upon how the minerals are

extracted from the mining area and the environmental impact depends upon the location and size

of deposits and the methods adopted for its exploration. By adopting good mining practices it is

moving towards harmonious development where both the operational and environmental

aspects are accorded due weightage.

Every quarry lease holder shall take all possible precautions for the protection of environment and

control of pollution while conducting quarry operation. Under the mining operation this

management plan is required.

The proposed quarry lease area named Sri Gandreti Seetharam of road metal and building stone

over an extent of 1.54 Ha. Located at Sy.No.7, Sompuram Village, Vepadu Mandal, Vizianagaram

District, Andhra Pradesh state submitted an application for grant of quarry lease. The asst. director

of mines and geology Vizianagaram vide File No. 8295/Q/2017 dated. 06.03.2018 submitted

proposals on the application duly recommending for grant of quarry lease in favour of Sri Gandreti

Seetharam, S/o. Late Sanyasappadu.

After careful examination of proposals the asst. director of mines and geology, Vizianagaram is

decided in principle for grant of quarry lease for road metal and building stone for the applied mine

for a period of 10 years subject to submission of approved mining plan with a condition that the

approved mining plan shall reflect the restrictions to be adopted by the application while quarry

operations. For the same the deputy director of mines & geology, Visakhapatnam sent a notice vide

939/Q3V/2018 dated.29.03.2018.

The approved mining plan prepared as per guidelines issued in Form T in G.O.Ms. No.56, Industries

& Commerce (MII) Department dated. 30.04.2016 under Rule 7A of APMMC Rules’ 1966 and

progressive mine closure plan underRule 23(B) of MCDR 1988 for the first five years period and

accordingly submitted & got approved by Deputy Director of Mines & Geology vide Letter

No.919/MP/VZM/2018 dated. 05.05.2018.

Page 4: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Page 4 of 15

NAME & ADDRESS OF SITE:

Sri. Gandreti Seetharam,

Sy.No.7, Sompuram Village,

Vepada Mandal, Vizianagaram District, A.P – 535579

NAME & ADDRESS OF LESSEE:

Sri. Gandreti Seetharam

S/o. Late Sanyasappadu,

L.Kota Village & Mandal,

Vizianagaram District, A.P – 535361

SALIENT FEATURES OF THE PROJECT:

Particulars Details

Name of the project Sri Gandreti Seetharam

Road Metal & Building Stone quarry

Location Sy.No.7, Sompuram Village, Vepadu Mandal, Vizianagaram

District, A.P.

Land use pattern Individual Owner

Mineral Road Metal & Building Stone

Mining Lease area 1.54 Hect.

Sy.No 7

Land Use Govt. Land

Lease Validity 10 Years

Production Capacity 41361.60 Cu.mt/year

Toposheet No. 65 N/4

Latitude& Longitude (1) 18°03'15.47"N, 83°07'18.16"E

(2) 18°03'14.57"N, 83°07'18.15"E

(3) 18°03'14.33”N, 83°07'16.47"E

(4) 18°03'11.02"N, 83°07'16.82"E

(5) 18°03'10.67"N, 83°07'13.50"E

Page 5: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Page 5 of 15

(6) 18°03'14.99"N, 83°07'13.04"E

Topography Hilly area

Method of mining Open cast semi mechanized

Estimated project cost 10 Lakhs

EMP Cost 1.0 Lakh

Man Power Total : 25 NOs

Mines manager – 01

Mine Supervisor – 1 No

Skilled workers – 6 Nos

Semi Skilled Workers – 6 Nos

Un Skilled workers – 11 Nos

No of working days 300 days per annum

Water demand and supply 4 KLD

Nearest habitation/town Ramaswamipeta village at a distance of 1.25 km

Vizianagaram town located at 40kms

Mandal Head Quarters Vepada is located a t 11.54 kms via seethampeeta road.

Nearest Airport The nearest Airport is Visakhapatnam which is about 42

kms from mine site.

Nearest Connectivity The quarry lease area can be approached from sompuram

village road, stat transport bus services ply from

srungaavarapu kota, vepada & vizianagaram.

Nearest Railway Station The nearest Railway Station is Lakkavarapu kota which is

about 6.5 kms from mine site.

Port Facility Visakhapatnam port about 52 km

Power Supply Electricity is available in all the villages and in the nearby

agricultural lands for bore wells.

DETAILS OF THE AREA

The details of the lease area to be grant, ownership etc. is as below:

Page 6: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Page 6 of 15

Whether area is recorded in forests : No

Existence of Public road : No public road passes

TOPO SHEET : Area falls in survey of India (65 N/4)

BOUNDARIES OF QUARRY :North – Hill

South – Hill & Water Body

East – Hill & Agricultural Lands

West – Hill & Agricultural Lands

No interlinked projects were associated with this project.

COORDINATES OF PROJECT AREA

S.No Latitude (N) Longitude (E)

1 18°03'15.47"N 83°07'18.16"E

2 18°03'14.57"N 83°07'18.15"E

3 18°03'14.33”N 83°07'16.47"E

4 18°03'11.02"N 83°07'16.82"E

5 18°03'10.67"N 83°07'13.50"E

6 18°03'14.99"N 83°07'13.04"E

Toposheet no. 65 N/4

District & State Tehsil Village Area in

hect.

Khasra

No.

Mineral

Name

Lease

Period

Vizianagaram

Andhra Pradesh

Vepada Sompuram 1.54 7 Building stone

and road metal

10Years

Page 7: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

TOPOMAP

Page 8: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Village Map:

Page 9: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Satellite Image/google image of the mining area:

of the mining area:

Page 10: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

TOPOGRAPHY:

The quarry lease applied area is located o a hillock with a maximum elevation of 50 m above ground

level within the quarry lease applied area with topo relief in NE direction. The lowest contour is 75 m

and the highest contour is 125 m in topo plan.

DRAINAGE:

Sub- Dendritic/Parallel Pattern in N-S direction

VEGETATION :

Sparse with tron bushes, areas around the barren rock land are cultivation lands.

CLIMATE:

The area is falling under tropical zone. The weather is hot and humid with a tropoical climate and

thereby no distinct seasons.

25 dec C in winter & 48 deg C in summer usually.

The wind direction is in SW to NE. The coolest months are December and January, when it is pleasant at

27 deg C to 30 deg C.

There is heavy monsoon rain at the end of summer with depression in the Bay of Bengal.

RAINFALL:

The average annual rainfall of the area is 1000mm

SOIL TYPE :

Heavy Soil

LAND USE PATTERNS :

Agriculture and Cultivated lands

Page 11: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

GEOLOGY AND EXPLORATION:

The eastern ghat mobile belt (EGMB) is more than 600 km in length form vizianagaram in the North to

Ongole in the South. This belt is more than 100 km in width in Northern part and tapers down to less

than 20 km in the south, it has broad actuated trend with westward convexity. The NNE-SSW trend in

the southern part of the belt changes NE-SW in the North. EGMB is divided into 3 longitudinal

zones viz.,

1. Western-Charnockitic Zone

2. Central – Khondalite Zone

3. Eastern – Migmatite Zone

While in the northern parts in Srikakulam, Vizianagaram & Visakhapatnam districts the central

Khondalite Zone occupies major part of the area. Whereas western Charnockite Zone occurs in the

Southern part. The rocks in this belt are represented High grade granulite facies of Metamorphism and

suffered by complex deformation. The stratigraphic succession of EGMB is as follows:

Recent Alluvium, Beach Sands, River Sand

Quarternary Laterite, Lateritic Soils

Upper Gondawana Sandstone with Interbedded Clays and Connglmorate

Easter Ghats Migmatitic Group

Super group

Charnokitic Derived Migmatites

Khondalite Derived Migmatites

Pre Cambrian Charnokite Group Hypersthene Gneiss

Pyroxene Gneiss

Khondalite Group Khondalite

Charnokitic/Gneissee

QUartzites

Intrusives Layered Anorthisites and associated mafics and chromiferrous ultra

mafics

Charnockite Group Charnockites with Mega Crystic K-Feldspar

Charnockite two pyroxene granulite/Amphiboites

Khondalite Group Calc-silicate-granulites

Page 12: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Garnet-silliminite-quartz-biotite—Feldspar-Graphite Gneiss

(Khondalite)

Quartzite –Garnet –Silliminite

Granitoid Suite Granitoid with Mega Crystic K-Feldspar undifferentiated (with

migmatitic dia textite, Augen) Perferoblastic granite and Gniesses.

Granet – Biotite Homophanus Granie /Gniess Leptynite, Local

Charnockite Neosomes and Relics

In vizianagaram district the EGMB is represented by vide range of litho units viz: Charnockites,

Khondalites, two pyroxene granulites, Migmatites, Leptynite and Intrusive Porphyroblastic

Charnockites. Large enclaves of Acid Charnockites, Khondalites and Meta Basic rocks occur within

Migmatites, which are largely seen in the area lying between R.Vamsadhara and Coast line.

DETAILED DESCRIPTION OF GEOLOGY AND LEASE AREA:

The present area is occupies by Charnockites, charckites is a garnet bearing quartz plagioclase

pyroxene, grey in color (Graniulite) with typical platly “Granoblastic”texture. This rock type might have

been derived from high-grade granulite facies metamorphism of a pile of volcanic intrusive. Tis rock

type is formed in N-S direction and this type of material is being excavated for road metal & Building

stone during previous years.

The material excavated from this area will be crushed as chips and the chips will be supplied to the

road works & building constructions. Accessory minerals like biotite and opaque cannot be identified

megascopically.

Entire quarry lease applied area is covered with road metal & building stone which is rising upto 50 m

above ground level trending SE-NW, the length of the exposed body measured 140 m in the area with

an average width of 99 m.

The road metal & building stone can be extracted from the rock available n the quarry lease applied

area which is useful in civil constructions purposes.

Page 13: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

DETAILS OF PROSPECTING CARRIED OUT:

1 old pit is existing in the quarry lease applied area .

Pit No Grids Area in sq.mtrs Avg depth in meters

1 N50-200 TO E00-150 6597 22.00

FUTURE PROGRAM OF EXPLORATION WITH DUE JUSTICIATION TAKING INTO CONSIDERATION

THE FUTURE TENTATIVE EXCAVATION PROGRAMME PLANNED IN FIRST FIVE YEARS :

Year No. of Bore Holes

(Core//RC/DTH)

Grid

Interval

Total

Meterage

No. of Pits

dimensions and

volume

No of trenches,

dimensions and

volume

1st N.A - - N.A N.A

2nd N.A - - N.A N.A

3rd N.A - - N.A N.A

4th N.A - - N.A N.A

5th N.A - - N.A N.A

Reserves and resources as per UNFC. Detailed calculation of reserves shall be stated:

TOTAL GEOLOGICAL RESERVES

Sections Category Sectional Area in

sq.mtrs

Sections

influence in

meters

Volume

A-A1 Proved 3624.00 99.00 358776.00

B-B1 Proved 1034 50.00 51700.00

TOTAL GEOLOGICAL RESERVES 410476.00

RESERVES BLOCKED UNDER 7.5M BUFFER ZONE

Sections Category Sectional Area in

sq.mtrs

Sections

influence in

meters

Volume

A-A1 Proved 573.00 99.00 56727.00

B-B1 Proved 558.00 50.00 27900.00

TOTAL BLOCKED 84627.00

Page 14: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

RESERVES BLOCKED UNDER SAFETY SLOPES

Sections Category Sectional Area in

sq.mtrs

Sections

influence in

meters

Volume

A-A1 Proved 587.00 99.00 58113.00

B-B1 Proved 275.00 50.00 13750.00

TOTAL BLOCKED 71863.00

RESERVES AVAILABLE FOR MINING:

TOTAL GEOLOGICAL RESERVES

A Geological Reserves 410476.00 M3

B Reserves Blocked under 7.5m buffer zone 84627.00 M3

C Reserves blocked under safety slopes 71863.00 M3

D Total reserves blocked (B+C) 156490.00 M3

E Reserves available for quarrying (A-(B+C)) 253986.00 M3

Extraction of Market grade reserves @100%

recovery

253986.00 M3

Life of the mine 253986.00 M3/41361.60 M3

6.15 Years

PROJECT DESCRIPTION WITH PROCESS DETAILS:

METHOD OF MINING:

The road metal & building stone in the quarry lease applied area is exposed on the surface with sheet.

Hence, it is proposed to quarry the sheet by open cast semi mechanized method by developing the

multiple benches of 6m height and with of 6m with drilling and blasting. The development of benches

in the sheet rock will be maintained 60o safety slopes under rules and regulations as per MMR 1961.

DRILLING:

Drill holes of 6m depth will be drilled in a staggered pattern at 3mx4m interval:

Drill hole dia : 54 mm upto 3-6.25 m long

Page 15: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Depth of inclination of drill hole : generally drilled vertically in an alignment

Explosive type : ANFO+Booster & Detonator Fuse

YEARWISE TENTATIVE EXCAVATION IN CUBIC METERS:

Year Pit

No

Total

tentative

excavation

Top

soil

OB/

SB/I

B

Rom from mineralized zone ROM

/WASTE

RATIO Clean ore Sub grade

ore

Mineral

rejects

M3 M3 M3 M3 M3 M3

1 2 3 4 5 6 7 8 9

1st 1 37548.00 Nil Nil 37548.00 Nil Nil 1:0

2nd 2 38388.00 Nil Nil 38388.00 Nil Nil 1:0

3rd 3 37968.00 Nil Nil 37968.00 Nil Nil 1:0

4th 4 46368.00 Nil Nil 46368.00 Nil Nil 1:0

5th 5 46536.00 Nil Nil 46536.00 Nil Nil 1:0

Total 206808.00 206808.00

Average 41361.60 41361.60

DUMP MANAGEMENT:

It is proposed to produce 206808.00 M3 of road metal and building stone aggregates during first 5 years

of plan period with an average annual production of 41361.60 M3. Multiple benches of 6m height and

6m width will be developed during the plan period as per MMR 1961.

STOCK YARD:

Temporary stocks will be maintained on day to day basis, entire ROM will be cleaed within days (i.e. 4

to 5 days).

QUARRYING PROGRAM FOR THE FIRST FIVE YEARS:

As per applicant purposed the quarry operations will start from south of the quarry lease area between

the grids N00-150 & E00-185 and between the RL 136-96 M to RL 55M. The excavation activity will be

Page 16: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

taken up in entire quarry lease applied area and advances northwards.

The volume calculations are made by the cross sectional area method discussed below:

YEAR ROAD METAL & BUILDING STONE

1st Mining from south of the quarry lease applied area covering the surface area of 447.00 M2

will be excavated producing 37458 M3 of road metal & building stone between the RL86-78

to RL70 and between the grids N00-100 to E00-150 covering sections A-A1, B-B1. The

workings advance northwards.

2nd The mining will contain due north of 1st year workings covering the surface area of 457.00

M2 will be excavated producing 38388 M3 of road metal & building stone between the

RL113-80m and between the grids N00-100 to E00-150 covering sections A-A1, B-B1. The

workings advance northwards.

3rd The mining will contain due north of 2nd year workings covering the surface area of 452.00

M2 will be excavated producing 37968.00 M3 of road metal & building stone between the

RL113-80m and between the grids N00-100 to E00-150 covering sections A-A1, B-B1. The

workings advance northwards.

4th The mining will contain due north of 3rd year workings covering the surface area of 552.00

M2 will be excavated producing 46368.00 M3 of road metal & building stone between the

RL70m to RL 55 m and between the grids N50-120 to E00-150 covering sections A-A1, B-

B1. The workings advance northwards.

5th The mining will contain due north of 4th year workings covering the surface area of 554.00

M2 will be excavated producing 46536.00 M3 of road metal & building stone between the

RL70m to RL 55 m and between the grids N00-70 to E00-150 covering sections A-A1, B-B1.

The workings advance northwards.

The year wise production proposed is shown in the following table:

YEAR WISE PRODUCTION FOR 5 YEARS

YEAR SECTIONAL

AREA IN

sq.mtrs

SECTIONAL

INFLUENCE

VOLUME RL’S

1 447.00 84.00 37548.00 RL 86-78 TO RL70

2 457.00 84.00 38388.00 RL113 TO RL80

Page 17: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

3 452.00 84.00 37968.00 RL 80 TO RL 55

4 552.00 84.00 46368.00 RL70 TO RL55

5 554.00 84.00 46536.00 RL70 TO RL 55

TOTAL 2465.00 206808.00

AVERAGE 492.40 41361.60

Quantum of Excavation: A total of 206808.00 m3 of road metal & building stone will be produced and

marketed during the first five years of plan period.

PRODUCTON SCHEDULE:

The production of road metal & building stone continuous throughout year except during monsoon.

That is 10 working months, 25 days per month are considered. The average production of 46536.80

cum.mtrs per year ( 300 days @ 155.12 cum.mtrs) can be easily achieved in a single shift with sufficient

men and machinery.

DRILLING AND BLASTING:

54 mm hammer drilling will be used for blasting holes in staggered pattern of 2 x 3m with depth of 6m.

each blast holes with 61 tons (24.40 cum.mtrs).

Proposed production per day @ 300 working

days per year

46536.80 cum mtrs

116342 tons max production

Drilling machine required with 54 mm drill rods.

Bench height 6.00 m

Spacing 3.00 m

Burden 4.00 m

Bulk density (insitu) 2.50

Depth of drilling 6.25 m

Yield per meter of drilling 3.00x4.00x6.25x2.50

187.50 tons (75 m3)

187.50 tons / 6.25 m

Page 18: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

30 tons ( 12 m3)

Rate of drilling 6m per hour

Drilling capacity per days with effective 6 hours 6x6= 36

Rate of production per day 1080 tons ( 432 m3)

Requirement of drilling per day for 155.12 m3 (

486.38 tons)

387.8 tons / 1080 tons

0.36 or say 1

No. of meters required 387.80 tons/30 tons

12.92 mtrs

No. of machines required per day considering 80%

availability

12.92/36 = 0.36 or say 1 machine

EXTENT OF MECHANIZATION:

S.No Machinery No’s

1 Excavator 1

2 Drilling Machines 1

3 Tractor with trailers 2

MINE DRAINAGE:

A Minimum and maximum depth of water table Shallow aquifers during monsoon period

and canal flows.

B Indicate maximum and minimum depth of

workings

RL 113-70 M to RL 55 m

C Quantity and Quality of water Portable

D Regional Drainage Pattern Sub-Dendritic

STOCKING OF MINERAL REJECTS / SUB GRADE MATERIAL AND DISPOSAL OF WASTE

Not applicable as no mineral rejects / sub grade material is anticipated.

USE OF MINERALS:

The rock quarried out will be utilized for construction of structures and for formation of roads. No

mineral rejects are anticipated.

PROCESSINGS OF ROM AND MINERAL REJECTS:

Page 19: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

The rock excavated in large sizes will be subjected to crushing and sizing to various sizes as suitable to

construction and road formation.

EMPLOYMENT:

S.No Category No. of Persons

1 Mines Manger 1

2 Mine supervisor 1

3 Skilled Workers 6

4 Semi skilled workers 6

5 Un skilled workers 11

PROGRESSIVE MINE CLOSURE PLAN

I Existing Land

Use Pattern

The quarry lease applied area is surrounded by barren lands and low level

hillocks comprising Road Metal & Building Stone of good quality. The

surrounding area of the quarry lease applied area are quarries for Road Metal

& Building Stone and beyond are agricultural lands

Ii Water Regime

The subject area is located on a hillock and the surrounding areas around are

agricultural lands.

The ground water occurs under confined conditions in both hard rock and

alluvium which are shallow in nature.

No impact on surface water or ground water is foreseen due to quarry

operations.

Iii Flora and Fauna

The whole area is occupied by scattered sparse vegetation of thorny trees and

small bushes. In the quarry lease applied area no wild animals are witnessed

as per the statements collected from the local population, since 50 years

Iv

Quality of Air,

Ambient Noise

Level and

Water

Air quality is good but at quarries it is filled with dust, due to haulage on the

road, blasting etc.

The noise generated mostly due to blasting, drilling, vehicular traffic

Road Metal & Building Stone quarrying will not affect water quality.

v Climatic The area is falling under tropical zone. The area is having Humid climate. The

Page 20: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Conditions temperature recorded in this area is 25°C in winter and about 48°C in summer

seasons. The wind direction is in SW to NE. The average annual rainfall of the

area is 1000 mm.

Vi Human

Settlement

The nearest village Ramaswamipeta is situated 1.250Km due NE of the quarry

lease applied area, having approximately population of 400 No’s. Agriculture

and sheep breeding are important profession of the people living in the village

besides involving themselves in quarrying activity.

Vii

Public

Buildings,

Places &

Monuments

No public buildings, important places and monuments are seen in and around

the quarry lease applied area. The applicant will adopt the safety measures

while conducting the quarry operations as per the Regulations of

Metalliferrous Mines Regulation 1961

Viii Sanctuaries No bird or animal sanctuaries are existing in 10 Km radius

Ix Eco-Sensitive

Areas

No Eco Sensitive are existing in 10 Km radius

LANDSCAPE CHANGES:

During the first 5 years 6,438 M2 of the quarry lease applied area will be reduced by 18 M.

AIR QUALITY:

The project includes various quarrying operations involving

• Development of Benches

• Approach Roads

• Haul Roads

• Drilling

• Blasting

• Excavation and Transportation

These operations generally result in generation of dust and thereby pose health hazards. However,

adequate control measures will be provided at every stage of operation such as water sprinkling at

loading and unloading point and on haul roads before transportation to reduce the fugitive dust

emissions.

Page 21: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Heavy Earth Moving Machinery like excavator, dumpers, dozer and other transport vehicles will

emit gaseous pollutants mainly CO and NOx.

The generation of dust is anticipated from various quarry activities i.e. drilling, blasting, loading,

haulage, unloading, and other activities related to quarry.

The increment in the fugitive emissions will be due to material handling and transportation

activity. These will be restricted to the lease area only by adopting water sprinkling, which will be

practiced at the quarry site to control air pollution load.

Ambient air quality standards promulgated by National Ambient Air Quality applicable to the

subject project are given below.

NAAQ STANDARDS

Pollutant Time Weighted Average

Concentration in

Ambient Air

Industrial, Residential,

Rural and Other Area

Sulphur Dioxide (SO2) Annual*

24 Hours**

50

80

Nitrogen Dioxide (NO2)

µg / M3

Annual*

24 Hours**

40

80

Particulate Matter (size

less than 10 µm ) or

PM10 µg / M3

Annual*

24 Hours**

60

100

Particulate Matter (size

less than 2.5 µm ) or

PM2.5 µg / M3

Annual*

24 Hours**

40

60

Dust levels will be higher within the active operational areas (quarry area) due to blasting and

transportation. However, in the buffer zone it is not likely to be affected by dust problems, when

proper dust suppression measures are taken.

Page 22: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

AIR QUALITY MANAGEMENT

The following measures will be adopted to mitigate air pollution generated due to the quarry

activities :

Water sprinkling while drilling

Rock breaker will be used for breaking over size boulders in order to reduce dust

and noise generation

Water spray on haulage roads & proper maintenance of haul roads will be done

Development of green belt around lease boundary, roads and other places will be

carried out to control the air pollution

Personal Protective Equipment like dust mask will be provided to all

employees working in the dusty areas

Proper maintenance of vehicles will be done to limit gaseous emissions

WATER QUALITY

Surface Water

There is no perennial surface water source in the quarry lease applied area. Ground water is the

source for the nearby habitation also.

Stone is non-toxic in nature. There will be no outside discharge of liquid effluent from the quarry

site.

GROUND WATER

Ground water pollution can take place only if the quarry rejects contain toxic substances, which

get leached by the precipitation water and percolate to the ground water table thus polluting

it. Any nearby wells or other sources of water can be rendered unfit for drinking and even for

industrial use.

This is not the case with this deposit as the stone or topsoil does not contain any harmful

ingredients. Moreover, stone constitutes of fairly inert and chemically non- reactive ingredients.

Water Pollution Control Measures

Page 23: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

No waste water will be generated during quarry operation

Garland drains all along the downstream boundary of the pit.

Rainwater falling in the quarry pit will flow based on the slope into the garland drain provided

with sedimentation pits.

Noise Levels

Noise generation is from operations at quarry development, excavation and transportation of

stone.

High noise levels will be confined to work zone areas only. Noise levels get diffused rapidly with

distance.

Noise impact is mainly restricted to the work zone areas. Hence, the noise levels impact due to the

quarry operations on community is insignificant.

Noise Control Measures

The following control measures will be adopted to keep the ambient noise levels well below the

limits.

Controlled blasting with proper spacing, burden, stemming and optimum charge / delay will be

maintained.

The blasting will be carried out during less human activity timings i.e. during lunch interval or

during change of shifts.

Proper maintenance, oiling and greasing of machines at regular intervals will be done.

Green belt and plantation will be developed wherever possible.

Vibration Levels

Ground vibration, fly rock, air blast, noise, dust and fumes are the effects of blasting on

environment. The seismic wave due to explosive energy in the ground can cause significant

damage to structures and disturbance to human occupants due to vibration.

The vibration/ Particle Velocity (Peak Particle Velocity) is measured in millimetre per second. The

standards for safe limit of PPV are established by Director General of Quarries Safety for safe level

Page 24: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

criteria through Circular No. 7 dated 29/8/1997. The safe level criteria PPV as mentioned in

Circular No. 7 of DGMS is presented below.

PERMISSIBLE PEAK PARTICLE VELOCITY (mm/s)

S.NO Type or Structure Dominant

<8Hz 8 - 25 Hz >25 Hz

A) Buildings / Structures not belonging to the owner

1. Domestic houses/ structures 5 10 15

2. Industrial Buildings 10 20 25

3. Objects of historical importance and 2 5 10

B) Buildings belonging to the owner with limited life span

1. Domestic houses/ structures 10 15 25

2. Industrial buildings 15 25 50

Blasting damage has been classified into four categories; and no appreciable damage occur when

PPV less than 17 mm / sec. So no effect is envisaged

EFFECT OF GROUND VIBRATION ON STRUCTURES

S.No. Category Description of Damage

1.

No

appreciable

damage

No formation of noticeable cracks

(PPV <17 mm / sec.)

Formation of fine cracks, fall of plaster, opening and lengthening

of old cracks, loosening of joints

2. Threshold Dislodging of loose objects, etc.

PPV – 17.75 mm / sec.)

3. Minor

Superficial not affecting the strength of structures – broken

windows. Hairline cracks in masonry around openings near

partition, broken windows. Fall of loose mortar etc. (PPV – 30

mm / sec).

4. Major

Formation of several large cracks, serious weakening of

structures, shifting of foundation, fall of masonry, ruptures of

opening vaults, etc. (PPV – 40 – 60 mm / sec)

Page 25: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

As the distance increases the PPV value is likely to reduce. The ground vibrations generated by

blasting during the quarry operations will be maintained well within standards prescribed by

DGMS by controlled blasting and optimum charge. Ground vibrations are not likely to affect the

structures in the vicinity of quarry lease area.

VIBRATIONS AND FLY ROCKS CONTROL MEASURES

The blasting operations will be carried out by drilling and blasting. The measures for abatement of

ground vibration, air blast and fly rocks are detailed below:

Blasting will be performed strictly as per the guidelines specified under MMR, 1961.

Proper design of blast with correct spacing, burden & optimum charge / delay

Supervision of drilling and blasting operations to ensure blast design geometry as per planning

Sub-drilling will be kept adequate to eliminate toe formation

Supervision of drilling and blasting operations to ensure blast design geometry

Sub-drilling will be kept just adequate to tear-off the bench bottom

Blasting operations will be carried out only during day time as per DGMS guidelines.

Proper warning signals will be used

Adequate safe distance from habitation as per standards from centre of blasting will be

maintained.

Drilling parameters like overburden, depth, diameter and spacing will be properly designed to

ensure proper blast.

Effective stemming of the explosives will be done in the drill holes.

Water Environment

The surface water environment will not be disturbed as the quarry is far off from the water

courses.

Acid Mine Drainage

No acids will be generated from Road Metal & Building Stone quarries

Surface Subsidence

No subsidence is anticipated in this regime as the basement rock is massive

Page 26: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

Socio Economics

The main occupation of villagers is agriculture and sheep raring. The commencement of quarrying

activity in this area improved the socio-economic status of the local people by creation of

employment and paying taxes to gram panchayath.

The quarrying in this area does not involve any hazardous methods. The quarrying will be Open

Cast Semi Mechanized Method. In this, the possibilities of small injuries is anticipated. The

applicant is providing First Aid facilities at quarry site.

Historical Monuments

No historical monuments exist within 5 Km radius

Bio-Diversity

No impact will happen to the Mankind, Flora and Fauna by the quarry operations, excepting minor

vibrations due to blasting, sound pollution and dust which will be under control and within the

permissible limits.

PROGRESSIVE RECLAMATION PLAN

The quarry lease applied area is part of hillock.

The pits will be utilized for water storage and water harvesting structure.

Year Pit No.

Mined out

area at the

beginning (Ha)

Additional area

proposed for

working in

the year (Ha)

Total Area (Ha)

Backfilling & Afforestation

in the year (Ha)

Mined out

area at the

end of the year (Ha)

1st 1 0.6597 0.5366 1.1963 - 1.1963

2nd 2 1.1963 (0.6500) (within the

pit in depth)

1.1963 - 1.1963

3rd 3 1.1963 (0.2689) (within the

pit

1.1963 - 1.1963

Page 27: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

in depth)

4th 4 1.1963 (0.2629) (within the

pit in depth)

1.1963 - 1.1963

5th 5 1.1963 (0.2787) (within the

pit in depth)

1.1963 - 1.1963

MINED OUT LAND

Land Use Pattern of the quarry area will be as follows :

CARE AND MAINTENANCE DURING TEMPORARY DISCONTINUANCE

The quarry workers are taken on contract basis on need based orders, the workers always get

Employment / Contract in similar quarries existing around. During monsoon these labour are busy

with agricultural activities.

Area M2 Hectares

Active Mine Area

Broken 6,597 0.6597

To be Broken (within the pit in depth)

5366 0.5366

TOTAL 11,963 1.1963

7.5 M Wide Safety Zone 3437 0.3437

Infrastructure (within the 7.5 M Buffer Zone)

(160) (0.016)

Roads (included in pit) (900) (0.090)

Dumps Existing Nil Nil

Proposed Nil Nil

TOTAL AREA UTILISED 11,963 1.1963

TOTAL MINE LEASE AREA 15,400 1.540

Page 28: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

ITEM DETAILS PROPOSED ACTUAL

Dump

Management

Area afforested (Ha)

1. No. of saplings planted

2. Cumulative no of plants

3. Cost including watch and care

during the year

Nil Nil

Area afforested

(ha) No. of

saplings

planted

Cumulative no

of plants Cost

including watch

and care during

the year

1. Area available for rehabilitation

(specify)

2. No of saplings planted in the

year

3. Cumulative no of plants

4. Any other method of

rehabilitation (specify)

5. Cost including watch and care

during the year

Plantation is

proposed all

along the

7.5 M Buffer

Zone

-

Reclamation

and

Rehabilitation

by backfilling

1. Void available for backfilling

(L x B x D) pit wise / stope wise

Void filled by waste / tailings

afforestation on the backfilled

area

2. Rehabilitation by making water

reservoir Any other means

(specify)

No back

filling is

proposed as

no

considerable

waste is

anticipated

to be

generated

-

Rehabilitation

of waste land

within lease

1. Area available (Ha)

2. Area rehabilitated

No

proposals

are made

-

Page 29: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

DETAILS OF AREA CONSIDERED FOR COMPUTATION OF FINANCIAL ASSURANCE

S.

N

o.

Head Area

put

on

use

at the

start

of

plan

(in

Ha.)

Additio

nal

require

ment

during

the plan

period

(in Ha.)

Total

(in

Ha.)

Area

consider

ed as

fully

reclaime

d and

rehabilit

ated

(in Ha.)

Net

area

consid

ered

for

calcula

tion (in

Ha.)

1 2 3 4 5 6 7

1 Area under

Mining

0.659

7

0.5366 1.196

3

- 1.1963

2 Storage for Top

Soil

Nil N.A. N.A. N.A.

3 Overburden /

Dump

Nil Nil Nil Nil

4 Mineral Storage Nil Nil Nil Nil

5 Infrastructure

(Workshop,

Administrative

Building etc.,)

Nil (0.016)

(within

the

7.5 M

BZ)

(0.01

6)

(withi

n the

7.5 M

BZ)

- (0.016)

(within

the

7.5 M

BZ)

6 Roads (0.09

0)

(inclu

ded

in pit)

Nil (0.09

0)

(inclu

ded

in pit)

- (0.090)

(includ

ed

in pit)

7 Railways Nil N.A. N.A. - N.A.

8 Green Belt Nil (0.075)

(within

the

7.5 M

BZ)

(0.07

5)

(withi

n the

7.5 M

BZ)

- (0.075)

(within

the

7.5 M

BZ)

9 Tailing Pond Nil N.A. N.A. - N.A.

10 Beneficiation

Plant

Nil - - - -

Page 30: PRE-FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/District/pfr/...PRE-FEASIBILITY REPORT M/s. SRI.GANDRETI SEETHARAM Mining Project: Category ‘B2’ Area: 1.54 Hectare

Pre Feasibility Report

11 Mineral

Separation Plant

Nil - - - -

12 Township Area Nil N.A. N.A. - N.A.

13 Oth

ers

Retai

ning

Wall

Nil Nil Nil - -

Fenci

ng

aroun

d the

pit in

lengt

h (M)

Nil (366 M) (366

M)

- (366

M)

GRAND TOTAL A B C =

(A +

B)

D E = (C-

D)

0.659

7

0.5366 1.196

3

- 1.1963