93
1 sr. no. Particulars Pg no. 1 Introduction to precast concrete 3 2 Types and procedure of precast concrete construction 12 3 Precast technology in residential building 21 4 Case study on the precast technology in “Bandra worli sea link (BWSL)” 68 5 Research paper study on the “future of precast technology in law rise building” 94

Precast technology with the case study of BWSL

Embed Size (px)

DESCRIPTION

this is the report on the precast technology in const. industry .

Citation preview

  • 1

    sr. no. Particulars Pg no.

    1

    Introduction to precast concrete

    3

    2

    Types and procedure of precast concrete construction

    12

    3

    Precast technology in residential building

    21

    4

    Case study on the precast technology in Bandra worli

    sea link (BWSL)

    68

    5

    Research paper study on the future of precast

    technology in law rise building

    94

  • 2

    Precast technology

    Subject: Advanced construction practice

    Topic: Precast technology

    Prepared by: Hardik Patel (PT101214)

    Guided by: Prof. Jyoti Trivedi

    Dr. Ganesh Devkar

    Date: 7th oct. 2014

  • 3

    Precast Concrete

    Introduction to precast concrete

    Types and procedure of precast concrete construction

    Precast technology in residential building

    Case study on the precast technology in Bandra worli

    sea link (BWSL)

    Research paper study on the future of precast

    technology in law rise building

    Video on manufacturing of precast wall

    Video on installation of precast modular pavement

  • 4

    Precast Concrete

    Precast concrete is a construction

    product produced by casting concrete in

    a reusable mould or "form" which is then

    cured in a controlled environment,

    transported to the construction site and

    lifted into place. In contrast, standard

    concrete is poured into site-specific

    forms and cured on site.

  • 5

    History

    precast paneled buildings were pioneered

    in Liverpool England, in 1905

    A process was invented by city engineer John

    Alexander Brodie.

    Between 1917 and 1932, they erected 145

    such buildings

  • 6

    Why Precast???

    Speed to market

    Strong image

    High quality

    Low maintenance

    Effective pricing

    Safety

    Early input

  • 7

    Why precast ?? As a

    Project Manager Elimination of needs for supports / scaffolding

    Elimination of temporary structures

    Reduced health and safety risks

    Reduction in lorry traffic and traffic management

    Easier management of steel procurement

    Elimination for long and continuous pouring operations

    Significant reduction/elimination of temporary shuttering

    Controlled curing of concrete

    Improved quality controls performed at the factory

    Process not subjected to weather conditions

  • 8

    Precast concrete Products

    Agricultural Products

    Building and Site Amenities

    Retaining Walls

    Sanitary and Storm water

    Utility Structures

    Water and Wastewater Products

    Transportation and Traffic Related Products

    Modular Paving

    Marine Products

  • 9

    Raw Materials

    Portland cement

    water

    Sand

    Gravel

    admixtures

    For light weight

    clay, shale, or slate

    pumice and scoria blast furnace

  • 10

    Design

    The shapes and sizes of most common concrete blocks have been standardized to ensure uniform building construction.

    block design, called a split-faced block, includes a rough, stone-like texture on one face of the block instead of a smooth face

    we must consider not only the desired shape, but also the manufacturing process required to make that shape

    We must consider the utility facility requirements in building during design

  • 11

    Procedure for

    precast

    manufacturing

  • 12

    Procedure for precast construction

    Production of reinforced cages and main connections

    Assembly of moulds

    Mix being poured

    Compaction of concrete using poker vibrator

    Precast concrete being moved to the storage area

    Storage of high-quality units in storage area

    Transport to site

    Erection at site

    Finished building

  • 13

    Production of reinforced cages and

    main connections

  • 14

    Assembly of moulds

  • 15

    Mix being poured

  • 16

    Compaction of concrete using poker

    vibrator

  • 17

    Precast concrete being moved to the

    storage area

  • 18

    Storage of high-quality units in

    storage area

  • 19

    Transport to site

  • 20

    Erection at site

  • 21

    Types of precast construction

    Large-panel systems

    Frame systems

  • 22

    Large-Panel Systems

    The designation large-panel system refers to multistory structures composed of large wall and floor concrete panels connected in the vertical and horizontal directions so that the wall panels enclose appropriate spaces for the rooms within a building. These panels form a box-like structure

  • 23

    Large panel

  • 24

  • 25

    Frame Systems

    Precast frames can be constructed using either linear

    Elements or spatial beam-column sub assemblages.

    Precast beam-column sub assemblages have the advantage that the connecting faces between the sub assemblages can be placed away from the critical frame regions; however, linear elements are generally preferred because of the difficulties associated with forming, handling, and erecting spatial elements.

    The use of linear elements generally means placing the connecting faces at

    the beam-column junctions.

  • 26

    Installation CONSIDERATIONS

    All safety issues on site when handling precast elements,

    especially so when working within a tight site

    The lifting capacity of the crane used

    The working boom-radius of the crane

    The suitability of construction materials for the purpose of use,

    i.e. sealant, grouting, shim plate, propping etc

    Co-ordination with the precaster and specialist supplier to achieve the best performance and working method - precaster often provide relevant technical requirements to the contractor during the design development phase to avoid discrepancy

  • 27

    Crane Position

  • 28

  • 29

    Setting Out

    1. Surveyor to set cross reference.

    2. Transfer grid and mark wall position on slab.

    3. Mark 100mm offset line from rear building

    edge.

    4. Offset wall position by 200 mm.

    5. Secure 2x2 timber to the floor at wall edge to guide wall.

  • 30

    Setting Out

  • 31

  • 32

    Wall Positioning

    1. The first wall in place has to be the partition wall

    at the rear.

    2. Mark a line parallel to and 100mm from the

    external edge of the wall.

    3. Place shim plate @~500 c/c on the floor and

    level to wall soffit. Shim plate may also be

    placed on Non-shrink mortar bed and allow to

    set.

    4. Adjust position of the dowel bar.

  • 33

    Setting Out

  • 34

  • 35

    Wall Adjustment

    1. Position adjacent walls and plumb wall corners

    at 200 mm offset

    2. Adjust verticality until within +2 or 2 mm

    3. Ensure the four faces of every walls are

    adjusted

    4. Position string 250 mm from face of walls

    5. Walls within the same line are to be adjusted

    within same tolerance

    6. Ensure air-pocket is fully grouted

  • 36

    Wall Adjustment

  • 37

  • 38

    Beam Setting Out

    1. Cast wall joint.

    2. Mark 1 m reference line.

    3. Confirm pocket level. Position shim plate to

    correct beam soffit level if required.

    4. Mark position of beam on floor.

    5. Hoist beam in place and check top level.

    6. Plumb beam to verify position on floor below.

    7. Ensure beam verticality with a spirit level.

    8. Wedge beam against pocket and grout the

    gap between the beam and the wall.

  • 39

    Beam Setting Out

  • 40

  • 41

    Slab Setting Out

    1. Position the slab temporary supports and

    adjust the slab soffit level approximately.

    2. Raise the height of the supports about 5 mmabove slab

    soffit level

    3.Hoist slab in place on top of beam and support.

    4.Verify level of every plank soffit at four corners

    and center.

    5. Adjust level of temporary support accordingly

  • 42

    Slab Setting Out

  • 43

    Staircase

    1. Position landing or slab and verify soffit

    level at four corners.

    2. Adjust level to within tolerance.

    3. Position shim plates at staircase support

    location to correct level.

    4. Verify level difference between pegs on

    top and below.

    5. Hoist staircase in place.

    6. 10mm gap between precast plank andstaircase

  • 44

    Staircase

  • 45

  • 46

    Installation Requirements

    Elements of control

    Alignment, Verticality and Levels

    Tolerance level

    1. For Wall

    Vertical deviation +2 mm, -2 mm

    Horizontal deviation 0 mm

    2. For Beam & Slab

    Departure from intended horizontal position, +2 mm or 2 mm

    Departure from intended vertical position, +2 mm or 2 mm

  • 47

    Connection types

  • 48

  • 49

    Columns Connection

  • 50

  • 51

    Beam-column connection

  • 52

  • 53

    Slab-Beam Connection

  • 54

  • 55

    CONSTRAINTS SOLUTIONS

    ! Small road in front of site may not !

    allow crane and delivery trailers up to 3.Sm wide to

    park.

    Use smaller crane and trailers to deliver and

    install small

    components.

    ! Crane and trailer are unable negotiate small

    turning radius junctions of small roads.

    to ! Study the locality and look for at available space

    for turning. Have one worker direct traffic while crane

    and trailer is turning.

    ! Diversion of existing services such ! as

    lamp-posts, fire hydrants and overhead electrical

    cables may be necessary.

    ! Existing trees and shrubs in front ! of

    site require National Parks Board

    approval before they can

    be removed and later reinstated.

    Diversion must be done before installation of precast

    components begins.

    The consultants must write in to National Parks

    Board for approval much earlier before construction

    begins.

  • 56

  • 57

  • 58

    Cost saving

  • 59

  • 60

    Time saving

  • 61

  • 62

    Time comparision

  • 63

    Material saving

  • 64

    Limitations

    Each panel variation (especially openings, bracing inserts and lifting inserts) calls for complex, specialized

    engineering design.

    It is often more expensive than alternatives (can be offset by reduced construction times, earlier access by following

    trades, and simplified finishing and services installation).

    Building services (power, water and gas outlets; conduits and pipes) must be accurately cast in and are difficult to add or alter later. This requires detailed planning and layout at design stage when plumbing and electrical trades are not usually involved.

    Erection requires specialized equipment and trades.

    High level site access required

    Panel connection and layout for lateral bracing requires detailed design.

    Temporary bracing requires floor and wall inserts that have to be repaired

    later.

  • 65

    Research paper study

    The Future for Precast Concrete in Low-Rise Housing

    by. Dr Jacqueline Glass (BA (Hons), Dip Arch, Dip BRS, Phd, CertHE.)

    Dr Jacqueline Glass is the British Cement Association Senior Lecturer in the School of Architecture at Oxford Brookes University where she has been carrying out research in concrete construction since 1994. Dr Glass is currently Project Manager of an EPSRC funded research project in innovation in reinforced concrete and has previously contributed to Partners in Technology projects on tilt-up and hybrid concrete construction. Dr Glass is Architectural Consultant to the British Cement Association and the Reinforced Concrete Council and is an active participant on several concrete industry trade associations. She has published widely in both trade journals and scholarly publications and has lectured in the UK and USA on a broad range of concrete related topics.

  • 66

    The Future for Precast Concrete in

    Low-Rise Housing

    This report is about the future use of precast concrete in low-rise housing in the UK. It has been produced in response to a growing level of interest in prefabrication.

    focuses on the use of precast concrete, and considers the history of precast concrete in housing

    examines the key features of concrete in general, and precast concrete specifically. Fire resistance, thermal mass, acoustic insulation and durability are included together with a discussion of cost and value issues

    considerations such as services integration and adaptability are related to the future needs of occupants, and procurement strategies are noted.

    Report also contains an account of the current market success of

    other materials in the prefabricated housing sector

  • 67

    Conclusions and recommendations

    1. The problems of the past can be avoided

    2. Low-rise is not high rise

    3. Cultural and perceptual views are critical

    4. The market potential for precast concrete exists

    5. The balance of cost and value needs to be clear

    6. Precast means innovation in delivery

    7. People need to be convinced

  • 68

    Case study on

    Precast deck of

    BWSL

  • 69

    Why precast segmental deck????

    Total length : 5.6 kilometres

    Width : 2 x 20 meters (66 ft)

    Height :126 meters (413 ft)

    Longest span :2 x 250 meters (820 ft)

    Clearance below :20 meters (66 ft)

    The Maritime Board does not allow marine traffic in monsoon

    season.

  • 70

    Decision for precast segmental

    construction

    800m long Precast Segmental Approach Bridge on

    Bandra Side.

    200m long Precast Segmental Approach Bridge between Bandra Cable Stayed Bridge and Worli Cable Stayed Bridge.

    1400m Precast Segmental Approach Bridge on Worli

    Side.

    811m long link to Khan Abdul Ghaffar Khan Road

    comprising 510m Precast Segmental Bridge and

    310m Cast-in-Situ Bridge.

  • 71

    SAGMENT PARAMETERS

    a hollow concrete box section with 3 cores

    Length:1.5m to 3.1m.

    post tensioned

    slender and lightweight deck is to reduce the longitudinal

    stiffness

    pre-casting yard using short line method

    A typical 50m span comprises of 15 numbers of precast

    segments, a Pier segment and 200mm (nominal) in-situ wet

    joints

    8 cells to makes all the different types of segments.

    centralized pre-casting yard using short line method of casting

    Sophisticated software for correct casting curves

    A complete construction of a segment takes about a month (20

    to 30 days)

  • 72

  • 73

    60

  • 74

    Segment Construction Procedure

    survey team sets the bulkhead, the rebar setup

    takes place

    After rebar setup is done, the concrete is poured in the

    formwork

    initial tensioning about 30% of its maximum capacity

    After strength of about 40Mpa final testing with rest of

    the 70% load

    Shifted to store at yard

    Transported by trailer truck to site

    Transported by barge in the sea

    Erection by gantry

  • 75

    Connection of male-female segment with wet concrete

  • 76

    equipments which deployed in

    the pre-casting yard

    1) Hydraulic Jacks of different capacities

    2) Turn Buckles

    3) Gantry, for lifting segments

    4) Tower Crain

    5) Concrete Pumps

    6) Cutting and bending machines for rebar of

    segments.

  • 77

  • 78

    Formwork and rebar setup

  • 79

  • 80

    A segment being cast and its conjugate

    65

  • 81

    Casting Yard

  • 82

  • 83

  • 84

    Erection of segment

    The precast concrete sections of the deck were launched incrementally between the pillars using a truss system, known as the balanced cantilever method

    The two segments are being linked through a male-female joint, in the meanwhile the casted segment is allowed to gain strength and also its curing is done side by side.

    The precast sections were then epoxied together and given a certain degree of pre-stress to hold them in place

    Once each span had completed and geometrical adjustments made the primary continuous tendons were stressed to the required level.

  • 85

    Equipments which deployed in the

    erection

    Launching Truss: Weighing 1250 tonnes and measuring 112 m in length, it was used for lifting segments each weighing 130 tonnes. This has been fabricated in India.

    Flat barge: Size 30x12x2m. Like motor boats, they are driven inside the sea for material transportation.

    Self-propelled barge: It is a barge with a machine component and is

    used for concrete transportation.

    Crawler crane: Capacity ranges from 75-150 tons. It is used for material and heavy lifting activities. 13 barges for concrete

    eight steel boats

    three tug boats

    six smaller passenger boats.

  • 86

    The Erection Gantry

  • 87

    71

  • 88

    Erection of segment

  • 89

    72

  • 90

  • 91

    Challenge of Ground Stabilisation for Pre-Cast Yard

    located on reclaimed land

    yard caters to casting, storing and handling of pre-

    cast Segments

    numbers of segments 2342

    The storage capacity of yard 470nos.

    Area is limited, the segments stored in three layers.

    The bearing capacity of the ground was was very

    poor to less than2 T/Sqm.

  • 92

    Solution

    Excavation of the ground to a depth of ~

    2.5Mtrs.

    Strengthening the ground using rubble soling

    and filling the voids with sand.

    The soling thus done was compacted layer by

    layer using vibratory rollers.

    Total area of the Pre-cast Yard was covered with

    a layer of PCC.

    RCC Footing done to facilitate storing of

    segments.

  • 93

    Challenges for project manager

    The superstructure of the approach bridges was the heaviest spans in the country to be built with span-by-span method using overhead gantry through a series of vertical and horizontal curves.

    Erection of 20000 MT Bandra cable-stayed deck supported on stay cables within a very close tolerance of deviations in plan and elevation.

    Navigation and transporting 19 precast segments in 24

    hours at different open sea locations was a challenge.

    How to move the large truss from the Bandra end of the bridge to the Worli end without having to dismantle the truss which would be too time consuming on such a high profile structure with a strict timescale.