Hampton Avenue Capital Improvement Project
Danée McGee, P.E. Project Manager: Charlotte Storm Water Services
Cliff Nelson, P.E.Project Manager: Baker Engineering, Inc.
October 11, 2012
Baker Engineering
Project Team & Meeting Purpose
Charlotte Storm Water Services: Project Management
Baker Engineering: Design Consultant
Explanation of Storm Water Program: Why Are We Here?
Obtain Public Input:Your Part in the Process…
Provide Project Overview: What Are We Doing?
Explanation of Next Steps:What is Coming Next…
Baker Engineering
Charlotte’s Storm Water Program
Water Quality
Maintenance
Capital Improvements
Baker Engineering
During the project:
Public Input
– Mailers Every Four Months – Website Updates: http://Stormwater.Charmeck.Org
– Public Meetings
– Questionnaires and Property Owner Surveys
– Email and Phone Contact as Needed
Baker Engineering
Project Phases
1. Planning
2. Design
3. Permitting (401/404)
4. Easement Acquisition
5. Bid & Construction
– Public Involvement Throughout
Baker Engineering
Drainage Conditions in The Neighborhood
Baker Engineering
Hampton Avenue CIP Area
Baker Engineering
Preferred Alternative for Design
Cost/Benefit: $$
Alleviate Structure Flooding:addresses
Alleviate Intersection Flooding: intersections
Repair Aging/Failing Infrastructure:where
Baker Engineering
Final Project Phases - How things Work:
Next Steps
– Design Phase
– 401/404 Permitting
– Easement Acquisition
– Bid and Construction
Baker Engineering
Questions &
Comments
Baker Engineering