Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
Preparations for Installation, Testing and Commissioning based on Experience at
CERN, SNS and Siemens
Eugène Tanke
FRIB / MSU
ESS Seminar, Lund, 6 March 2013
E.Tanke, Seminar at ESS, Lund, 6 March 2013 2
Outline
Project Goal for the Accelerator Path towards the Goal Technical obstructions on the Path and some Remedies pertaining to installation,
testing and commissioning Summary and conclusion
E.Tanke, Seminar at ESS, Lund, 6 March 2013 3
Project Goal and typical path towards it
For the accelerator the Project Goal translates as: Deliver a (fully) integrated and (fully) functional
accelerator on time and within budget Reach specified beam performance at the output
Given the design, reaching the goal will require Scheduling each of the installation, testing and
commissioning phases and doing the actual installation, testing and
commissioning and tracking that scope is implemented on schedule and
within budget and success is guaranteed...
E.Tanke, Seminar at ESS, Lund, 6 March 2013 4
Questionable Path towards the Goal
E.Tanke, Seminar at ESS, Lund, 6 March 2013 5
Preparations for Installation
Receiving, Assembly, Testing and Storage area is crucial SNS had RATS facility of more than 5500 m2
Installation will be further aided by Installing tested equipment (FAT*) Service Building: Detailed rack layout and rack
installation plan Tunnel: Lattice file, containing names and locations
in global coordinates of beam line devices Good estimate and coordination of work involved
SNS "Field Coordination" 119 FTEy
*Factory Acceptance Test
E.Tanke, Seminar at ESS, Lund, 6 March 2013 6
Obstructions on the Path towards the Goal (1)
Ultimately during beam commissioning (if not sooner) lack of performance may show up
Examples of root causes for lack of performance are poor documentation, poor design, poor quality materials, lack of integration, machining errors, cabling errors, software errors, alignment errors, inadequate testing etc
Such deficiencies are not uncommon (most if not all labs have their examples) and...
…can be very costly and time consuming to fix
E.Tanke, Seminar at ESS, Lund, 6 March 2013 7
Obstructions on the Path towards the GoalDesign phase: LHC magnets from FNAL* (2)
* http://fnal.gov/directorate/OQBP/index/oqbp_misc/Final_LHC_Root_Cause_Analysis_Report_Rev2_19Sep07.pdf
E.Tanke, Seminar at ESS, Lund, 6 March 2013 8
Obstructions on the Path towards the GoalConstruction/assembly phase: SNS DTL (3)
Shortly before mounting drift tubes in the first SNS DTL tank (#3), vacuum leaks were detected on the drift tubes
Leaks were traced to e-beam weld (water/vacuum)
E-beam was deflected due to insufficient shunting of the PMQ field, missing the intended joint
E-beam penetrated the Cu body and damaged the PMQs
E.Tanke, Seminar at ESS, Lund, 6 March 2013 9
Obstructions on the Path towards the GoalTesting phase: CERN RFQ2a (4)
Performance of the CERN RFQ2a was hampered by oil pollution from a roughing pump due to an improperly functioning vacuum interlock system
An additional RFQ (RFQ2b) had to be built
CERN RFQ2b (200 mA p)
with pulsed ion source on the
right and linac2 on the left
E.Tanke, Seminar at ESS, Lund, 6 March 2013 10
Can one reduce the risk of such Obstructions ?
Proper testing and Q/A procedures combined with full integration will reduce or even eliminate such risk But what exactly should one test and how?
In industry the so-called V-model is widely used (see next slide)
How can one improve systems integration?
E.Tanke, Seminar at ESS, Lund, 6 March 2013 11
V-model as defined in industry
DVM=Design Verification MethodDVP=Design Verification Plan
E.Tanke, Seminar at ESS, Lund, 6 March 2013 12
V-model applied in an accelerator: Requirements Definition
Define and document System Requirements, and the Sub-System, Device requirements and specifications driven by these, e.g. Magnet requirements (45 deg dipole, 5 cm aperture
1T , 1 m, dB<0.1%) drive specifications (e.g. RT, n windings of diameter x, 100 A, yoke shape etc)
Avoid requirements/specifications that cannot be tested
Do not list the same requirements in multiple documents
Once device/system built, test against these requirements
E.Tanke, Seminar at ESS, Lund, 6 March 2013 13
Now we may have a handle on this problem
E.Tanke, Seminar at ESS, Lund, 6 March 2013 14
Define and document test plans Define appropriate and comprehensive tests e.g.
Leak test a water cooling system with water or with helium?
Verify in/out control of diagnostics
Test against requirements/specifications and document results
Use a Design Verification Matrix (DVM) to track which requirements have been verified
V-model applied in an accelerator:Requirements Verification
E.Tanke, Seminar at ESS, Lund, 6 March 2013 15
V-model applied in an accelerator:Siemens Particle Therapy systems
Synchrotron and Linac
Layout for Kiel facility (now dismantled)Raster scan
E.Tanke, Seminar at ESS, Lund, 6 March 2013 16
Test at vendor where appropriate
Test equipment before installation and where appropriate, have as much tested as possible at the vendor (FAT) Avoids time loss due to shipping equipment back Witness construction and tests at vendor
Due to schedule pressure, one may be tempted to skimp on testing because after installation and/or during beam commissioning proper functioning of equipment will be confirmed, but.....
E.Tanke, Seminar at ESS, Lund, 6 March 2013 17
Consequences of insufficient / delayed testing (as apposed to thorough / early)
If proper functioning of equipment is not confirmed after installation and/or during commissioning, one may suffer substantial delays
Commissioning is typically on the critical path
increased costs Example: how much does it cost to run the cryoplant during
4 hours of debugging and repair of a magnet problem? (additional) rework "standing army"
E.Tanke, Seminar at ESS, Lund, 6 March 2013 18
Can one reduce the risk of such Obstructions (to reaching the Goal) ?
Proper testing and Q/A procedures combined with full integration will reduce or even eliminate such risk But what exactly should one test and how?
In industry the so-called V-model is widely used
How can one improve systems integration? Preparation: Set up a framework for integration, that allows
for tracking of requirements. Industry uses tools such as DOORS or Caliber to assist in the DVM function
Preparation: Sign off on interface definition by system owners on both sides of each interface during design
Clearly define installation, testing and commissioning phases (see following slide)
E.Tanke, Seminar at ESS, Lund, 6 March 2013 19
Typical installation, testing and commissioning sequence
Given the accelerator design, reaching this sequence will consist of the following phases Building/buying accelerator equipment Equipment testing prior to installation (FAT) Equipment installation (phase A) Equipment testing (stand alone) (phase B) Equipment integration or V test (phase C) Equipment testing with beam (phase pre-D) Equipment beam commissioning (phase D)
Project is helped by clearly defining handover points from one phase to the next
E.Tanke, Seminar at ESS, Lund, 6 March 2013 20
Systems Integration on Site (V tests)
"Vertical" Tests (Phase C) are end to end tests across multiple systems When planning these, take installation and
commissioning into account To be performed after successful FATs/stand alone
tests of all systems concerned Cables should also undergo stand alone testing
(Phase B in preparation for C) The cables used to test a device in the FAT are usually not
the same cables as installed on the facility Cables may be hooked up to the wrong device/terminals
E.Tanke, Seminar at ESS, Lund, 6 March 2013 21
The goal of Beam Commissioning (Phase D) is to achieve the required beam parameters at the output under required conditions
In preparation for beam commissioning, beam diagnostics should be tested with a (pilot) beam (Phase pre-D)
Testing should include a full V test Subsequently, the beam itself can be
commissioned
Preparations for Beam Commissioning (1)
E.Tanke, Seminar at ESS, Lund, 6 March 2013 22
Beam Commissioning is aided by a Beam Commissioning plan, delineating
Commissioning team Commissioning sequences, e.g.
Source to RFQ input, Source to DTL input
Commissioning sequence details Detailed description of measurements to be made and their
durations, backed up by beam dynamics simulations, including those
away from the nominal setting
Preparations for Beam Commissioning (2)
E.Tanke, Seminar at ESS, Lund, 6 March 2013 23
Preparations for Beam Commissioning (3)SNS example of commissioning sequence
TASKDuration (shifts)
Peak Current
(mA)
Pulse Width (usec)
Rep Rate (Hz)
Beam Power (kW)
Beam stop Priority
1 Ion Source and RFQ Startup 4.5 20 50 3 0.0075 MEBT high
2 Beam transport to MEBT beam stop 10 20 50 3 0.0075 MEBT high
3 Beam transport through DTL 1 to Energy Degrader/Faraday Cup 6 5 20 2 0.0005 ED/FC high4 Beam transport through DTL to D-plate Beamstop 7 20 10 2 0.003 D-plate high5 Commission D-plate Diagnostics and MPS 17 20 50 2 0.015 D-plate high6 Perform Fault Studies 4 10 20 2 0.003 D-plate high7 RF System Checkout/Verification with Beam 4 20 100 3 0.045 D-plate high8 Establish Phase and Amplitude Set-point 23 20 50 3 0.0225 D-plate high9 Establish Transverse Matching Conditions 14 20 50 3 0.0225 D-plate high10 Establish Long-Pulse Operation 8 20 680 3 0.306 D-plate high11 Perform Aperture Scan 7 5 10 2 0.00075 D-plate low12 Establish Nominal 38 mA beam conditions at DTL output 13 38 50 3 0.04275 D-plate high13 Characterize DTL 1 nominal output beam 16 38 50 3 0.04275 D-plate high14 Commission Chopper Systems 15 38 50 3 0.04275 MEBT med15 Characterize DTL 1 chopped output beam 9 38 50 3 0.04275 D-plate med16 High Duty Factor Measurements 18 38 680 30 5.814 D-plate high17 Other Measurements low
Example for SNS DTL Tank 1
E.Tanke, Seminar at ESS, Lund, 6 March 2013 24
Preparations for Beam Commissioning (4)SNS example of commissioning form
Have "sanity check" alternatives In this case, check RF tank amplitude on cavity
E.Tanke, Seminar at ESS, Lund, 6 March 2013 25
Commissioning is aided by support from beam dynamics tools
Various tools: Off-line model(s) On-line model(s) Virtual accelerator
RFQ (foto) and linac originally foreseen for SSC being used for production of medical isotopes
Loss in beam transport to target was found Debugged with off-line code DYNAC
E.Tanke, Seminar at ESS, Lund, 6 March 2013 26
Use of multiple beam dynamics codes aids understanding of measured beam
During the MEBT commissioning of CERN Linac3, measured and simulated beam emittances and Twiss parameters seemed to be similar, but...
double checking with another emittance measurement gear and with another code (DYNAC*) demonstrated flaws in both the simulation and measurement
*DYNAC source code available at: http://dynac.web.cern.ch/dynac/dynac.html
E.Tanke, Seminar at ESS, Lund, 6 March 2013 27
Success of Commissioning helped by well planned use of temporary diagnostics
Apart from using "inline" diagnostics, use strategically placed temporary ones
Use emittance scanner to measure beam at the input plane of the RFQ
Explore other settings than the nominal one Could condition RFQ in parallel "parking" position
Use bunch length, energy and energy dispersion measurements as well as an emittance scanner to characterize the beam at the input plane of the linac
Compare measurement results from inline and temporary diagnostics with each other and with beam dynamics code(s) results
E.Tanke, Seminar at ESS, Lund, 6 March 2013 28© Siemens AG 2011, Healthcare Sector, Particle Therapy. All rights reserved.
Temporary diagnostics used at the RFQ input and the IH DTL input at Siemens
RFQ and IH placed in "parking position", allowing for simultaneous beam commissioning and RF conditioning
E.Tanke, Seminar at ESS, Lund, 6 March 2013 29
Examples of temporary Diagnostics
"D-Plate" used behind SNS DTL tank 1
Emittance scanner with fast Faraday cup and end cup at location of
Siemens RFQX and Y grids can be read out simultaneously
for real time isometric profile plot
E.Tanke, Seminar at ESS, Lund, 6 March 2013 30
Optimize sequence duration by planning simultaneous installation, testing and commissioning (macroscopic scale)
Base durations on bottom-up estimates from system/task owners
Have on-site day to day planning (microscopic scale)
Define clear handover from one phase to the next
e.g. final alignment is part of installation include handover parameters as needed
Managing Installation, Testing and Commissioning
E.Tanke, Seminar at ESS, Lund, 6 March 2013 31
SNS CCL during installation and....
8 CCL segments linked by bridge couplers; awaiting installation of inter-segment quadrupoles
Photo courtesy of Oak Ridge National Laboratory
E.Tanke, Seminar at ESS, Lund, 6 March 2013 32
…..simultaneous DTL1 Commissioning
Towards remainder of DTL and CCL
PPS Access
Ion source & LEBTRFQ
MEBTDTL tank 1
D-plate
D-plate
E.Tanke, Seminar at ESS, Lund, 6 March 2013 33
Installation, testing and beam commissioning will profit from
well defined scope and plans for each of these as well as durations (based on bottom-up estimates from system/task owners)
well defined handover from one phase to the next
Equipment/system tests are crucial to successful and timely project completion
There are methods to reduce the risk and impact of "system failures"
Summary highlights
E.Tanke, Seminar at ESS, Lund, 6 March 2013 34
….successfully aid in reaching the end goal
Conclusion
There are methods that will.....
and will help avoid undesirable outcome(s)
E.Tanke, Seminar at ESS, Lund, 6 March 2013 35
Thank you for your attention !