Upload
doanduong
View
216
Download
0
Embed Size (px)
Citation preview
12/9/2015 Badan Tenaga Nuklir Nasional 1
Geni Rina Sunaryo Director for Nuclear Reactor Technology and Safety Center, BATAN
IAEA Technical Meeting on the Status of Deep Burn Concepts for HTGR, IAEA HQ, Vienna, 7 – 9 December 2015, C-0343
12/9/2015 Badan Tenaga Nuklir Nasional 2
Reaktor Daya Experimental RDE
Experimental Power Reactor
Multi Purpose Power Reactor MPPR
Reaktor Daya SerbaGuna RDSG
Reaktor Daya Non Komersial RDNK (BAPETEN)
Non Commercial Power Reactor
Key Fact (2013)
• 13,466 islands, area: 9.8 million
km2 (81% of sea)
• Population: 250 M; 80% live in
Java-Madura-Bali-Sumatera
• Electrification Ratio ~72%
4
% 15
%
67
%
11
%
3
%
Distribution of Energy Consumption
Distribution of Energy Consumption
Energy Mix Projection (National Energy Policy 2014)
Note: Nuclear is categorized into the new energy
Non-Commercial Experimental or Demonstration Power Reactor
(Act 10/1997 and Gov. Regulation No. 2 (2014)
Nuclear Power Development Plan
RDE
12/9/2015 Badan Tenaga Nuklir Nasional 10
• Act No 17 Year 2007: National Long Term
Development Planning
Mandate from the Act: During 3rd Mid Term
Development Plan (RPJM) 2015-2019: starting
nuclear energy utilization for electricity by
considering strict safety factor.
• GR No.2 Year 2014 : Licensing of Nuclear
Installation and Utilization of Nuclear Material
Article 5:
(1) Construction, Operation, and Decommissioning
of Non-Commercial Power Reactor or Non-
Commercial Non-Power Reactor is implemented
by BATAN
• President Regulation 2/2015: National Mid Term
Development Planning 2015-2019 give mandate to
for implementing small scale of NPP
• The result of public opinion polling, 72 % agree to
NPP
To demonstrate the safe operation of small
scale NPP
As a role model for developing SMR – east
Indonesia
To improve the ability to master technology of
NPPs for deployment of larger power NPPs in
the future;
Objective
2013 2014 2015 2016 2017 2018 2019 2020 2021
Technology Selection
Pre-Project Team
Blueprint
PMO Establishment
OO Establishment
URD,DUR,
DID, Spec Tec
FS, Design Eng. SAR, EPC Bidding Doc
Bid ding
Pre-FS
SEP, SEMS
Site Licensing Process
Construction Licensing Process
Env. Licensing Process
Other Licensing
Operation Licensing Process
Commissioning Licensing Process
Doc for Const. Permit
G to G
Agreeement
Engineering, procurement, Construction, installation
Construction Management CM
Bidding
Site Dev.
Basic & Detail Engineering
Consortium
+ Sub-Con
Mech & Electr Procurement
Civil Work
Nucl. Fuel& Material
Installation
Training / OJT / HRD / Recruitment / Certification of Operators
Support from IAEA
Site Evaluation
14
OPERATION
MULTI YEAR PACKAGE CONTRACT
MULTI YEAR PACKAGE CONTRACT
PreProject
ProjectManagement
EPCActivities
OperationActivities
Licensing
HRD
Progress of the Project
1. Finish compiling the RDE Requirement, included in
TOR for RDE's Basic Engineering Design Package
(BEDP) work.
2. Currently working with Consultant for the Basic
Engineering Design Package of RDE, which should
be finish in 2015. This include the Conceptual
Design, Safety Analysis Report, Front-End
Engineering Design, and EPC Bidding Document.
3. Submitting the Site Evaluation Report to the
regulatory body as part of Site Permit application.
Construction – Comissioning – Operation RDE
Preparation Construction
Approval for Design
Change
RDE STATUS
Site study
Site evauation
Commissioning and Operation
Design Coceptual , FS
Basic Detail
Construction Doc. Permit
2016 2021
Approval for Site
Evaluation Program
Site Permit
Design Approval Construction
Permit
Commissioning and Operation
License
18
PROJECT STATUS (1/2)
1. Site Evaluation for Site Permit (2014-2016)
• Site Evaluation Program (SEP) and Management System of
Site Evaluation, that have been approved by BAPETEN on
25 February 2015
• Application for Site Permit have been implemented on 27
October 2015
• Waiting for BAPETEN Evaluation
2. Pre Project Activities (2015)
Contract with RENUKO Consortium: 24 April 2015
• Conceptual Design & Front End Engineering Design
• Integrated FS (including Site Development Plan, Master Plan,
Cost Breakdown Structure/CBS, Work Breakdown
Structure/WBS, Risk Analysis)
• Design Information Questionnaire , Reactor Main Data, EPC
Bidding document, PSAR.
19
PROJECT STATUS (2/2)
3. Environmental Impact Assessment (EIA) (2015)
• TOR EIA have been approved by Ministry of Environment
• EIA will be prepared at 2016, and the target 2016 will
obtain environmental permit
4. Cooperation and International Agreement for supporting
the Project
• China, Japan, Russia
5. Public Acceptance
• It have conducted intensive socialization in the
community around the project, employees of Puspiptek,
as well local governments
Signing the Contract (BATAN-RENUKO, 24 APRIL 2015)
12/9/2015 Badan Tenaga Nuklir Nasional 20
PRELIMINARY ENGINEERING DESIGN FOR I-Experimental Power Reactor
12/9/2015 21
PROJECT STATUS (PER 2 Dec 2015) OF RENUKO CONTRACT
No
Document Status Remark
1 WBS 00. Implementation of QA System
Ok
2 WBS 01. Feasibility Study
14 Chapter: Importance of Project, Project Schedule, Project and Operational Cost, Site, Environmental, SDP, Fuel Supply, Spent Fuel and RA Waste, CBA, Risk Analysis, National Participation, Lay Out
Detail Project Schedule have not been delivered.
3 WBS 02. CONCEPTUAL DESIGN
61 Items: General Feature, Reactore Core, NSSS, Fracture Diagram, Hot Gas Duct, Primary Gas Blower, Steam Generator, pressure control, pressure relief, Helium Purification, Physical Protection, cogeneration interface, steam turbine,cavity cooler, fuel handling, etc
Safety System, emergency System still TBD
12/9/2015 22
PROJECT STATUS (PER 2 DEC 2015) OF RENUKO CONTRACT (Cont)
No Document Status Remark
4 WBS 03. FEED 40 ITEMS: BEDD
5 WBS 04: SAR 12 Chapter Accident Analysis not yet provided
6 WBS 05. DID Ok
7 WBS 06. DUR OK Detail Project Schedule have not been delivered.
8 WBS 07. EPC Tender Documents
Not Yet Completed
Still under development
Audiency/ courtesy call with 3 Ministers and Key Institution Leader
12/9/2015 Badan Tenaga Nuklir Nasional 23
Strategic Development
2015 2016 ~ 2019
Reverse Engineering of Legacy Code
In-House Improvement
Current Status
BATAN’s Code
TIMCOAT Have permission
Prof. Ballinger
Paralel Computation Study
Uncertainty and Sensitivity Analyses
TOOLS
Design and Safety Analyses
Dispersion Analyses
Core Neutronic Analyses
Heat and Flow
Analysis
TRISO Fuel Performance
Analyses
MC-based
neutronic core
analysis based
on MVP, MVP-
BURN, and
MCPBR method.
• Porous media approach of
PBR core analysis
• CFD-based core analysis
using FLUENT
• System analysis using
Flownex code using
FLOWNEX
Analysis and method
development based on TIMCOA
code. (in cooperation with Prof.
Ballinger at MIT)
Application of Latin Hypercube
Sampling in TRISO fuel performance
analysis, applied in TIMCOAT code.
1. LEU-based PBR design Performing design study for LEU-based PBR design.
Preliminary Neutronic Design Study of High Burn up OTTO
Cycle PBR; Average discharge burnup of 131.1 Mwd/Kg-HM
using a 17% U-235 enrichment with 4g HM/pebble loading.
PBR Design Study
3. Th-based design Ongoing research to optimized the Th-based fuel PBR.
2. Pu-based PBR design Performing design study for Pu-based PBR design.
Preliminary Neutronic Study on Pu-based OTTO Cycle PBR;
Average discharge burnup of 419.7 Mwd/Kg-HM using a 2.5
g/pebble loading of Pu-isotopes fuel (From LWR-waste with 47.5
Mwd/Kg-HM level).
Average discharge burnup of 131.1 Mwd/Kg-HM using a 17% U-
235 enrichment with 4g HM/pebble loading.
Source:
T. Setiadipura, D. Irwanto, Zuhair, Atom Indonesia 41 (2015) 7
LEU-based PBR
Source:
T. Setiadipura, D. Irwanto, Zuhair, Atom Indonesia (submitted)
Average discharge burnup of 419.7 MWd/Kg-HM using a
2.5 g/pebble loading of Pu-isotopes fuel.
Pu-based PBR
Fuel Research Facilities in Indonesia
Fuel Element Production Installation (FEPI)
for research reactor fuel in (Serpong)
To supply fuel for research reactor, (U3O8-Al; U3Si2-
Al fuel; and conduct U-Mo and U-Zr based fuel
HTGR Fuel Programme in Indonesia
Human resources
development
Trainings for personnel
Plant and Licensing from fuel vendor
Funding - Regular budget - Extra budgetary - Others
International Cooperation
Universities and Technical Institutes
for Accelerating R&D
BATAN’s Education and Training Center for
Preparing HRD
Construction of fuel production plant in reactor complex in Serpong
Produce fuel for Indonesia’s
experimental power reactor
To establish close cooperation for capacity building
HTGR Fuel R&D Facility
HTGR Fuel Industry
To demonstrate
Integrity of designed Fuel
To establish close cooperation to obtain skilled personnel
12/9/2015 Badan Tenaga Nuklir Nasional 38
Kernel Preparation using selfmade equipment TRISO coating preparation using selfmade equipment Fuel sphere compaction using self equipment
RECENT STATUS
3 MAIN PROCESS IN HTGR PEBBLE BED FUEL FABRICATION
Equipment for point 1, 2, & 3
have been procured from
NUKEM and arrived on
December 5, 2015,
PROBLEM ENCOUNTERED (1): budgeting for LABSCALE FUEL FABRICATION
LABORATORY procurement
12/9/2015 Badan Tenaga Nuklir Nasional 39
2015 2016 2017 2018 2019
KERNEL PREPARATION (1): • Broth Solution
Preparation Equpments • Gel ADU Preparation
Equipments • Ageing, Washing, and
Drying (AWD).
KERNEL PREPARATION (1): • Calcining
Equipment • Sntering
Equipment • Sieving and
Sorting Equipment
• Portionong Equipment
• Kernel Preparation Quality Control Equipments
TRISO PREPARATION: • FB-CVD Coating
Equipment. • Sieving of Coated
Particles Equipment.
• Sorting of Coated Particles (CP).
• Sampling and Portioning of CP.
• TRISO Quality Control Equipments
MATRIX PREPARATION: • Graphite Mixer • Kneader • Drying Oven • Pre Crusher • Hammer Miill • MGP Mixer • Matrix Quality
Control Equipments
FUEL SPHERE COMPACTION: • Overcoating of
coated particles Equipment
• OCP Drying • Sieving and Sorting • Combining and
Portioning • Pressing of the core
and the fuel sphere • Machining • Carbonising • Annealing • Fuel Sphere QC
Equipments
LABSCALE FUEL FABRICATION LABORATORY procurement Is held every year (2015 – 2019)
Equipment have
been procured
from NUKEM and
arrived on
December 5,
2015,
12/9/2015 Badan Tenaga Nuklir Nasional 40
PROBLEM ENCOUNTERED (2) INTERNATIONAL Cooperation
Technical Assistance: - Review of design specification - Fabrication parameters - Qualification program - Licensing
Development of human resources: - HTGR fuel experts - Skilled workers for industry - Quality control specialists - Management
Irradiation testing and Post Irradiation Examination - Testing of fuel - Post irradiation examination
Development of similar facilities in Indonesia
R&D Works - Fuel development - Improve process parameters - Enhanced fuel parameters
Testing facilities abroad
Universities and R&D Facilities abroad
Nuclear Fuel
Institutes
International organizations,
e.g. IAEA
RDE will be an” Indonesian NPP mastery” for future NPP commercialization especially for SMR size
12/9/2015 Badan Tenaga Nuklir Nasional 41
CONCLUSION