Presentation of the Project „Preparation of ceasing of dangerous junctions

Zoltán JákliKÖZOP Head of Completition Department Magyar Közút NZrt.

TABLE OF CONTENT

I. Network of Magyar Közút NZrt. II. Evolution of projects

III. Traffic security projects of MK NZrt. IV. Presentation of the „preparation” project

Expected impacts

V. Future plans, outlook

Lorem Ipsum

Length of the national public roads: 31 698,0 km

75 % of the entire public road traffic Goes here

From the national public roads, the main network is 8339,8 km

From the Main network 2253,6 km is "E" read, Part of the European network

27 % of the length of national public roads represent Crossing sections

7435 pc bridges and 8669 public road junctions may be found on national public roads

I. Network of the „Magyar Közút Nzrt.”

I. Network of the „Magyar Közút Nzrt.”Traffic volume on the I. and II. class main roads and expressways (2011)

I. Network of the „Magyar Közút Nzrt.”

Traffic volume of tracks on the I. and II. class main roads and expressways (2011)

I. The network of Magyar Közút Nzrt.

Accidents with personal injuries on the I. and II. class main roads (2007-2011)

2007 2008 2009 2010 20110

1000

2000

3000

4000

5000

6000

Halálos balesetek Súlyos kimenetelű balesetekKönnyű kimenetelű balesetek Összes személyis sérüléses baleset

Num

ber o

f acc

iden

ts

- 54 %

Accidents with personal injuries in junctions without traffic lights (I., II. class main roads; 2007-2011)

I. The network of Magyar Közút Nzrt.

2007 2008 2009 2010 20110

200

400

600

800

1000

1200

1400

1600

Halálos balesetek Súlyos sérüléses baleset

Könnyű sérüléses balesetek Összes sz. s. baleset

Bale

sete

k sz

áma

- 48 %

I. The network of Magyar Közút Nzrt

Counties concerned by the project

II. EVOLUTION OF THE PROJECT

Subvention

Idea

Source

Contract

The project starts…

Major results July 29, 2011. Minister of National Development – ordering letter

Source: KÖZOP-3.5.0-09-11 „Improvement of access to areas”

May 15, 2012. Conclusion of Contracts of support for Project 2 • KÖZOP-3.5.0-09-11-2011-0015 „Preparation of ceasing

of dangerous junctions”• KÖZOP-3.5.0-09-11-2011-0016 „Developments improving

the security of traffic in the national network of public roads”

October 5, 2012. MK KözOP- approval of the rule for calculation of specific production cost

• Project management costs• Installation of guardrails by our own implementation • Provisory traffic techniques during the construction by our own

implementation November of 2012. The feasibility studies are ready

October 20, 2011. Reception of project proposal

III. TRAFFIC SECURITY PROJECTS OF MK NZRT.

March 28,2012. Governemental decision – position of outstanding project

IV. Presentation of the preparatory project

Why the roundabout?

• Better recognition• Favourable flow of

traffic Less points of conflicts

• Lower speed• In total : HIGHER

SECURITY

Fejlesztésre javasolt helyszínek

IV. Presentation of the preparatory project

• Plan making• Authorization• Execution plans• Acquisition of territory (if

necessary)• Archeology (if necessary)

Examined parameters• Current geometric formation

• Situation of accidents (2007 – 2011), traffic conditions

• Expected decrease in the number of accidents

• Estimated investment & operating costs

• Foreign territory involvement

• Territory involvement of Natura 2000

• Involvement due to archeological values

• Other external effects

• Economic efficiency indicators (Net current value, profit-cost rate, inner rate of return)

IV. Presentation of the preparatory project

IV. Presentation of the preparatory project

• Junction of main road no.471. and road 4918.

Especially dangerous site, in total 21 traffic accidents with personal injuries occurred in the junction and surroundings in the examined period

The relative accident indicator of the site calculated onto the junction is 11,39 [b/107 jmkm/year]

• Junction of main road no. 471. and road no. 4918.

In case of rebuilding the junction, Rb=10 m inner radius and Rk=17 m outside radius of roundabout is recommended

IV. Presentation of the preparatory project

• Junction of Main road no.62. – Road s. 70447. (M7 sub-junction)

Examined site at half-trefoil junction of Motorway M7, and tree-branches „T” junction with traffic sign regulation of the second class road no. 62.

The relative accident indicator of the place calculated onto the junction is [9,01 b/107 jmkm/year]

IV. Presentation of the preparatory project

• 62. sz. főút – 70447. j. út (M7 alcsomópont) csomópontja

In case of rebuilding the junction, it is recommended to build a roundabout of Rb=15 m inner radius and Rk=23,5 m of exterior radius

IV. Presentation of the preparatory project

Traffic safety deficienciesIt is hard to recognize and perceive the junction, the view of the straight passing is prevailing from the side-direction, too.

The left turning lane is used for irregular overtaking

IV. Presentation of the preparatory project

The geometric shaping of the junctions, the built-up of independent turning left lanes from all directions and the „guiding” effect of the electricity pylons help the progression at high speed

The acute angle connecting of the main direction and of the sub-direction is especially unfavourable, both from the aspect of perception and from the aspect of providing an adequate associated line

Traffic safety deficiencies

IV. Presentation of the preparatory project

IV. Presentation of the preparatory project

5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12

Támogatási szerződés megkötése 2012.05.15Megvalósíthatósági tanulmány elkészítése és jóváhagyása 2012.12.31

Tervezés81 sz. főút 26+300- 26+630 móri körforgalom tervezése 2013.10.31Kör geometriájú csomópont tervezése (4. sz. főút 226+200- 226+500) 2013.11.30További 21 db körforgalmú csomópont tervezése 2013.11.30

TerületelőkészítésTerületszerzés 2014.03.31Régészet 2014.05.31Lőszermentesítés 2014.06.01

ElszámolásZáró kifizetési kérelem, pénzügyi zárás 2014.06.30

KommunikációKommunikációs terv jóváhagyása 2012.08.03Projektindító sajtóesemény 2012.05.15

KÖZOP-3.5.0-09-11-2011-0015"Balesti gócpontok megszüntetésének előkészítése"

Tevékenységek teljesítés 2012 2013 2014

Table of timing

CountryAverage decrease (%)

Total accidents personal injury accidents

Australia 41-61 45-87

France   57-78

Germany 36  

Holland 47  

Great-Britain   25-39

United States 37 51

Hungary   47 (71)

V.

Estimated decrease in annual victims and injured

V. Expected impacts

Accidents at the selected junctions between 2007 and 2011

Fatal Serious i.Slight Total Died Serious injur. Slight injured Total

Urban road 1 17 58 76 1 18 94 113

Rural road 11 50 75 136 14 75 186 275

No. of accidents No. of injured persons

Died Serious injured Slightly injured

0,05 0,9 4,7

Rural road 1,932 10,35 25,668

Urban road

V. Expected impacts

0 1 2 3 4 5 6 7 8 9 101112131415161718192021222324252627282930

-10,000,000

-5,000,000

-

5,000,000

10,000,000

15,000,000

20,000,000

NPV

Years

Thou

sand

Hun

garia

n Fo

rints

• Construction as soon as possible– New resource– New TSZ (Contract of Support)– NIF? MK?

• Continuous search of causes ad focus– New sites, new solutions

• Development of the water draining system

• Development of bridges, removal of bottle-necks

V. Future plans, outlook