21
PROJECT REPORT

Presentation Report of DC-ASR

Embed Size (px)

Citation preview

PROJECT REPORT

Master Plan, DreamCity-Amritsar

S.NO.

ENTITY REMARKS

1 TOTAL PLOTS 740 no's (as per latest master plan 06.05.2013)Handover to Facility = 384 No's

2 DC- CLUB with swimming pool. 01 no; Area=103231 sqft.

3 DG 1010 KVA HT = 3 Nos.

4 STP 550 KLD x 2 Nos.

5 USS 750KVA x 10

6 LT Panel 05nos.

7 Villas – 500 Sq. Yd. Total =11 No'sHandover to Facility = 3 No's

8 Villas – 325 Sq. Yd. Total =10 No'sHandover to Facility = 3 No'sOffered = 1 No's

9 Villas – 250 Sq. Yd. Total = 17 No'sHandover to Facility = 4 No'sOffered = 1 No's

TOTAL PROJECT FEATURES

S.NO.

ENTITY REMARKS

10 Independent Floors – 325 Sqyds Total =60 No'sHandover to Facility = 18 No'sOffered = 10 No's

11 Independent Floors – 250 Sqyds Total = 87 No'sHandover to Facility = 16 No'sOffered = 9 No's

12 Water Supply & Storage Tank Tank- 550 KL X 2nosWater Supply to township by 3nos 18.5 KW HPN

system.

13 Bore well 3 nos. bore well (2 nos. Done) 1 bore well connection pending.

14 Dual Energy Metering Controlling Pulse for DG and Grid Power

15 RHP Total = 11 No'sStatus = structure work complete in 3 No's

16 Central green park Area = 4.697 Acres

S.NO ENTITIES REMARKS

1 ESTATE BOUNDARY 80 % COMPLETED.

2 SERVICES SEWER AND STORM WATER LINES ARE COMPLETED ONLY PANCHAYAT LAND AREA WORK IN PROGRESS.

3 UGT WATER SUPPLY THROUGH VIA PUMP ROOM STARTED.LINE REPAIRING WORK IN PROGRESS.

5 PLOT BOUNDARY PHASE-I – PLOT BOUNDARY WORK IN PROGRESSPHASE – 2- PLOT BOUNDARY WORK COMPLETEPHASE – 3 – PLOT BOUNDARY ONLY PAINT WORK IN UNDER PROGRESSPHASE – 4 – PLOT BOUNDARY WORK IN PROGRESS ONLY 1000 SQYD PLOTS & ALL OTHER HAND OVER TO FACILITY.

4 INDEPENDENT FLOORS ALL STRUCTURE WORK COMPLETE IN ALL TYPES OF FLOORS . NOW , FINISHING WORK IN PROGRESS .

5 DC- CLUB with swimming pool ALL STRUCTURE WORK 90% COMPLETE , INTERNAL BRICK WORK START IN ZONE-A & ZONE-B & EXTERNAL PLASTER WORK IN PROGRESS.

6 CENTRAL GREEN COMPLETE IN ALL RESPECT & OFFERED TO HANDOVER TO FACILITY DEPARTMENT.

7 HT DGSWITCHING STATION

HT DG & PANEL COMMISSIONING in Progress

WORK IN PROGRESS

500 sqyds Villas

325 sqyds Villas

250 sqyds Villas

325 sqyds DC-FLOORS

250 sqyds DC-FLOORS

PLOT BOUNDARY

DC- CLUB

DG EXHAUST CHIMNEY

View of 25 mtr Road

WORK IN PROGRESS

CENTRAL GREEN PARK

MONTH TOTAL MANPOWER

May-13 575

June-13 560

July-12 580

Aug-12 620

Sep-12 570

Oct-12 490

NOV’12 520

DEC’12 580

JAN’13 610

FEB’13 630

MAR’13 560

APR’13 420

MAY’13 390

JUNE’13 350 - 380

MANPOWER

May

-12

Jun-1

2Ju

l-12

Aug-12

Sep-1

2

Oct-12

Nov-12

Dec-12

Jan-13

Feb-13

Mar

-13

Apr-13

May

-13

Jun-1

30

100200300400500600700

Chart TitleColumn1Column2Column3Column4Column5Column6Column7Column8Column9Column10Column11

Manpower-Month chart

Execution of Infra works is in progress through major contractor and small agencies for better control is implemented and same mode is devised for balance works .

Expedition of Villas, Independent floors and plot boundary through major contractors.

Expedition of permanent electricity through experienced agency.

ACTION PLAN

MONTH500 SQYD

VILLA

325 SQYD VILLAS

250 SQYD VILLAS

325 SQYD DC FLOOR

250 SQYD DC FLOOR

JULY-13 5 5 3 16 8

AUG-13 0 1 4 6 0

SEP-13 1 0 0 4 16

OCT-13 1 0 0 0 3

NEXT FOUR MONTH DELIVERY

THANK YOU