Upload
ruby-sims
View
215
Download
1
Tags:
Embed Size (px)
Citation preview
Presentation Title A holistic view of energy
efficiency improvement in power generation.
New technology, renovation & modernization and process improvement.
ByName: Souvik DuttaDesignation: Dy Chief Engineer(Gen)Date:26.08.11
New technology, renovation & modernization and process improvement.
A holistic view of energy efficiency improvement in power generation.
SolutionsSolutions
New New Technology Technology
Renovation & Modernization
New New Technology Technology
Renovation & Modernization
New Technology
Process Improvement
SolutionsSolutions
Adoption of New Technology
in Thermal Power GenerationAdoption of New Technology
in Thermal Power Generation
Major Initiatives for higher efficiency……
Adoption SAdoption Supercritical, upercritical, Ultra supercritical Ultra supercritical TechnologyTechnology
Adoption SAdoption Supercritical, upercritical, Ultra supercritical Ultra supercritical TechnologyTechnology
Adoption of Combined Adoption of Combined cycle Technologycycle Technology
Adoption of Combined Adoption of Combined cycle Technologycycle Technology
Adoption of Adoption of Integrated Integrated Gasification Combined Gasification Combined Cycle (IGCC) Suitable Cycle (IGCC) Suitable for Indian Coalfor Indian Coal
Adoption of Adoption of Integrated Integrated Gasification Combined Gasification Combined Cycle (IGCC) Suitable Cycle (IGCC) Suitable for Indian Coalfor Indian Coal
Adaptation Adaptation Supercritical / Ultra supercritical TechnologySupercritical / Ultra supercritical Technology
Development of Ultra Mega Power Development of Ultra Mega Power Projects (UMPPs) has been Projects (UMPPs) has been identified as a thrust area in order identified as a thrust area in order to increase plant efficiency.to increase plant efficiency.
Development of Ultra Mega Power Development of Ultra Mega Power Projects (UMPPs) has been Projects (UMPPs) has been identified as a thrust area in order identified as a thrust area in order to increase plant efficiency.to increase plant efficiency.
These are very large sized projects with These are very large sized projects with supercritical technology, approximately supercritical technology, approximately 4000 MW each involving an estimated 4000 MW each involving an estimated investment of about Rs. 16,000 crore investment of about Rs. 16,000 crore each.each.
These are very large sized projects with These are very large sized projects with supercritical technology, approximately supercritical technology, approximately 4000 MW each involving an estimated 4000 MW each involving an estimated investment of about Rs. 16,000 crore investment of about Rs. 16,000 crore each.each.
Adaptation Adaptation Supercritical / Ultra supercritical TechnologySupercritical / Ultra supercritical Technology
Salient features of the Plant and Choice of TechnologySalient features of the Plant and Choice of Technology
• The Ultra Mega Power Projects would use Super Critical Technology with a view to achieve higher levels of fuel efficiency, which results in saving of fuel and lower green- house gas emissions.• Flexibility in unit size subject to adoption of specified minimum Supercritical parameters.• Integrated power project with dedicated captive coal blocks for pithead projects.• Coastal projects to use imported coal.
Salient features of the Plant and Choice of TechnologySalient features of the Plant and Choice of Technology
• The Ultra Mega Power Projects would use Super Critical Technology with a view to achieve higher levels of fuel efficiency, which results in saving of fuel and lower green- house gas emissions.• Flexibility in unit size subject to adoption of specified minimum Supercritical parameters.• Integrated power project with dedicated captive coal blocks for pithead projects.• Coastal projects to use imported coal.
247/537/565
(660 MW)
170/537/537
(500 MW)
‘02 ‘07 ‘22‘17‘12Xth Plan
XIth Plan
XIIth Plan
XIIIth Plan
‘00
247/565/593
(660/800 MW)
280/600/620
(800-1000 MW)
320/600/620
(800-1000 MW)
Gro
ss E
ffic
ien
cy, G
CV
Bas
is
38%
39%
43%
42%
41%
40%
Solutions
Current scenario
Indian Efficiency Roadmap
Increasing Unit size & steam parameters
Indian Efficiency Roadmap
Increasing Unit size & steam parameters
Pr/MST/RHT
0
2
4
6
8
10
12
14
200 LMZ (1978) 200 KWU (1979) 500 KWU (1982) 500 KWU Mod(1998)
500 High RH(2006)
660 SC 660/800 SC
Heat
Rat
e Im
prov
emen
t (%
)
P = 170 ataMST = 537RHT = 537
P = 170 ataMST = 537RHT = 565
P = 247 ataMST = 537RHT = 565
P = 247 ataMST = 565RHT = 593
P = 170 ataMST = 537RHT = 537
P = 130 ataMST = 537RHT = 537
P = 150 ataMST = 537RHT = 537
Heat rate Improvement Over The Years
Indian Efficiency Roadmap
Increasing Unit size & steam parameters
Indian Efficiency Roadmap
Increasing Unit size & steam parameters
Parameters for Higher Efficiency……
Plant Type Unit Size(MW)
Main Steam Pr (Bar)
Main Steam (Temp 0c)
Reheat (Temp 0c)
Notes
Sub critical 500 170 537 537 Common practice in India
Low Supercritical
660 247 537 565 India’s first supercritical
station at Mundra by Adani
High Supercritical
660/800 247-280 565 593 Parameters for Mundra Tatapower
Ultra Supercritical
1000 295 600 600 In operation in Japan/China
Ultra Mega Power Projects : Indian Scenario
Sasan power Ltd
Jharkhand integrated power Ltd
Coastal Gujrat Power
Ltd power Ltd
Coastal Andhra
Power Ltd
Awarded Projects
Projects under process
Orissa Integrated Power Ltd
Akaltara Power Ltd
Coastal Tamil Nadu Power Ltd
Coastal Maharashtra Mega Power
Ltd
Coastal Karnataka Power Ltd
Sakhi Gopal Integrated Power Co Ltd Orissa
Gogarapalli Integrated
Power co Ltd Orissa
Tatiya Andhra
Mega Power Ltd
Concerns: Viability at agreed upon Concerns: Viability at agreed upon tariff due to changed scenario of tariff due to changed scenario of imported coalimported coal
IPP:Adani Power,Mundra
Name of project & capacity as per LOI
Name of successful bidder
Date of LOI Levelised Tariff(Rs/Kwh)
Mundra Gujrat(5X800 MW)
M/S Tatapower Ltd 28/12/06 2.26
Sasan M.P(6X660 MW)
M/S Reliance Power Ltd 01/08/07 1.19
Krishnapatnam Andhra pradesh(5X800 MW)
M/S Reliance Power Ltd 30/11/07 2.33
Tilya Jharkhand(6X660 MW)
M/S Reliance Power Ltd 12/02/09 1.77
Ultra Mega Power projects awarded through tariff based competitive bidding route.
Plants have higher operating parameters and increased efficiency levels.
Awarded UMPP Projects
WAIGAOQIAO THERMAL
POWER STATION
P H A S E - I I I : 2 X 1 0 0 0 M W
SHANGHAI, CHINA
Ultra Supercritical 1000 MW units in China
Adoption Adoption IGCC (Integrated gasification combined cycle) TechnologyTechnology
An integrated gasification combined cycle (IGCC) is a technology that turns coal into gas—synthesis gas (syngas).
Excess heat from the primary combustion and generation is then passed to a steam cycle, similarly to a combined cycle gas turbine.
This then also results in improved efficiency compared to conventional pulverized coal.( 46% to 52%)
In the IGCC plants, the production of CO2 during the gasification process offers the opportunity for relatively low-cost CO2 capture and storage (CCS), which may give the future IGCC plants some competitive and environmental advantages over super critical plants
An integrated gasification combined cycle (IGCC) is a technology that turns coal into gas—synthesis gas (syngas).
Excess heat from the primary combustion and generation is then passed to a steam cycle, similarly to a combined cycle gas turbine.
This then also results in improved efficiency compared to conventional pulverized coal.( 46% to 52%)
In the IGCC plants, the production of CO2 during the gasification process offers the opportunity for relatively low-cost CO2 capture and storage (CCS), which may give the future IGCC plants some competitive and environmental advantages over super critical plants
IGCC (Schematic diagram of the process)
IGCC (Schematic diagram of the process)
NITROGEN
LOCKHOPPERPRESSURISATION
COAL
BUFFER / WEIGHINGHOPPER
COOLED GAS
CLEANEDGAS
DUST
FILTER
COMBUSTOR
COMP
RESS
ORAI
R
TURBINE
EXHAUST GASES
WATER PUMP
CONDENSER
ALTERNATOR
TURBINE
BOILE
R
STEAM
STEAMTURBINE
HEAT
RECOVERYGAS
TURBINECLEANINGGASIFIERDRYER
COAL
DRIED
COAL DRYING
AND GAS COOLING
CYCLONE
AIR
AIR
HOT GASASH/ CHAR
CO2
TO STACK STEAM
ASH/ CHAR
NITROGEN
LOCKHOPPERPRESSURISATION
COAL
BUFFER / WEIGHINGHOPPER
COOLED GAS
CLEANEDGAS
DUST
FILTER
COMBUSTOR
COMP
RESS
ORAI
R
TURBINE
EXHAUST GASES
WATER PUMP
CONDENSER
ALTERNATOR
TURBINE
BOILE
R
STEAM
STEAMTURBINE
HEAT
RECOVERYGAS
TURBINECLEANINGGASIFIERDRYER
COAL
DRIED
COAL DRYING
AND GAS COOLING
CYCLONE
AIR
AIR
HOT GASASH/ CHAR
CO2
TO STACK STEAM
ASH/ CHAR
IGCC
Efficiency and reliability improvements are also expected for Efficiency and reliability improvements are also expected for the IGCC technology. Its efficiency is estimated to grow from the IGCC technology. Its efficiency is estimated to grow from
46% in 2010 to 52% in 2020. 46% in 2010 to 52% in 2020.
Some major IGCC plants, worldwideSome major IGCC plants, worldwide
580 MW, Kentucky Pioneer Energy, USA580 MW, Kentucky Pioneer Energy, USA
512 MW, ISAB Energy, Italy512 MW, ISAB Energy, Italy
342 MW, Nippon Oil Corporation Refinery, Japan342 MW, Nippon Oil Corporation Refinery, Japan
335 MW, Elcogas, Spain335 MW, Elcogas, Spain
250 MW, Tampa Electric Company, USA250 MW, Tampa Electric Company, USA
Efficiency and reliability improvements are also expected for Efficiency and reliability improvements are also expected for the IGCC technology. Its efficiency is estimated to grow from the IGCC technology. Its efficiency is estimated to grow from
46% in 2010 to 52% in 2020. 46% in 2010 to 52% in 2020.
Some major IGCC plants, worldwideSome major IGCC plants, worldwide
580 MW, Kentucky Pioneer Energy, USA580 MW, Kentucky Pioneer Energy, USA
512 MW, ISAB Energy, Italy512 MW, ISAB Energy, Italy
342 MW, Nippon Oil Corporation Refinery, Japan342 MW, Nippon Oil Corporation Refinery, Japan
335 MW, Elcogas, Spain335 MW, Elcogas, Spain
250 MW, Tampa Electric Company, USA250 MW, Tampa Electric Company, USA
India first IGCC power plant is coming up at Vijayawada, foundation for which has been laid. The 125 MW plant will be built in the premises of Vijayawada Thermal Power Plant (VTPS).
BHEL and APGENCO has jointly funded this project.
The main constraint of IGCC technology is cost (+35%), more land requirement and higher auxiliary consumption for producing syn gas.
India first IGCC power plant is coming up at Vijayawada, foundation for which has been laid. The 125 MW plant will be built in the premises of Vijayawada Thermal Power Plant (VTPS).
BHEL and APGENCO has jointly funded this project.
The main constraint of IGCC technology is cost (+35%), more land requirement and higher auxiliary consumption for producing syn gas.
IGCC
250 MW IGCC plant: Tampa Electric Company, USA
Solutions
Renovation and
Modernization (R&M) as
per CEA guidelines Renovation and
Modernization (R&M) as
per CEA guidelines
Increase in availability and plant load factor of thermal power stations
Renovation and modernization for achieving higher efficiency levels.
Setting minimum acceptable standards & plan for R&M for projects below
standard with clear cost benefit analysis
If economic operation does not appear feasible through R&M, then there may be no alternative to closure of such plants as the last resort.
In cases of plants with poor O&M record a change of management may to be considered so as to improve the efficiency to acceptable standards.
Increase in availability and plant load factor of thermal power stations
Renovation and modernization for achieving higher efficiency levels.
Setting minimum acceptable standards & plan for R&M for projects below
standard with clear cost benefit analysis
If economic operation does not appear feasible through R&M, then there may be no alternative to closure of such plants as the last resort.
In cases of plants with poor O&M record a change of management may to be considered so as to improve the efficiency to acceptable standards.
Renovation and Modernization (R&M) as per CEA guidelines
Improvement in performance parameters – PLF,
availability, heat rate/efficiency, auxiliary power
consumption, partial loading & forced outage.
Restore derated capacity
Extension of economic life.
Obsolescence & non availability of spares (eg C&I)
Environmental issues/other statutory requirements.
Safety requirements.
Improvement in performance parameters – PLF,
availability, heat rate/efficiency, auxiliary power
consumption, partial loading & forced outage.
Restore derated capacity
Extension of economic life.
Obsolescence & non availability of spares (eg C&I)
Environmental issues/other statutory requirements.
Safety requirements.
NEED FOR R&M – EXISTING UNITS
FUTURE APPROACH TOWARDS R&M
NEAR PAST FUTUREIn-kind replacement Cost effective technology upgrades
Restoration of lost capacity Uprating of capacity
Attain design efficiency Improve upon design Efficiency
Reactive R&M Pro-active R&M
From Time based R&M Condition Monitoring & R&M
Optimisation through cost
benefit evaluation
NEAR PAST FUTUREIn-kind replacement Cost effective technology upgrades
Restoration of lost capacity Uprating of capacity
Attain design efficiency Improve upon design Efficiency
Reactive R&M Pro-active R&M
From Time based R&M Condition Monitoring & R&M
Optimisation through cost
benefit evaluation
Sl No Particulars R&M LEP
I Number of thermal power
stations
21 23
Ii Number of thermal units
76 53
Iii Estimated cost in Rs crores
4487 12433
iv Total capacity involved
18965 7318
R&M and Life extension program (LEP) during 11th plan(2007-11)
INDIA: Power generation Capacity in MW as on 30th June 2011. Source: CEA website.
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
MW
Coal Gas Diesel Neuclear Hydro Renewable Total Captive
Source of power
Capacity in MW as on 30th June 2011. Source: CEA website.
54.66%
10%
2.7%
10.43%
21.53%
0.68%
11.02%
96.74 Billion watts
176.99 Billion watts
58.59 60.65 61.15 62.7265.93
67.7869.89
70.5674.91
80.44
96.74
0
10
20
30
40
50
60
70
80
90
100
2000-2001
2001-2002
2002-2003
2003-2004
2004-2005
2005-2006
2006-2007
2007-2008
2008-2009
2009-2010
Jun-11
INDIA: Power generation Capacity (Billion Watts) for Coal/Lignite based plants >25 MW capacity
Improvement Trend
Results of R&M
National Thermal plant performance (Coal lignite based>25 MW) (PLF)
68.7
4 69.9
7
72.3
4
72.9
6
74.8
4
73.7
1
77.0
3
78.7
5
77.2
2
77.6
8
62
64
66
68
70
72
74
76
78
80
PLF %
2000
-200
1
2001
-200
2
2002
-200
3
2003
-200
4
2004
-200
5
2005
-200
6
2006
-200
7
2007
-200
8
2008
-200
9
2009
-201
0
Year
Improvement Trend
Results of R&M
National Thermal plant performance (Coal /lignite based>25 MW) (PAF)
79
.84
79
.91
81
.83
81
.93
82
.93
81
.78
83
.72
84
.76
85
.05
85
.1
84
.24
77
78
79
80
81
82
83
84
85
86
PAF %
20
00
-20
01
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
20
10
-20
11
Year
79
.84
79
.91
81
.83
81
.93
82
.93
81
.78
83
.72
84
.76
85
.05
85
.1
84
.24
77
78
79
80
81
82
83
84
85
86
PAF %
20
00
-20
01
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
20
10
-20
11
Year
Improvement Trend
Results of R&M
National Thermal plant performance (Coal /Lignite based>25 MW) (Aux%)
9.0
1
8.7
2
8.5
3
9.0
5
8.5
7
8.4
4
8.2
9
8.1
7
8.3
3
8.3
4
7.6
7.8
8
8.2
8.4
8.6
8.8
9
9.2
Aux %
20
00
-20
01
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
Year
9.0
1
8.7
2
8.5
3
9.0
5
8.5
7
8.4
4
8.2
9
8.1
7
8.3
3
8.3
4
7.6
7.8
8
8.2
8.4
8.6
8.8
9
9.2
Aux %
20
00
-20
01
20
01
-20
02
20
02
-20
03
20
03
-20
04
20
04
-20
05
20
05
-20
06
20
06
-20
07
20
07
-20
08
20
08
-20
09
20
09
-20
10
Year
Improvement Trend
Results of R&M
Solutions
Process Improvement Process Improvement
Process parameters to be improved……
Auxiliary power consumption
Heat rate
Oil figure
Plant load factor
Plant availability factor
Auxiliary power consumption
Heat rate
Oil figure
Plant load factor
Plant availability factor
Reduction of Auxiliary power consumption
Sharing of CESC’S
experience in reduction of
Auxiliary Power consumption Sharing of CESC’S
experience in reduction of
Auxiliary Power consumption
Southern Generating Station. CESC Ltd
Commissioning of Variable Frequency Drives for U#2 ID Fans in February 2011
Objective: To reduce auxiliary power consumption
Commissioning of Variable Frequency Drives for U#2 ID Fans in February 2011
Objective: To reduce auxiliary power consumption
Make: Leader & Harvest Electric Technologies Co. Ltd, China
Indian Partner: Yantra Harvest Energy Pvt. Ltd, Pune
Product : Medium-Voltage VFD
Model: HARSVERT – A06.6/50
Rated Input Voltage: 6.6 KV
Rated Capacity: 450 KW
Rated Output Current : 50 A
Output Frequency Modulation: 0-50 Hz
Output Voltage Modulation: 0 – 6.6KV
Control Mode: Sinusoidal multi-level Pulse Width Modulation
Make: Leader & Harvest Electric Technologies Co. Ltd, China
Indian Partner: Yantra Harvest Energy Pvt. Ltd, Pune
Product : Medium-Voltage VFD
Model: HARSVERT – A06.6/50
Rated Input Voltage: 6.6 KV
Rated Capacity: 450 KW
Rated Output Current : 50 A
Output Frequency Modulation: 0-50 Hz
Output Voltage Modulation: 0 – 6.6KV
Control Mode: Sinusoidal multi-level Pulse Width Modulation
VFD ESSENTIALS
Harvest MV Drive consists of
Input Transformer
Power Cell
Control System
VFD ESSENTIALS
Multi-winding Phase Shifting Input Transformer (Dry-type) Multi-winding Phase Shifting Input Transformer (Dry-type) comprising of 18 nos. Secondary (6 Per phase with Phase-comprising of 18 nos. Secondary (6 Per phase with Phase-shifted at 20,10,0,-10,-20 Degrees for 36-pulse rectification) & 1 shifted at 20,10,0,-10,-20 Degrees for 36-pulse rectification) & 1 no. Auxiliary Winding for Supply to Cooling Fans of Power no. Auxiliary Winding for Supply to Cooling Fans of Power CabinetCabinet
Primary Winding Rating : 6600V / 49.4 APrimary Winding Rating : 6600V / 49.4 A
Secondary Winding Rating: 710V / 25.5 ASecondary Winding Rating: 710V / 25.5 A
Auxiliary Winding Rating : 380 V/ 12.2 AAuxiliary Winding Rating : 380 V/ 12.2 A
VFD ESSENTIALS
The Equipment
Unit Load Particulars Pre-VFD period
Post-VFD period
Net savings per fan
Full load ID fan average load (KW)
370 KW 229 KW 133.5 KW
75 MW AC load (KW)
NIL 7.5 KW
Part load ID fan average load (KW)
335 KW 159 KW 168.5 KW
50-55 MW AC load
(KW)
NIL 7.5 KW
ID fan reduction in auxiliary power consumption after installation of VFD
Note: Above Readings are in winter months. Expected AC Load in Summer : 25 KW
36 % savings36 % savings
50 % savings50 % savings
Payback for two fans:18 to 20 months
Forthcoming VFD projects in CESC Ltd in the current financial year.
Southern Generating Station:
Installation of four numbers VFD’S for two ID fans & two FD fans of Unit no 1. Project: cost 410 lakhs.
Titagarh Generating Station:
Installation of VFD,S for two ID fans in one unit.Project
cost: 200 Lakhs
Southern Generating Station.CESC Ltd :Micro Hydle project
45 KW Micro Hydel Project at condenser
cooling water outfall (3X15 KW)
Objective: To reduce auxiliary power consumption
by extracting power from wasted energy
45 KW Micro Hydel Project at condenser
cooling water outfall (3X15 KW)
Objective: To reduce auxiliary power consumption
by extracting power from wasted energy
Basic concept
Specifications of the 15KW micro hydle turbine generator set• Rated capacity: 15KW (At Generator output)• Rated net head: 1.8 m• Rated discharge: 1 m3/s • Type of turbine: Propeller 4 blade inverted siphon • Rated turbine speed: 360 rpm• Runner diameter: 1000 mm• Type of generator: Induction• Method of drive: Flat belt• Turbine efficiency: 86%
Specifications of the 15KW micro hydle turbine generator set• Rated capacity: 15KW (At Generator output)• Rated net head: 1.8 m• Rated discharge: 1 m3/s • Type of turbine: Propeller 4 blade inverted siphon • Rated turbine speed: 360 rpm• Runner diameter: 1000 mm• Type of generator: Induction• Method of drive: Flat belt• Turbine efficiency: 86%
Southern Generating Station.45 KW(3x15 KW) Micro Hydel Project ph-1Supplier: Pentaflow Hydro Engineers.Delhi
Southern Generating Station. CESC Ltd
Commissioning of phase -1 of the project completed in February 2011
Average 12-14 KW is being generated from
the first 15 KW unit
In subsequent phases another two such sets will be commissioned
Commissioning of phase -1 of the project completed in February 2011
Average 12-14 KW is being generated from
the first 15 KW unit
In subsequent phases another two such sets will be commissioned
Electricity saved each year considering import for 75% time of a day for 350 days in a year
15 KW X 8400 hrs/year X0.75= 94500 KW-h / Year
This is equivalent to a savings of Rs 435000 / year
With a project cost of Rs 14.3 lakhs/unit payback is approximately3.3 years
In the subsequent years other than minor maintenance costs 100% savings will be achieved
For three such units the projected savings will be approximately Rs 10 lakhs
Auxiliary Energy Saved
Micro hydle during installation
Thank You !
The future of mankind is in our
hands. Let us act responsibly
to keep the world cleaner for
our future generation.
The future of mankind is in our
hands. Let us act responsibly
to keep the world cleaner for
our future generation.