Upload
steven-snyder
View
399
Download
7
Embed Size (px)
Citation preview
What the QMS Audit does not tell you
Presented At:
API Exhibition on International Standards (AXIS) 2016
Kuala Lumpur, Malaysia-January 13-15, 2016
Confidential and Proprietary Information – Not For Distribution
QMS Audit or Technical Audit
• QMS audits are required typically don’t identify (and are not intended to) specific
technical non-conformances of critical manufacturing processes
due to time restraints, audit scope, auditor abilities or combination of
• Independent technical capability assessment/audit by SME’s
proven “Value Added” in addition to the QMS audit
verifies effectiveness of an organization’s real overall abilities
Background
• A procedure, system & detailed checklist were established
Focus was on specific special processes vs. system e.g. Welding, NDT, Heat Treating & Coatings ITP’s-Pressure Testing-HSE System in place• Initiated after realization that QMS audits were not
providing technical capabilities of companies at the “shop floor level”
Technical Audits of Vendors after the QMS Audit
• Why? Repeated non-conforming issues observed during manufacturing by TPIs, costing delays or down-time
• Who? Major OEMs (all with ISO 9001-2008), most with API Monograms; sub-vendors of these major OEM’s was of major concern
• What was learned? QMS Audits of ISO 9001, API Q1 and/or API Monogram OEM’s revealed need to dig deeper into why reoccurring NC’s
Technical Audit Scope
• Performed by an auditor, engineer or subject matter expert to evaluate deficiencies or areas of improvement in a process
• Scope: confirm the facility has technical capability, personnel & equipment to comply with:
API Standard’s and ASME IX, ASME V, ASME B31.3, AWS D1.1, DNV-OS-E101-C401, ABS-CDS, NACE MR-0175, etc.. for the equipment manufacturing- Welding, PWHT, NDT, Coating, Testing of Drilling and WCE.
Technical Audit Process
• Scheduled after a QMS audit and scores/ CAR’s reviewed
• Prior to visit: Audit Plan is submitted relative documents requested in advance for
review and planning
• Prevents wasted time on site that needs to be spent in the shops instead
Requested when sending Audit Plan• A master matrix of vendor’s Quality Procedures and Work Instructions for reference • The document review will include but not be limited to the following:
• Matrix of WPS/PQR’s, qualified welders lists, example of identification cards and/or continuity logs• Copy of applicable company’s NDT Written Practice or contract agencies; applicable NDT
Procedures approved by ASNT NDT Level III’s or CSWIP/PCN, EN473, ISO 9712, Master Matrix of NDT inspectors by method & certifications/exams available, including any subcontracted NDT techs and current eye exams.
• Weld consumable control procedures, heat treating procedure/s to include subcontract • Traceability/serialization procedure/s per the applicable API standard & QMS• Coatings procedure/s and requirements for QC inspector qualifications• Procedure/s for contract review, ITP/QP router development, notification of witness/hold points to
buyer and system for management of these notifications and FAT’s.• Weld inspection, weld monitoring and identification/weld/NDT map procedures• Hydro-pressure testing procedures-calibration and records• Master matrix of calibrated equipment’s, weld machines, NDT equipment, Furnace, PWHT,
pressure gauges, etc.• Management of sub-vendors process, i.e. via supply chain or other.• A list of your sub-contractors you will be using for the TOI project• Drawing revision control procedures
About the Technical Auditors
• NDT qualifications & experience in manufacturing. Preferably ASNT certified NDT Level III
• Welding engineer / competent welding technologist qualifications (minimum AWS CWI-CSWIP)
• Well versed in fabrication “dirty boots” approach, understands variables in manufacturing processes
• Knows standards and codes applicable to the manufacturing itself -- key to the Technical Audit
• Trained & certified QMS Lead Auditor / ASQ-CQA, IRCA, RAB, etc.
Checklist - allows for a Scoring based upon question value
Sample: Welding Section checklist
Sample:NDT Section
Scored based upon documented and implemented
OEM top findings – All ISO 9001 or Q1 with API Monogram
Most common technical audit findings per standard or Code not met
ASME IX API 6A API 16A API 16C API 4F
WPS/PQR’s 4130 or other no P no. listed material or not properly qualified, KSI not referenced or construction code on approved WPS/PQR
X X X X -
Welding Inspectors qualification not properly documented or a training procedure in place
- X X X X
Lack of Visual Weld Inspection procedure with proper accept criteria as per standard or code
- X X X X
UT Calibration Program-per ASTM 428 and scanning to proper procedures ASTM/ASME/AWS
- X - - X
MRB-Data Books not per Standard or incomplete documents
- X X X X
Hardness reports missing inform - X X X -
Common Technical Audit Findings
Most common technical audit findings ASME-IX-AWS-D1.1, DNV-C401
API 6A API 16A API 16C API 4F
Inadequate ITP’s or no refer to standards and accept criteria on them
- X X X X
Class society approval of WPS/PQR’s for missing information or no approval at all and being used
X X X X X
NDT reports without correct PSL level or missing accept criteria/inform, D1.1-, ASME V, B31.3, etc.. applicable section
X X X X
Clad thickness measurement procedure not fully implemented or documented
X - - -
NDT Personnel Certification records files not supported by required training records and experience per SNT-TC-1a or ISO-9712
X X X X-
• Several Vendors had poor or non compliant methods for weld maps implemented, although most had procedures for
Missing Weld Maps
W-1
Weld ID – 56WPS # 12675VT-okPWHT Report # 23NDT-RT/UT after PWHT and Hardness report # AAFFiller wire Heat #
Sample Test Chart record view pen arm; skipping, negative zero mark and excessive test pressure range
Manufacturing Records / Data Book is always reviewed and accepted by the following parties:
ClassOwnerOwner Client (in some occasions)
Tab
#1Ta
b #2
Tab
#3Ta
b#4
Tab
#5Ta
b #6
Tab
#7Ta
b #8
Tab
#9
Rig or Equip Name
Data Book Contents
Manufacturing Record Book
MRB-Data Book Check Sheet helpful to TPI
COMPLETE RIG NAME
WHAT TYPE OF NDT (MT, PT VT)
MT—MAGNETIC TESTINGPT– PENETRANT TESTINGVT--VISUAL
IF USING MANUAL YOKE:LIST THE AVERAGE LIFT WEIGHT OF YOKE
ACCEPTANCE STANDARD
VENDOR’S INTERNAL PROC. #
MATERIAL TYPE
ENSURE ONLY LEVEL II OR LEVEL III PERFORMS INSPECTION.
EQUIPMENT ID
NDT BEFORE /AFTER HEAT TREATMENT (PWHT)
Commonly Missing Info on NDT Reports
Summary
• Technical Audits are Value Added• They mitigate risk to the project:
Identify the “weak links” in vendors’ critical manufacturing processes that can lead to major failures-
• Welding, NDT, Heat Treatment, Coatings are high cost NC’s• Understanding the vendors’ approach to final documentation,
MRBs.• Establishing customer’s expectations and requirements• Offering objective evaluation of vendors’ overall technical
capability from a shop floor, “dirty boots” perspective• Capitalizing on opportunities for improvement is the goal• They tell you what the QMS audit does not
Steven T. SnyderTransocean
ASNT NDT Level III, AWS-SCWI/CWE, API-SIFE & 577, ASQ-CQA, IRCA-QMS Principal Auditor
THANK YOU
Confidential and Proprietary Information – Not For Distribution