Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Embed Size (px)

Citation preview

Page 1: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Princeton UniversityPlasma Physics LaboratoryEVMS Certification Review

EVMS Implementation on NSTX-USteve Langish

October 4 - 6, 2011

Page 2: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

2

Page 3: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Overview

• Organization• Planning, Scheduling, and Budgeting• Accounting Considerations• Status (outside ANSI/EIA 748)• Analysis and Management Reports• Revisions and Data Maintenance

3

Page 4: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

ANSI 748 Elements

4

Planning, Scheduling, & Budgeting

Organization

AccountingConsiderations

Revisions

- Define the work

-Assign responsibilities

-The Control Account

- Schedule all work

- Authorize all work

- Time-phase the work

- Develop cost accounts

- Costs Elements

- Cost summarization

- Understand contract status

- Use data for decision-making

Assignments made to responsible organizations

Maintenance of budget, work, and schedule relationships

Do not modify past budget or actuals (w/o permission)

All documents properly maintained

Analysis & Management Reports

Page 5: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Organization: Work Breakdown Structure (WBS)• The Work Breakdown Structure (WBS) for NSTX

Upgrade Project can be found the Project Execution Plan (PEP).

5

• This is the total NSTX WBS which the Upgrade project follows.

• Not all elements applicable

• This is the total NSTX WBS which the Upgrade project follows.

• Not all elements applicable

• A product-oriented, hierarchical outline of all work elements required to accomplish the entire work scope of the project.

• Each element is decomposed to the Work Package level

• A product-oriented, hierarchical outline of all work elements required to accomplish the entire work scope of the project.

• Each element is decomposed to the Work Package level

Page 6: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Organization: Organizational Breakdown Structure (OBS)

• The Organization Breakdown Structure (OBS) can also be found the in the Project Execution Plan (PEP).

6

PPPL Laboratory DirectorS.Prager

Deputy Director for OperationsA. Cohen

Sources & ControlsM. Cropper

NBI Beamline Services, Duct, and

VV modsM. Denault

NBI ArmorK. Tresemer

NBI PowerR. Ramakrishnan

NTC EquipmentRelocation

E. Perry

Control Sys Data Acquisition

P.Sichta

Auxiliary SystemsW. Blanchard

ConstructionE. Perry

Integrated Testing/StartupC.Gentile

Centerstack Dsgn & FabJ. Chrzanowski

NSTX Upgrade Project Manager

R. StrykowskyDeputy and Construction

ManagerE. Perry

Project ControlsS. Langish

NSTX Centerstack ManagerL. Dudek

NSTX Neutral Beam Manager

T. StevensonEngineering Support

Sys Analysis: P. TitusSys Integr: C. NeumeyerSys Engr: R. Simmons

Associate DirectorM. Williams

Structures & SupportsM. Smith

Electrical SystemsR. Ramakrishnan

DiagnosticsR.Kaita

Centerstack PFCK. Tresemer

NSTX Upgrade ProjectFederal Project Director

J. MakielDeputy Federal Project Director

A.Indelicato

NSTX Program ManagerFusion Energy Sciences

B. Sullivan

Acquisition ExecutiveAssociate Director for

Fusion Energy SciencesE. Synakowski

PPPLNSTX UpgradeProject Team

DOE ProgramOffice

PPPLManagement

DOE SiteOffice

DOE Site ManagerContracting OfficerPrinceton Site Office

Best Practices & OutreachJ. Delooper

QA/QCJ. Malsbury

Env. Safety , Health & SecurityJ.Levine

Princeton UniversityPPPL Advisory Board

VPSW. Blanchard

Digital Coil ProtectionR. Hatcher

MPTS InterfaceG. Labik

Page 7: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Organization: Control Account

• All planning, scheduling, budgeting, work authorization and cost accumulation occur at the Control Account (intersection of WBS/OBS) as depicted on Responsibility Assignment Matrix (RAM).

7

Page 8: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Organization: Responsibility Assignment Matrix

8

• This is not the entire RAM• This is not the entire RAM

NSTX Upgrade Project Responsibility Assignment MatrixWBS Element Organization Breakdown Structure

L3 L4 L5 DESCRIPTIONControl Account Tresemer Smith Chrzanowski Cropper Stevenson Denault Raki Dudek BAC

LOE ($K) LOE (%)

1.1.0 Project Integrated Model (1000) 1000 X 385 193 50

1.1.1 Center Stack Upgrade (1001) 1001 X 2,169 0 0

1.1.1 Passive Plate Analysis and Upgrade Activity (1002) 1002 X 251 0 0

1.1.2 Vacuum Vessel and Support Structure (1200) 1200 X 3,554 0 0

1.1.3 Center Stack Upgrade Project Design Support (1300) 1300 X 1,063 1,063 100

1.1.3.2 Outer Toroidal Field Coils (1301) 1301 X 338 0 0

1.1.3.3.1 Center Stack – TF Inner Legs/Bundle(1304) 1304 X 2,595 0 0

1.1.3.3.1 TF Joint Stand and Performance Test (1303) 1303 353 0 0

1.1.3.3.2 Ohmic Heating Solenoid (1305) 1305 X 4,556 211 5

1.1.3.3.3 Inner PF Coils (1306) 1306 X 669 0 0

1.1.3.3.4 Center Stack Casing Job (1307) 1307 X 904 0 0

1.1.3.3.4 Center Stack Assembly (1302) 1302 X 990 0 0

1.1.3.3.4 Center Stack Magnets Systems 1310 Closed 442 0 0

Page 9: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

9

ANSI 748 Elements

Planning, Scheduling, & Budgeting

Organization

AccountingConsiderations

Revisions

- Define the work

-Assign responsibilities

-The Control Account

- Schedule all work

- Authorize all work

- Time-phase the work

- Develop cost accounts

- Costs Elements

- Cost summarization

- Understand contract status

- Use data for decision-making

Assignments made to responsible organizations

Maintenance of budget, work, and schedule relationships

Do not modify past budget or actuals (w/o permission)

All documents properly maintained

Analysis & Management Reports

Page 10: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling & Budgeting:Work Authorization

• Control Account Plan (CAM Notebook Tab 2) includes the following items:– Authorization Document

(WAD)– Resource Loaded Schedule

(Primavera)

– Work Approval Form (WAF) – Estimates, Risk, contingency etc. (On-line interactive Excel worksheet designed for CAM’s)

– WBS Dictionary– Budgeted Cost per month

10

Page 11: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling & Budgeting: WAFs

11

• Work is laid out in discrete WPs/PPs

• Estimated• Sequenced• Interdependancies• Time phasing• Risk/Contingency estimates• Review/Approval• Completed by the CAM ( Job

Manager) for each Control Account (Job)

Tab ACover/Approval Page

Tab ACover/Approval Page

Page 12: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling & Budgeting: WAFs

12

Tab BCost & Schedule Estimate

Tab BCost & Schedule Estimate

Page 13: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling & Budgeting: WAFs

13

Tab CRisk and Uncertainty

Tab CRisk and Uncertainty

Page 14: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling & Budgeting: WAFs

14

Tab DM&S Detail

Tab DM&S Detail

Page 15: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Schedule Process

15

ENG-053WAF Review

ENG-053WAF Review

Page 16: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling, and Budgeting:Resource Loaded Schedule (Primavera)

• Resource loaded schedule with sequenced work and task interdependencies.• This is result of WAF/WAD process.

16

Explain each of these columns…

Page 17: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling, and Budgeting: Milestones

• PEP Milestones shown in the project schedule. Level 1 and 2 Milestones shown.

17

Page 18: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

18

Planning, Scheduling, and Budgeting: Critical Path

Page 19: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

19

Planning, Scheduling, and BudgetingTime-phased Budget (from Cobra)

$k/month

Page 20: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

• Earned Value (EV) or Budgeted Cost of Work Performed (BCWP) is “earned” according to the Earned Value Technique assigned to the Work Package (Activity).– Discrete (typically used EVTs on NSTX-U)

• 0/100 (All EV earned when WP is completed)• 50/50 (50% earned when started, 50% earned when

finished – most future tasks < 40 days are 50/50)• % Complete (incremental earned based on assessment)

– Non-discrete• Level of Effort (LOE)

Planning, Scheduling, and Budgeting:Earned Value Techniques

20

Page 21: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

21

ANSI 748 Elements

Planning, Scheduling, & Budgeting

Organization

AccountingConsiderations

Revisions

- Define the work

-Assign responsibilities

-The Control Account

- Schedule all work

- Authorize all work

- Time-phase the work

- Develop cost accounts

- Costs Elements

- Cost summarization

- Understand contract status

- Use data for decision-making

Assignments made to responsible organizations

Maintenance of budget, work, and schedule relationships

Do not modify past budget or actuals (w/o permission)

All documents properly maintained

Analysis & Management Reports

Page 22: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

• Primary vehicle for recording labor costs is via the Timesheet Systems

• Report total time

22

Accounting Considerations: Timesheets

Page 23: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Accounting Considerations: Job Cost Reports

23

• Costs are captured on Job Cost Reports

• Labor (hours) by skill and name

• Subcontracts/Requisitions• RFBA process used to

correct errors (ref Accounting Manual – Tony Bleach)

• CAMs receive a copy of Job Cost Report before Monthly Status Meeting. (also available on-line for all of PPPL)

Control Account Numbers = Job Numbers

• Total monthly cost for the CA by expense element

• direct expenses 1x,2x,3x, & 4x• indirect expenses 5x,6x

Procurements

Labor (hours)

x labor rate

Page 24: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

• Loaded rates were used in the development of the Primavera P3 schedule.

• Based upon standard PPPL labor, overhead and escalation rates. Vetted by budget office.

• Indirect & Overhead rates controlled by the Budget office (ref Budget Office Manual- Marie Iseicz)

• P3 rates then transferred to Cobra

24

Accounting Considerations: RatesREVISED 10/26/10 BASELINE CD2 RATES**

P3 period --->01oct09 - 30sep2010

01oct10 - 30sep2011

01oct11 - 30sep2012

01oct12 - 30sep2013

01oct13 - 30sep2014

FY11Avg hourly rate wo/benefits P3 Res Code

FY 2010 Loaded Rates

FY 2011 Loaded Rates

FY 2012 Loaded Rates

FY 2013 Loaded Rates

FY 2014 Loaded Rates

$95.20 D///RM 196.42 207.51 227.56 232.34 240.21$80.28 E///AM 165.64 174.99 191.89 195.92 202.56$28.03 EA//CB 66.22 71.48 78.39 80.04 82.75$49.74 EA//DM 117.51 126.85 139.11 142.03 146.84$92.35 EA//EC1 147.25 153.08 167.23 170.10 175.20$92.35 EA//EC2 147.25 153.08 167.23 170.10 175.20$92.35 EA//EC3 147.25 153.08 167.23 170.10 175.20$92.35 EA//EC4 147.25 153.08 167.23 170.10 175.20$75.55 EA//EM 178.48 192.68 211.29 215.73 223.04$52.50 EA//ES1 83.71 87.02 95.07 96.70 99.60$71.00 EA//ES2 113.21 117.69 128.57 130.77 134.70$48.98 EA//SB 115.71 124.91 136.98 139.86 144.60$39.45 EA//TB 93.20 100.61 110.33 112.65 116.46$52.80 EC//AM 121.47 125.45 137.57 140.46 145.22$56.37 EC//EM 129.68 133.93 146.87 149.95 155.03$42.90 EC//SB 98.69 101.93 111.77 114.12 117.99$58.56 EC//SM 134.72 139.13 152.57 155.78 161.06$28.59 EC//TB 65.77 67.93 74.49 76.05 78.63$29.33 EC//TS1 46.77 48.62 53.11 54.02 55.64$41.12 EE//AM 95.02 101.28 111.07 113.40 117.24

$100.00 EE//EC1 159.45 165.76 181.08 184.19 189.72$100.00 EE//EC2 159.45 165.76 181.08 184.19 189.72$100.00 EE//EC3 159.45 165.76 181.08 184.19 189.72$70.19 EE//EM 162.20 172.89 189.59 193.57 200.13$50.60 EE//SB 116.93 124.63 136.67 139.54 144.27$63.06 EE//SM 145.72 155.32 170.33 173.91 179.80$34.08 EE//TB 78.75 83.94 92.05 93.99 97.17$89.95 EM//EC1 143.42 149.10 162.88 165.68 170.65$89.95 EM//EC2 143.42 149.10 162.88 165.68 170.65$61.25 EM//EM 145.33 158.21 173.49 177.14 183.14$46.83 EM//SB 111.11 120.96 132.65 135.43 140.02$60.93 EM//SM 144.57 157.38 172.58 176.21 182.18$36.04 EM//TB 85.51 93.09 102.08 104.23 107.76

EM//ST (sb tb hybrid) 91.13 99.21 108.79 111.08 114.84$70.03 FC//AC1 111.66 116.08 126.81 128.99 132.86$65.51 FC//AM 146.65 162.79 178.51 182.26 188.44$71.37 R///RM 157.56 171.13 187.65 191.60 198.09$30.81 R///RMQ 68.02 73.87 81.01 82.71 85.51$60.27 RC//EM 133.05 144.51 158.47 161.80 167.28$37.62 LP//TB 116.43 123.00 134.88 137.72 142.39

1.00 31 1.818 1.906 2.022 2.056 2.1181.00 35 1.232 1.263 1.294 1.327 1.3601.00 39 1.594 1.699 1.793 1.815 1.8611.00 41 1.178 1.255 1.286 1.318 1.3511.00 48 1.000 1.025 1.051 1.077 1.1041.00 54 1.594 1.658 1.758 1.788 1.842

FY2010 FY2011 FY2012 FY2013 FY2014PPPL Labor Benefits 29.4% 31.5% 32.0% 32.5% 33.0%EC Burden (5322) 11.5% 9.0% 9.0% 9.0% 9.0%EM Burden (5323) 15.0% 18.5% 18.5% 18.5% 18.5%EE Burden (5325) 12.0% 13.0% 13.0% 13.0% 13.0%EA Burden (5326) 14.5% 17.0% 17.0% 17.0% 17.0%Overtime Burden (53) 14.0% 15.0% 15.0% 15.0% 15.0%Research Burden (52) 7.0% 10.0% 10.0% 10.0% 10.0%HP Burden (55) 50.0% 50.0% 50.0% 50.0% 50.0%P&CO Burden (56) 8.5% 14.0% 14.0% 14.0% 14.0%Travel Burden (61) 10.5% 10.0% 10.0% 10.0% 10.0%Site Burden (62) 43.0% 48.0% 52.4% 50.5% 50.5%MHX Burden (64) 16.0% 20.0% 20.0% 20.0% 20.0%LDRD (67) 0.0% 0.0% 0.0% 0.0% 0.0%Sci Ed (68) 0.0% 0.0% 0.0% 0.0% 0.0%G&A (69) 11.5% 12.0% 12.0% 12.0% 12.0%labor escalation 0.0% 0.0% 3.0% 3.0% 3.0%Non labor escalation 0.0% 2.5% 2.5% 2.5% 2.5%

labor escalation compounded 1 1.0000 1.0300 1.0609 1.0927non labor escalation compounded 1 1.0250 1.0506 1.0769 1.1038

Page 25: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Accounting Considerations:Subcontracts with EV Flow-down

• The earned value flow-down subcontracts are generally high dollar value high-risk subcontracts. These subcontracts require careful planning prior to solicitation and award. The solicitation (RFP) or Memorandum of Understanding (MOU) must include the proper language and the subcontract the appropriate contract clauses, including full description of the reporting requirements. The reporting requirements include monthly earned value, and performance reporting from the subcontractor to PPPL. Requirements for reporting are described in the Request for Proposal (RFP) and formalized in

the contract.

25

Page 26: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Monthly Statusing

26

Page 27: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Status: Monthly Calendar

27

Monthly EVMS calendar posted at the bottom of the CAM notebook web site

Page 28: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Status:Initiation Email

28

Job Number

Activity ID Activity Name EVMS Rule

Act. % Comp

Updated % Comp

Forecast Finish

ETC-EAC Change

BL Start BL Finish

7100CS7000031 FY2011 Project Management A 82.4 10/01/2010 09/30/2011

7100CS7000031G FY2011 General Arrangement Drawings

A 82.4 10/01/2010 09/30/2011

7100CS7000031R FY2011 Project Reviews A 82.4 10/01/2010 09/30/2011

7100CS7000041 FY2012 Project Mangement A 0 10/03/2011 09/28/2012

7100CS7000041G FY2012 General Arrangement Drawings

A 0 10/03/2011 09/28/2012

7100CS7000041R FY2012 Project Reviews A 0 10/03/2011 09/28/2012

Page 29: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Status: Monthly Status Process

29

Page 30: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Status: EVMS Data Flow

30

Page 31: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Planning, Scheduling, & Budgeting

Organization

AccountingConsiderations

Revisions

- Define the work

-Assign responsibilities

-The Control Account

- Schedule all work

- Authorize all work

- Time-phase the work

- Develop cost accounts

- Costs Elements

- Cost summarization

- Understand contract status

- Use data for decision-making

Assignments made to responsible organizations

Maintenance of budget, work, and schedule relationships

Do not modify past budget or actuals (w/o permission)

All documents properly maintained

Analysis & Management Reports

ANSI 748 Elements

Page 32: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Analysis & Management Reports:Contract Performance Reports (CPR Formats 1,2,3)

32

Page 33: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Analysis & Mngmt Reports: PPPL’s CPR Format 2 Type Report

33

Page 34: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Analysis & Management Reports:Format 5 Explanations & Problem Analyses• Thresholds are specified in the PEP• Variance reported when any WBS Level 2 cumulative to

date variance exceeds:– SV +10% AND >$50K or any impact on any DOE Level 1 or 2

Milestone– CV +10% AND >$50K – Upcoming PEP draft makes above a bit less restrictive

• CAM for Control Account which is driving the variance prepares analysis report (this has been added to draft change being made to PEP)

• Project Manager may also choose to request a VAR for further variance explanation/analysis

34

Page 35: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Variance Reporting Process

35

Page 36: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Analysis & Management Reports:Format 5 Explanations & Problem Analyses

36

Page 37: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

• PPPL PMSD (Procedure 8 Monthly Status Reporting) indicates the following for ETC– On a monthly basis, the CAM shall review the Estimate to Complete

(ETC) for the elements of their control account. If, in the judgment of the CAM, the current ETC does not accurately reflect the cost for the remaining work in the control account, the CAM develops a new estimate and submits it to the Project Manager. CAMs should include in the ETC any cost variances to date as well as estimates for known pending changes and mitigation of known risks.

37

Analysis & Management Reports: Estimate at Complete

Page 38: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Analysis & Management Reports: Estimate at Complete

• Bottoms up estimate required every 6 months by PEP• Last completed in June• Monthly EAC/ETC updates gathered in monthly update/status

meetings

38

Page 39: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Analysis & Management Reports:June Bottom’s Up

39

Page 40: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

40

ANSI 748 Elements

Planning, Scheduling, & Budgeting

Organization

AccountingConsiderations

Revisions

- Define the work

-Assign responsibilities

-The Control Account

- Schedule all work

- Authorize all work

- Time-phase the work

- Develop cost accounts

- Costs Elements

- Cost summarization

- Understand contract status

- Use data for decision-making

Assignments made to responsible organizations

Maintenance of budget, work, and schedule relationships

Do not modify past budget or actuals (w/o permission)

All documents properly maintained

Analysis & Management Reports

Page 41: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Revisions & Data Maintenance: Change Control Process

41

Page 42: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Revisions & Data Maintenance:Change Control Thresholds

• Thresholds are specified in the PEP

42

Page 43: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Revisions & Data Maintenance:Engineering Change Proposals (ECPs)

• Procedure NSTXU-PROC-001 NSTXU Configuration Control is the vehicle to incorporate authorized changes in budgets and schedules.

43

Page 44: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Revisions & Data Maintenance:Engineering Change Proposals (ECPs) Log

44

NSTXU-ECP- WBS

Control Account Description of Change

Approval

Level In $KContract Budget

Base (CBB) ContingencyTotal Project Cost

(TPC)Date

             Increase/

BalanceIncrease/

BalanceIncrease/

BalanceDecrease Decrease Decrease

1 1.7.1.5 7700/7710Combine CA 7700 & 7710 into one CA (7710) Direct Allocations

25-Apr-11 3 $0 $0 $77,317 $0 $16,992 $0 $94,309

2 1.6 6100Move the Baseline Start date for task 6100-0041 to 12 April 2012

8-Jun-11 3 $0 $0 $77,317 $0 $16,992 $0 $94,309

3 1.6 6100Reduce man-hours on task 6100-0041. Add this budget as M&S in task 6100-0049D

19-Sep-11 3 $0 $0 $77,317 $0 $16,992 $0 $94,309

4                        

5                        

http://nstx-upgrade.pppl.gov/Engineering/ProjectStatus/Configuration_Control/ECPindex.htm

Page 45: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

• http://www-local.pppl.gov/EVMS/CAMNB/INDEX.htm

CAM Notebooks

45

Page 46: Princeton University Plasma Physics Laboratory EVMS Certification Review EVMS Implementation on NSTX-U Steve Langish October 4 - 6, 2011

Questions

Questions ???