    ROLTA INDIA LIMITED REV : NEW GSD-307

    DOCUMENT NUMBER : GSD - 307

    REVISION : NEW

    ROLTAMANUAL OF INSTRUCTIONS

    SUBJECT : Standard Geospatial Services Procedure for Software Development

    PURPOSE : To provide details of steps to follow for Software Development

    Authorization Name Date

    Prepared by: Mahesh Wankhedekar Sept 2009

    Reviewed by Deepak Vedak Sept 2009

    Approved by (DO) Bob Britton

    Page 1 of14

  • 8/6/2019 Procedure for Software Development

    2/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    REVISION HISTORY

    Revision No. Date PageParagraph/

    SectionNature of Change

    Page 2 of14

  • 8/6/2019 Procedure for Software Development

    3/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    INDEX

    S.N. Title Page No

    1 Purpose 5

    2 Scope 5

    3 Definitions & Acronyms 5

    4 Responsibilities 6

    5 Software Request Origin 6

    6 Software Development 8

    7 Processing in Applications 11

    8 Security of System Files 12

    9 Handling Change Request 13

    10 Software Development Process Flow 15

    11 Software Request Form 16

    Page 3 of14

  • 8/6/2019 Procedure for Software Development

    4/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    Purpose

    This procedure defines the implementation of Software Development system in accordance

    with the requirements of ISO/IEC 27001:2005 standard. This procedure defines the method

    for maintaining the security of application system software and information occurring in

    GSD through a formal process. This procedure also ensures that all the software requests

    are documented and maintained properly for possible re-use in future.

    2.0 Scope

    This procedure applies to the control of documents and data pertaining to the projects and

    groups of GSD SBG, which are within the scope of implementation of Information Security

    Management System.

    3.0 Definitions & AcronymsISMS Information Security Management System

    Author Document Person designated to create or revise a document

    Document ISMS procedure, work instruction, manual, or associated form,

    which is used to control the processes.

    Signature/Sign Handwritten, electronically written, or electronically typed name

    of an individual that indicates an act of approval, disapproval,

    review, etc.

    Procedure A specified way to carry out a process or activity.

    Record Document established to provide evidence of conformity to

    requirements.

    Report Document describing the finding about an activity or incident.

    ISM Information Security Manager

    SVN SVN

    QA Quality Assurance

    DDD Design Data Document

    CR Change Request

    IPR Intellectual Property Rights

    Page 4 of14

  • 8/6/2019 Procedure for Software Development

    5/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    4.0 Responsibilities

    The responsibilities for Software request Handling are distributed as follows:

    4.1 The Software program Requestor shall:

    4.1.1 Identify requirement of new routines or enhancement in the existing routine.4.1.2 Report the same to the Software Manager through online Software request

    form.

    4.2 The respective Department Administrators shall:

    4.2.1 Review the software request for feasibility and approve its implementation.

    4.3. The Software Manager shall:

    4.3.1 Act on the Software (Program) Request received.

    4.3.2 Estimate time required to complete the software program, assign

    development task to software developers.

    4.3.3 Undertake regular reviews of the effectiveness of the ISMS taking into

    account results of reports, suggestions and feedbacks.

    4.4. The software developer shall:

    4.4.1 Investigate and determine the details of the software requirement.4.4.2 Check and confirm, if all parameters required to build the software are

    provided by the requestor.

    4.5. The Executive Director shall:4.5.1 Provide appropriate resources to support the ISMS, maintain and continually

    improve the ISMS.4.5.2 Carry out reviews of software request reports and react appropriately to the

    results of the reviews.

    5.0 Software Requests Origin

    5.1 Origination of requisition of software Program

    Requests for Software program originate from different sources and at different stages of aProject. Basically, the needs for software programmes are realized at the time of a) Project

    initiation or when the b) Project is already under production.

    a) Pilot Projects:

    Most of the requests for software program find their origin at the time of

    1. Project Kick-off meeting

    Page 5 of14

  • 8/6/2019 Procedure for Software Development

    6/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    2. Finalizing Project specifications

    3. Identifying deviation from specifications

    4. Project Meeting comprising of Technical Support team, QA team and the

    project manager.

    b) Projects already under Production:

    Most of the software enhancements find their origin at the time when the software is

    being used in production. Some new routines also are requested at this stage, but

    their numbers are few compared to the initial stages.

    Software requests are reported through the online software request form. This form also

    helps in the Software review process and serves as a database that helps prevent re-

    producing the same software.

    6.0 Software Development

    6.1 Planning Stage

    The planning stage establishes an overview of the intended software product, anduses this to establish the basic project structure, evaluate feasibility and risks

    Page 6 of14

    Project

    Planning

    Requirements

    Definition

    Design

    Development

    Integration &

    Test

    Installation &

    Acceptance

  • 8/6/2019 Procedure for Software Development

    7/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    associated with the project, and describe appropriate management and technicalapproaches.

    High Level Product requirements are listed out which percolate down to defining allsoftware product requirements. Each requirement is recorded with some minimum

    information like title and textual description; although in some instances additionalinformation and references to external documents are included.

    6.2 Requirement Definition Stage

    The requirements gathering process takes as its input, the goals identified in the high-level

    requirements section of the project plan.

    In this stage, major Function, like input & output data validation, critical processes to be

    managed, as well as mission critical inputs, outputs and reports, of the intended application

    are defined.

    The requirements are fully describe in the Requirements Document. This document contain

    complete descriptions of each requirement, including diagrams and references to external

    documents as necessary.

    The outputs of the requirements definition stage include the requirements document and

    an updated project plan.

    6.3 Design Stage

    The design stage takes as its initial input the requirements identified in the approved

    requirements document. For each requirement, a set of one or more design elements may

    be produced.

    Design elements describes the desired software features in detail, and generally include

    functional hierarchy diagrams, screen layout diagrams, tables of business rules, business

    process diagrams, pseudo-code, and a complete entity-relationship diagram with a full data

    dictionary.

    These design elements describe the software in sufficient detail that skilled programmersmay develop the software with minimal additional input.

    The outputs of the design stage are the design document and an updated project plan.

    6.4 Development Stage

    Page 7 of14

  • 8/6/2019 Procedure for Software Development

    8/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    The development stage takes as its primary input the design elements described in theapproved design document.

    For each design element, a set of one or more software artifacts may be produced.

    All software codes are maintained on Tortoise SVN (SVN) for ensuring Version

    Maintenance, revision history, etc. All codes relating to a project are stored in a folder

    created for that particular project. Only software developers and other important team

    members assigned for that project have privilege to view the contents of this folder for

    security reasons.

    The outputs of the development stage include a fully functional set of software that satisfiesthe requirements and design elements previously documented, and an updated projectplan.

    6.5 Integration & Test Stage

    During the integration and test stage, the software artifacts, online help, and test data are

    migrated from the development environment to a separate test environment.

    The software, in the encrypted format, along with the DDD is provided to the testing team

    who perform the entire test using the test cases prepared by them.

    All the modules of the software provided to the testing team are in encoded format to

    ensure security and prevent leakage of code.

    The outputs of the integration and test stage include an integrated set of software, an

    acceptance plan, which contains the final suite of test cases, and an updated project plan.

    6.6 Installation & Acceptance Stage

    During the installation and acceptance stage, the software artifacts and initial production

    data are loaded onto the production server. All test cases are run to verify the correctness

    and completeness of the software. Successful execution of the test suite is a prerequisite

    to acceptance of the software by the customer.

    After customer personnel have verified that the initial production data load is correct and

    the test suite has been executed with satisfactory results, the customer formally accepts

    the delivery of the software.

    Page 8 of14

  • 8/6/2019 Procedure for Software Development

    9/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    The primary outputs of the installation and acceptance stage include a production

    application, a completed acceptance test suite, and a memorandum of customer

    acceptance of the software.

    After receipt of acceptance, the project is locked by Project Manager, by archiving all

    software items, the implementation map, the source code, and the documentation for

    future reference.

    7.0 Processing in ApplicationsAppropriate controls are designed into applications, including user developed applications

    to ensure correct processing. These controls include the validation of input data, internal

    processing and output data.

    Input Data Validation

    Data input to application is validated to ensure that this data is correct and appropriate. The

    following check-list is referred to while preparing validation for any application:

    1. Limiting fields to specific input data to detect following errors

    a. Out-of-range values

    b. Invalid characters in data fields

    c. Missing or incomplete data

    d. Exceeding upper and lower data volume limits

    e. Unauthorized or inconsistent control data

    2. Periodic review of the content of key fields to confirm their validity and integrity

    3. Inspecting hard-copy input documents for any unauthorized changes4. procedures for responding to validation errors

    5. procedures for testing the plausibility of input data

    Control of Internal Processing

    Validation checks are incorporated into applications to detect any corruption of information

    through processing errors or deliberate acts.

    The design and implementation of applications ensures that the risks of processing failures

    leading to a loss of integrity are minimized.

    Some specific areas:

    1. The use of add, modify and delete functions to implement changes to data.

    a. For any one of these functions, all other are disabled

    b. Error handling if any deviation occurs than the intended purpose

    Page 9 of14

  • 8/6/2019 Procedure for Software Development

    10/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    2. A database is maintained for all application running in batch mode; the status of

    all processes is maintained in the database and the next process initiates only

    after the successful completion of the previous process.

    3. Protection against attacks using buffer overruns/overflows.

    Output Data Validation

    Data output from application is validated to ensure that the processing of stored information

    is correct and appropriate to the circumstances.

    Output validation includes

    1. Plausibility checks to test whether the output data is reasonable.

    2. reconciliation control counts to ensure processing of all data

    3. providing sufficient information for a reader or subsequent processing system to

    determine the accuracy, completeness, precision and classification of the

    information

    8.0 Security of System Files

    Access to system files and program source code is controlled and IT projects and support

    activities are conducted in a secure manner. Care is taken to avoid exposure of sensitive

    data in test environments. All program source codes are stored and maintained on SVN.

    Control of operational software

    The updating of operational software applications are only performed by trainedadministrators upon appropriate management authorizations.

    Applications and operating system software are implemented only after extensive and

    successful testing.

    The operational software applications are handed over to the IPR department who keeps a

    control of all implemented software as well as the system documentation.

    Previous versions of application software are retained and are archived together with all

    required information and parameters, configuration details and supporting software.

    Access control to program source code

    Access to program source code and associated items are controlled, in order to prevent

    the introduction of unauthorized functionality and to avoid unintentional changes. This is

    achieved by central storage of codes in Tortoise SVN.

    Page 10 of14

  • 8/6/2019 Procedure for Software Development

    11/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    SVN configuration: Client-Server configuration

    An organized, central storage location for the projects software codes

    A method for applying meaningful descriptions to every project folder and everysource code

    Security against multiple writers updating the same code simultaneously

    Added file protection with backup utilities

    Prevents leakage of information since only authorized users can access the datastored in SVN

    9.0 Handling Change Request (CR)

    Software development or modifications due to deviations from the DDD, arising from

    additional requirements identified by the client or otherwise, should be controlled

    systematically.

    1. All software codes and DDD are maintained on the Tortoise SVN database,

    which automatically maintains version history and assigns version numbers to

    the latest modified code or document.

    2. For identifying changes in code vis--vis changes required by client, all the

    software codes carry appropriate comments.

    3. The changes in specifications or any additional requirements are received

    through a Change request template only which is duly signed or authorized by

    the issuing party.

    4. Any Change in request is reviewed for any possible changes it may require on

    any other procedure.

    5. All CR, after implementation, result in updating the DDD and the old version is

    identified or disposed accordingly.

    6. Every change in software is made only with a proper CR in place.

    7. Implementation of CR is ensured and track of all CRs is maintained in a CR

    Database.

    8. CR requiring change in operating system is reviewed and tested the process

    of incorporating this change follows the normal change request process flow.

    (as shown in the following flow chart)

    Page 11 of14

  • 8/6/2019 Procedure for Software Development

    12/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    Process flow of Change Request

    Page 12 of14

    Identify change

    in Specification

    Request Client to

    issue an ECR

    Receive Client

    Approval for the

    ECR

    A document describing thedetails of additional work along

    with the effort estimation is sentto the Client

    Identify the need of

    any additional

    routines / modifyingexisting ones

    Modify / Add

    routine as

    required.

    Study relatedprocess/routine for any

    changes required.

    Data reviewed

    by QA / Client

    for confirmation

    of ECR

    implementation

    All routines are

    maintained on SVN andchanges are tracked.

    Close the ECR

    Modifications

    acceptable?

    No

    Yes

    Update the CR

    Database with the

    new entry.

    Update the CR

    Database

    accordingly.

  • 8/6/2019 Procedure for Software Development

    13/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    10.0 Software Development Process Flow

    Page 13 of14

    Receive request for new software/modification of existing software through

    the online form

    Department Manager evaluates thefeasibility of the software and approves

    the implementation

    Software Manager estimates the time requirement of developing the softwareand assigns the task to the concerned software developer

    The software developer verifies if all requirements to develop routine are furnished by the

    requestor, before starting the development of the routine

    The software developer releases the software tothe requestor and changes the status of software

    to Closed

    The requestor, after checking the softwareagainst his requirements, requests the QA to

    certify.

    On QA Certification, the software isreleased for final use.

    QA tests the software vis--vis requirements.

    QA Pass

    QA Fail

    AA

    B

    DevelopmentissueRequesting issue

    Return toA

    Return toB

  • 8/6/2019 Procedure for Software Development

    14/14

    ROLTA INDIA LIMITED REV : NEW GSD-307

    11.0 Software Request Form

    Description of the software requirement can be written in area provided against Routine

    Details. Also, provision to attach relevant documents is available.

    Page 14 of14