Upload
buithuan
View
223
Download
2
Embed Size (px)
Citation preview
Country ReportI&C Overview of NPPs at Pakistan
Waseem Uddin FarooqiDirector (I&C), DNPEP, PAEC
26th Meeting of the IAEA Technical Working Group
on Nuclear Power Plant Instrumentation and Control
24-26 May 2017
Vienna, Austria.
Presentation Layout
• Introduction
• Current Status of I&C in NPPs
• I&C Modernization in NPPs
• Modifications under FRAP
• R&D Project
• Recommendations
2
NPPs in Pakistan
S. No. Name Location Capacity Type Date of CommercialOperation
1 KANUPP-1 (K-1) Karachi 137/98 MWe PHWR Dec. 1972
2 CHASHNUPP-1 (C-1) Chashma 325 MWe PWR Sep. 2000
3 CHASHNUPP-2 (C-2) Chashma 340 MWe PWR May 2011
4 CHASHNUPP-3 (C-3) Chashma 340 MWe PWR Dec. 2016
5 CHASHNUPP-4 (C-4) Chashma 340 MWe PWR Under Commissioning
6 KANUPP-2 (K-2) Karachi 1100 MWe PWR Under Construction
7 KANUPP-3 (K-3) Karachi 1100 MWe PWR Under Construction
4
Type MW Shares
Hydel 32,660 20.1%
Oil 7,760 4.8%
Gas 83,760 51.5%
Coal 19,910 12.2%
Nuclear 8,800 5.4%
Renewable 9,700 6.0%
Total 162,590 100.0%
Source: Planning Commission, Medium Term Development Framework, 2005-10
Electricity generation capacity in 2030
GOP Target for Nuclear Power in
Energy Security Plan
7
Current Status of I&C in NPPs
8
S. No. System C-1/C-2/C-3/C-4 K-2/K-3
1 Reactor Protection System
Two Loop System Architecture,Conventional, Hardwired, Modular
Three Loop enhanced System Architecture,Conventional, Hardwired, Modular
2 Nuclear Instrumentation System
2SR, 2IR, 4PR Neutron Detectors 4SR, 4IR, 4PR Neutron Detectors
3 In-Core Instrumentation System
Periodic Flux Monitoring, 30 locations, 03 Miniature fission chambers , 36 TC
Continues Flux Monitoring,44 locations, 7 Self powered neutron detectors per location, 46 TC
4 Process and Control System
Conventional sensors and transmitters, PID controllers, PLC/DCS Based Instrumentation in Conventional Island
Conventional sensors and transmitters, conventional controllers for safety, DCS based for non safety
Current Status of I&C in NPPs
9
S. No. System C-1/C-2/C-3/C-4 K-2/K-3
5 Plant Computer System
Plant Monitoring, Data Logging,Alarm Surveillance
Plant Monitoring & Control, Data Logging, Alarm Surveillance
6 Main Control Room System
Control: ConventionalMonitoring: Digital /Analog
Control: Analog/ DigitalMonitoring: DigitalComputerized Operating Procedures
Need for I&C Modernization
• Ageing & Obsolescence are major factor for I&C
modernization at NPPs
• Ageing is the degradation of I&C system /equipment
with time and use
• Obsolescence is the result of unavailability of spare
parts, loss of the suppliers, new regulatory requirements,
emerging technologies etc. 10
• Following major Up gradation were carried out at K-1:
1) Replacement of Plant Computer System
2) Replacement of Instrumentation Loops
3) Replacement of Process Information System
4) Replacement of Fuel Handling Computer
5) Installation of Fire Alarm System
6) Replacement of Metrological Instrumentation
7) Installation of Safety Parameter Display System
8) Installation of Post Accident Monitoring System
11
I&C Modernization Project at K-1
Fuel Manipulator Crane (FMC) at C-1
13
• FMC control system Upgradation was carried out during
RFO-07 (2011) indigenously by PAEC
• Old PLC based control system was upgraded by
advanced PLC & HMI with enhanced features
14
• MSR, Temperature Control System (RTC) Upgradation
was carried out during RFO-09 (2014) indigenously.
• Conventional modular system was replace by PLC
based advanced system with “Touch Panel” for HMI in
MCR
MSR RTC Up-gradation at C-1
15
• CPC HMI Station up-gradation was carried out during
RFO-09 (2014) indigenously by PAEC
• The color graphics terminal was replaced with HMI,
based on general purpose industrial computers
Plant Computer System (CPC) at C-1
March 1, 2016
16
• ETS up-gradation was carried out during RFO-10 (2016)
indigenously by PAEC
• Replacement of obsolete PLCs along with operator test
panel, with latest PLCs along with HMI
Emergency Turbine Trip System (ETS)
at C-1
17
• CRV Train-B was replaced during RFO-10 (2016) and
replacement of CRV Train-A is planned in RFO-11,
indigenously by PAEC
• Obsolete computer was replaced with advanced PLC &
HMI having Enhanced Features
Reactor Vessel Level
Monitoring System (CRV) at C-1
18
• CDA System was up-graded during RFO-10 (2016)
indigenously by PAEC
• The older system was replaced with FPGA based data
acquisition system
MCR Data Acquisition System (CDA)
at C-1
19
• CPF System was up-graded during RFO-10 (2016)
indigenously by PAEC
• The obsolete computer with DOS interface was replaced
with advanced embedded controllers
Plant Fire Detection, Alarm &
Protection Control System (CPF)
20
• Up-gradation of DEH is currently in progress during
RFO-11 ,carried out by PAEC & Shanghai Xinhua, China
• The older system will be replaced with advanced DCS
based system
DEH Up-gradation at C-1
I&C Modifications at C-2
• Addition of temperature monitoring of MG Set and other
cooling pumps on local panel & Plant Computer
• Addition of time delay in Reactor Coolant Pump (RCP)
upper bearing oil level low
• Replacement of In-core Nuclear Instrumentation System
distribution cabinet in reactor building
• Replacement of Circulating Cooling Water pump rubber
bearing and Cooling Water flow switches
• Replacement of RCP A/B thermal dispersion (FCI) level
switches with float type21
Fukushima Response Action Plan
• In response to Fukushima NPPs Accident PAEC
Corporate office developed and issued Fukushima
Response Action Plan (FRAP) for KANUPP and
CNPGS in August 2011
• Post Fukushima assessment of each nuclear power
plants was conducted as a part of FRAP
• Issues identified during the assessment were addressed
in the form of various activities to be undertaken at
C-1/C-2 and K-1
• In this regard following are some important electrical and
I&C related modifications carried out at NPPs
22
FRAP
E&IC Modifications at K-1
23
• Environmental Gamma Radiation Monitoring (EGRM)
network installed
• An Emergency Control Center (ECC) is available on site
and Alternate Emergency Control Center (AECC) is
away from site
• Necessary plant documents / procedures are available at
AECC
• Satellite phone has also been made available beside the
already available land-line and mobile communication
facilities.
• Portable Diesel Generator(DG) is also available at AECC
FRAP
E&IC Modifications at K-1
24
• Energization scheme of plant essential busses via
portable 300 kVA DG has been implemented
• A 375 kVA DG has been installed to energize essential
buses
• Energization scheme of essential buses through DGs (2
x 500 kVA) for extended SBO, has also been
implemented
• Installation of Accident Monitoring Instrumentation (AMI)
loops is in progress
FRAP
E&IC Modifications at K-1
25
• 230 VDC conserved from 01 hr to 07 hrs.
• DGs (2x100 kVA) installed (at higher elevation) for
continuous charging of station batteries
• Alternate power from 220 VAC UPS provided to medium
pressure ECCS MOVs
• Emergency lighting shifted from 230V DC to 220V AC
UPS to further conserve DC power
• Up-gradation of some fire alarm loops is underway
FRAP
E&IC Modifications at C-1/C-2
26
• One AECC exists at site, another is under consideration
further away from site
• Movable diesel generator are made available
• Alternate communication equipment is provided at MCRs
and also at ECCs
• Replacement of pneumatic type fire detectors with flame
detectors at Main and Auxiliary Transformer
FRAP
E&IC Modifications at C-1/C-2
27
• Installation of fire detectors in power cabinets
• A dedicated DG for use as DC Batteries charger with
hook-up arrangements has been installed
• A procedure “DC Load Shedding” is under preparation
which will be made part of SEOP, “Loss of all AC”
• Increased DC power capacity from 02 hours time to 07
hours
R&D Project on Smart Calibration &
Ageing
• To supplement the periodic maintenance, R&D of smart
calibration for I&C equipment is being conducted at
DNPEP, PAEC
• Mathematical model based estimation of calibration
related parameters of faulty equipment in I&C loops
• Abstract of the research work is already summited for
consideration in ISOFIC 2017
28
R&D Project on Smart Calibration
& Ageing
• Project Methodology
• Plant telemetry is acquired by the estimator
• Dynamic mathematical model is used to estimate the
equipment parameters
• Estimated values will show the effects of ageing and any
calibration requirements
• Project Benefits
• Online/offline analysis capability
• Enhanced process availability, low calibration /
maintenance workout, and improved ageing management
31-May-17
29
Recommendations to IAEA
• Guidelines on comparative and analytical aspects on
international codes & standards
• Digital I&C Systems review, evaluation, life cycle
management and V&V
• Digital MCR HFE design & review methods
• I&C aspects of computerized operator support systems
• Roadmap of Cyber Security implementation
• Cost effective I&C modernization techniques
• Active involvement of member states in the preparation &
review I&C related publications30
Special Thanks for Contributors
.
• Mr. Saeed –Ur– Rahman, GM (CNPGS)
• Mr. Sami Uddin, Director (NPS)
• Mr. Abdul Razzaq, Manager (I&C), C-1
• Mr. Maraj Khalid, Manager (I&C), C-2
• Mr. Muhammad Farooq, Manager (I&C), C-3
• Mr. Ahmed Yar, SE, DNPEP
• Mr. Aqeel ,SE, DNPEP
• Mr. Naveed A. Khan, SE, DNPEP
31