Production Control & Planning (Part 2)

Embed Size (px)

Citation preview

  • 8/9/2019 Production Control & Planning (Part 2)

    1/328

    Topic 3

  • 8/9/2019 Production Control & Planning (Part 2)

    2/328

    By the end of this topic, you should be able to: Define inventory;

    State the functions and types of inventory;

    List the requirements for effective inventorymanagement;

    Identify inventory models for independent demand;

    Explain dependent inventory model requirement;

    Describe the MRP structure; and Determine lot-sizes in a MRP system.

    2

  • 8/9/2019 Production Control & Planning (Part 2)

    3/328

    Inventory

    Why do you think that Inventory isimportant for an organization?

    Stored resource that is used tosatisfy current or future need iscalled inventory.

  • 8/9/2019 Production Control & Planning (Part 2)

    4/328

    Functions of Inventory

    To provide a stock of goodsTo avoid shortages or stock-outs due to

    bad weather, quality problems orimproper delivery.To reduce the cost of goods by

    minimizing purchasing and inventory

    costTo allow operations to continue smoothly

    with the use of work-in-processinventory.

  • 8/9/2019 Production Control & Planning (Part 2)

    5/328

    Inventory

    types

    Raw materialWork-in-progress

    (WIP)

    Maintenance/

    Repair/Operating

    (MRO)

    supply

    Finished

    good

    5

  • 8/9/2019 Production Control & Planning (Part 2)

    6/328

  • 8/9/2019 Production Control & Planning (Part 2)

    7/328

    1010 2020 3030 4040 5050 6060 7070 8080 9090 100100Percentage of itemsPercentage of items

    Percentageof

    dollarv

    alue

    Percen

    tageof

    dollarv

    alue

    100100

    9090

    8080

    7070

    6060

    5050

    4040

    3030

    2020

    1010

    00

    Class C

    Class A

    Class B

  • 8/9/2019 Production Control & Planning (Part 2)

    8/328

    ABC analysis - steps

    1. Classify the items of inventories, determining theexpected use in units and the price per unit for eachitem.

    2. Determine the total value of each item by multiplyingthe expected units by its units price

    3. Rank the items in accordance with the total value,giving first rank to the item with highest total valueand so on.

    4. Compute the ratios (percentage) of number of units ofeach item to total units of all items and the ratio oftotal value of each item to total value of all items.

    5. Combine items on the basis of their relative value toform three categories: -A, B and C.

  • 8/9/2019 Production Control & Planning (Part 2)

    9/328

    ABC analysis - example

    A firm has 7 different items in its inventory. The firm wishes tointroduce an ABC inventory system. Suggest a breakdown of theitems into A, B & C classifications

  • 8/9/2019 Production Control & Planning (Part 2)

    10/328

    ABC analysis - example

  • 8/9/2019 Production Control & Planning (Part 2)

    11/328

    Activity 8

    Rank the itemsand assignthem to theA,B or C class

    Item RM Value AnnualUsage

    1 0.01 1200

    2 0.03 1200003 0.45 100

    4 1.00 44000

    5 4.50 9006 0.90 350

    7 0.30 70000

    8 1.50 200

  • 8/9/2019 Production Control & Planning (Part 2)

    12/328

    Inventory models

    Independent demandsdemands of various items

    unrelated to each other

    Dependant demandsneed of any one item is

    the need for some other item

    12

  • 8/9/2019 Production Control & Planning (Part 2)

    13/328

    Holding Cost cost associated with maintaining the inventory warehouse and

    protecting

    Setup Cost

    arranging specific equipment setups, filling out the required papersand moving out the previous stock of material

    Ordering Cost

    clerical cost to prepare the purchase and production order such as

    counting items and calculating order quantities

    Shortage Cost

    Associated with demand when stocks have been depleted. Whensales are lost because of stock-outs, the firm loses both profit marginon unmade sales and its customers good will. Some will even sufferwith lateness penalties.

  • 8/9/2019 Production Control & Planning (Part 2)

    14/328

    Inventory models

    Fix-order Quantity/

    EOQ model

    Fixed-time Period/

    Fixed Order

    Interval System

    Quantity Discount

    14

  • 8/9/2019 Production Control & Planning (Part 2)

    15/328

    Notations

    The following are the notation that will beused in developing the inventory models.

    D = Annual demand

    Q = Quantity ordered (in units)

    S = Annual Setup/Ordering cost per order

    H = Annual Holding Cost per unit

    C = Total annual Cost

  • 8/9/2019 Production Control & Planning (Part 2)

    16/328

    HowHowMuch?Much?

    When!When!

  • 8/9/2019 Production Control & Planning (Part 2)

    17/328

    Bird feeder container.Sales are 18 units/week.Supplier charges = $60/unitOrder cost = $45Annual holding cost = 25% of unit valueMuseum operates = 52weeks/yearManagement decision 390 unit lot sizeWhat is the annual cost?Would lot size 468 be better?

  • 8/9/2019 Production Control & Planning (Part 2)

    18/328

    1.1. Demand rate is constantDemand rate is constant

    2.2. No constraints on lot sizeNo constraints on lot size3.3. Only relevant costs are holding andOnly relevant costs are holding and

    ordering/setupordering/setup

    4.4. Decisions for items are independentDecisions for items are independentfrom other itemsfrom other items

    5.5. No uncertainty in lead time or supplyNo uncertainty in lead time or supply

    AssumptionsAssumptions

  • 8/9/2019 Production Control & Planning (Part 2)

    19/328

    Inventory depletionInventory depletion

    (demand rate)(demand rate)ReceiveReceive

    orderorder

    1 cycle1 cycle

    On-h

    an

    dinventory(u

    nits)

    On-h

    an

    dinventory(u

    nits)

    TimeTime

    QQ

    AverageAverage

    cyclecycle

    inventoryinventory

    QQ22

  • 8/9/2019 Production Control & Planning (Part 2)

    20/328

    Annualcost

    (dollars)

    Annua

    lcost(dol

    lars)

    Lot Size (Lot Size (QQ))

    Holding cost (Holding cost (HCHC))

    Ordering cost (Ordering cost (OCOC))

    Total cost =Total cost = HCHC++ OCOC

  • 8/9/2019 Production Control & Planning (Part 2)

    21/328

    Example 15.2Example 15.2

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

  • 8/9/2019 Production Control & Planning (Part 2)

    22/328

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    Example 15.2Example 15.2

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Bird feeder costs

    C= (H) + (S)Q

    2

    D

    Q

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15S= $45 Q= 390 units

    C = $2925 + $108 = $3033

  • 8/9/2019 Production Control & Planning (Part 2)

    23/328

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    Bird feeder costs

    C= (H) + (S)Q

    2

    D

    Q

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15S= $45 Q= 390 units

    C = $2925 + $108 = $3033

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Example 15.2Example 15.2

  • 8/9/2019 Production Control & Planning (Part 2)

    24/328

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    Bird feeder costs

    C= (H) + (S)Q

    2

    D

    Q

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15S= $45 Q= 390 units

    C = $2925 + $108 = $3033

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Example 15.2Example 15.2

  • 8/9/2019 Production Control & Planning (Part 2)

    25/328

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    Bird feeder costs

    C= (H) + (S)Q

    2

    D

    Q

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15S= $45 Q= 468468 units

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Example 15.2Example 15.2

    C = $3510 + $90 = $3600

    HQ

    SD

    =

  • 8/9/2019 Production Control & Planning (Part 2)

    26/328

    EOQformula:

    H

    DSQ

    H

    DSQ

    HQDS

    HSS

    2*

    2

    2

    2

    2

    2

    =

    =

    =

    =

    H

    DSQ

    H

    DSQ

    HQDS

    HQ

    SS

    D

    2*

    2

    2

    2

    2

    2

    =

    =

    =

    =

  • 8/9/2019 Production Control & Planning (Part 2)

    27/328

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Example 15.2Example 15.2

    Bird feeder costs

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15

    S= $45 Q= EOQ

    C= (H) + (S)Q

    2

    D

    QEOQ =

    2DSH

  • 8/9/2019 Production Control & Planning (Part 2)

    28/328

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Example 15.2Example 15.2

    Bird feeder costs

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15

    S= $45 Q= 75

    C= (H) + (S)Q

    2

    D

    QEOQ =

    2DSH

  • 8/9/2019 Production Control & Planning (Part 2)

    29/328

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Example 15.2Example 15.2

    Bird feeder costs

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15

    S= $45 Q= 75

    C= (H) + (S)Q

    2

    D

    QEOQ =

    2DSH

    C = $562 + $562 = $1124

  • 8/9/2019 Production Control & Planning (Part 2)

    30/328

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Example 15.2Example 15.2

    Bird feeder costs

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15

    S= $45 Q= 75

    C= (H) + (S)Q

    2

    D

    QEOQ =

    2DSH

    C = $562 + $562 = $1124

    LowestLowest

    costcost

    BestBest QQ

    (EOQ)(EOQ)

  • 8/9/2019 Production Control & Planning (Part 2)

    31/328

    Example 15.2Example 15.2

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Bird feeder costs

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15

    S= $45 Q= 75

    C= (H) + (S)Q

    2

    D

    QEOQ =

    2DSH

    C = $562 + $562 = $1124

    LowestLowest

    costcost

    BestBest QQ

    (EOQ)(EOQ)

  • 8/9/2019 Production Control & Planning (Part 2)

    32/328

    LowestLowest

    costcost

    BestBest QQ

    (EOQ)(EOQ)

    Example 15.2Example 15.2

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Bird feeder costs

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15

    S= $45 Q= 75

    C= (H) + (S)Q

    2

    D

    QEOQ =

    2DSH

    C = $562 + $562 = $1124

  • 8/9/2019 Production Control & Planning (Part 2)

    33/328

    LowestLowest

    costcost

    BestBest QQ

    (EOQ)(EOQ)

    Example 15.2Example 15.2

    30003000

    20002000

    10001000

    00

    | | | | | | | |

    5050 100100 150150 200200 250250 300300 350350 400400

    Lot Size (Lot Size (QQ))

    Annualcost(d

    ollars)

    Annualcost(d

    ollars)

    Total cost = (Total cost = (HH) + () + (SS))DD

    QQQQ

    22

    Holding cost = (Holding cost = (HH))QQ

    22

    Ordering cost = (Ordering cost = (SS))DDQQ

    CurrentCurrentcostcost

    CurrentCurrent

    QQ

    Bird feeder costs

    D = (18 /week)(52 weeks) = 936 unitsH= 0.25 ($60/unit) = $15

    S= $45 Q= 75

    C= (H) + (S)Q

    2

    D

    QEOQ =

    2DSH

    C = $562 + $562 = $1124

    Time between orders

    TBOEOQ

    = = 75/936 = 0.080 yearEOQ

    D

    TBOEOQ = (75/936)(12) = 0.96 months

    TBOEOQ = (75/936)(52) = 4.17 weeks

    TBOEOQ = (75/936)(365) = 29.25 days

  • 8/9/2019 Production Control & Planning (Part 2)

    34/328

    Activity 9

    A company that markets a product Z would liketo reduce its inventory cost by determining theoptimal number of Z to obtain per order. The

    annual demand is 1960 units, thesetup/ordering cost is RM5 per order, and theholding cost per unit per year is RM1.

    (a) Calculate the optimal number of units perorder.

    (b) If a 260-day working per year, find thenumber of orders, N.

    (c) Calculate the total inventory costs.

  • 8/9/2019 Production Control & Planning (Part 2)

    35/328

    HowHowMuch?Much?

    When!When!

  • 8/9/2019 Production Control & Planning (Part 2)

    36/328

  • 8/9/2019 Production Control & Planning (Part 2)

    37/328

  • 8/9/2019 Production Control & Planning (Part 2)

    38/328

    Inventory

    models

    Master

    Production

    Schedule

    (MPS)

    Bill of

    Material

    (BOM)

    Accurate

    Inventory

    Records

    Purchase

    Order

    Standing

    Lead Time

    for each

    component

    38

  • 8/9/2019 Production Control & Planning (Part 2)

    39/328

    Bills ofmaterials

    Engineeringand process

    designs

    Inventorytransactions

    Inventoryrecords

    Othersources

    of demand

    Authorizedmaster production

    schedule

    Materialrequirements

    plan

    MRPMRP

    explosionexplosion

  • 8/9/2019 Production Control & Planning (Part 2)

    40/328

    Seat cushion

    Seat-frameboards

    Frontlegs A

    Ladder-backchair

    Backlegs

    Leg supports

    Back slats

  • 8/9/2019 Production Control & Planning (Part 2)

    41/328

    J (4)Seat-frame

    boards

    I (1)

    Seatcushion

    H (1)

    Seatframe

    G (4)

    Backslats

    F (2)

    Backlegs

    C (1)Seat

    subassembly

    D (2)Frontlegs

    B (1)Ladder-backsubassembly

    E (4)Leg

    supports

    AALadder-backLadder-back

    chairchair

  • 8/9/2019 Production Control & Planning (Part 2)

    42/328

    Ladder-back chair

    Kitchen chair

    Desk chair

    1 2

    April May

    3 4 5 6 7 8

    Aggregateproduction planfor chair family

    200

    670670

    200

    150

    120

    200

    150

    200

    120

    670670

  • 8/9/2019 Production Control & Planning (Part 2)

    43/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements

    1 2 3 4 5 6 7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    Week

    150150

    230230

    00

    00

    00

    00

    120120

    00 00

    150150

    00

    120120

    00 00

    37

    0000

  • 8/9/2019 Production Control & Planning (Part 2)

    44/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    Explanation:Gross requirements are the total demand forthe two chairs. Projected on-hand inventoryin week 1 is 37 + 230 150

  • 8/9/2019 Production Control & Planning (Part 2)

    45/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    Explanation:Gross requirements are the total demand forthe two chairs. Projected on-hand inventoryin week 1 is 37 + 230 150 = 117 units.

  • 8/9/2019 Production Control & Planning (Part 2)

    46/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

  • 8/9/2019 Production Control & Planning (Part 2)

    47/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    Projected on-handinventory balanceat end of week t

    Inventory onhand at endof week t - 1

    Grossrequirements

    in week t

    Scheduledor plannedreceipts in

    week t

    = +

  • 8/9/2019 Production Control & Planning (Part 2)

    48/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 33 33 153153 273273 273273

    Projected on-handinventory balanceat end of week t

    Inventory onhand at endof week t - 1

    Grossrequirements

    in week t

    Scheduledor plannedreceipts in

    week t

    = +

  • 8/9/2019 Production Control & Planning (Part 2)

    49/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 33 33 153153 273273 273273

    Explanation:

    Without a new order in week 4,there will be a shortage of threeunits: 117 + 0 + 0 120 = 3units.

  • 8/9/2019 Production Control & Planning (Part 2)

    50/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117

  • 8/9/2019 Production Control & Planning (Part 2)

    51/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    Explanation:Adding the planned receiptbrings the balance to117 + 0 + 230230 120 = 227 units.

  • 8/9/2019 Production Control & Planning (Part 2)

    52/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    Explanation:Adding the planned receiptbrings the balance to117 + 0 + 230230 120 = 227 units.

  • 8/9/2019 Production Control & Planning (Part 2)

    53/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    230230

    Explanation:Offsetting for a two-week lead timeputs the corresponding plannedorder release back to week 2.

  • 8/9/2019 Production Control & Planning (Part 2)

    54/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    230230

    Explanation:Offsetting for a two-week lead timeputs the corresponding plannedorder release back to week 2.

  • 8/9/2019 Production Control & Planning (Part 2)

    55/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    230230

    227227 7777 4343

    Explanation:The first planned order lastsuntil week 7, when projectedinventory would drop to 43.

  • 8/9/2019 Production Control & Planning (Part 2)

    56/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    230230

    227227 7777

    230230

    Explanation:Adding the second plannedreceipt brings the balance to77 + 0 + 230230 120 = 187.

  • 8/9/2019 Production Control & Planning (Part 2)

    57/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    230230

    227227 7777

    230230

    Explanation:Adding the second plannedreceipt brings the balance to77 + 0 + 230230 120 = 187.

    187187

  • 8/9/2019 Production Control & Planning (Part 2)

    58/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    230230

    227227 7777

    230230

    187187

    230230

    Explanation:The corresponding plannedorder release is for week 5.

  • 8/9/2019 Production Control & Planning (Part 2)

    59/328

    Item: CDescription: Seat subassembly

    Lot Size: 230 unitsLead Time: 2 weeks

    Grossrequirements 150150

    1

    230230

    117117

    00

    2

    00

    00

    3

    00

    120120

    4

    00

    5

    00

    150150

    6

    00

    120120

    7

    00

    8

    00Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    0000

    117117 117117 227227

    230230

    230230

    227227 7777

    230230

    187187

    230230

    187187

  • 8/9/2019 Production Control & Planning (Part 2)

    60/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Grossrequirements

    1 2 3 4 5 6 7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    Week

    150150

    230230

    117117

    120120 150150 120120

    37 117117 117117

  • 8/9/2019 Production Control & Planning (Part 2)

    61/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    POQlot

    size

    Gross requirementsfor weeks4, 5, and 6

    Inventory atend of week 3=

  • 8/9/2019 Production Control & Planning (Part 2)

    62/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

  • 8/9/2019 Production Control & Planning (Part 2)

    63/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    (120 + 0 + 150)

  • 8/9/2019 Production Control & Planning (Part 2)

    64/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    (120 + 0 + 150) 117

  • 8/9/2019 Production Control & Planning (Part 2)

    65/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    (120 + 0 + 150) 117 = 153 units

    153153

  • 8/9/2019 Production Control & Planning (Part 2)

    66/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    (120 + 0 + 150) 117 = 153 units

    153153

  • 8/9/2019 Production Control & Planning (Part 2)

    67/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    (120 + 0 + 150) 117 = 153 units

    153153

    150150

  • 8/9/2019 Production Control & Planning (Part 2)

    68/328

    Item: C

    Description: Seat subassembly

    Lot Size: P= 3

    Lead Time: 2 weeks

    Gross

    requirements150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-handinventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    (120 + 0 + 150) 117 = 153 units

    153153

    150150

    153153

  • 8/9/2019 Production Control & Planning (Part 2)

    69/328

    Item: CDescription: Seat subassembly

    Lot Size: P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    (120 + 0) 0 = 120 units

    153153

    150150

    153153

    150150 00 00 00

    120120

    120120

  • 8/9/2019 Production Control & Planning (Part 2)

    70/328

    Item: CDescription: Seat subassembly Lot Size:P= 3Lead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    153153

    150150

    153153

    150150 00 00 00

    120120

    120120

  • 8/9/2019 Production Control & Planning (Part 2)

    71/328

  • 8/9/2019 Production Control & Planning (Part 2)

    72/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements

    1 2 3 4 5 6 7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    Week

    150150

    230230

    117117

    120120 150150 120120

    37 117117 117117

  • 8/9/2019 Production Control & Planning (Part 2)

    73/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    L4Llot

    size

    Gross requirementsin week 4

    Inventory balanceat end of week 3=

  • 8/9/2019 Production Control & Planning (Part 2)

    74/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    = 120 117 = 3L4Llot

    size

  • 8/9/2019 Production Control & Planning (Part 2)

    75/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    3

    = 120 117 = 3L4Llot

    size

  • 8/9/2019 Production Control & Planning (Part 2)

    76/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    3

    3

    0

    = 120 117 = 3L4Llot

    size

  • 8/9/2019 Production Control & Planning (Part 2)

    77/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventory

    Plannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    3

    3

    0 00

  • 8/9/2019 Production Control & Planning (Part 2)

    78/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventoryPlannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    3

    3

    0

    150

    00

    150

  • 8/9/2019 Production Control & Planning (Part 2)

    79/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventoryPlannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    3

    3

    0

    150

    00

    150

    0

    120

    120

  • 8/9/2019 Production Control & Planning (Part 2)

    80/328

    Item: CDescription: Seat subassembly Lot Size: L4LLead Time: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventoryPlannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    3

    3

    0

    150

    00

    150

    0

    120

    120

    0

  • 8/9/2019 Production Control & Planning (Part 2)

    81/328

  • 8/9/2019 Production Control & Planning (Part 2)

    82/328

    The FOQ rule generates high averageThe FOQ rule generates high averageinventory because it creates remnants.inventory because it creates remnants.

    The POQ rule reducesThe POQ rule reduces

    average on-hand inventoryaverage on-hand inventory

    because it does a betterbecause it does a better

    job of matching orderjob of matching order

    quantity to requirements.quantity to requirements. The L4L rule minimizesThe L4L rule minimizes

    inventory investmentinventory investment

    but maximizes the number of orders placed.but maximizes the number of orders placed.

  • 8/9/2019 Production Control & Planning (Part 2)

    83/328

  • 8/9/2019 Production Control & Planning (Part 2)

    84/328

    Material requirements plan

    Action notices Releasing new orders Adjusting due dates

    Priority reports Dispatch lists Supplier schedules

    Capacity reports Capacity requirements planning Finite capacity scheduling Input-output control

    Manufacturing resources plan

    Performance reportsCost andprice data

    Routingsand time

    standards

    MRPMRPexplosionexplosion

  • 8/9/2019 Production Control & Planning (Part 2)

    85/328

    J (4)Seat-frame

    boards

    H (1)Seat

    frame

    I (1)Seat

    cushion

    C (1)Seatsubassembly

  • 8/9/2019 Production Control & Planning (Part 2)

    86/328

    Item: Seat subassemblyLot size: 230 units

    Leadtime: 2 weeks

    Gross

    requirements 150150

    1

    230230

    117117

    2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Scheduledreceipts

    Projectedon-hand

    inventoryPlannedreceipts

    Planned orderreleases

    37

    Week

    117117 117117

    0 00 0

    00 00 000 00 0

    227 227 77 187 187

    230230

    230230

  • 8/9/2019 Production Control & Planning (Part 2)

    87/328

    Item: Seat subassemblyLot size: 230 units

    Leadtime: 2 weeks

    Grossrequirements

    150150

    1 2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    0 00 0

    230

    230

    230

    230

  • 8/9/2019 Production Control & Planning (Part 2)

    88/328

    Item: Seat subassemblyLot size: 230 units

    Leadtime: 2 weeks

    Grossrequirements

    150150

    1 2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    0 00 0

    230

    230

    230

    230

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    1

    00

    2 3 4 5 6 7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    40

    Week

    00

    00

    00300 00 0

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    1

    00

    2 3 4 5 6 7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    0

    Week

    00

    00

    000 00 0

  • 8/9/2019 Production Control & Planning (Part 2)

    89/328

    Item: Seat subassemblyLot size: 230 units

    Leadtime: 2 weeks

    Grossrequirements 150150

    1 2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    0 00 0

    230

    230

    230

    230

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    0

    1

    0

    2 3 4 5 6 7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    40

    Week

    230

    0 0 0300 00 0

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    0

    1

    0

    2 3 4 5 6 7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    0

    Week

    230

    0 0 00 00 0

    Usage quantity: 1Usage quantity: 1 Usage quantity: 1Usage quantity: 1

  • 8/9/2019 Production Control & Planning (Part 2)

    90/328

    Item: Seat subassemblyLot size: 230 units

    Leadtime: 2 weeks

    Grossrequirements 150150

    1 2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    0 00 0

    230

    230

    230

    230

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    00

    1

    00

    2 3

    00

    4 5 6 7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    40

    Week

    230 2300

    00 00 00300 00 0

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    00

    1

    00

    2 3

    00

    4 5 6 7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    0

    Week

    230 2300

    00 00 000 00 0

    Usage quantity: 1Usage quantity: 1 Usage quantity: 1Usage quantity: 1

  • 8/9/2019 Production Control & Planning (Part 2)

    91/328

    Item: Seat subassemblyLot size: 230 units

    Leadtime: 2 weeks

    Grossrequirements 150150

    1 2 3

    120120

    4 5

    150150

    6

    120120

    7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    0 00 0

    230

    230

    230

    230

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    00

    1

    00

    4040

    2 3

    00

    4 5

    00

    6

    00

    7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    40

    Week

    110110 110110

    230 2300 0

    00 00 00300 00 0

    110 180 180 180 180

    300

    300

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    00

    1

    00

    00

    2 3

    00

    4 5

    00

    6

    00

    7 8

    Scheduled

    receipts

    Projectedon-handinventory

    Plannedreceipts

    Plannedorderreleases

    0

    Week

    00 00

    230 2300 0

    00 00 000 00 0

    0 0 0 0 0

    230

    230

    230

    230

  • 8/9/2019 Production Control & Planning (Part 2)

    92/328

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    300

    300

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    230

    230

    230

    230

    00 00 00 00230 2300 000 00 00 00230 2300 0

  • 8/9/2019 Production Control & Planning (Part 2)

    93/328

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    300

    300

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    230

    230

    230

    230

    00 00 00 00230 2300 000 00 00 00230 2300 0

    Grossrequirements

    1

    00

    2 3 4 5 6 7 8

    Scheduled

    receipts

    Plannedreceipts

    Plannedorderreleases

    200

    Week

    00 00 000 00 0

    Projectedon-handinventory

    Item: Seat-frame boardsLot size: 1500 units

    Leadtime: 1 week

  • 8/9/2019 Production Control & Planning (Part 2)

    94/328

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    300

    300

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    230

    230

    230

    230

    00 00 00 00230 2300 000 00 00 00230 2300 0

    Grossrequirements

    00

    1

    00

    2 3

    12001200

    4 5

    00

    6

    00

    7 8

    Scheduled

    receipts

    Plannedreceipts

    Plannedorderreleases

    200

    Week

    0 00 0

    00 00 000 00 0

    Projectedon-handinventory

    Item: Seat-frame boardsLot size: 1500 units

    Leadtime: 1 week

    Usage quantity: 4Usage quantity: 4

  • 8/9/2019 Production Control & Planning (Part 2)

    95/328

    Item: Seat framesLot size: 300 units

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    300

    300

    Item: Seat cushionLot size: L4L

    Leadtime: 1 week

    Grossrequirements

    1 2 3 4 5 6 7 8

    Plannedreceipts

    Plannedorderreleases

    Week

    230

    230

    230

    230

    00 00 00 00230 2300 000 00 00 00230 2300 0

    Grossrequirements

    00

    1

    00

    200200

    2 3

    12001200

    4 5

    00

    6

    00

    7 8

    Scheduled

    receipts

    Plannedreceipts

    Plannedorderreleases

    200

    Week

    200200 200200

    0 00 0

    00 00 000 00 0

    500 500 500 500 500

    1500

    1500

    Projectedon-handinventory

    Item: Seat-frame boardsLot size: 1500 units

    Leadtime: 1 week

  • 8/9/2019 Production Control & Planning (Part 2)

    96/328

  • 8/9/2019 Production Control & Planning (Part 2)

    97/328

  • 8/9/2019 Production Control & Planning (Part 2)

    98/328

    Authorizedproduction

    plan

  • 8/9/2019 Production Control & Planning (Part 2)

    99/328

    Authorizedproduction

    plan

    Prospective masterproduction

    schedule

  • 8/9/2019 Production Control & Planning (Part 2)

    100/328

    Are resourcesavailable?

    Authorizedproduction

    plan

    Prospective masterproduction

    schedule

  • 8/9/2019 Production Control & Planning (Part 2)

    101/328

    NoNoAre resources

    available?

    Authorizedproduction

    plan

    Prospective masterproduction

    schedule

  • 8/9/2019 Production Control & Planning (Part 2)

    102/328

    No

    YesYes

    Are resourcesavailable?

    Authorizedproduction

    plan

    Prospective masterproduction

    schedule

    Authorized master

    production schedule

  • 8/9/2019 Production Control & Planning (Part 2)

    103/328

    NoNo

    YesYes

    Are resourcesavailable?

    Authorizedproduction

    plan

    Prospective masterproduction

    schedule

    Materialrequirements

    planning

    Authorized master

    production schedule

  • 8/9/2019 Production Control & Planning (Part 2)

    104/328

  • 8/9/2019 Production Control & Planning (Part 2)

    105/328

    MPS quantityMPS quantity

    (0 for week 1)(0 for week 1)Inventory =Inventory = + =+ =

    55 chairs55 chairs

    currently incurrently in

    stockstock

    38 chairs already38 chairs already

    promised forpromised for

    delivery in week 1delivery in week 1

    1717

    chairschairs

  • 8/9/2019 Production Control & Planning (Part 2)

    106/328

    MPS quantity(0 for week 1)

    Inventory = + =55 chairs

    currently instock

    38 chairs alreadypromised for

    delivery in week 1

    17chairs

    Item: Ladder-back chair

    MPS start

    MPS quantity

    Projected on-handInventory

    Customer orders(booked)

    Forecast

    QuantityOn Hand:

    April

    55 1 2

    30 30

    38 27

  • 8/9/2019 Production Control & Planning (Part 2)

    107/328

    MPS quantity(0 for week 1)

    Inventory = + =55 chairs

    currently instock

    38 chairs alreadypromised for

    delivery in week 1

    17chairs

    Explanation:Forecast is less than bookedorders in week 1; projectedon-hand inventorybalance = 55 + 0 38 = 17.

    Item: Ladder-back chair

    MPS start

    MPS quantity

    Projected on-handInventory

    Customer orders(booked)

    Forecast

    QuantityOn Hand:

    April

    55 1 2

    30 30

    38 27

    17

    0

  • 8/9/2019 Production Control & Planning (Part 2)

    108/328

    MPS quantity(0 for week 1)

    Inventory = + =55 chairs

    currently instock

    38 chairs alreadypromised for

    delivery in week 1

    17chairs

    Explanation:Forecast exceeds booked orders inweek 2; projected on-hand inventorybalance = 17 + 0 30 = 13. Theshortage signals a need to schedule anMPS quantity for completion in week 2.

    Explanation:Forecast is less than bookedorders in week 1; projectedon-hand inventorybalance = 55 + 0 38 = 17.

    Item: Ladder-back chair

    MPS start

    MPS quantity

    Projected on-handInventory

    Customer orders(booked)

    Forecast

    QuantityOn Hand:

    April

    55 1 2

    30 30

    38 27

    17 -13

    0 0

  • 8/9/2019 Production Control & Planning (Part 2)

    109/328

  • 8/9/2019 Production Control & Planning (Part 2)

    110/328

    Item: Ladder-back chair Order Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17

    0

  • 8/9/2019 Production Control & Planning (Part 2)

    111/328

    Item: Ladder-back chair Order Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17

    0

    137137

    150

  • 8/9/2019 Production Control & Planning (Part 2)

    112/328

    Item: Ladder-back chair Order Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17

    0

    137137

    150

    Explanation:

    On-hand inventory balance= 17 + 150 30 = 137137. TheMPS quantity is needed toavoid a shortage of 30 17 = 13chairs in week 2.

  • 8/9/2019 Production Control & Planning (Part 2)

    113/328

    Item: Ladder-back chairOrder Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17

    0

    137137

    150

    Explanation:The time needed to assemble

    150150 chairs is one week. Theassembly department muststart assembling chairs in week1 to have them ready by week 2.

    150

  • 8/9/2019 Production Control & Planning (Part 2)

    114/328

    Item: Ladder-back chairOrder Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17 137 107

    0 150 0

    150 0

  • 8/9/2019 Production Control & Planning (Part 2)

    115/328

    Item: Ladder-back chairOrder Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17 137 107 77

    0 150 0 0

    150 0 0

  • 8/9/2019 Production Control & Planning (Part 2)

    116/328

    Item: Ladder-back chairOrder Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17 137 107 77 42

    0 150 0 00

    150 0 00

  • 8/9/2019 Production Control & Planning (Part 2)

    117/328

    Item: Ladder-back chairOrder Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17 137 107 77 42 7

    0 150 0 00 0

    150 0 00 0

  • 8/9/2019 Production Control & Planning (Part 2)

    118/328

    Item: Ladder-back chairOrder Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17 137 107 77 42 7 122

    0 150 1500 00 0

    150 1500 00 0

  • 8/9/2019 Production Control & Planning (Part 2)

    119/328

    Item: Ladder-back chairOrder Policy: 150 unitsLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders(booked)

    Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantityon Hand:

    55

    17 137 107 77 42 7 122 87

    0 150 1500 00 0 0

    150 1500 00 0 0 0

  • 8/9/2019 Production Control & Planning (Part 2)

    120/328

    Item: Ladder-back chairOrder Policy: 150 units

  • 8/9/2019 Production Control & Planning (Part 2)

    121/328

    Item: Ladder-back chairLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders

    (booked)Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantity

    on Hand: 55

    17 137 107 77 42 7 122 87

    0 150 1500 00 0 0

    150 1500 00 0 0

    Available-to-promise (ATP)inventory

    0

    Item: Ladder-back chairOrder Policy: 150 units

  • 8/9/2019 Production Control & Planning (Part 2)

    122/328

    Item: Ladder back chairLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders

    (booked)Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantity

    on Hand: 55

    17 137 107 77 42 7 122 87

    0 150 1500 00 0 0

    150 1500 00 0 0

    Available-to-promise (ATP)inventory

    1717

    0

    Explanation:The total of customer ordersbooked until the next MPS

    receipt is 38 units. The ATP =55 (on-hand) + 0 (MPSquantity) 38 = 1717.

    Item: Ladder-back chairOrder Policy: 150 unitsL d Ti 1 k

  • 8/9/2019 Production Control & Planning (Part 2)

    123/328

    Item: Ladder back chairLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders

    (booked)Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantity

    on Hand: 55

    17 137 107 77 42 7 122 87

    0 150 1500 00 0 0

    150 1500 00 0 0

    Available-to-promise (ATP)inventory

    1717 9191

    0

    Explanation:The total of customer orders

    booked until the next MPSreceipt is 27 + 24 + 8 = 59units. The ATP = 150 (MPSquantity) 59 = 9191units.

    Item: Ladder-back chairOrder Policy: 150 unitsL d Ti 1 k

  • 8/9/2019 Production Control & Planning (Part 2)

    124/328

    Item: Ladder back chairLead Time: 1 week

    Forecast

    1

    3838

    3030

    2

    2727

    3030

    3

    2424

    3030

    4

    88

    5

    00

    3535

    6

    00

    3535

    7

    00

    8

    00

    Customerorders

    (booked)Projectedon-handinventory

    MPS quantity

    MPS start

    35353535

    April May

    3030

    Quantity

    on Hand: 55

    17 137 107 77 42 7 122 87

    0 150 1500 00 0 0

    150 1500 00 0 0

    Available-to-promise (ATP)inventory

    1717 9191 150

    0

  • 8/9/2019 Production Control & Planning (Part 2)

    125/328

    Week

    1 2 3 4 5 6 7 8 9 10

    0 150 0 0 0 0 150 0 0 0MPSquantity

  • 8/9/2019 Production Control & Planning (Part 2)

    126/328

    WeekWeek

    1 2 3 4 5 6 7 8 9 10

    0 150 0 0 0 0 150 0 0 0MPSquantity

    DemandDemandtimetime

    fencefence

  • 8/9/2019 Production Control & Planning (Part 2)

    127/328

  • 8/9/2019 Production Control & Planning (Part 2)

    128/328

    Item: AOrder Policy: 50 unitsLead Time: 1 week

  • 8/9/2019 Production Control & Planning (Part 2)

    129/328

    Lead Time: 1 week

    Forecast

    Customerorders

    (booked)Projectedon-handinventory

    MPS quantity

    MPS start

    WeekQuantity

    on Hand: 5

    Available-to-promise (ATP)inventory

    1

    3030

    1010

    2

    2020

    4040

    3

    55

    1010

    4

    88

    5

    00

    00

    6

    22

    4040

    7

    00

    8

    00

    2020002020

    25

    50

    3030

    7

    00

    8

    00

    1010

  • 8/9/2019 Production Control & Planning (Part 2)

    130/328

  • 8/9/2019 Production Control & Planning (Part 2)

    131/328

    Manufacturing resource planCost and

    financial data

    Purchasingreports

    Financial/accounting

    reports

    Sales andmarketing

    reports

    Humanresourcereports

    Manufacturingreports

    Inventory recordsInventory transactions

    Bills of materialsRoutings

    Time standards

    MRPMRP

    explosionexplosion

    Master production schedule

    Customer orders Forecasts

    Material requirements plan

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    132/328

    PlanPlanTru-RainbowTru-Rainbow

    CompanyCompany

    15001500

    12501250

    10001000

    750750

    500500

    250250

    00

    | | | |

    11 22 33 44QuarterQuarter

    Pai

    nt(t

    housandsof

    gallons)

    Paint(t

    housandsof

    gallons)

    RequirementsRequirements

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    133/328

    PlanPlanTru-RainbowTru-Rainbow

    CompanyCompany

    15001500

    12501250

    10001000

    750750

    500500

    250250

    00

    | | | |

    11 22 33 44QuarterQuarter

    Pai

    nt(t

    housandsof

    gallons)

    Paint(t

    housandsof

    gallons)

    Production planProduction plan

    RequirementsRequirements

  • 8/9/2019 Production Control & Planning (Part 2)

    134/328

    ProductionProductionI tInventory

  • 8/9/2019 Production Control & Planning (Part 2)

    135/328

    PlanPlanTru-RainbowTru-Rainbow

    CompanyCompany

    110110

    400400

    15001500

    12501250

    10001000

    750750

    500500

    250250

    00

    | | | |

    11 22 33 44QuarterQuarter

    Pai

    nt(t

    housandsof

    gallons)

    Paint(t

    housandsof

    gallons)

    510510

    300300

    InventoryInventoryconsumptionconsumption

    Production planProduction plan

    RequirementsRequirements

    InventoryInventory

    accumulationaccumulation

    ProductionProductionInventoryInventory

  • 8/9/2019 Production Control & Planning (Part 2)

    136/328

    PlanPlanTru-RainbowTru-Rainbow

    CompanyCompany

    110110

    400400

    15001500

    12501250

    10001000

    750750

    500500

    250250

    00

    | | | |

    11 22 33 44QuarterQuarter

    Paint(t

    housandsof

    gallons)

    Paint(t

    housandsof

    gallons)

    510510

    300300

    InventoryInventoryconsumptionconsumption

    Production planProduction plan

    RequirementsRequirements

    InventoryInventory

    accumulationaccumulation

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    137/328

    PlanningPlanning

    TableauTableauTru-RainbowTru-Rainbow

    CompanyCompany

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    138/328

    PlanningPlanning

    TableauTableauTru-RainbowTru-Rainbow

    CompanyCompany Total Cost

    Quarter Cost

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    139/328

    PlanningPlanning

    TableauTableauTru-RainbowTru-Rainbow

    CompanyCompany Total Cost

    Quarter Cost

    1 250($0) + 30($1.00) + 20($1.90) = $68

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    140/328

    PlanningPlanning

    TableauTableauTru-RainbowTru-Rainbow

    CompanyCompany Total Cost

    Quarter Cost

    1 250($0) + 30($1.00) + 20($1.90) = $682 420($1.30) + 90($1.80) + 340($1.00) = 1,048

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    141/328

    PlanningPlanning

    TableauTableauTru-RainbowTru-Rainbow

    CompanyCompany Total Cost

    Quarter Cost

    1 250($0) + 30($1.00) + 20($1.90) = $682 420($1.30) + 90($1.80) + 340($1.00) = 1,0483 110($1.30) + 90($1.80) + 200($2.20)

    + 750($1.00) + 150($1.50) = 2,100

    ProductionProduction

  • 8/9/2019 Production Control & Planning (Part 2)

    142/328

    PlanningPlanning

    TableauTableauTru-RainbowTru-Rainbow

    CompanyCompany Total Cost

    Quarter Cost

    1 250($0) + 30($1.00) + 20($1.90) = $682 420($1.30) + 90($1.80) + 340($1.00) = 1,0483 110($1.30) + 90($1.80) + 200($2.20)

    + 750($1.00) + 150($1.50) = 2,1004 450($1.00) + 90($1.50) + 110($1.90) = 794

    Total $4,010

  • 8/9/2019 Production Control & Planning (Part 2)

    143/328

  • 8/9/2019 Production Control & Planning (Part 2)

    144/328

    1 450 90 20 5602 450 90 200 7403 750 150 200 1,1004 450 90 110 650

    Totals 2,100 420 530 3,050

    Regular-Time Overtime Subcon-Quarter Production Production tracting Total

    Anticipation Inventory

    Quarter Quantity

  • 8/9/2019 Production Control & Planning (Part 2)

    145/328

    1 450 90 20 5602 450 90 200 7403 750 150 200 1,1004 450 90 110 650

    Totals 2,100 420 530 3,050

    Regular-Time Overtime Subcon-Quarter Production Production tracting Total

    Anticipation Inventory

    Quarter Quantity

    1 250 + 560 300 = 510

    2 510 + 740 850 = 4003 400 + 1,100 1,500 = 04 0 + 650 350 = 300

  • 8/9/2019 Production Control & Planning (Part 2)

    146/328

    Topic 4

    Alternatives Quarter

    12

    34

    TotalCapacity

    Unuse

    dCapacit

    y

    Requirements

    Quarter

    Subcontract

    Overtime

    Regulartime

    Subcontract

    Overtime

    Regulartime

    Subcontract

    Overtime

    Regulartime

    Subcontract

    Overtime

    Regulartime

    Beginning

    inventory1

    2

    3

    4

  • 8/9/2019 Production Control & Planning (Part 2)

    147/328

    By the end of this topic, you should beable to: Discuss the aggregate planning

    strategies; Describe some of the methods used in

    aggregate planning;

    Identify assignment method, sequencingrules and Johnsons rule; and

    Explain shop loading, sequencingmonitoring.

    147

    Planning RelationshipsPlanning Relationships

  • 8/9/2019 Production Control & Planning (Part 2)

    148/328

    g pg p

    BusinessBusinessor annualor annual

    planplan

    Planning RelationshipsPlanning Relationships

  • 8/9/2019 Production Control & Planning (Part 2)

    149/328

    g pg p

    BusinessBusinessor annualor annual

    planplan

    ProductionProductionor staffingor staffingplanplan

    Planning RelationshipsPlanning Relationships

  • 8/9/2019 Production Control & Planning (Part 2)

    150/328

    g pg p

    MPS orMPS orworkforceworkforcescheduleschedule

    BusinessBusinessor annualor annual

    planplan

    ProductionProductionor staffingor staffingplanplan

    Planning RelationshipsPlanning Relationships

  • 8/9/2019 Production Control & Planning (Part 2)

    151/328

    g pg p

    MPS orMPS orworkforceworkforcescheduleschedule

    BusinessBusinessor annualor annual

    planplan

    ProductionProductionor staffingor staffingplanplan

    Planning RelationshipsPlanning Relationships

  • 8/9/2019 Production Control & Planning (Part 2)

    152/328

    g pg p

    MPS orMPS orworkforceworkforcescheduleschedule

    BusinessBusinessor annualor annual

    planplan

    ProductionProductionor staffingor staffingplanplan

    Managerial InputsManagerial Inputs

  • 8/9/2019 Production Control & Planning (Part 2)

    153/328

    Aggregate

    plan

    Managerial InputsManagerial Inputs

  • 8/9/2019 Production Control & Planning (Part 2)

    154/328

    Aggregate

    plan

    Customer needs

    Demand forecasts

    Competition behavior

    Distribution and marketing

    Managerial InputsManagerial Inputs

  • 8/9/2019 Production Control & Planning (Part 2)

    155/328

    Cost data

    Financial condition

    of firm

    Accounting and finance

    Aggregate

    plan

    Customer needs

    Demand forecasts

    Competition behavior

    Distribution and marketing

    Managerial InputsManagerial Inputs

  • 8/9/2019 Production Control & Planning (Part 2)

    156/328

    Labor-market conditions

    Training capacity

    Human resources

    Cost data

    Financial condition

    of firm

    Accounting and finance

    Aggregate

    plan

    Customer needs

    Demand forecasts

    Competition behavior

    Distribution and marketing

    Managerial InputsManagerial Inputs

  • 8/9/2019 Production Control & Planning (Part 2)

    157/328

    New products

    Product design changes

    Machine standards

    Engineering

    Labor-market conditions

    Training capacity

    Human resources

    Cost data

    Financial condition

    of firm

    Accounting and finance

    Aggregate

    plan

    Customer needsDemand forecasts

    Competition behavior

    Distribution and marketing

    Managerial InputsManagerial Inputs

  • 8/9/2019 Production Control & Planning (Part 2)

    158/328

    Supplier capabilities

    Storage capacity

    Materials availability

    Materials

    New products

    Product design changes

    Machine standards

    Engineering

    Labor-market conditions

    Training capacity

    Human resources

    Cost data

    Financial condition

    of firm

    Accounting and finance

    Aggregate

    plan

    Customer needsDemand forecasts

    Competition behavior

    Distribution and marketing

    Managerial InputsManagerial Inputs

  • 8/9/2019 Production Control & Planning (Part 2)

    159/328

    Supplier capabilities

    Storage capacity

    Materials availability

    Materials

    Current machine capacitiesPlans for future capacities

    Workforce capacitiesCurrent staffing level

    Operations

    New products

    Product design changes

    Machine standards

    Engineering

    Labor-market conditions

    Training capacity

    Human resources

    Cost data

    Financial condition

    of firm

    Accounting and finance

    Aggregate

    plan

    Customer needsDemand forecasts

    Competition behavior

    Distribution and marketing

  • 8/9/2019 Production Control & Planning (Part 2)

    160/328

    Minimize Costs/Maximize ProfitsMinimize Costs/Maximize Profits

    Maximize Customer ServiceMaximize Customer Service

    Minimize Inventory InvestmentMinimize Inventory Investment Minimize Changes in ProductionMinimize Changes in Production

    RatesRates

    Minimize Changes in WorkforceMinimize Changes in WorkforceLevelsLevels

    Maximize Utilization of Plant andMaximize Utilization of Plant and

    EquipmentEquipment 160

  • 8/9/2019 Production Control & Planning (Part 2)

    161/328

    TABLE 14.1 PLANNING STRATEGIES FOR AGGREGATE PLANS

    Possible Alternatives Possible AlternativesStrategy during Slack Season during Peak Season

    4. Level #2: constant Layoffs, building antici- Hiring, depleting antici-outputrate pation inventory, pation inventory, over-

    undertime, vacations time, subcontracting,backorders, stockouts

    1. Chase #1: vary workforce Layoffs Hiringlevel to match demand

    2. Chase #2: vary output Layoffs, undertime, Hiring, overtime,rateto match demand vacations subcontracting

    3. Level #1: constant No layoffs, building No hiring, depletingworkforcelevel anticipation inventory, anticipation inventory,

    undertime, vacations overtime, subcontracting,backorders, stockouts

    Aggregate Planning ProcessAggregate Planning Process

  • 8/9/2019 Production Control & Planning (Part 2)

    162/328

    gg g ggg g g

    Determinerequirements forplanning horizon

    Aggregate Planning ProcessAggregate Planning Process

  • 8/9/2019 Production Control & Planning (Part 2)

    163/328

    gg g ggg g g

    Determinerequirements forplanning horizon

    Identify alternatives,constraints, and costs

    Aggregate Planning ProcessAggregate Planning Process

  • 8/9/2019 Production Control & Planning (Part 2)

    164/328

    gg g ggg g g

    Determinerequirements forplanning horizon

    Identify alternatives,constraints, and costs

    Prepare prospectiveplan for

    planning horizon

    Aggregate Planning ProcessAggregate Planning Process

  • 8/9/2019 Production Control & Planning (Part 2)

    165/328

    gg g ggg g g

    Determinerequirements forplanning horizon

    Identify alternatives,constraints, and costs

    Prepare prospectiveplan for

    planning horizon

    Is the planacceptable?

    Aggregate Planning ProcessAggregate Planning Process

  • 8/9/2019 Production Control & Planning (Part 2)

    166/328

    gg g g

    Determinerequirements forplanning horizon

    Identify alternatives,constraints, and costs

    Prepare prospectiveplan for

    planning horizon

    Is the planacceptable?

    NoNo

    Aggregate Planning ProcessAggregate Planning Process

  • 8/9/2019 Production Control & Planning (Part 2)

    167/328

    gg g g

    Determinerequirements forplanning horizon

    Identify alternatives,constraints, and costs

    Prepare prospectiveplan for

    planning horizon

    Implement andupdate the plan

    Is the planacceptable?

    NoNo

    YesYes

    Aggregate Planning ProcessAggregate Planning Process

  • 8/9/2019 Production Control & Planning (Part 2)

    168/328

    gg g g

    Determinerequirements forplanning horizon

    Identify alternatives,constraints, and costs

    Prepare prospectiveplan for

    planning horizon

    Move aheadto next

    planning session

    Implement andupdate the plan

    Is the planacceptable?

    NoNo

    YesYes

  • 8/9/2019 Production Control & Planning (Part 2)

    169/328

    Regular-Time CostsRegular-Time Costs

    Overtime CostsOvertime Costs

    Hiring andHiring and

    Layoff CostsLayoff Costs

    InventoryInventory

    Holding CostsHolding Costs Backorder and Stockout CostsBackorder and Stockout Costs

    169

    Dock Aisle

  • 8/9/2019 Production Control & Planning (Part 2)

    170/328

    170

    DockDock AisleAisle

  • 8/9/2019 Production Control & Planning (Part 2)

    171/328

    TIME PERIODTIME PERIOD

    11 22 33 44 55 66 TotalTotal

    Requirement*Requirement* 66 1212 1818 1515 1313 1414 7878

    Current employment = 10 part-time clerksCurrent employment = 10 part-time clerks * Number of part-time employees* Number of part-time employees

    171

    DockDock AisleAisle

  • 8/9/2019 Production Control & Planning (Part 2)

    172/328

    TIME PERIODTIME PERIOD

    11 22 33 44 55 66 TotalTotal

    Requirement*Requirement* 66 1212 1818 1515 1313 1414 7878

    Current employment = 10 part-time clerksCurrent employment = 10 part-time clerks

    1.1. No more than 10 new hires in any periodNo more than 10 new hires in any period

    2.2. No backorders are permittedNo backorders are permitted

    3.3. Overtime can not exceed 20% of regular-time capacityOvertime can not exceed 20% of regular-time capacity

    4.4. The following costs can be assigned:The following costs can be assigned:

    Regular-time wageRegular-time wage $2,000/period at 20 hours/week$2,000/period at 20 hours/weekOvertime wagesOvertime wages 150% of regular-time150% of regular-time

    HiringHiring $1,000/person$1,000/person

    LayoffsLayoffs $500/person$500/person

    * Number of part-time employees* Number of part-time employees

    172

    Dock Aisle

  • 8/9/2019 Production Control & Planning (Part 2)

    173/328

    TIME PERIODTIME PERIOD

    11 22 33 44 55 66 TotalTotal

    Requirement*Requirement* 66 1212 1818 1515 1313 1414 7878

    Current employment = 10 part-time clerksCurrent employment = 10 part-time clerks

    1.1. No more than 10 new hires in any periodNo more than 10 new hires in any period

    2.2. No backorders are permittedNo backorders are permitted

    3.3. Overtime can not exceed 20% of regular-time capacityOvertime can not exceed 20% of regular-time capacity

    4.4. The following costs can be assigned:The following costs can be assigned:

    Regular-time wageRegular-time wage $2,000/period at 20 hours/week$2,000/period at 20 hours/weekOvertime wagesOvertime wages 150% of regular-time150% of regular-time

    HiringHiring $1,000/person$1,000/person

    LayoffsLayoffs $500/person$500/person

    Peak Requirement

    173

    Dock Aisle

  • 8/9/2019 Production Control & Planning (Part 2)

    174/328

    TIME PERIODTIME PERIOD

    11 22 33 44 55 66 TotalTotal

    Requirement*Requirement* 66 1212 1818 1515 1313 1414 7878

    Current employment = 10 part-time clerksCurrent employment = 10 part-time clerks

    1.1. No more than 10 new hires in any periodNo more than 10 new hires in any period

    2.2. No backorders are permittedNo backorders are permitted

    3.3. Overtime can not exceed 20% of regular-time capacityOvertime can not exceed 20% of regular-time capacity

    4.4. The following costs can be assigned:The following costs can be assigned:

    Regular-time wageRegular-time wage $2,000/period at 20 hours/week$2,000/period at 20 hours/weekOvertime wagesOvertime wages 150% of regular-time150% of regular-time

    HiringHiring $1,000/person$1,000/person

    LayoffsLayoffs $500/person$500/person

    Peak Requirement

    1.20w= 18 employees in peak period

    174

    Dock Aisle

  • 8/9/2019 Production Control & Planning (Part 2)

    175/328

    TIME PERIODTIME PERIOD

    11 22 33 44 55 66 TotalTotal

    Requirement*Requirement* 66 1212 1818 1515 1313 1414 7878

    Current employment = 10 part-time clerksCurrent employment = 10 part-time clerks

    1.1. No more than 10 new hires in any periodNo more than 10 new hires in any period

    2.2. No backorders are permittedNo backorders are permitted

    3.3. Overtime can not exceed 20% of regular-time capacityOvertime can not exceed 20% of regular-time capacity

    4.4. The following costs can be assigned:The following costs can be assigned:

    Regular-time wageRegular-time wage $2,000/period at 20 hours/week$2,000/period at 20 hours/weekOvertime wagesOvertime wages 150% of regular-time150% of regular-time

    HiringHiring $1,000/person$1,000/person

    LayoffsLayoffs $500/person$500/person

    Peak Requirement

    1.20w= 18 employees in peak period

    w

    = = 15 employees

    18

    1.20

    175

    Dock Aisle

  • 8/9/2019 Production Control & Planning (Part 2)

    176/328

    TIME PERIODTIME PERIOD

    11 22 33 44 55 66 TotalTotal

    Requirement*Requirement* 66 1212 1818 1515 1313 1414 7878

    Current employment = 10 part-time clerksCurrent employment = 10 part-time clerks

    1.1. No more than 10 new hires in any periodNo more than 10 new hires in any period

    2.2. No backorders are permittedNo backorders are permitted

    3.3. Overtime can not exceed 20% of regular-time capacityOvertime can not exceed 20% of regular-time capacity

    4.4. The following costs can be assigned:The following costs can be assigned:

    Regular-time wageRegular-time wage $2,000/period at 20 hours/week$2,000/period at 20 hours/weekOvertime wagesOvertime wages 150% of regular-time150% of regular-time

    HiringHiring $1,000/person$1,000/person

    LayoffsLayoffs $500/person$500/person

    Peak Requirement

    1.20w= 18 employees in peak period

    w

    = = 15 employees

    18

    1.20

    176

  • 8/9/2019 Production Control & Planning (Part 2)

    177/328

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    178/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    Required employeesRequired employees

    178

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    179/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11

    Required employeesRequired employees

    179

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    180/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11 XX XX XX XX XX

    Required employeesRequired employees

    180

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    181/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11 XX XX XX XX XX

    RequirementRequirement 55 33 77 88 9*9* 33 22

    Required employeesRequired employees

    181

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    182/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11 XX XX XX XX XX

    RequirementRequirement 55 33 77 88 9*9* 33 22EmployeeEmployee 22 XX XX XX XX XX

    Required employeesRequired employees

    182

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    183/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11 XX XX XX XX XX

    RequirementRequirement 55 33 77 88 9*9* 33 22EmployeeEmployee 22 XX XX XX XX XX

    RequirementRequirement 44 22 66 77 8*8* 33 22

    Required employeesRequired employees

    183

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    184/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11 XX XX XX XX XX

    RequirementRequirement 55 33 77 88 9*9* 33 22EmployeeEmployee 22 XX XX XX XX XX

    RequirementRequirement 44 22 66 77 8*8* 33 22

    EmployeeEmployee 33 XX XX XX XX XX

    Required employeesRequired employees

    184

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    185/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11 XX XX XX XX XX

    RequirementRequirement 55 33 77 88 9*9* 33 22EmployeeEmployee 22 XX XX XX XX XX

    RequirementRequirement 44 22 66 77 8*8* 33 22

    EmployeeEmployee 33 XX XX XX XX XX

    RequirementRequirement 33 11 55 66 7*7* 33 22

    Required employeesRequired employees

    185

    Scheduling ServicesScheduling Services

  • 8/9/2019 Production Control & Planning (Part 2)

    186/328

    DayDay MM TT WW ThTh FF SS SuSu

    Number of employeesNumber of employees 66 44 88 99 10*10* 33 22

    EmployeeEmployee 11 XX XX XX XX XX

    RequirementRequirement 55 33 77 88 9*9* 33 22EmployeeEmployee 22 XX XX XX XX XX

    RequirementRequirement 44 22 66 77 8*8* 33 22

    EmployeeEmployee 33 XX XX XX XX XX

    RequirementRequirement 33 11 55 66 7*7* 33 22EmployeeEmployee 44 XX XX XX XX XX

    Required employeesRequired employees

    186

    Scheduling ServicesScheduling Ser