Upload
buinhi
View
216
Download
1
Embed Size (px)
Citation preview
1
HAERY SIHOMBING 1
MATERIAL REQUIREMENT PLANNING
Production Planning and Control
Haeryip Sihombing
Universiti Teknikal Malaysia Melaka
(UTeM)
4aBMFP 4513
MRP Overview
MRP is known as a push system, since it plans production according to forecasts of future demand and pushes out products accordingly
MRP planning is based on time buckets (or periods)
Orders (current demand) and forecasts (future demand) for end-items drive the system
These requirements drive the need for subassemblies and components at lower levels of the bill-of-materials (BOM)
MRP Systems
The inventory control mechanisms we studied to
this point are much better for single-item planning
Many products manufacturers produce have a
complex bill-of-materials (recipe of components)
Demand for components is dependent on end-
product demand (which we’ll call independent
demand items)
MRP systems encode the interdependence
among various end-items and components
MRP Overview
The end-item demands are translated into a Master Production Schedule (MPS)
MPS contains: Gross Requirements
On-Hand Inventory
Scheduled Receipts
MRP Procedure: Netting: Subtract out on-hand and scheduled receipts from
Gross Requirements
Lot Sizing: Given net requirements, determine periods in which production will occur, and the corresponding lot sizes (often uses Wagner-Whitin lot sizing procedure)
MRP Overview
MRP Procedure (cont’d) Time Phasing: Offset due dates of required items based
on lead times to determine order release times
BOM Explosion: Go down to the next level in the BOM and use the lot sizes at the higher level to determine gross requirements
Repeat for all levels in the BOM
Notes on Netting: We first use on-hand inventory to satisfy gross
requirements
If on-hand inventory is insufficient to meet some future demand and scheduled receipts are scheduled following this future demand, it doesn’t make sense to plan a new order, since an outstanding order exists
MRP Overview
Notes on Netting (cont’d) Instead of generating any new orders, we first attempt to
expedite currently scheduled receipts so they arrive earlier (we assume this is possible, if not, the schedule will be infeasible and customers will require notification of a delay)
When currently scheduled receipts are exhausted and netted out, we then have a set of net requirements that we use as requirements for the lot sizing procedure.
For now we’ll assume one of two very simple lot sizing rules: Lot-for-lot
Fixed order period (FOP)
2
MRP Example
Consider the following BOM:
And the table of req’ts
Part A
100 (2) 200
300 400
Part A 1 2 3 4 5 6 7 8
Gross Req’ts 15 20 50 10 30 30 30 30
Sched. Receipts 10 10 100
Adj. SRs
Proj. On-Hand 20
Net Req’ts
Planned Order Rec.
Planned Order Rel.
MRP Example
We first see how far our on-hand can take us, and whether we’ll
have to adjust the scheduled receipts
Since the first 3 periods demand equals 85, and the sum of the
on-hand plus SRs until then is 40, we should adjust SRs by
expediting the order receipt scheduled for period 4
We can then project on-hand inventory
Part A 1 2 3 4 5 6 7 8
Gross Req’ts 15 20 50 10 30 30 30 30
Sched. Receipts 10 10 100
Adj. SRs 20 100
Proj. On-Hand 20 5 5 55 45 15 -15
Net Req’ts
Planned Order Rec.
Planned Order Rel.
MRP Example
From period 6 on we have no on-hand or
scheduled receipts, so the deficit becomes net
requirements
Part A 1 2 3 4 5 6 7 8
Gross Req’ts 15 20 50 10 30 30 30 30
Sched. Receipts 10 10 100
Adj. SRs 20 100
Proj. On-Hand 20 5 5 55 45 15 -15
Net Req’ts 15 30 30
Planned Order Rec.
Planned Order Rel.
MRP Example
Suppose our lot-sizing rule is an FOP = 2
Suppose producing Part A (given that all of its
components are available takes 2 periods
We then generate the planned order releases
Part A 1 2 3 4 5 6 7 8
Gross Req’ts 15 20 50 10 30 30 30 30
Sched. Receipts 10 10 100
Adj. SRs 20 100
Proj. On-Hand 20 5 5 55 45 15 -15
Net Req’ts 15 30 30
Planned Order Rec. 45 30
Planned Order Rel. 45 30
MRP Example
Next, we move down in the BOM to
component 100:
Component 100 has 40 on-hand, no
scheduled receipts and a 2 week lead time
Part A
100 (2) 200
300 400
Component 100 1 2 3 4 5 6 7 8
Gross Req’ts 90 60
Sched. Receipts
Adj. SRs
Proj. On-Hand 40 40 40 40 -50
Net Req’ts 50 60
Planned Order Rec. 50 60
Planned Order Rel. 50 60
Lot Sizing Rules for MRP
We discussed three lot-sizing procedures:
Lot-for-lot, FOP, and Wagner-Whitin
Here we consider additional heuristic rules
Fixed Order Quantity and EOQ Each time we order, we order a set amount
We cannot directly apply the EOQ formula, since we have no constant demand rate, D
One strategy is to use the average demand per period in place of D in the EOQ formula and use the result as the fixed order quantity
We schedule order receipts for periods in which we project negative on-hand inventory
3
Lot-Sizing Rules
Part-Period Balancing Example
Suppose our requirements for the next 9 periods are
• (0, 15, 45, 0, 0, 25, 15, 20, 15)
• Let A = $150, and let h = $2 per unit per period
Our first setup is in period 2:
Since $90 is closer to $150, we use the setup in period 2
to satisfy demand for periods 2 and 3 (Q2 = 60)
Satisfy demand until: Setup Cost Part-Periods Holding Cost
2 $150 0 $0
3 $150 45 $90
6 $150 145 $290
Lot-Sizing Rules
Part-Period Balancing Example (cont’d)
Our next setup is in period 6
The setup in period 6 covers demand until period 8
Satisfy demand until: Setup Cost Part-Periods Holding Cost
6 $150 0 $0
7 $150 15 $30
8 $150 55 $110
9 $150 100 $200
More Lot-Sizing Rules
Least-Unit Cost Heuristic
Do a setup in the first period necessary (call this
period i), then
Work forward, period by period (as with PPB) and
calculate the average cost incurred per unit
Stop at the first period in which the cost per unit increases,
call this period i + k.
The setup in period i covers demand from period i to
period i + k – 1.
More Lot-Sizing Rules
Silver Meal Heuristic
Do a setup in the first period necessary (call this
period i), then
Work forward, period by period (as with PPB) and
calculate the average cost incurred per period
Stop at the first period in which the cost per period
increases, call this period i + k.
The setup in period i covers demand from period i to
period i + k – 1.
Safety Stock and Safety Lead Times
MRP assumes data are deterministic
Lead times are fixed
Demand requirements are certain
Lot size yields are 100%
This is clearly not the case in most production environments
Safety stock inflates requirements to buffer against demand uncertainties
Safety lead times inflate expected lead time to ensure supply availability at production stages
Also inflate requirements based upon expected yield
If yield equals y, multiple requirements by 1/y
Benefits of MRP
1. Better response to customer orders
2. Faster response to market changes
3. Improved utilization of facilities and labor
4. Reduced inventory levels
4
Dependent Demand
The demand for one item is related to the demand for another item
Given a quantity for the end item, the demand for all parts and components can be calculated
In general, used whenever a schedule can be established for an item
MRP is the common technique
Dependent Demand
1. Master production schedule
2. Specifications or bill of material
3. Inventory availability
4. Purchase orders outstanding
5. Lead times
Effective use of dependent demand inventory models requires the following
Master Production Schedule (MPS)
Specifies what is to be made and when
Must be in accordance with the aggregate production plan
Aggregate production plan sets the overall level of output in broad terms
As the process moves from planning to execution, each step must be tested for feasibility
The MPS is the result of the production planning process
Master Production Schedule (MPS)
MPS is established in terms of specific products
Schedule must be followed for a reasonable length of time
The MPS is quite often fixed or frozen in the near term part of the plan
The MPS is a rolling schedule
The MPS is a statement of what is to be produced, not a forecast of demand
Master Production Schedule (MPS)
A customer order in a job shop (make-to-order) company
Modules in a repetitive (assemble-to-stock) company
An end item in a continuous (make-to-stock) company
Can be expressed in any of the following terms:
Aggregate Production Plan
Months January February
Aggregate Production Plan 1,500 1,200(shows the totalquantity of amplifiers)
Weeks 1 2 3 4 5 6 7 8
Master Production Schedule(shows the specific type andquantity of amplifier to beproduced
240 watt amplifier 100 100 100 100
150 watt amplifier 500 500 450 450
75 watt amplifier 300 100
Figure 14.2
5
The Planning Process
Figure 14.1
Change production
plan?Master production schedule
ManagementReturn oninvestmentCapital
EngineeringDesigncompletion
Aggregate production
plan
ProcurementSupplierperformance
Human resourcesManpowerplanning
ProductionCapacityInventory
MarketingCustomerdemand
FinanceCash flow
The Planning Process
Figure 14.1
Is capacity plan being
met?
Is execution meeting the
plan?
Change master
production schedule?
Change capacity?
Change requirements?
No
Execute material plans
Execute capacity plans
Yes
Realistic?
Capacity requirements plan
Material requirements plan
Master production schedule
Focus for Different Process Strategies
Stock to Forecast
(Product Focus)
Schedule finished product
Assemble to Order or Forecast(Repetitive)
Schedule modules
Make to Order
(Process Focus)
Schedule orders
Examples: Print shop Motorcycles Steel, Beer, Bread
Machine shop Autos, TVs Lightbulbs
Fine-dining restaurant Fast-food restaurant Paper
Typical focus of the master production
schedule
Number of end items
Number of inputs
Figure 14.3
Bills of Material
List of components, ingredients, and materials needed to make product
Provides product structure
Items above given level are called parents
Items below given level are called children
BOM Example
B(2) Std. 12” Speaker kit C(3)Std. 12” Speaker kit w/ amp-booster1
E(2)E(2) F(2)
Packing box and installation kit of wire,
bolts, and screws
Std. 12” Speaker booster assembly
2
D(2)
12” Speaker
D(2)
12” Speaker
G(1)
Amp-booster
3
Product structure for “Awesome” (A)
A
Level
0
BOM Example
B(2) Std. 12” Speaker kit C(3)Std. 12” Speaker kit w/ amp-booster1
E(2)E(2) F(2)
Packing box and installation kit of wire,
bolts, and screws
Std. 12” Speaker booster assembly
2
D(2)
12” Speaker
D(2)
12” Speaker
G(1)
Amp-booster
3
Product structure for “Awesome” (A)
A
Level
0
Part B: 2 x number of As = (2)(50) = 100
Part C: 3 x number of As = (3)(50) = 300
Part D: 2 x number of Bs
+ 2 x number of Fs = (2)(100) + (2)(300) = 800
Part E: 2 x number of Bs
+ 2 x number of Cs = (2)(100) + (2)(150) = 500
Part F: 2 x number of Cs = (2)(150) = 300
Part G: 1 x number of Fs = (1)(300) = 300
6
Bills of Material
Modular Bills
Modules are not final products but components that can be assembled into multiple end items
Can significantly simplify planning and scheduling
Bills of Material
Planning Bills
Created to assign an artificial parent to the BOM
Used to group subassemblies to reduce the number of items planned and scheduled
Used to create standard “kits” for production
Bills of Material
Phantom Bills
Describe subassemblies that exist only temporarily
Are part of another assembly and never go into inventory
Low-Level Coding
Item is coded at the lowest level at which it occurs
BOMs are processed one level at a time
Accurate Records
Accurate inventory records are absolutely required for MRP (or any dependent demand system) to operate correctly
Generally MRP systems require 99% accuracy
Outstanding purchase orders must accurately reflect quantities and schedule receipts
Lead Times
The time required to purchase, produce, or assemble an item
For purchased items – the time between the recognition of a need and the availability of the item for production
For production – the sum of the order, wait, move, setup, store, and run times
Time-Phased Product Structure
| | | | | | | |
1 2 3 4 5 6 7 8Time in weeks
F
2 weeks
3 weeks
1 week
A
2 weeks
1 week
D
E
2 weeks
D
G
1 week
1 week
2 weeks to produce
B
C
E
Start production of DMust have D and E completed here so
production can begin on B
Figure 14.4
7
MRP Structure
Figure 14.5
Output Reports
MRP by period report
MRP by date report
Planned order report
Purchase advice
Exception reports
Order early or late or not needed
Order quantity too small or too large
Data Files
Purchasing data
BOM
Lead times
(Item master file)
Inventory data
Masterproduction schedule
Material requirement
planning programs
(computer and software)
Determining Gross Requirements
Starts with a production schedule for the end item – 50 units of Item A in week 8
Using the lead time for the item, determine the week in which the order should be released – a 1 week lead time means the order for 50 units should be released in week 7
This step is often called “lead time offset” or “time phasing”
Determining Gross Requirements
From the BOM, every Item A requires 2Item Bs – 100 Item Bs are required in week 7 to satisfy the order release for Item A
The lead time for the Item B is 2 weeks –release an order for 100 units of Item B in week 5
The timing and quantity for component requirements are determined by the order release of the parent(s)
Determining Gross Requirements
The process continues through the entire BOM one level at a time – often called “explosion”
By processing the BOM by level, items with multiple parents are only processed once, saving time and resources and reducing confusion
Low-level coding ensures that each item appears at only one level in the BOM
Gross Requirements Plan
Table 14.3
Week
1 2 3 4 5 6 7 8 Lead Time
A. Required date 50Order release date 50 1 week
B. Required date 100Order release date 100 2 weeks
C. Required date 150Order release date 150 1 week
E. Required date 200 300Order release date 200 300 1 week
F. Required date 300Order release date 300 3 weeks
D. Required date 600 200Order release date 600 200 1 week
G. Required date 300Order release date 300 1 week
Net Requirements Plan
8
Net Requirements Plan Determining Net Requirements
Starts with a production schedule for the end item – 50 units of Item A in week 8
Because there are 10 Item As on hand, only 40 are actually required – (net requirement) = (gross requirement - on-hand inventory)
The planned order receipt for Item A in week 8 is 40 units – 40 = 50 - 10
Determining Net Requirements
Following the lead time offset procedure, the planned order release for Item A is now 40 units in week 7
The gross requirement for Item B is now 80 units in week 7
There are 15 units of Item B on hand, so the net requirement is 65 units in week 7
A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5
Determining Net Requirements
A planned order receipt of 65 units in week 7 generates a planned order release of 65 units in week 5
The on-hand inventory record for Item B is updated to reflect the use of the 15 items in inventory and shows no on-hand inventory in week 8
This is referred to as the Gross-to-Net calculation and is the third basic function of the MRP process
Gross Requirements Schedule
Figure 14.6A
B C
5 6 7 8 9 10 11
40 50 15
Lead time = 4 for AMaster schedule for A
S
B C
12 138 9 10 11
20 3040
Lead time = 6 for SMaster schedule for S
1 2 3
10 10
Master schedulefor B
sold directly
Periods
Therefore, these are the gross requirements for B
Gross requirements: B 10 40 50 2040+10 15+30
=50 =45
1 2 3 4 5 6 7 8Periods
MRP Planning Sheet
Figure 14.7
9
Net Requirements Plan
The logic of net requirements
available inventory
net requirements
on hand
scheduled receipts+– =
total requirements
gross requirements
allocations+
MRP Management
MRP is a dynamic system
Facilitates replanning when changes occur
System nervousness can result from too many changes
Time fences put limits on replanning
Pegging links each item to its parent allowing effective analysis of changes
MRP and JIT
MRP is a planning system that does not do detailed scheduling
MRP requires fixed lead times which might actually vary with batch size
JIT excels at rapidly moving small batches of material through the system
Finite Capacity Scheduling
MRP systems do not consider capacity during normal planning cycles
Finite capacity scheduling (FCS) recognizes actual capacity limits
By merging MRP and FCS, a finite schedule is created with feasible capacities which facilitates rapid material movement
Small Bucket Approach
1. MRP “buckets” are reduced to daily or hourly
The most common planning period (time bucket) for MRP systems is weekly
2. Planned receipts are used internally to sequence production
3. Inventory is moved through the plant on a JIT basis
4. Completed products are moved to finished goods inventory which reduces required quantities for subsequent planned orders
5. Back flushing based on the BOM is used to deduct inventory that was used in production
Lot-Sizing Techniques
Lot-for-lot techniques order just what is required for production based on net requirements
May not always be feasible
If setup costs are high, costs may be high as well
Economic order quantity (EOQ)
EOQ expects a known constant demand and MRP systems often deal with unknown and variable demand
10
Lot-Sizing Techniques
Part Period Balancing (PPB) looks at future orders to determine most economic lot size
The Wagner-Whitin algorithm is a complex dynamic programming technique
Assumes a finite time horizon
Effective, but computationally burdensome
Lot-for-Lot Example
1 2 3 4 5 6 7 8 9 10
Gross requirements 35 30 40 0 10 40 30 0 30 55
Scheduled receipts
Projected on hand 35 35 0 0 0 0 0 0 0 0 0
Net requirements 0 30 40 0 10 40 30 0 30 55
Planned order
receipts30 40 10 40 30 30 55
Planned order
releases30 40 10 40 30 30 55
Holding cost = $1/week; Setup cost = $100
Lot-for-Lot Example
1 2 3 4 5 6 7 8 9 10
Gross requirements 35 30 40 0 10 40 30 0 30 55
Scheduled receipts
Projected on hand 35 35 0 0 0 0 0 0 0 0 0
Net requirements 0 30 40 0 10 40 30 0 30 55
Planned order
receipts30 40 10 40 30 30 55
Planned order
releases30 40 10 40 30 30 55
Holding cost = $1/week; Setup cost = $100
No on-hand inventory is carried through the systemTotal holding cost = $0
There are seven setups for this item in this planTotal setup cost = 7 x $100 = $700
EOQ Lot Size Example
1 2 3 4 5 6 7 8 9 10
Gross requirements 35 30 40 0 10 40 30 0 30 55
Scheduled receipts
Projected on hand 35 35 0 0 0 0 0 0 0 0 0
Net requirements 0 30 0 0 7 0 4 0 0 16
Planned order
receipts73 73 73 73
Planned order
releases73 73 73 73
Holding cost = $1/week; Setup cost = $100;
Average weekly gross requirements = 27; EOQ = 73 units
EOQ Lot Size Example
1 2 3 4 5 6 7 8 9 10
Gross requirements 35 30 40 0 10 40 30 0 30 55
Scheduled receipts
Projected on hand 35 35 0 0 0 0 0 0 0 0 0
Net requirements 0 30 0 0 7 0 4 0 0 16
Planned order
receipts73 73 73 73
Planned order
releases73 73 73 73
Holding cost = $1/week; Setup cost = $100;
Average weekly gross requirements = 27; EOQ = 73 units
Annual demand = 1,404Total cost = setup cost + holding costTotal cost = (1,404/73) x $100 + (73/2) x ($1 x 52 weeks)Total cost = $3,798Cost for 10 weeks = $3,798 x (10 weeks/52 weeks) =
$730
PPB Example
1 2 3 4 5 6 7 8 9 10
Gross requirements 35 30 40 0 10 40 30 0 30 55
Scheduled receipts
Projected on hand 35
Net requirements
Planned order
receipts
Planned order
releases
Holding cost = $1/week; Setup cost = $100;
EPP = 100 units
11
PPB Example
1 2 3 4 5 6 7 8 9 10
Gross requirements 35 30 40 0 10 40 30 0 30 55
Scheduled receipts
Projected on hand 35
Net requirements
Planned order
receipts
Planned order
releases
Holding cost = $1/week; Setup cost = $100;
EPP = 100 units
2 30 0
2, 3 70 40 = 40 x 1
2, 3, 4 70 40
2, 3, 4, 5 80 70 = 40 x 1 + 10 x 3 100 70 170
2, 3, 4, 5, 6 120 230 = 40 x 1 + 10 x 3
+ 40 x 4
+ =
Combine periods 2 - 5 as this results in the Part Period closest to the EPP
Combine periods 6 - 9 as this results in the Part Period closest to the EPP
6 40 0
6, 7 70 30 = 30 x 1
6, 7, 8 70 30 = 30 x 1 + 0 x 2
6, 7, 8, 9 100 120 = 30 x 1 + 30 x 3 100 120 220+ =
10 55 0 100 0 100
Total cost 300 190 490
+ =
+ =
Trial Lot Size
Periods (cumulative net Costs
Combined requirements) Part Periods Setup Holding Total
Lot-Sizing Summary
For these three examples
Lot-for-lot $700
EOQ $730
PPB $490
Wagner-Whitin would have yielded a plan
with a total cost of $455 for this example
Lot-Sizing Summary
In theory, lot sizes should be recomputed whenever there is a lot size or order quantity change
In practice, this results in system nervousness and instability
Lot-for-lot should be used when economical
Lot sizes can be modified to allow for scrap, process constraints, and purchase lots
Lot-Sizing Summary
Use lot-sizing with care as it can cause considerable distortion of requirements at lower levels of the BOM
When setup costs are significant and demand is reasonably smooth, PPB, Wagner-Whitin, or EOQ should give reasonable results
Extensions of MRP
Closed-Loop MRP
MRP system provides input to the capacity plan, MPS, and production planning process
Capacity Planning
MRP system generates a load report which details capacity requirements
This is used to drive the capacity planning process
Changes pass back through the MRP system for rescheduling
Closed-Loop MRP System
Figure 14.8
12
MRP Problems
MRP does not account for production capacity limits (or their effects on lead times)
Inflated safety lead times lead to high WIP levels
System nervousness: MRP is not robust to changes in customer requirements
Replanning the current schedule based on changes can lead to infeasible schedules
Frozen zones specify a number of periods in which the schedule is fixed (cannot be changed)
Can lead to problems with sales and marketing depts.
Time fences are usually used, where the first X weeks are absolutely frozen, the next Y weeks can allow changes with a possible customer financial penalties, and beyond X + Y weeks is open for any changes
From ERP to APS Systems
ERP systems still at best only contain the basic MRP II
logic for planning and controlling production
More advanced production planning logic requires
customized development within the ERP system
Advanced Production and Scheduling (APS) systems
complement ERP systems by providing more sophisticated
production planning and scheduling logic
Firms such as I2 Technologies and Manugistics have
enjoyed tremendous growth in the late 1990’s due to their
APS systems
APS Systems Capabilities
Demand Planning – Sophisticated forecasting techniques
to analyze customer buying patterns
Supply Planning – Synchronizes operations of
manufacturers, suppliers, and logistics service providers
through information exchange. Provides better, more
accurate information for managing incoming materials
Demand fulfillment – Provides more accurate estimates of
order fulfillment dates; manages order promising, provides
backlog management, and tracks order fulfillment
APS’s have modules for managing pull systems and can
dynamically track WIP, throughput, and cycle times