1 WAMEDH M.T. AL-MUSSAWI | Basrah, Iraq | [email protected] | +964-770-808-0397 and +964-780-979-5500 PROFESSIONAL EXPERIENCE EMPLOYMENT HISTORY Professional Engineer Experience: To build new 400 bed education hospital in Karbala with three buildings with 10 heavy and low current systems. Two new civil defense and extinguisher plants for low and heavy (power) current systems. Three field projects to supervision on transmission lines and service transformers in three new towns. As the Senior Electrical Engineer at the KBR project, responsible for rebuilding all items for H.V, M.V. and L.V. systems in Degassing and Compression stations. Designed and checked all electrical items for quality control. At the Bechtel Hartha water treatment plan project, supervised the setup and maintenance for starter panels, circuit breakers, switchgear and cables. Maintained and refurbished several types of motors (15-355), 2MVA transformers and several types of starters; and installed all bulks for the site. During the installation of Schneider MCCs, I monitored and maintained junction boxes, cable insulation, laying cable, installation of change-over panels, level controllers for level sensors, setting of equipment for change-over, motor circuit breakers, thermal relay (overload), Timer and Earth leakage (Merlin Gerin, Telemechanique), and the insulation testing and installation of submersible pumps. At the KBR South Camp in Basrah International Airport, I installed switch gear panels, junction boxes, cables, glands and termination cables. Conducted several project studies and prepared project proposals for the government of Basrah. Worked with several Cargo and Oil Marine and Shipping companies to maintain and upgrade power systems and communication systems. This included A.C. generators, D.C. generators, and A.C.-D.C. generators. Leadership &Administration: Extensive supervisory experience, leading several teams of engineers at the KBR, Bechtel, and Al- Site Consultant engineer with MK Associated and UNIVERSAL ACARSON COMPANY December 2009•]till the date With several Iraqi companies like silver stone company and Schneider brunch in Basra September 2007] october 2009 Mott Macdonald as senior electrical engineer April 2007‐septmber 2007 KELLOGG BROWN AND ROOT (KBR), Iraq Senior Electrical Engineer June 2005 – April 2007 AL-RATBA’A (BECHTEL Sub-Contractor), Iraq Supervisor, Electrical Engineer June 2004 – April 2005 MAJED ABDALLAH SHIPPING, U.A.E. Electrical Engineer April 2003 – August 2008 NASSEM AL-FAIHA’A, Iraq & U.A.E. Electrical Engineer September 2001 – April 2003 AL-SEEBA CONTRACT,Iraq Supervisor, Electrical Engineer 2001 TECHNICAL SKILLS Electrical Engineering Professional Electrical Safety – Lockout/Tag out Motor Starting Professional Office Tools: Microsoft Word Microsoft Excel Microsoft PowerPoint EDUCATION & AWARDS Bachelor of Science in Electrical Engineering University of Basrah Basrah, Iraq 1999 Lead Awareness Training, 2005 KBR Lockout / Tag Out Training, 2005 KBR Defensive Driving Training, 2005 KBR

Professional CV - Wamedh Al-Mussawi

Embed Size (px)

Citation preview

Page 1: Professional CV - Wamedh Al-Mussawi

1

WAMEDH M.T. AL-MUSSAWI | Basrah, Iraq | [email protected] |

+964-770-808-0397 and +964-780-979-5500

PROFESSIONAL EXPERIENCE EMPLOYMENT HISTORY

Professional Engineer Experience:

To build new 400 bed education hospital in Karbala with three buildings with 10 heavy and low current

systems.

Two new civil defense and extinguisher plants for low

and heavy (power) current systems.

Three field projects to supervision on transmission lines and service transformers in three new towns.

As the Senior Electrical Engineer at the KBR project, responsible for rebuilding all items for H.V, M.V. and L.V. systems in Degassing and Compression stations. Designed and checked all electrical items for quality control.

At the Bechtel Hartha water treatment plan project, supervised the setup and maintenance for starter panels, circuit breakers, switchgear and cables. Maintained and refurbished several types of motors (15-355), 2MVA transformers and several types of starters; and installed all bulks for the site.

During the installation of Schneider MCCs, I monitored and maintained junction boxes, cable insulation, laying cable, installation of change-over panels, level controllers for level sensors, setting of equipment for change-over, motor circuit breakers, thermal relay (overload), Timer and Earth leakage (Merlin Gerin, Telemechanique), and the insulation testing and installation of submersible pumps.

At the KBR South Camp in Basrah International Airport, I installed switch gear panels, junction boxes, cables, glands and termination cables.

Conducted several project studies and prepared project proposals for the government of Basrah.

Worked with several Cargo and Oil Marine and Shipping companies to maintain and upgrade power systems and communication systems. This included A.C. generators, D.C. generators, and A.C.-D.C. generators.

Leadership &Administration:

Extensive supervisory experience, leading several teams of engineers at the KBR, Bechtel, and Al-

Site Consultant engineer with MK Associated and UNIVERSAL ACARSON COMPANY December 2009•]till the date

With several Iraqi companies like silver stone company and Schneider brunch in Basra

September 2007] october 2009

Mott Macdonald as senior electrical engineer April 2007‐septmber 2007

KELLOGG BROWN AND ROOT (KBR), Iraq Senior Electrical Engineer June 2005 – April 2007

AL-RATBA’A (BECHTEL Sub-Contractor), Iraq Supervisor, Electrical Engineer June 2004 – April 2005

MAJED ABDALLAH SHIPPING, U.A.E. Electrical Engineer April 2003 – August 2008

NASSEM AL-FAIHA’A, Iraq & U.A.E. Electrical Engineer September 2001 – April 2003

AL-SEEBA CONTRACT,Iraq Supervisor, Electrical Engineer 2001

TECHNICAL SKILLS

Electrical Engineering Professional

Electrical Safety – Lockout/Tag out

Motor Starting

Professional Office Tools: Microsoft Word Microsoft Excel Microsoft PowerPoint

EDUCATION & AWARDS

Bachelor of Science in Electrical Engineering University of Basrah Basrah, Iraq 1999

Lead Awareness Training, 2005 KBR

Lockout / Tag Out Training, 2005 KBR

Defensive Driving Training, 2005 KBR

Page 2: Professional CV - Wamedh Al-Mussawi

2

SEEBA projects.

Significant experience with managing projects, studying requests for information and proposals, preparing project offers, and working with government and private clients in project planning and negotiation.

First Aid Training, 2006 KBR

400v Areva switchgears, Interlocking, and Protection Training, 2007 Petroleum Cultural Center SOC

Outstanding Performance Recognition, 2007 KBR

REFERENCES

Charles Haynes, KBR – PCO Oil Program Engineering Coordinator

[email protected]&[email protected] Javed Sultan, KBR – PCO Oil Program Senior Electrical Engineer

[email protected]

Page 3: Professional CV - Wamedh Al-Mussawi

3

Page 4: Professional CV - Wamedh Al-Mussawi

4

Page 5: Professional CV - Wamedh Al-Mussawi

5

Page 6: Professional CV - Wamedh Al-Mussawi

6

Page 7: Professional CV - Wamedh Al-Mussawi

7

Page 8: Professional CV - Wamedh Al-Mussawi

8

Page 9: Professional CV - Wamedh Al-Mussawi

9

Page 10: Professional CV - Wamedh Al-Mussawi

10

Page 11: Professional CV - Wamedh Al-Mussawi

11

Page 12: Professional CV - Wamedh Al-Mussawi

12

Page 13: Professional CV - Wamedh Al-Mussawi

13

Page 14: Professional CV - Wamedh Al-Mussawi

14

Page 15: Professional CV - Wamedh Al-Mussawi

15

Page 16: Professional CV - Wamedh Al-Mussawi

16

Page 17: Professional CV - Wamedh Al-Mussawi

17

Page 18: Professional CV - Wamedh Al-Mussawi

18

Page 19: Professional CV - Wamedh Al-Mussawi

19

Page 20: Professional CV - Wamedh Al-Mussawi

20