Progress of Shintake Monitor Work
KEK site meetingAugust 26, 2009
T. Yamanaka
IP Target
• Design was fixed.• Fabrication is going on now.
Design of IP TargetDesign of IP Target
Collimator Scan
• Preparation of hardware is almost finished.– Only just lead collimator block is not prepared.
• Remaining task is to write scanning program
Background Monitor
• Drive system of background monitor is prepared.
• It need just only lead converter sheet
Cherenkov Detector
• Fabrication was finished.• Calibration of photon nu
mber using cosmic ray was almost finished.
• Put Cherenkov detector at the actual position as a trial
Cosmic Ray Data
Laser Transport
• Ordered a mount table for laser transport line as same as the EXT LW group
• It will be connected by PVC pipe to the mount table of EXT LW group.
Put this optical table on a mount
Replacement of Actuators
• Mirror actuators are changed from old ones.• New actuators (Thorlabs) need Windows’s base
d control– Windows machine is prepared– They are connected to PC by USB
• By using “AnywhereUSB” USB devices are converted to LAN
– To control by program and communicate with EPICS, LabVIEW is installed
• Need to write LabVIEW program Now here