Progress Report for DC System Project_as of January 132013

Embed Size (px)

Citation preview

  • 7/30/2019 Progress Report for DC System Project_as of January 132013

    1/3

    RAISSY TRADING & CONSTRUCTION CO. LTD.

    DAILYPROGRESSREPORTProjectName:ReplacementOfDCSystemForSubstaionInAsir ProjectStarted: October6,2012Location :AsirRegion ReportNo.:10PeriodCovered : Date: January13,2013S/N DESCRIPTION

    Date

    Start

    Date

    Finish

    ToDate TotalRemarks

    Accomp AccompI Mobilization

    1 Manpower 10/06/12 11/05/12 100% completed

    2 EquipmentandTools 10/06/12 10/10/12 100% completed3 Materials 10/10/12 28/12/12 100% completed

    SUBSTATIONDCSYSTEMINSTALLATION

    IReplacementOfDCSysteminKamisNorth

    S/S

    1 DeliveryOfMaterialsToSubstation 10/07/12 10/08/12 100% completed2 InstallationofNewBatteryCharger 10/14/12 10/15/12 100% completed3 InstallationofNewBatteryCells 10/16/12 10/17/12 100% completed4 Fillingofelectrolytestobatterycells 10/18/12 10/20/12 100% completed5 CablingandWiringofNewDCSystem 11/20/12 11/21/12 100% completed6 TestingandCommissioning

    DCDistributionPanelis

    alreadyavailablefrom

    SCECO

    7 Dismantlin of the existin s stem8 Housekeeping&HandovertoClient(SEC)II ReplacementOfDCSysteminMilitary1S/S

    1 DeliveryOfMaterialsToSubstation 10/09/12 10/10/12 100% completed2 Installation

    of

    New

    Battery

    Charger 10/21/12 10/22/12 100% completed

    3 InstallationofNewBatteryCells 10/23/12 10/24/12 100% completed4 Fillingofelectrolytestobatterycells 11/04/12 11/05/12 100% completed5 CablingandWiringofNewDCSystem 11/22/12 11/24/12 100% completed6 TestingandCommissioning AwaitingforSCECOto

    providesecondary

    transformerfor380VAC

    powersupply.

    7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)

    III ReplacementOfDCSysteminMilitary2S/S

    1 DeliveryOfMaterialsToSubstation 10/11/12 10/13/12 100% completed2 InstallationofNewBatteryCharger 11/06/12 11/07/12 100% completed3 InstallationofNewBatteryCells 11/08/12 11/10/12 100% completed4 Fillingofelectrolytestobatterycells 11/11/12 11/12/12 100% completed5 CablingandWiringofNewDCSystem 11/25/12 11/26/12 100% completed6 TestingandCommissioning AwaitingforSCECOto

    providesecondary

    transformerfor380VAC

    powersupply.

    7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)

    IVReplacementOfDCSysteminSaratObeida

    S/S

    1 DeliveryOf

    Materials

    To

    Substation 10/14/12 10/14/12 100% completed

  • 7/30/2019 Progress Report for DC System Project_as of January 132013

    2/3

    2 InstallationofNewBatteryCharger 11/13/12 11/14/12 100% completed3 InstallationofNewBatteryCells 11/15/12 11/17/12 100% completed4 Fillingofelectrolytestobatterycells 11/18/12 11/19/12 100% completed5 CablingandWiringofNewDCSystem 11/27/12 12/02/12 100% completed6 TestingandCommissioning

    Scheduledfortestingan

    commissioning7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)V

    ReplacementOfDCSysteminMuhayil

    SouthS/S

    1 DeliveryOfMaterialsToSubstationtransferofmaterialisto

    bescheduledin

    coordinationwithSCECO

    Twobatterysystem

    replacementwillbe

    installed.

    2 InstallationofNewBatteryCharger3 InstallationofNewBatteryCells4 Fillingofelectrolytestobatterycells5 CablingandWiringofNewDCSystem6 TestingandCommissioning7 Dismantlingoftheexistingsystem8 Housekeeping&HandovertoClient(SEC)

    PORTABLEDCSYSTEMINSTALLATION

    I AssemblyOf

    1st

    Portable

    DC

    System

    1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 12/01/12 12/10/12 100% completed4 InstallationofNewBatteryCells 12/11/12 12/13/12 100% completed5 Fillingofelectrolytestobatterycells 12/15/12 12/16/12 100% completed6 CablingandWiringofPortableDCSystem 12/17/12 12/19/12 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)

    II Assembly

    Of

    2nd

    Portable

    DC

    System1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 12/20/12 12/22/12 100% completed4 InstallationofNewBatteryCells 12/23/12 12/24/12 100% completed5 Fillingofelectrolytestobatterycells 12/25/12 12/28/12 100% completed6 CablingandWiringofPortableDCSystem 12/29/12 12/30/12 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)

    III AssemblyOf3rdPortableDCSystem

    1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 01/02/13 01/04/13 100% completed4 InstallationofNewBatteryCells 01/02/13 01/06/13 100% completed5 Fillingofelectrolytestobatterycells 01/07/13 01/07/13 100% completed6 CablingandWiringofPortableDCSystem 12/28/12 12/29/12 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)

    IV AssemblyOf4rthPortableDCSystem

    1 DeliveryOf

    Materials

    To

    Substation 100% completed

  • 7/30/2019 Progress Report for DC System Project_as of January 132013

    3/3

    2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 01/07/13 01/08/13 100% completed4 InstallationofNewBatteryCells 01/09/13 01/11/13 100% completed5 Fillingofelectrolytestobatterycells 01/12/13 01/13/13 25%6 CablingandWiringofPortableDCSystem 01/11/13 01/12/13 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)V AssemblyOf5thPortableDCSystem

    1 DeliveryOfMaterialsToSubstation 100% completed2 AssemblyOfMobileCabinet 100% completed3 InstallationofNewBatteryCharger 01/08/13 01/08/13 100% completed4 InstallationofNewBatteryCells 01/10/13 01/11/13 100% completed5 Fillingofelectrolytestobatterycells 01/12/13 01/13/13 25%6 CablingandWiringofPortableDCSystem 01/11/13 01/12/13 90%7 TestingandCommissioning8 Housekeeping&HandovertoClient(SEC)

    PreparedBy:

    Eng'r.FrederickGuisando SiteEngineer