Project Authorization for Building Demolitions at:
• 2306 & 2338 East 11th St• 3502 Lincoln Ave• 1110 Alexander Ave
Item No.: 5ADate of Meeting: August 15, 2019
As referenced in Resolution No. 2018-01-PT, Exhibit A, Delegation of Authority Master Policy, Paragraph IV.B.(2), project costs exceeding $300,000 require approval from Port Commission.
Request project authorization in the amount $2,077,000, for a total authorized amount of $2,458,000, for the building demolitions at 2306 & 2338 East 11th St, 3502 Lincoln Ave, and 1110 Alexander Ave, Master Identification Nos. 101442.01, 101442.02, 101442.03, and 101452.01.
Project AuthorizationBuilding Demolitions
2
BackgroundBuilding Demolitions
• The proposed improvements include demolition of four buildings:
• 2306 & 2338 East 11th Street formerly occupied by Fastco for approx. 50 years former mini-storage and screen printing business
• 3502 Lincoln Avenue formerly occupied by American Fast Freight
• 1110 Alexander Avenue former marine construction laydown yard used by Orion
Marine Construction
3
Aerial image of four properties
4
Ground-level image of 2306/2338 E. 11th Street
2306 East 11th Street5
2338 East 11th Street6
Ground-level image of 3502 Lincoln Avenue
3502 Lincoln Avenue7
Ground-level image of 1110 Alexander Avenue
1110 Alexander Avenue8
Project Description and DetailsBuilding Demolitions
The scope of work includes the following:• Design and specifications for Public Work
Contracting.• Hazardous materials investigation and
abatement.• Demolition of the buildings and surrounding
landscaping to provide a level site.• Disposal of the buildings.
9
Project BenefitBuilding Demolitions
• Eliminate liabilities and expenses associated with vacant buildings.
• Repurpose non-performing assets. • Support terminal expansion and truck queuing
opportunities along 11th Street corridor.• Prepare properties for future uses identified in
the Port’s Strategic Plan to support the Port’s core business.
10
Project ScheduleBuilding Demolitions
Activity TimeframeAdvertise Bids August 2019Bid Opening September 2019Contract Award October 2019Substantial Completion July 2020
11
Sheet1
ActivityTimeframe
Advertise BidsAugust 2019
Bid OpeningSeptember 2019
Contract AwardOctober 2019
Substantial CompletionJuly 2020
Sheet2
Sheet3
Source of FundsBuilding Demolitions
• The estimated cost of the Construction for this project is $2,077,000.
• The estimated budget for this project is $2,458,000.
• The current Capital Investment Plan (CIP) allocates $2,458,000 for this project.
12
Financial SummaryBuilding Demolitions
Property Phase This Request Total Previous Requests Total Cost
Design $0 $69,000 $69,000 Construction $271,750 $0 $271,750 Design $0 $94,000 $94,000 Construction $387,300 $0 $387,300 Design $0 $136,000 $136,000 Construction $298,050 $0 $298,050 Design $0 $82,000 $82,000 Construction $1,119,900 $0 $1,119,900
Total $2,077,000 $381,000 $2,458,000
2306 E. 11th
2338 E. 11th
3502 Lincoln
1110 Alexander
13
Sheet1
PropertyPhaseThisTotal Previous RequestsTotal Cost
Request
2306 E. 11thDesign$0$69,000$69,000
Construction$271,750$0$271,750
2338 E. 11thDesign$0$94,000$94,000
Construction$387,300$0$387,300
3502 LincolnDesign$0$136,000$136,000
Construction$298,050$0$298,050
1110 AlexanderDesign$0$82,000$82,000
Construction$1,119,900$0$1,119,900
Total$2,077,000$381,000$2,458,000
PropertyPhaseThis RequestTotal Previous RequestsTotal Cost
2306 E. 11thDesign$0$69,000$69,000
Construction$271,750$0$271,750
2338 E. 11thDesign$0$94,000$94,000
Construction$387,300$0$387,300
3502 LincolnDesign$0$136,000$136,000
Construction$298,050$0$298,050
1110 AlexanderDesign$0$82,000$82,000
Construction$1,119,900$0$1,119,900
Total$2,077,000$381,000$2,458,000
Environmental Impacts/ReviewBuilding Demolitions
Permitting: • This project is subject to SEPA review.• Environmental permits from US Army Corps of
Engineers (USACE), Washington Department of Ecology (Ecology), or Washington Department of Fish and Wildlife (WDFW) are not required.
• City of Tacoma will determine if Alexander Avenue demolition qualifies for shoreline permit exemption.
Remediation: N/A
14
Environmental Impacts/ReviewBuilding Demolitions
Stormwater:Temporary Erosion and Sediment Control (TESC) Plan and appropriate stormwater best management practices (BMPs) will be implemented during demolition.
Air Quality:• Construction equipment will meet all state and local
emission standards and regulations.• Port anti-idling policy will be enforced.
• Dust control BMPs will be implemented, as necessary.
15
ConclusionBuilding Demolitions
Request project authorization in the amount $2,077,000, for a total authorized amount of $2,458,000, for the Building Demolitions at 2306 & 2338 East 11th St, 3502 Lincoln Ave, and 1110 Alexander Ave, Master Identification Nos. 101442.01, 101442.02, 101442.03, and 101452.01.
16
Slide Number 1Slide Number 2Slide Number 3Aerial image of four properties�Ground-level image of �2306/2338 E. 11th StreetSlide Number 6Ground-level image of �3502 Lincoln AvenueGround-level image of �1110 Alexander AvenueSlide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16
Project Authorization for Building Demolitions at:
2306 & 2338 East 11th St
3502 Lincoln Ave
1110 Alexander Ave
Item No.: 5A
Date of Meeting: August 15, 2019
1
As referenced in Resolution No. 2018-01-PT, Exhibit A, Delegation of Authority Master Policy, Paragraph IV.B.(2), project costs exceeding $300,000 require approval from Port Commission.
Request project authorization in the amount $2,077,000, for a total authorized amount of $2,458,000, for the building demolitions at 2306 & 2338 East 11th St, 3502 Lincoln Ave, and 1110 Alexander Ave, Master Identification Nos. 101442.01, 101442.02, 101442.03, and 101452.01.
Project Authorization
Building Demolitions
2
Background
Building Demolitions
The proposed improvements include demolition of four buildings:
2306 & 2338 East 11th Street
formerly occupied by Fastco for approx. 50 years
former mini-storage and screen printing business
3502 Lincoln Avenue
formerly occupied by American Fast Freight
1110 Alexander Avenue
former marine construction laydown yard used by Orion Marine Construction
3
Aerial image of four properties
4
Ground-level image of 2306/2338 E. 11th Street
2306 East 11th Street
5
2338 East 11th Street
6
Ground-level image of 3502 Lincoln Avenue
3502 Lincoln Avenue
7
Ground-level image of 1110 Alexander Avenue
1110 Alexander Avenue
8
Project Description and Details
Building Demolitions
The scope of work includes the following:
Design and specifications for Public Work Contracting.
Hazardous materials investigation and abatement.
Demolition of the buildings and surrounding landscaping to provide a level site.
Disposal of the buildings.
9
Project Benefit
Building Demolitions
Eliminate liabilities and expenses associated with vacant buildings.
Repurpose non-performing assets.
Support terminal expansion and truck queuing opportunities along 11th Street corridor.
Prepare properties for future uses identified in the Port’s Strategic Plan to support the Port’s core business.
10
Project Schedule
Building Demolitions
11
Source of Funds
Building Demolitions
The estimated cost of the Construction for this project is $2,077,000.
The estimated budget for this project is $2,458,000.
The current Capital Investment Plan (CIP) allocates $2,458,000 for this project.
12
Financial Summary
Building Demolitions
13
Environmental Impacts/Review
Building Demolitions
Permitting:
This project is subject to SEPA review.
Environmental permits from US Army Corps of Engineers (USACE), Washington Department of Ecology (Ecology), or Washington Department of Fish and Wildlife (WDFW) are not required.
City of Tacoma will determine if Alexander Avenue demolition qualifies for shoreline permit exemption.
Remediation:
N/A
14
Environmental Impacts/Review
Building Demolitions
Stormwater:
Temporary Erosion and Sediment Control (TESC) Plan and appropriate stormwater best management practices (BMPs) will be implemented during demolition.
Air Quality:
Construction equipment will meet all state and local emission standards and regulations.
Port anti-idling policy will be enforced.
Dust control BMPs will be implemented, as necessary.
15
Conclusion
Building Demolitions
Request project authorization in the amount $2,077,000, for a total authorized amount of $2,458,000, for the Building Demolitions at 2306 & 2338 East 11th St, 3502 Lincoln Ave, and 1110 Alexander Ave, Master Identification Nos. 101442.01, 101442.02, 101442.03, and 101452.01.
16
ActivityTimeframe
Advertise BidsAugust 2019
Bid OpeningSeptember 2019
Contract AwardOctober 2019
Substantial CompletionJuly 2020
Sheet1
ActivityTimeframe
Advertise BidsAugust 2019
Bid OpeningSeptember 2019
Contract AwardOctober 2019
Substantial CompletionJuly 2020
Sheet2
Sheet3
PropertyPhaseThis Request
Total Previous
Requests
Total Cost
Design$0 $69,000 $69,000
Construction$271,750 $0 $271,750
Design$0 $94,000 $94,000
Construction$387,300 $0 $387,300
Design$0 $136,000 $136,000
Construction$298,050 $0 $298,050
Design$0 $82,000 $82,000
Construction$1,119,900 $0 $1,119,900
Total$2,077,000 $381,000 $2,458,000
2306 E. 11
th
2338 E. 11
th
3502 Lincoln
1110 Alexander
Sheet1
PropertyPhaseThisTotal Previous RequestsTotal Cost
Request
2306 E. 11thDesign$0$69,000$69,000
Construction$271,750$0$271,750
2338 E. 11thDesign$0$94,000$94,000
Construction$387,300$0$387,300
3502 LincolnDesign$0$136,000$136,000
Construction$298,050$0$298,050
1110 AlexanderDesign$0$82,000$82,000
Construction$1,119,900$0$1,119,900
Total$2,077,000$381,000$2,458,000
PropertyPhaseThis RequestTotal Previous RequestsTotal Cost
2306 E. 11thDesign$0$69,000$69,000
Construction$271,750$0$271,750
2338 E. 11thDesign$0$94,000$94,000
Construction$387,300$0$387,300
3502 LincolnDesign$0$136,000$136,000
Construction$298,050$0$298,050
1110 AlexanderDesign$0$82,000$82,000
Construction$1,119,900$0$1,119,900
Total$2,077,000$381,000$2,458,000