Upload
akira
View
66
Download
13
Tags:
Embed Size (px)
DESCRIPTION
Project Control – Earned Value Management. Earned Value Management is a methodology used to measure and communicate the real physical progress of a project taking into account the work complete, the time taken and the costs incurred to complete that work. - PowerPoint PPT Presentation
Citation preview
Project Control – Earned Value Management
Earned Value Management is a methodology used to measure and communicate the real physical progress of a project taking into
account the work complete, the time taken and the costs incurred to complete that work.
Earned Value helps evaluate and control project risk by measuring project progress
in monetary terms.
Jan 2011 Slide 2 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
By taking a snapshot of the project and calculating the Earned Value metrics we can
compare the planned with the actual and make a subjective assessment of the project
progress.
By extrapolating the curves and further calculation we can also estimate the costs to
project completion and the probable completion date.
Jan 2011 Slide 3 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Steps in Setting up an Earned value Management system
Define the scope of the works. Set up a Work Breakdown Structure (WBS). Develop a Project Master Schedule showing
when every Work Package will be carried out. Allocate budget costs to each Work Package
(the lowest level of WBS). Establish a practical way of measuring the
actual work completed. Set, in concrete, the performance
measurement baseline.
Jan 2011 Slide 4 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Jan 2011 Slide 5 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Budgeted Cost for Work Scheduled (BCWS) – the budgets for all activities planned to be completed.
The BCWS curve is derived from the Work Breakdown Structure, the project budget and the Project Master Schedule. The cost of each Work Package is calculated and the cumulative cost of completed Works Packages is shown based on the planned completion dates shown in the Master Schedule.
Jan 2011 Slide 6 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Actual Cost of Work Performed (ACWP) – the real costs of the work charged against the completed activities.
The ACWP curve is found by actual measurement of the work completed. Actual costs recorded from invoices and workmen's time sheets. This appears a daunting task but it can be very simple with sufficient planning and organizing.
Jan 2011 Slide 7 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Budgeted Cost of Work Performed (BCWP) –the planned costs of the work allocated to the completed activities. This is the Earned Value.
The BCWP is calculated from the measured work complete and the budgeted costs for that work.Earned Value = Percentage project complete X Project Budget
Jan 2011 Slide 8 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Variances
Schedule and cost variances can both be calculated in monetary terms from the data needed to produce the S-curves.
Schedule variance is the difference between the Earned Value and the planned budget.SV = BCWP – BCWS
Cost Variance is the difference between the Earned Value and the actual costs of the works.CV = BCWP - ACWP
Jan 2011 Slide 9 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Schedule Variance (SV)• Indicates the deviation between the work
content performed and the work content scheduled for the control period
Jan 2011 Slide 10 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Cost Variance (CV)• A positive CV indicates a lower actual cost
than budgeted for the control period, while a negative CV indicates a cost overrun
Jan 2011 Slide 11 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Performance IndicesSchedule Performance Index and Cost Performance Index give indications of the health of the project. Is the project on time, in budget or what?
Schedule Performance Index is a ratio of Earned Value and the planned value of completed works. SPI = BCWP / BCWS SPI < 1 is not good
Cost Performance Index is a ratio of Earned Value and the actual costs of completed works. CPI = BCWP / ACWP CPI < 1 is not good
Jan 2011 Slide 12 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Schedule Performance Index (SPI)
• Defined as the ratio BCWP/BCWS
• A value close to 1 indicates an activity that is on schedule
• Values greater than 1 suggest the activity is ahead of schedule
• Values less than 1 indicate a schedule overrun
Jan 2011 Slide 13 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Cost Performance Index (CPI)• Defined as the ratio BCWP/ACWP
• A value close to 1 indicates an activity that is on budget
• Values greater than 1 suggest the activity is below budget
• Values less than 1 indicate a budget overrun
Jan 2011 Slide 14 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Rules of Thumb for EVA Numbers
• Negative numbers for cost and schedule variance indicate problems in those areas. The project is costing more than planned or taking longer than planned
• CPI and SPI less than 1 indicate problems
Jan 2011 Slide 15 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Two Additional Formulas
• What will be the final cost of the project if status quo is maintained? Estimated cost at completion (EAC) EAC = the original cost estimate for the project, called the
Budget-at-Completion (BAC), divided by the Cost Performance Index
EAC = (BAC / CPI)
• What is the estimated time to complete the project if status quo is maintained? Estimated time to completion (ETC) ETC = the original time estimate for the project divided by
Schedule performance index (SPI) ETC = (original time estimate / SPI)
Jan 2011 Slide 16 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Critical Ratio•(Actual Progress/Scheduled Progress) X (Budgeted Costs/Actual Costs)•This critical ratio is a good measure of the general health of a project as it combines both schedule and cost in that a poor performance in one is compensated by a good performance in the other. A critical ratio greater than 1 is good, less than one is bad. Furthermore the project manager should also set control limits on the various critical ratios. If the ratios are outside the limits then corrective action is necessary.
Jan 2011 Slide 17 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Uses of Earned value• Earned Value is based on the idea that the value of the product
of the project increases as tasks are completed. And therefore the Earned Value is a measure of the real progress of the project.
• Earned Value provides a standard means of objectively measuring work accomplished by integrating cost, schedule and technical performance into one set of metrics so that effective comparisons can be made.
• Earned Value can be used to communicate the progress of the works. This is historical information, "water under the bridge", you can't do anything about it.
• The more relevant use to the proactive project manager is to measure variances and define trends. Actions can then be taken to reduce the unwanted variances and the wayward trends.
Jan 2011 Slide 18 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Table 6-7. Earned Value Formulas
Term Formula Earned Value Budgeted Cost of Work Performed (BCWP) =
budgeted cost of task X % complete Cost Variance CV=BCWP-ACWP (actual cost of work performed) Schedule Variance SV=BCWP-BCWS (budgeted cost of work
scheduled) Cost Performance Index CPI=BCWP/ACWP Schedule Performance Index SPI = BCWP/BCWS
Jan 2011 Slide 19 of 17 Project Control - Earned Value Management System, By Prof. Nadpurohit
Table 6-6. Earned Value Calculations for One Activity After Week One
Activity Week 1 Week 2 Total % Complete after Week 1
EarnedValue after Week 1
(BCWP) Purchase web server 10,000 0 10,000 75% 7,500 Weekly Plan (BCWS) 10,000 0 10,000 Weekly Actual (ACWP) 15,000 5,000 20,000 Cost Variance (CV) -7,500 Schedule Variance (SV) -2,500 Cost Performance Index (CPI)
50%
Schedule Performance Index (SPI)
75%
Jan 2011 Slide 20 of 17 Project Control - Earned Value Management System, By Prof. Nadpurohit
Figure 6-2. Earned Value Calculations for a One-Year Project After Five Months
Jan 2011 Slide 21 of 17 Project Control - Earned Value Management System, By Prof. Nadpurohit
In the Figure above• Budget at Completion = BAC = original budget at the
planned completion date• Time at Completion = TAC = original completion time• In the figure above, `100,000 in month 12• Estimate at completion = EAC = BAC/CPI• Estimate at completion = `100,000/.83 = `120,455• Estimated time to complete = ETAC = TAC/SPI• Estimated time to complete = 12/.96 = 12.55 mos.
Jan 2011 Slide 22 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Updating cost estimates• BAC = Budget at completion = total budget
of the project activities based on the original project plan
• Assuming the original budget (the BAC) was `200,000 and the CPI is 1.12, what is EAC?
• EAC = BAC / CPI = `200,000 / 1.12
• `178,571
Jan 2011 Slide 23 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Updating schedule estimates
• TAC = Time at completion = total time required to complete the schedule
• ETAC = Estimated (revised) time to complete
• Assuming the TAC was 12 months what is the ETAC?
• ETAC = TAC / SPI = 12 / .77• 15.6 months• Project will be delayed almost 4 monthsJan 2011 Slide 24 of 37 Project Control - Earned Value Management System,
By Prof. Nadpurohit
Updating, Cont’d• WR = Work Remaining = budgeted cost of
the work not yet accomplished by the end of the reporting period
• WR = BAC - BCWP• ETC = updated estimate of the cost of
work remaining = COST(WR)• EAC = updated estimate of the total
project cost = ACWP + ETC
Jan 2011 Slide 25 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Figure 6-3. Earned Value Chart for Project After Five Months
-
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
100,000
1 2 3 4 5 6 7 8 9 10 11 12
Month
$
BCWS or Cumulative Plan ACWP or Cumulative Actual BCWP or Cumulative EV
BCWS
ACWP
BWCP
BAC
EAC
Jan 2011 Slide 26 of 17 Project Control - Earned Value Management System, By Prof. Nadpurohit
Using Software to Assist in Cost Management
• Spreadsheets are a common tool for resource planning, cost estimating, cost budgeting, and cost control
• Many companies use more sophisticated and centralized financial applications software for cost information
• Project management software has many cost-related features
Jan 2011 Slide 27 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Using MS Project for Execution & Control
• First, make certain your project plan is complete and final
• Second, save it as a baseline
• Begin entering actual information – Actual costs– Percentage complete
Jan 2011 Slide 28 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Tracking: MS Project will track—
• Task start dates
• Task finish dates
• Task duration
• Task cost work
• Percentage of task that is complete
Jan 2011 Slide 29 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Getting Earned Value Data Visible
• You can go to view and replace the entry table with the Earned Value table
• Or, you can enter the earned value columns into your existing table through the Insert Column facility.– The columns are BCWP, BCWS, ACWP, CV,
SC, SPI, CPI, etc.You can also request the Tracking Gantt Chart
off the LHS side of MS Project
Jan 2011 Slide 30 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Entering actual start & Finish dates for a task
• On the view bar, click Gantt chart
• In the task name field select the task to update
• On the Tools menu, point to tracking and click Update Tasks
• Under Actual, type the dates in the Start and Finish boxes
Jan 2011 Slide 31 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Indicating progress on a task as a percentage
• In the task name field of the Gantt Chart
• Double click—this brings up the task information sheet
• Select the general tab
• In the percentage complete box type a whole number between 0 and 100
Jan 2011 Slide 32 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Entering actual costs for a resource assignment
• On the Tools menu, click options, then click the calculation tab
• Clear the Actual costs are always calculated by MS Project check box
• Click OK• On the view bar, click Task usage• On the view menu, point to the Table, and click Tracking• Drag the divider bar to the right to view the Activity Cost field• In the activity cost field, type the actual cost for the
assignment for which you want to update costs
Jan 2011 Slide 33 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
a) Define “earned value”. Explain how the variances and indices used in ‘earned value analysis’ are effective for project control.
b) The following information is available at end of day 40 of a new plant erection project. Determine if the project is under control based on Earned Value evaluation system, and if not, what is the likely extent of cost and time over-runs at completion.
Activity
Immediate Predecessor
s
Duration
Total Budget for
activity Rs. ‘000
Actual costTill Date Rs. ‘000
Actual % Completio
nTill date
A - 10 300 250 100
B A 8 400 450 100
C A 12 350 380 100
D C 0 0 0 0
E B, D 18 405 400 70
F E 16 450 -- 0
Jan 2011 Slide 34 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
a) The progress observed at the end of the Seventh day from the beginning on a 12 day duration project is as given in the following table. The actual cost incurred till date is reported to be Rs. 3,100. Draw a Gantt chart for the project and find the project performance on the basis of Cost and Schedule Performance Indices. (Assume the activity costs are incurred uniformly over its duration.)
ACTIVITY IMMEDIATE PREDECESSORS
ESTIMATED DURATION
IN DAYS
BUDGETED COST OF
ACTIVITY
ACTUAL % COMPLETION AT END OF DAY 7
A - 3 600 100 %
B - 1 200 100 %
C A 4 800 75 %
D B 4 700 100 %
E B 5 500 95 %
F D 2 200 80 %
G E 3 500 50 %
H C 4 400 0 %
I F 2 600 0 %
J G 3 300 0 %
Jan 2011 Slide 35 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
a) A project comprising of 10 activities with total expected duration of 35 weeks was reviewed on completion of 20 weeks after start. The physical progress of various activities as assessed and actual costs incurred till date are compared with expected progress and budgeted figures as under:
ACTIVITY % COMPLETION COST IN RS. LACS
SCHEDULED ACTUAL BUDGETED TOTAL ACTUAL TILL DATE
1 100 100 10.0 12.0
2 100 100 12.0 12.5
3 70 60 18.0 12.0
4 55 50 25.0 13.0
5 30 25 20.0 6.0
6 10 0 15.0 0.0
7 0 0 10.0 0.0
8 0 0 8.5 0.0
9 0 0 6.5 0.0
10 0 0 5.0 0.0
TOTAL 130.0 55.5
If the costs are incurred linearly in proportion to activity completion, find out the I)Budgeted Cost of Work Scheduled (BCWS)II)Budgeted Cost of Work Performed (BCWP)III)Cost VarianceIV)Cost Performance Index (CPI)Schedule Performance Index (SPI) Jan 2011 Slide 36 of 37 Project Control - Earned Value Management System,
By Prof. Nadpurohit
Jan 2011 Slide 37 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Why Earned Value Analysis??• You can’t tell what your true cost variance
is because you don’t know where you are relative to schedule– Suppose you are behind schedule but also
you have spent less than what the schedule has called for. Are you really under budget?
Jan 2011 Slide 38 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit
Cost Control
• Project cost control includes– monitoring cost performance– ensuring that only appropriate project
changes are included in a revised cost baseline
– informing project stakeholders of authorized changes to the project that will affect costs
• Earned value analysis is an important tool for cost control
Jan 2011 Slide 39 of 37 Project Control - Earned Value Management System, By Prof. Nadpurohit