Project ManagementA Managerial Approach
Chapter 9
Resource Allocation
Critical Path Method - Crashing a Project
CPM includes a way of relating the project schedule to the level of physical resources allocated to the project
This allows the project manager to trade time for cost, or vice versa
In CPM, two activity times and two costs are specified, if appropriate for each activity
Critical Path Method - Crashing a Project
The first time/cost combination is called normal, and the second set is referred to as crash
Normal times are “normal” in the same sense as the ‘m’ time estimate of the three times used in PERT
Crash times result from an attempt to expedite the activity by the application of additional resources
Critical Path Method - Crashing a Project
Careful planning is critical when attempting to expedite (crash) a project
Expediting tends to create problems; and the solution to one problem often creates several more problems that require solutions
Some organizations have more than one level of crashing
Fast-Tracking
Another way to expedite a project is known as “fast-tracking”
It refers to overlapping the design and build phases of a project
Because design is usually completed before construction starts, overlapping the two activities will result in shortening the project duration
The Resource Allocation Problem
A shortcoming of most scheduling procedures is that they do not address the issues of resource utilization and availability
Scheduling procedures tend to focus on time rather than physical resources
Time itself is always a critical resource in project management, one that is unique because it can neither be inventoried nor renewed
The Resource Allocation Problem
Schedules should be evaluated not merely in terms of meeting project milestones, but also in terms of the timing and use of scarce resources
A fundamental measure of the project manager’s success in project management is the skill with which the trade-offs among performance, time, and cost are managed
The Resource Allocation Problem
The extreme points of the relationship between time use and resource use are these: Time Limited: The project must be
finished by a certain time, using as few resources as possible. But it is time, not resource usage, that is critical
Resource Limited:The project must be finished as soon as possible, but without exceeding some specific level of resource usage or some general resource constraint
The Resource Allocation Problem
If all three variables - time, cost, specifications - are fixed, the system is “overdetermined”
In this case, the project manager has lost all flexibility to perform the trade-offs that are so necessary to the successful completion of projects
A system-constrained task requires a fixed amount of time and known quantities of resources
Resource Loading
Resource loading describes the amounts of individual resources an existing schedule requires during specific time periods
The loads (requirements) of each resource type are listed as a function of time period
Resource loading gives a general understanding of the demands a project or set of projects will make on a firm’s resources
Resource Loading
An excellent guide for early, rough project planning
Because the project action plan is the source of information on activity precedences, durations, and resources requirements, it is the primary input for both the project schedule and its budget
The action plan links the schedule directly to specific demands for resources
Resource Loading
The PERT/CPM network technique can be modified to generate time-phased resource requirements
The project manager must be aware of the ebbs and flows of usage for each input resource throughout the life of the project
It is the project manager’s responsibility to ensure that the required resources, in the required amounts, are available when and where they are needed
Resource Leveling
Resource leveling aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances
The purpose is to create a smoother distribution of resource usage
Several advantages include: Less hands-on management is required May be able to use a “just-in-time” inventory
policy
Resource Leveling
When resources are leveled, the associated costs also tend to be leveled
The project manager must be aware of the cash flows associated with the project and of the means of shifting them in ways that are useful to the parent firm
Resource leveling is a procedure that can be used for almost all projects, whether or not resources are constrained
Constrained Resource SchedulingThere are two fundamental approaches to
constrained allocation problems: Heuristic Methods Optimization Models
Heuristic approaches employ rules of thumb that have been found to work reasonably well in similar situations
Optimization approaches seek the best solutions but are far more limited in their ability to handle complex situations and large problems
Heuristic Methods
Heuristic approaches to constrained resource scheduling problems are in wide, general use for a number of reasons: 1. They are the only feasible methods of
attacking the large, nonlinear, complex problems that tend to occur in the real world of project management
2. While the schedules that heuristics generate may not be optimal, they are usually quite good- certainly good enough for most purposes
Heuristic Methods
Most heuristic solution methods start with the PERT/CPM schedule and analyze resource usage period by period, resource by resource
In a period when the available supply of a resource is exceeded, the heuristic examines the tasks in that period and allocates the scarce resource to them sequentially, according to some priority rule
Technological necessities always take precedence
Heuristic MethodsCommon priority rules:
As soon as possible As late as possible Shortest task first Most resources first Minimum slack first Most critical followers Most successors Arbitrary
Heuristic Methods
Most priority rules are simple adaptations of the heuristics used for the traditional “job shop scheduling” problem of production/operations management
Most heuristics use a combination of rules: a primary rule, and a secondary rule to break ties
As the scheduling heuristic operates, one of two events will result: The routine runs out of activities before it runs out of
resources The routine runs out of resources before all activities
have been scheduled
Optimizing MethodsThe methods to find an optimal
solution to the constrained resource scheduling problem fall into two categories: Mathematical programming
Enumeration
Mathematical programming can be thought of as liner programming (LP) for the most part
Optimizing Methods
Linear programming is usually not feasible for reasonably large projects where there may be a dozen resources and thousands of activities
In the late 1960s and early 1970s, limited enumeration techniques were applied to the constrained resource problem
Tree search, and branch and bound methods were devised to handle up to five resources and 200 activities
Multiproject Scheduling and Resource Allocation
The most common approach to scheduling and allocating resources to multiple projects is to treat the several projects as if they were each elements of a single large project
Another way of attacking the problem is to consider all projects as completely independent
To describe such a system properly, standards are needed by which to measure scheduling effectiveness
Multiproject Scheduling and Resource Allocation
Three important parameters affected by project scheduling are: Schedule slippage
Resource utilization
In-process inventory
The organization (or the project manager) must select the criterion most appropriate for its situation
Multiproject Scheduling and Resource Allocation
Schedule slippage, often considered the most important of the criteria, is the time past a project’s due date or delivery date when the project is completed
Resource utilization is of particular concern to industrial firms because of the high cost of making resources available
The amount of in-process inventory concerns the amount of work waiting to be processed because there is a shortage of some resource
Multiproject Scheduling and Resource Allocation
All criteria cannot be optimized at the same time
As usual, the project manager will have to make trade-offs among the criteria
A firm must decide which criterion to evaluate its various scheduling and resource allocation options
Mathematical Programming
Mathematical programming can be used to obtain solutions to certain types of multiproject scheduling problems
These procedures determine when an activity should be scheduled, given resource constraints
Mathematical programming, however, is rarely used in project management to handle the multiproject problem (mostly, heuristics are used)
Mathematical Programming
The three most common objectives of mathematical programming are: 1. Minimum total throughput time (time in the shop)
for all projects
2. Minimum total completion time for all projects
3. Minimum total lateness or lateness penalty for all projects
These objectives are most appropriate for ‘job shop’ type solutions to resource constraints
Heuristic Techniques
There are scores of different heuristic-based procedures in existence
They represent rather simple extensions of well-known approaches to job-shop scheduling: Resource Scheduling Method Minimum late finish time Greatest resource demand Greatest resource utilization Most possible jobs
Summary
The critical path method (CPM) is a network constructed in the same manner as PERT but considers the possibility of adding resources to tasks to shorten their duration
The resource allocation problem is concerned with determining the best trade-offs between available resources, including time, throughout the duration of the project
Summary
Resource loading is the process of calculating the total load from project tasks on each resource for each time period of the project’s duration
Resource leveling is concerned with evening out the demand for various resources required in a project by shifting tasks within their slack allowances
Chapter 9-29
Summary
There are two basic approaches to addressing the constrained resources allocation problem: Heuristic methods Optimizing methods
For multiproject scheduling, three important measures of effectiveness are schedule slippage, resource utilization, and level of in-process inventory
Summary
When a new project is added to a multiproject system, the amount of slippage is directly related to the average resource load
Mathematical programming models for multiproject scheduling aim to either minimize total throughput time for all projects, minimize the completion time for all projects, or minimize total lateness for all projects
Resource Allocation
Questions?
Resource Allocation
Picture Files
Resource Allocation
Figure 9-1
Resource Allocation
Figure 9-2
Resource Allocation
Figure 9-3
Resource Allocation
Figure 9-4
Resource Allocation
Figure 9-5
Resource Allocation
Figure 9-6
Resource Allocation
Figure 9-7
Resource Allocation
Figure 9-8
Resource Allocation
Figure 9-9a
Resource Allocation
Figure 9-9b
Resource Allocation
Figure 9-10
Resource Allocation
Figure 9-11
Resource Allocation
Figure 9-12
Resource Allocation
Figure 9-13
Resource Allocation
Figure 9-14
Resource Allocation
Figure 9-15
Resource Allocation
Figure 9-16
Resource Allocation
Table Files
Resource Allocation
Resource Allocation
Resource Allocation