 Assignment Record Form Student Name : K. Sivabala Naidu IC / Passport Number : 861101-56-5057 Nationality : Malaysian IPE Index Number : MYS-0100588 Teamie Index Number : [email protected] Learning Centre : KL Course : MBA Term : 1 Module Title : Project Management Centre Facilitator Name : Dr. Dasaratha Rao  Assignment Submission Due Date : 1 st  June 2014 Status : Active I declare that this is an original piece of work undertaken by me. I confirm that I have read and understood the IPE regulations with regard to referencing and plagiarism.  YES NO Note: Please read the “Instruction to Upload the Assignment on TeamieLearning Portal” before uploading your assignment.  

Project Management Assignment IPE-MBA KSivabala Naidu

  • Upload
    naidu01

  • View
    230

  • Download
    0

Embed Size (px)

DESCRIPTION

project management,assignment, klia2

Citation preview

  • Assignment Record Form

    Student Name : K. Sivabala Naidu

    IC / Passport Number : 861101-56-5057

    Nationality : Malaysian

    IPE Index Number : MYS-0100588

    Teamie Index Number : [email protected]

    Learning Centre : KL

    Course : MBA

    Term : 1

    Module Title : Project Management

    Centre Facilitator Name : Dr. Dasaratha Rao

    Assignment Submission Due Date : 1st June 2014

    Status : Active

    I declare that this is an original piece of work undertaken by me.

    I confirm that I have read and understood the IPE regulations with regard to referencing and

    plagiarism.

    YES NO

    Note: Please read the Instruction to Upload the Assignment on TeamieLearning Portal before uploading your assignment.

  • IPE MBA Project Management Assignment Page 2 of 17

    Executive summary

    The purpose of this report was to undertake a thorough investigation about as to the various

    causative factors which may have contributed to the failure of KLIA 2 by Malaysia Airports

    Holdings Berhad (MAHB) wherein the cost overrun was from RM 1.9 Billion to RM 4.0 Billion

    and with more than 2 years of delay in its completion.

    One of the major factors which may have contributed to the cost overrun and delayed completion

    is the inability to manage change. As we know, managing the changes in a project is a part of

    project management life cycle. Based on the report, given by CEO & Managing Director of

    Malaysia Airports Holdings Berhad (MAHB) Tan Sri Bashir Ahmad, the new terminal was

    delayed three times from its original completion date of September 2011, is because of the new

    requirements. If only the additional or new requirements was managed with a scope which is a

    major factor in having a balanced project management these cost overrun and delay would not

    had occurred.

    After taking all the project success and failure factors into consideration, I would like to

    recommend to the Chairperson of the MAHB Board of Directors to use Statement of Work

    (SOW). Plan the purpose of the project by taking into consideration, the risk management and

    scope in this case is to finish the KLIA 2 as per the initial project planning without running away

    from the schedule and cost and to clearly outline the possible risks, and management of the risk

    so that when a change or new requirements arises we could manage it without interrupting the

    iron triangle, where the main components are quality, scope, cost and schedule. Which is the key

    being the co-ordination between all the sectors working in building KLIA 2.

  • IPE MBA Project Management Assignment Page 3 of 17

    Table of contents

    Introduction

    1.1 Purpose 4

    1.2 Overview. 4

    Main Body

    2.1 The cost overrun & delays.......... 6

    2.2 The lack of change management team in Project KLIA 2 .... 8

    2.3 The purpose of project management life cycle in a project 11

    2.4 Statement of Work (SOW). 13

    2.5 The common pitfalls in a project.... 15

    Conclusion & Recommendations. 16

    References. 17

    Word count: 4.013

  • IPE MBA Project Management Assignment Page 4 of 17

    Introduction

    1.1) Purpose

    The purpose of this report was to undertake a thorough investigation about as to the various

    causative factors which may have contributed to the failure of KLIA 2, by Malaysia Airports

    Holdings Berhad (MAHB) wherein the cost overrun was from RM1.9 Billion to RM 4.0 Billion

    and with more than 2 years of delay in its completion. Based on the report provided by Tan Sri

    Bashir Ahmad, CEO & Managing Director of Malaysia Airports Holdings Berhad (MAHB), the

    cost of KLIA 2 has been doubled due to revision to increase 71% of its original capacity. The

    revised plan is based from Air Asias growth projection, this is simply because Air Asia being

    the main stake holder in KLIA 2. In 2013, Air Asia has flown more than 21.85 million

    passengers in LCCT. With 3% growth annually, the initially planned KLIA 2 will be crowded in

    10 years time. To build such airport at that time will cost us double or triple. Therefore the

    revision took place to avoid building another airport in the next 10 15 years time.

    1.2) Overview

    The KLIA 2 is built to be Malaysia's Next Generation Hub the airport hub that will allow

    seamless connectivity between low-cost and full service carriers. The new KLIA 2 terminal is

    measured to be at least 257,000 m2, with 60 gates, 8 remote stands, 80 aerobridges, plus a retail

    space of 32,000 m2 to accommodate 225 retail outlets. It is designed to cater 30 million

    passengers a year with the provision to expand to 45 million. Built at a cost around 4.0 billion

    ringgit which was noticeably a cost overrun, the KLIA 2 was scheduled to open on April 2013

    but delayed. Below is a table comparing the cost and other criteria of KLIA, LCCT and KLIA 2.

    Adding to that, KLIA 2 was built to replace the current LCCT. Firstly, Air Asia the fastest

    growing and largest low cost airline in Asia needs a bigger home to accommodate a larger

    number of passengers. Secondly, is to accommodate KLIAs growth and vision. How does

    KLIA2 fit into KLIAs vision? The terminal has an integrated international concourse that will

    enable seamless transfer to domestic flights and vice versa. In other words, it will provide more

    traffic to KLIA. Not only that, due to limited runway capacity faced by Changi Airport,

    Soekarno Jakarta Airport and Bangkok Suvarnabhurmi Airport, ours KLIA is set to be a regional

  • IPE MBA Project Management Assignment Page 5 of 17

    hub in Southeast Asia. The completion of KLIA2 will bring the airports total capacity to 85

    million. But more importantly, the additional runway from KLIA2 will reduce congestion. In

    addition, KLIA 2 is also designed to be a retail airport. The large terminal is due to the large

    space for retail. Airport operator now comprehend that more revenue must come from this

    source. The reason is many middle income people from Southeast Asia choose to fly with Low

    Cost Carrier and they expect much more amenities once they land. When you consider there are

    550 million people in ASEAN and only around 4% are currently flying, you can see the potential

    in retail.

    The major key player being; Developer Malaysia Airports Holdings Berhad (MAHB),

    Contractor UEM Construction Bina Puri JV, Design Architect LKMD Architecture Sdn.

    Bhd., Architects - A.Hanapiah Architect and Arkitek ICB Sdn. Bhd. As in any branch or division

    of a business unit one needs to have a clear notion on the accountability and responsibility within

    the project management domain too. The project managers must be well aware of their

    responsibilities and the accountability towards the project whether it is a success or a failure. The

    airport operator, which took over as project manager from KLIA consult in November 2011, has

    been blamed for the delay and higher cost of completing KLIA 2, a terminal dedicated to low

  • IPE MBA Project Management Assignment Page 6 of 17

    cost carriers. Project manager should be coordinating all the sectors and failure in

    communication which will result in failure of delivering the project as per cost and schedule.

    Main Body

    2.1) The cost overrun and delays

    The delay and cost overrun has been mainly due to changes of the design of the airport

    and its size it was initially meant to handle a passenger volume of 30 million but this was scaled

    up to 45 million passengers per year based on the recent Air Asias growth projection. Thus,

    there were a 71% of its original capacity been changed. What started as a 150,000 m2 terminal

    with 50 semi contact gates and 2.5km runway, to a 257,000 m2 terminal with 68 gates fully

    aerobridges and 3.9km runway. Rather than anticipating and managing the changes, the parties

    involved in KLIA 2 began to point finger at each other. There is clearly a shortage of

    coordination between the major key players. For example, MAHB which has come under fire

    from all sides for the delay in the completion of KLIA 2 is pointing finger at Air Asia Berhad,

    government agencies and the main contractor. The baggage handling system was relocated on

    the advice of the Department of Civil Aviation. This clearly shows that there were no prior

    discussion with related agencies and department before the project execution period. There was

    no prior anticipation. There was an increase in the scope of work. Below I have attached a table

    of the specifications of the upgrades. Changes, upgrades and new addition are not a stranger in

    the event of a project management, thus the problem or the reason for the project failure in terms

    of cost overrun and inability to deliver on time is due to poor management skill. Thus, the parties

    involved should be able to see clearly that the problem was not the change; it was the inability to

    adapt and deliver to the change. The final design is supposed to be frozen says the main

    contractor The Star online June 28. This statement itself shows the lack of anticipation. The

    planning part is one of the key in project management life cycle. Under the planning vice comes

    risk plan and acceptance plan which will be elaborated in the later part.

  • IPE MBA Project Management Assignment Page 7 of 17

    Major upgrades in specifications

  • IPE MBA Project Management Assignment Page 8 of 17

    2.2) The Lack of Change Management Team in Project KLIA 2

    Project management is an approach to managing work within the constraints of time, cost

    and business objectives. Whether you are using Six Sigma, DMAIC or Lean, there are

    techniques and tools project teams can apply to plan, control and monitor results. Change

    management can and should follow a similar structured process. Prosci, whose change

    management methodology is one of the most widely used and recognized approaches for

    managing the people side of change, includes a set of assessments to help you identify risk and

    address assumptions you may have made in planning for the project. At each gate or phase of

    your project, Prosci defines specific plans to help execute and manage the change to ensure you

    not only meet your business objectives, but new processes are adopted and sustained. While

    project management handles the technical side of the project, change management facilitates the

    acceptance of the initiative taking place. Project management life cycle focuses on the technical

    aspect of moving from current state to future state while change management focuses on people

    aspect. Change management and project management are complementary disciplines with a

    common objective. When applied using proven steps and tools, you greatly increase your

    probability of success. How dependent are your project outcomes on people changing the way

    they do their work? No matter how well we follow the project plan, if people do not change the

    way they do their job, we will not achieve the desired business results.

    The failure of KLIA 2 is due to the absence in change management. The number one rule

    in change management is preparing for the change and preparing change management team. We

    can clearly see that in KLIA 2 they were not at all open to the idea of a future change thus the

    change has been viewed as a glitch in the project. And when there is a change in the project, the

    people need to cope with the change. Here the partys involved in KLIA 2 does not manage to

    change their mindset and work phase accordingly. If there is an increase in job scope thus there

    is a need to increase the velocity of the work of the people and maybe a need to increase the

    number of workforce. They should have anticipated such changes in the beginning of the project

    itself and have an allocation of cost if such changes would have occurred. In KLIA 2 they did

    blame the cost overrun due to the increase of number of workers needed. This shows that such

    changes were not anticipated by the team. Projects are naturally subjected to change and it is up

    to the project management team to deal with it. If only there was a change management team in

  • IPE MBA Project Management Assignment Page 9 of 17

    Project KLIA 2, the changes or any upgrades nor additional ideas would have been managed

    with structure and delays or cost overrun could been monitored and controlled. People have a

    natural tendency to resist change. No matter how flawlessly executed, the project will not meet

    its objectives if no one follows the new process, uses the new technology or changes the way

    they work. The more effective your change management plan, the more likely your project is to

    finish on or under budget. Effective change management ensures faster speed of adoption,

    increased proficiency and higher utilization.

  • IPE MBA Project Management Assignment Page 10 of 17

  • IPE MBA Project Management Assignment Page 11 of 17

    2.3) The Purpose of Project Management Life Cycle in a Project

    Despite the fact that no two projects are exactly alike, but all projects must go through

    these four phases of project management life cycle. Initiation involves starting up the project by

    documenting a business case, conducting a feasibility study, coming up with the terms of

    reference, appointing the team and setting up a project office. Planning involves setting out the

    roadmap for the project by creating the following plans: project plan, resource plan, financial

    plan, quality plan, acceptance plan and communications plan. Execution involves building the

    deliverables and controlling the project delivery, scope, costs, quality, risks and issues. Closure

    involves winding down the project by releasing staff, handing over deliverables to the

    customer and completing a post implementation review.

    In the initiation part of the project, these are the steps to be done; develop a business case,

    undertake a feasibility study, establish the project charter, appoint the project team, set up the

    project office and perform phase review. In the planning phase we need to create a project plan,

    resource plan, financial plan, quality plan, risk plan, an acceptance plan, communications plan,

    procurement plan, contract the suppliers, define the tender process, issue a statement of work,

    request for information, request for proposal, and create a supplier contract and perform another

    phase review. In the project execution phase, we build deliverables and perform monitor and

    control, perform time, cost, quality, risk and issue management and perform procurement

    management acceptance and communications management. In the closure phase, we perform

    project closure and review project completion.

    At the beginning of project initiation, a project manager is assigned. The project manager

    works with the project sponsor to identify the necessary resources and team members needed to

    further develop the key project parameters Cost, Scope, Schedule, and Quality (CSSQ). The

    project team documents its charge in the form of a project charter, which is based on the project

    proposal, which includes the initial business case. Approval of the Project Charter by the Project

    Sponsor authorizes the designated team to begin the initial planning effort. The initial Project

    Plan resulting from Project Initiation differs in the level of detail and the validity of its estimates

    from Project Origination, and must be at a level sufficient to acquire any additional resources

    needed to progress to the next phase. The Project Plan also includes plans for involving and

  • IPE MBA Project Management Assignment Page 12 of 17

    communicating with all the parties that are affected by the project, as well as identification of an

    initial set of foreseeable risks that can threaten the project. At the conclusion of Project Initiation,

    based on the initial planning documents, the Business Case is revised and re-evaluated and a

    decision is made to halt or proceed with the project.

    Project Planning builds on the work done in Project Initiation, refining and augmenting

    CSSQ and Project Plan deliverables. Usually, additional members join the Project Team, and

    they assist the Project Manager in further elaborating the details of the Cost, Scope, Schedule

    and Quality. A number of key elements are added to the Project Plan, including project-specific

    items such as change control, acceptance management and issue management, as well as

    externally-focused items such as organizational change management and project transition. The

    initial list of project risks is augmented, and detailed mitigation plans are developed. At the

    conclusion of Project Planning, the Business Case is revised and re-evaluated based on the

    completed planning documents and a decision is again made to either halt the project, or to

    commit the resources necessary for Project Execution and Control.

    Project Execution and Control is where most of the resources are applied / expended on

    the project. A significant number of team members will join the project at the beginning of this

    phase. The primary task of the Project Manager during Project Execution and Control is to

    enable the Project Team to execute the tasks on the defined Project Schedule and develop the

    product or service the project is expected to deliver. The Project Manager uses the processes and

    plans prepared during Project Initiation and Project Planning to manage the project, while

    preparing the organization for the implementation of the product / service and for transitioning

    the product / service responsibility from the Project Team to the Performing Organization.

    In Project Closeout, the Project Team assesses the outcome of the project, as well as the

    performance of the Project Team and the Performing Organization. This is accomplished

    primarily through soliciting and evaluating feedback from Customers, Project Team members,

    Consumers and other stakeholders. The primary purpose of this assessment is to document best

    practices and lessons learned for use on future projects.

  • IPE MBA Project Management Assignment Page 13 of 17

    2.4) Statement of Work (SOW)

    It is important to create a statement of work (SOW) for the case study where we identify

    the purpose, scope, project deliverables, goals and objectives and cost and schedule estimates. In

    risk management we need to identify, analyze and have a risk plan. In risk management we need

    to identify the sources of risk, determine the available funding, time constraint, staffing,

    customer relations, project size and / or complexity, overall structure and organizational

    resistance. Risk analysis is broadly defined to include risk assessment, risk characterization, risk

    communication, risk management, and policy relating to risk. Risk analysis is a technique used

    to identify and assess factors that may jeopardize the success of a project or achieving a goal.

    This technique also helps to define preventive measures to reduce the probability of these factors

    from occurring and identify counter measures to successfully deal with these constraints when

    they develop to avert possible negative effects on the competitiveness of the company. One of

    the more popular methods to perform a risk analysis in the computer field is called facilitated

    risk analysis process (FRAP). FRAP analyzes one system, application or segment of business

    processes at time. FRAP assumes that additional efforts to develop precisely quantified risks are

    not cost effective because; such estimates are time consuming, risk documentation becomes too

    voluminous for practical use, specific loss estimates are generally not needed to determine if

    controls are needed and without assumptions there is little risk analysis. After identifying and

    categorizing risks, a team identifies the controls that could mitigate the risk. The decision for

    what controls are needed lies with the business manager. The team's conclusion as to what risks

    exists and what controls needed are documented along with a related action plan for control

    implementation.

    The Risk Impact / Probability Chart are based on the principle that a risk has two primary

    dimensions; Probability A risk is an event that "may" occur. The probability of it occurring can

    range anywhere from just above 0% to just below 100%. *Note: It can't be exactly 100%,

    because at that juncture it would be a certainty, not a risk. And it can't be exactly 0%, or it would

    not be a risk. Impact A risk, by its very nature, always has a negative impact. However, the size

    of the impact varies in terms of cost and impact on health, human life, or some other critical

    factor. The chart allows you to rate potential risks on these two dimensions. The probability that

    a risk will occur is represented on one axis of the chart and the impact of the risk, if it occurs,

  • IPE MBA Project Management Assignment Page 14 of 17

    on the other. It is advisable to use these two measures to plot the risk on the chart. This gives a

    very quick and a clearer view of the priority that needed to be given to each. You can then decide

    what resources needed to be allocated to managing that particular risk.

    I believe there is a drooping in the risk management of the KLIA 2 project. Based on the

    report by The Edge, the Senior General Manager of Malaysia Airports Holdings Berhad

    (MAHB) Datuk Azmi Murad stated that the reason for the delay is the contractor could not

    deliver maybe due to under estimation of the difficulties. MAHB has issued 212 non -

    compliances report progressively to UEM Bina Puri JV since it started construction in the main

    building. UEM Bina Puri JV, the main contractor of KLIA 2, is appealing against the

    liquidated and ascertained damages (LAD) fine slapped on it by Malaysia Airports Holdings

    Berhad (MAHB). Bina Puri Construction Sdn. Bhd. Director Henry Tee Hock Hin said the joint

    venture (JV) would appeal based on the terms and conditions of the contract that stated that the

    contractor could appeal for an extension of time (EOT) to finish up the work, as there had been

    many last minute requests and additional changes made by stakeholders. These were the

    extensions of time (EOT) granted by Malaysia Airports Holdings Berhad (MAHB) to the

    contractor as reported by The Edge April 2012 ; Contractor was given EOT by MAHB,

    October / November 2012 ; Contractors commit to opening of the airport on May 2013, January

    2013 ; Contractor asks for 6 more weeks and commits to airport opening on June 28, May 7 ;

    MAHB makes announcement to Bursa Malaysia that the contractor may have difficulty in

    meeting the project deadline, May 16 : The contractor as for an EOT until Jan 2014 without any

    justification, May 29 : Malaysia Airports Holdings Berhad makes an announcement to the Bursa

  • IPE MBA Project Management Assignment Page 15 of 17

    that the contractor has notified that it cannot meet its contractual obligation to deliver KLIA 2 by

    June 28 and on June 18 contractor confirms April 30th

    2014 as the new completion date. As per

    seen in this case there was a lot of risks in this project. Malaysia Airports Holdings Berhad and

    UEM Bina Puri JV had recently been embroiled in a spat blaming each other for the works that

    could not be completed in time for the opening of KLIA 2. When all the major stakeholders and

    key players start blaming each other it brings upon the risk of project delivery failure. This is

    where the project manager should have used his skills of project management and risk

    management.

    2.5) The Common Pitfalls in a Project

    There are several pitfalls in a project contributing to its failure such as unclear objectives,

    lack of senior management support and lack of effective project integration, inadequate funding,

    change in business priorities, original assumptions being invalid, an ineffective team, and lack of

    effective communication processes. In order to ensure a project success there are a few factors to

    be kept in mind and put to work such as coordination and relations, adequacy of structure and

    control, the project uniqueness, importance, and public exposure, success criteria salience and

    consensus, a competitive and budgetary pressure, initial over - optimism, conceptual difficulty

    and internal capabilities build up. In KLIA 2 there were a few changes made after the retail

    optimization plan (ROP). Optimization means finding an alternative with the most cost effective

    or highest achievable performance under the given constraints, by maximizing desired factors

    and minimizing undesired ones. But its uncertain the ROP was coordinated with all the

    participating parties, for example the contractor was not briefed prior hand about the possibilities

    of changes in the final design. These have been one the major factor for the downfall of this

    KLIA 2 project. There was absence in effective communication and privation in co-ordination

    and relations.

  • IPE MBA Project Management Assignment Page 16 of 17

    Conclusion & Recommendations

    We have discussed the various relevant factors which may have contributed to the failure

    of KLIA 2 by Malaysia Airports Holdings Berhad (MAHB). The key factors being lack of

    anticipation to the project plan changes and a poor risk management.

    Thus, I would recommend to the chairperson of MAHB in the future projects have a

    change management team where they help execute and manage change to ensure, you not only

    meet your business objectives but new processes are adopted and sustained.

    Other than that its crucial to follow the four phases of project management life cycle and

    not skipping any of these phases will ensure the success of the project. It is also important to

    create statement of work (SOW) for the business case to identify the purpose, scope, project

    deliverables, goals and objectives and cost and schedule estimates. These ensure we do not run

    out of the planning we initially made thus preventing mishaps such as cost overrun or delays.

    Adding to that the risk management team should calculate the possible risks with the help

    of risk impact / probability chart. This gives a quick and clear view of the priority we need to

    give each, and help us to decide what resource to allocate in managing the particular risk.

    Therefore as conclusion project management skills should be incorporated with the

    theories and models I have presented in my study above should be followed to attain project

    success, as these are the models proven by researches and trials. I hope these recommendations

    will help to elevate the project success in future business cases.

  • IPE MBA Project Management Assignment Page 17 of 17

    References

    1. Company's Background. 2013, KLIA 2, viewed 16 May 2014

    2. KLIA 2 Proposal. 2013, Proposal, viewed 16 May 2014

    3. Info KLIA 2. 2014, Comparison between klia2,klia and lcct, viewed 18 May 2014

    4. Project Management. 2012, Accountability in Project Management, viewed 20 May 2014

    5. The Edge Malaysia. 2014, highlight: klia2 delay, MAHB reveals all, viewed 19 May

    2014

    6. Project Management. 2012, project management life cycle, viewed 2 May 2014

    7. Russell D. Archibald,Project Life Cycle Model .2013, The Six-Phase Comprehensive

    Project Life Cycle Model Including the Project Incubation/Feasibility Phase and the

    PostProject Evaluation Phase, viewed 18 May 2014

    8. Change Management. 2014, the change management process , viewed 19 May 2014

    9. PMMP. 2011, The project management life cycle, viewed 19 May 2014

    10. PM HUT. 2012, an introduction to project management life cycle, viewed 20 May 2014

    11. SRA. 2014, risk analysis, viewed 21 May 2014

    12. Project Smarts. 2013, risk analysis matrix, viewed 21 May 2014