Upload
sams007
View
327
Download
4
Embed Size (px)
DESCRIPTION
All about the project Management presentation includes the basic introduction,project types,project life cycle,project planning and process,project review techniques,pert/cpm,gannt chart,network diagrams,cost of project and financing with analysis.
Citation preview
Presentation on
2Samee Bhangu
Presented by Mr. Samee
Bhangu
MBSM 4th Sem
College of Statistics & Actuarial Sciences
University of the Punjab Lahore, Pakistan.
3Samee Bhangu
A project is a unique endeavor to produce a set of deliverables within clearly specified time, cost and quality constraints.Projects are different from standard business operational activities as they: Are unique in nature. Have a defined timescale. Have an approved budget. Have limited resources. Involve an element of risk. Achieve beneficial change.
5Samee Bhangu
A unique, one-time operational activity or effort
Requires the completion of a large number of interrelated activities
Established to achieve specific objective Resources, such as time and/or money,
are limited Typically has its own management
structure Need leadership
6Samee Bhangu
constructing houses, factories, shopping malls, athletic stadiums or arenas
developing military weapons systems, aircrafts, new ships
launching satellite systems constructing oil pipelines developing and implementing new
computer systems planning concert, football games, or
basketball tournaments introducing new products into market
7Samee Bhangu
Project Management is the skills, tools and management processes required to undertake a project successfully. It incorporates: A set of skills. A suite of tools. A series of processes.
8Samee Bhangu
9Samee Bhangu
10
Sales
President
FinanceHumanFactors
EngineeringQualityControl
Production
TechnicianTest
EngineerPropulsionEngineer
Physiologist
ProjectManager
PsychologistStructuralEngineer
InspectionTechnician
Technician
Project 1
Project 2
ProjectManager
Samee Bhangu
1. Major Projects2. Large Projects3. Medium
Projects4. Small Projects
16-11
= of capital of Organization
=1/10 of capital of Organization
=1/100 of capital of Organization
=1/1000 of capital of Organization
Payne & Turner categorized into 4 types in 1999
Samee Bhangu
Type 2 projects
Product Development(Water)
Type 4 projects
Research and Organizational change(Air)
Type 1 Projects
Engineering(Earth)
Type 3 Projects
System development(Fire)
16-12
Greater
Chances of
Success
Samee Bhangu
Project planning Project scheduling Project control Project team
made up of individuals from various areas and departments within a company
Matrix organization a team structure with members from functional
areas, depending on skills required Project Manager
most important member of project team
13Samee Bhangu
Scope statement a document that provides an understanding, justification,
and expected result of a project Statement of work
written description of objectives of a project Organizational Breakdown Structure
a chart that shows which organizational units are responsible for work items
Responsibility Assignment Matrix shows who is responsible for work in a project
14Samee Bhangu
16Samee Bhangu
Figure 5: Full circle and arrow diagram for the computer project we are using as an example
17Samee Bhangu
Where one activity cannot start until another has been completed, we start the arrow for the dependent activity at the completion event circle of the previous activity. An example of this is shown below:
18Samee Bhangu
A different case is shown below
19Samee Bhangu
20
Activity Description Duration
1-2 Social work team to live in village 5w
1-3 Social research team to do survey 12w
3-4 Analyse results of survey 5w
2-4 Establish mother & child health program 14w
3-5 Establish rural credit programme 15w
4-5 Carry out immunization of under fives 4w
3
1
24
5
Samee Bhangu
Project Leader The TeamWork Methods and ProceduresWork Plan
21Samee Bhangu
Establishing objectivesDefining projectCreating work breakdown structure Determining resourcesForming organization
22Samee Bhangu
Resource Availability and/or Limits Due date, late penalties, early completion
incentives Budget
Activity Information Identify all required activities Estimate the resources required (time) to
complete each activity Immediate predecessor(s) to each activity
needed to create interrelationships
23Samee Bhangu
Gantt chart Critical Path Method (CPM) Program Evaluation &
Review Technique (PERT) Network Diagrams
25Samee Bhangu
26
Graph or bar chart with a bar for each project activity that shows passage of time
Provides visual display of project scheduleProvides visual display of project schedule
Gantt Chart
Samee Bhangu
Critical Path Method (CPM) E I Du Pont de Nemours & Co. (1957) for construction
of new chemical plant and maintenance shut-down Deterministic task times Activity-on-node network construction Repetitive nature of jobs
Project Evaluation and Review Technique (PERT) U S Navy (1958) for the POLARIS missile program Multiple task time estimates (probabilistic nature) Activity-on-arrow network construction Non-repetitive jobs (R & D work)
27Samee Bhangu
PERT-Program Evaluation and Review Technique, for planning and coordinating large projects and is concern about scheduling of activities
CPM-Critical Path Method, for planning and coordinating large projects and is concern about importance of activities
28Samee Bhangu
Learning Objectives Aware and Understand the Concepts
and Principles of PERT/CPM Analyze Business Problem and Relate to
the Applicability Of the Use of PERT/CPM Identify Business Problems and Use
PERT/CPM in its solution Solve Business Problems Using
PERT/CPM 29Samee Bhangu
Path A connected sequence of activities leading
from the starting event to the ending event Critical Path
The longest path (time); determines the project duration
Critical Activities All of the activities that make up the critical
path
30Samee Bhangu
Earliest Start Time (ES) earliest time an activity can start ES = maximum EF of immediate predecessors
Earliest finish time (EF) earliest time an activity can finish earliest start time plus activity time
EF= ES + t
31
Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
LS= LF - t
Latest finish time (LF)
latest time an activity can be completed without delaying critical path time
LS = minimum LS of immediate predecessors
Backward Pass
Samee Bhangu
Draw the CPM network Analyze the paths through the network Determine the float for each activity
Compute the activity’s float float = LS - ES = LF - EF
Float is the maximum amount of time that this activity can be delay in its completion before it becomes a critical activity, i.e., delays completion of the project
Find the critical path is that the sequence of activities and events where there is no “slack” i.e.. Zero slack Longest path through a network
Find the project duration is minimum project completion time
32Samee Bhangu
CPM Network
33
a, 6a, 6a, 6a, 6
f, 15f, 15f, 15f, 15
b, 8b, 8b, 8b, 8
c, 5c, 5c, 5c, 5
e, 9e, 9e, 9e, 9
d, 13d, 13d, 13d, 13
g, 17g, 17g, 17g, 17 h, 9h, 9h, 9h, 9
i, 6i, 6i, 6i, 6
j, 12j, 12j, 12j, 12
Samee Bhangu
PERT is based on the assumption that an activity’s duration follows a probability distribution instead of being a single value
Three time estimates are required to compute the parameters of an activity’s duration distribution: pessimistic time (tp ) - the time the activity would
take if things did not go well most likely time (tm ) - the consensus best
estimate of the activity’s duration optimistic time (to ) - the time the activity would
take if things did go well
34
Mean (expected time): te = tp + 4 tm + to
6
Variance: Vt =2 = tp - to
6
2
Samee Bhangu
Expected project time (T) Sum of critical path
activity times, t
Project variance (V) Sum of critical path
activity variances, v
16-35
Used to obtain probability of project completion!
Samee Bhangu
You’re a project planner for General Dynamics. A submarine project has an expected completion time of 40 weeks, with a standard deviation of 5 weeks. What is the probability of finishing the sub in 50 weeks or less?
16-36
© 1995 Corel Corp.
Samee Bhangu
16-37
T = 40
s = 5
50 X
Normal Normal DistributionDistribution
ZX T=
-=
-=
s50 40
52 0.
mz = 0
sZ = 1
Z2.0
Standardized Normal Standardized Normal DistributionDistribution
Samee Bhangu
Draw the network. Analyze the paths through the network and find the
critical path. The length of the critical path is the mean of the
project duration probability distribution which is assumed to be normal
The standard deviation of the project duration probability distribution is computed by adding the variances of the critical activities (all of the activities that make up the critical path) and taking the square root of that sum
Probability computations can now be made using the normal distribution table.
38Samee Bhangu
PERT (Program Evaluation and Review Technique)
PERT is a variation on Critical Path Analysis that takes a slightly more skeptical view of time estimates made for each project stage.
Use the formula below to calculate the time to use for each project stage:
39Samee Bhangu
40
= tp Timex
Z
Probability
Samee Bhangu
Immed. Optimistic Most Likely Pessimistic
Activity Predec. Time (Hr.) Time (Hr.) Time (Hr.) A -- 4 6 8B -- 1 4.5 5C A 3 3 3
D A 4 5 6 E A 0.5 1 1.5 F B,C 3 4 5 G B,C 1 1.5 5 H E,F 5 6 7 I E,F 2 5 8 J D,H 2.5 2.75 4.5 K G,I 3 5 7
41Samee Bhangu
42
AA
DD
CC
BBFF
EE
GG
II
HH
KK
JJ
PERT Network
Samee Bhangu
Activity ES EF LS LF Slack A 0 6 0 6
0 *critical B 0 4 5 9
5 C 6 9 6 9
0 * D 6 11 15 20 9 E 6 7 12 13 6 F 9 13 9 13
0 * G 9 11 16 18 7 H 13 19 14 20 1 I 13 18 13 18 0
* J 19 22 20 23 1 K 18 23 18 23 0 *
43Samee Bhangu
Vpath = VA + VC + VF + VI + VK
= 4/9 + 0 + 1/9 + 1 + 4/9 = 2path = 1.414
z = (24 - 23)/(24-23)/1.414 = .71
From the Standard Normal Distribution table:
P(z < .71) = .5 + .2612 = .7612
44Samee Bhangu
Define the project and all of its significant activities or tasks
Develop relationships among the activities. (Decide which activities must precede and which must follow others.)
Draw the network connecting all of the activities
Assign time and cost estimates to each activity
Compute the longest time path through the network. This is called the critical path
Use the network to help plan, schedule, monitor, and control the project
16-45Samee Bhangu
Useful at many stages of project management
Mathematically simple Uses graphical displays Gives critical path & slack time Provides project documentation Useful in monitoring costs
16-46Samee Bhangu
Assumes clearly defined, independent, & stable activities
Specified precedence relationships Activity times (PERT) follow
beta distribution Subjective time estimates Over-emphasis on critical path
16-47Samee Bhangu
Use of nodes and arrows Arrows An arrow leads from tail to head directionally
Indicate ACTIVITY, a time consuming effort that is required to perform a part of the work.
Nodes A node is represented by a circle- Indicate EVENT, a point in time where one or more activities
start and/or finish.
48
• Network analysis is the general name given to certain specific techniques which can be used for the planning, management and control of projects
• Activity– A task or a certain amount of work required in the project– Requires time to complete– Represented by an arrow
• Dummy Activity– Indicates only precedence relationships– Does not require any time of effort
Samee Bhangu
Main features of PERT/CPM is the use of a network or precedence diagram to depict major project activities and their sequential relationships
Two conventions in network construction;
1. Activities on Arrow- arrows designate activities.
2. Activities on node- nodes designate activities
49Samee Bhangu
Event Signals the beginning or ending of an activity Designates a point in time Represented by a circle (node)
Network Shows the sequential relationships among
activities using nodes and arrows
50
Activity-on-node (AON)
nodes represent activities, and arrows show precedence relationships
Activity-on-arrow (AOA)
arrows represent activities and nodes are events for points in time
Project Network
Samee Bhangu
51
32 0
1
31 1
11 2 4 6 7
3
5
Lay foundation
Design house and obtain financing
Order and receive materials
Dummy
Finish work
Select carpet
Select paint
Build house
AON Project Network for House
13
22
43
31 5
1
61
71Start
Design house and obtain financing
Order and receive materials
Select paintSelect carpet
Lay foundations Build house
Finish work
Samee Bhangu
52
AB
C
A must finish before either B or C can start
A
B
C both A and B must finish before C can start
D
C
B
Aboth A and C must finish before either of B or D can start
A
C
B
D
Dummy
A must finish before B can start
both A and C must finish before D can start
Samee Bhangu
53
2 3
Lay foundationLay foundation
Order materialOrder material
(a)(a) Incorrect precedence Incorrect precedence relationshiprelationship
(b)(b) Correct precedence Correct precedence relationshiprelationship
3
42
DummyDummyLay Lay foundationfoundation
Order materialOrder material
11
22 00
Samee Bhangu
54
Illustration of network analysis of a minor redesign of a product and its associated packaging.
The key question is: How long will it take to complete this project ?
Samee Bhangu
55
For clarity, this list is kept to a minimum by specifying only immediate relationships, that is relationships involving activities that "occur near to each other in time".
Samee Bhangu
Is this a Start Activity? Is this a Finish Activity? What Activity Precedes this? What Activity Follows this? What Activity is Concurrent with this?
56Samee Bhangu
Crashing reducing project time by expending additional
resources Crash time
an amount of time an activity is reduced Crash cost
cost of reducing activity time Goal
reduce project duration at minimum cost
58Samee Bhangu
59
Act
ivity
cos
t
Activity time
Crashing activity
Crash time
Crash cost
Normal Activity
Normal time
Normal cost
Slope = crash cost per unit time
Samee Bhangu
60
Crashing costs increase as project duration decreases Indirect costs increase as project duration increases Reduce project length as long as crashing costs are less than indirect costs
Time-Cost Tradeoff
cost
time
Direct cost
Indirect cost
Total project costMin total cost = optimal project time
Samee Bhangu
61
111212
2288
441212
3344 55
44
6644
7744
Samee Bhangu
62
Activity Normal time
Normal cost Rs
Crash time
Crash cost Rs
Allowable crash time
slope
1
2
3
4
5
6
7
12
8
4
12
4
4
4
3000
2000
4000
50000
500
500
1500
7
5
3
9
1
1
3
5000
3500
7000
71000
1100
1100
22000
5
3
1
3
3
3
1
400
500
3000
7000
200
200
7000
75000 110700
Samee Bhangu
Crash ActionYou may find that you need to
complete a project earlier than your Critical Path Analysis says is possible. In this case you need to take action to reduce the length of time spent on project stages.
63Samee Bhangu
As with Gantt Charts, in practice project managers tend to use software tools like Microsoft Project to create CPA Charts. Not only do these ease make them easier to draw, they also make modification of plans easier and provide facilities for monitoring progress against plans. Microsoft Project is reviewed at the top of our left hand title bar.
64Samee Bhangu
Learning Objectives Be Familiar and Understand the Concepts
and Principles of Project Financing and Budgeting
Know and understand how project cost is analysed and identify sources of financing
Identify and Analyze Project Costs and Benefits
Compute for the Financial and Economic Viability of Projects
66Samee Bhangu
How much will the project cost To develop To operate To maintain
Can we sustain project operations and maintenance?
67Samee Bhangu
How much is needed to operate and maintain the project in usable form?
If we can charge user fees, how much should it be? How much more is needed to collect the fees (administrative cost of collecting the fees)?
Given the fees, what is the projected number of users?
If we do not collect the fees, what is the projected number of users?
If the project cannot be expected to pay for itself, will the provincial government be willing to subsidize its operations and maintenance? By how much?
68Samee Bhangu
69
If operations and maintenance of the project cannot be sustained, either from project revenues or subsidies from the province, the project investment should not be undertaken.
Samee Bhangu
Equity (Owner’s Investment)
Loan (Banks and other sources)
Grant (Government and other Sources)
Co-Financing
70Samee Bhangu
BudgetPreparation
BudgetExecution
BudgetAccountability
BudgetReview
BudgetAuthorization
71Samee Bhangu
What is the output of the project? Output, not outcomes
Characterize the output Public, private, mixed Tradeable, nontradeable, partly
tradeable
72
?
Samee Bhangu
Financial considerations are often an important consideration in selecting projects
Three primary methods for determining the projected financial value of projects: Net present value (NPV) analysis Return on investment (ROI) Payback analysis
73Samee Bhangu
Net present value (NPV) analysis is a method of calculating the expected net monetary gain or loss from a project by discounting all expected future cash inflows and outflows to the present point in time
Projects with a positive NPV should be considered if financial value is a key criterion
The higher the NPV, the better
74Samee Bhangu
75
UsesExcel’snpvfunction
Notethat totalsare equal,butNPVsare not.
Samee Bhangu
76
Multiplyby thediscountrate eachyear, thentake cum.benefits –costs toget NPV
Samee Bhangu
Determine estimated costs and benefits for the life of the project and the products it produces
Determine the discount rate (check with your organization on what to use)
Calculate the NPV (see text for details) Notes: Some organizations consider
the investment year as year 0, while others start in year 1. Some people enter costs as negative numbers, while others do not. Check with your organization for their preferences.
77Samee Bhangu
Determine estimated costs and benefits for the life of the project and the products it produces
Determine the discount rate (check with your organization on what to use)
Calculate the NPV (see text for details) Notes: Some organizations consider
the investment year as year 0, while others start in year 1. Some people enter costs as negative numbers, while others do not. Check with your organization for their preferences.
78Samee Bhangu
Project Sponsorship at executive level
Good project charterStrong project managementThe right mix of team playersGood decision making structureGood communicationTeam members are working toward
common goals79Samee Bhangu
Failure to align project with organizational objectives
Poor scopeUnrealistic expectationsLack of executive sponsorshipLack of project management Inability to move beyond individual
and personality conflictsPolitics
80Samee Bhangu
Microsoft Project (Microsoft Corp.) MacProject (Claris Corp.) PowerProject (ASTA Development Inc.) Primavera Project Planner (Primavera) Project Scheduler (Scitor Corp.) Project Workbench (ABT Corp.)
82Samee Bhangu