Project Management Organization Structure

  • Upload
    omdeep

  • View
    218

  • Download
    0

Embed Size (px)

Citation preview

  • 8/14/2019 Project Management Organization Structure

    1/30

    Hierarchical structures

    Reports, Decides and Communicates-With all mapped on thesame association

    Do not work well with iterative and incremental softwaredevelopment process

    Manager is not necessarily always right

    Project-based structures

    Reports, Decides and Communicates-With are differentassociations

    Cut down on bureaucracy reduces development time Decisions are expected to be made at each level

    Hard to manage

  • 8/14/2019 Project Management Organization Structure

    2/30

    Hierarchical Structure

    Projects with high degree of certainty, stability, uniformity andrepetition.

    Requires little communication

    Role definitions are clear

    When? The more people on the project, the more need for a formal structure

    Customer might insist that the test team be independent from thedesign team

    Project manager insists on a previously successful structure

  • 8/14/2019 Project Management Organization Structure

    3/30

    Project-Based Structure

    Project with degree of uncertainty

    Open communication needed among members

    Roles are defined on project basis

    When?

    Requirements change during development

    New technology develops during project

  • 8/14/2019 Project Management Organization Structure

    4/30

    Corporation X

    Human

    Resources

    Marketing Engineering ProcurementManufacturing

    Finance &

    Administration

    Project Manager

    Project Team

    MA1 MA2 MA3 EN1 EN2 EN3 MF1 MF2 MF3 PR1 PR2

    Forming a (Dedicated) Project Team

    Staff are assigned away from various departments to work

    full-time on the project.

    OtherAreas

  • 8/14/2019 Project Management Organization Structure

    5/30

    The (dedicated) Project Team lies at one extreme end of the

    continuum which starts from undertaking projects using the

    (pure) functional form of project organization.

    A project manager is selected to head a core group of

    personell assigned from two or more functional units of theorganization and who are all required to work full-time on the

    project in question.

    Project Teams are usually cross-functional in nature and

    are a powerful means of dealing with complex assignments which

    may be difficult to do using other project organiza-tion forms.

  • 8/14/2019 Project Management Organization Structure

    6/30

    Advantage

    No structural impact on the functional organization occursonly

    the tempo-rary siphoning away of functional specialists from their

    respective areas for the duration of the project or for a phase of it

    when heir input is required in order to complete specialist tasks.

    Project completion time is comparatively smaller due to project

    personell devoting their efforts to the project in question full-timeand also because the flow of information and decision-making is

    generally not hindered by hierachies as it is in the functional form

    of organizing projects.

  • 8/14/2019 Project Management Organization Structure

    7/30

    Advantage

    Motivation, feeling of iden-tification and cohesiveness are strong

    in the project.

    Project personell share a common goal and they also share a

    collective responsibility for ensuring the realization of this goal.

    Cross-functional cooperation is strongly encouraged and

    promoted as a means of achieving the project goal.

    Cross-functional teams create a synergy effect which can handle

    tasks characterised by a high degree of complexity.

  • 8/14/2019 Project Management Organization Structure

    8/30

    Disadvantage

    A major criticism of the (dedicated) project team relates to the cost

    factor. Normally, a larger expense is involved because resources and

    facilities are assigned to the project on a full-time basis. Acrossprojects, this may result in a duplication of infrastructure and work.

    Projectitisproject personell evolve a collective identity

    encapsulating themselves from the enterprise, giving rise to a non-

    constructive usand themoutlook. Sometimes this not only

    undermines the integration of the project effort back into

    mainstream operations but also the subsequent assimilation of

    project personell back into their respective functional areas.

  • 8/14/2019 Project Management Organization Structure

    9/30

    Disadvantage

    The project may become over-dependent on the gamut of skills,

    expertise and experience held by the project personell and maynot seek to incorporate fresh skills, expertise and experience

    which is held by individuals and organiza-tional entities which are

    outside the project.

    The assimilation of project personell back into their respective

    functional units may prove difficult due to their prolonged

    absence from their units and the challenge of keeping up with

    the developments which have taken place in the functional units

    during the project period.

  • 8/14/2019 Project Management Organization Structure

    10/30

    Determining The Best Project Organization Form

    The projects size

    The projects strategic importance

    The projects innovation requirementThe projects level of required integration across functional

    delineations

    The project environments complexity

    The project budget and time constraintsThe project resource requirement level of stability

    In generalthe higher the level of these factors, the

    greater is the requirement of autonomy and authority for the

    project manager and his/her team in order to ensure the

    success of the project (i.e. a strong project matrix or

    dedicated project team is desirable).

  • 8/14/2019 Project Management Organization Structure

    11/30

    Criteria for organizational design decisions (Robert Youker, 1977)

    Criterion Functional

    Structure

    Matrix Structure Project Structure

    Uncertainty Low High High

    Technology Standard Complicated New

    Complexity Low Medium High

    Duration Short Medium Long

    Size Small Medium Large

    Importance Low Medium High

    Customer Diverse Medium One

    Interdependency

    (within)

    Low Medium High

    Interdependency

    (between)

    High Medium Low

    Time criticality Low Medium High

    Resource criticality Depends Depends Depends

    Differentiation Low High Medium

  • 8/14/2019 Project Management Organization Structure

    12/30

    Associations in organizational structures

    Reporting association: Used for reporting status information

    Decision association

    Used for propagating decisions

    Communication association Used for exchanging information needed for decisions (e.g.,

    requirements, design models, issues).

  • 8/14/2019 Project Management Organization Structure

    13/30

    Possible Mappings of ToDos to People

    One-to-One Ideal but often not worth to be called a project

    Many-to-Few

    Each project member assumes several roles ("hats")

    Danger of overcommittment

    Need for load balancing

    Many-to-"Too-Many"

    Some people don't have significant roles

    Bystanders Loosing touch with project

  • 8/14/2019 Project Management Organization Structure

    14/30

    Assigning Responsibilities To People

    To Do List for the Project

    Item 1

    Item 2

    Item 3

    Item 4

    Item 5

    Item 6

    Item 7

    Item 8

    Item 9

    Item 1

    Item 2

    Item 9

    Role 1

    Item 4Item 5

    Item 7

    Role 2

    Item 3

    Item 6

    Item 8

    Role 3

    Person A

    Role 1

    Role 2

    Person B

    Role 3

    Team A

  • 8/14/2019 Project Management Organization Structure

    15/30

    Using the Work Breakdown Structure

    1. Estimate and schedule the work (Durations, precedences on WBS)

    2. Organize and schedule resources (resource allocated WBS)

    3. Assign responsibilities(Resource ramp-up, resource allocated WBS)

    4. Estimate and allocate costs and budgets (costed WBS)

    5. Add up costs to different levels

    Task

    Levels on the WBS (phase, account/contract)

    Cost account

    Total project

    6. Get resource commitments

    7. Schedule start end dates

    8. Track expenditures, schedules and performance

    Work Breakdown Structure

  • 8/14/2019 Project Management Organization Structure

    16/30

    Implement Work Breakdown Structure

    Subdivision into Smaller Increments

    Level 1: Total Project

    Level 2: Systems of the Project

    Level 3: Subsystems of the Project

    Level 4: Units/Equipments

    Level 5: Work Packages or Components

  • 8/14/2019 Project Management Organization Structure

    17/30

    WBS serves several important Purposes, such as:

    Subdivision of Work

    Identification of Project Levels

    Work Sharing between Companies Economic Geographical Distribution of Funds

    Implementation of WBS Numbering System (Code) applicable to the

    entire Project

    Definition of Cost Account Structure

    Allocation of Funds

    Implementation of Project Control in line with the WBS Code

    Assignment of Responsibilities to Companies & Individual Managers

    Identification of Interfaces at all Levels

    Implementation of Documentation Numbers related to WBS Code

    Identification of Work Package

  • 8/14/2019 Project Management Organization Structure

    18/30

    Work Package Description

    Work Package (WP) Identification

    Title

    Identification of the WP in the WBS (WP Number) Date of the Start and End of the WP

    Company or Entity in charge of the WP Performance

    Work Package Manager

    Description of the WP Tasks to be Performed

    Tasks Explicitly Excluded

    WP Inputs

    Product(s) to be Completed or Delivered

  • 8/14/2019 Project Management Organization Structure

    19/30

    The

    Project Manager

  • 8/14/2019 Project Management Organization Structure

    20/30

    Leadership Skills:

    Vision and Strategy

    Establishing Direction

    Aligning People Communicating

    Negotiating

    Motivating and Inspiring

    Influencing Organizations

    Overcoming Barriers to Change

  • 8/14/2019 Project Management Organization Structure

    21/30

    General Management Skills:

    Planning

    Finance and Accounting

    Personnel Administration

    Technology

    Organizational Development

    Delegation

    Team Building

    Conflict Management

    Solving Problems

  • 8/14/2019 Project Management Organization Structure

    22/30

    Communications Skills:

    Writing

    Listening

    Speaking Presenting

    Media Relations

    Meeting Management

  • 8/14/2019 Project Management Organization Structure

    23/30

    Role of a project manager

    The role of a project manager is affected by the one-

    shot nature of the project

    The role of a project manager is difficult when team

    members are still linked to their permanent workareas

    Members may be assigned to several projects

    simultaneously

    Managers must rely on their communication skills

    and powers of persuasion

  • 8/14/2019 Project Management Organization Structure

    24/30

    Project manager attributes

    Leader & manager

    Facilitator, coordinator

    Communicator

    Credibility: Technical/Administrative

    Work under pressure

    Goal-oriented

    Innovator Versatilist

    Knowledgeable about the

    organization

    Political sensitivity

    Conflict: sense, confront,

    resolve

    Can deal with stress, chaos,

    ambiguity

    Planning and follow-

    through

    Ethical dilemmas

  • 8/14/2019 Project Management Organization Structure

    25/30

    Project manager attributes

    Specialist

    Generalist

    Versatilist

  • 8/14/2019 Project Management Organization Structure

    26/30

    Project manager duties

    Reports to senior management

    Communicates with users

    Plans and schedules

    Obtains and allocates resources

    Controls risks

    Manages people

    Coordinates

    Implements quality assurance

    Controls the budget

    Delivers results

  • 8/14/2019 Project Management Organization Structure

    27/30

    The

    Project Team

  • 8/14/2019 Project Management Organization Structure

    28/30

    Team Formation

    Top level Design

    Rough Subsystem Decomposition (beforerequirements analysis)

    Done during Predevelopment phase

    Team Formation done after Top Level Design

    Heuristics:

    One team for each subsystem

    One cross-functional task per team

    5-7 members per team

    Be prepared to iterate the team formation after system

    design when the subsystem decomposition is baseline

  • 8/14/2019 Project Management Organization Structure

    29/30

    Project teams

    Diversity of knowledge needed

    Cross-functional

    Self-directed Often ad-hoc or temporary

    Often distributed (geographically)

    Start and end dates

  • 8/14/2019 Project Management Organization Structure

    30/30

    Project personnel skills

    Technical

    Political

    Problem-oriented

    (vs. discipline-oriented) Goal-oriented

    Flexibility, adaptability

    High self-esteem

    can handle failure, risk, uncertainty, unexpected

    can share blame and credit