Project Management Professional (PMP) Study Guide[1]

Embed Size (px)

Citation preview

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    1/284

    Certification Study Guide

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    2/284

    PMI Certification Materials To assist PMI candidates for completing the PMI

    certification exam administered by the ProjectManagement Institute

    Content is from A Guide To The Project ManagementBody Of Knowledge (PMBOK)

    www.pmi.org

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    3/284

    Recurring Themes Historical Records need to collect and use for planning,

    estimating and risk

    Kickoff meetings are important

    Work Breakdown Structures Do not introduce benefits that are not stated in

    requirements

    Needs of all stakeholders should be taken into account

    during all projects Team Members must be involved in project planning

    Project Mangers must be pro-active

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    4/284

    Chapter 1

    Introduction Project temporary endeavor undertaken to create

    a unique product or service

    Has a definite beginning and end and interrelatedactivities

    Programs adopt new set of objectives and continueto work; projects ceasewhen declared objectives

    have been attained

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    5/284

    Chapter 1

    Introduction Projects are unique characteristics are progressively

    elaborated

    Progressively: proceeding in steps

    Elaborated: worked with care and detail

    Scope of project should remain constant even ascharacteristics are progressively elaborated

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    6/284

    Chapter 1 - Introduction Project Management: the application of

    knowledge, skills, tools and techniques to project

    activities in order to meet or exceed stakeholderneeds and expectations from a defined project balancing the following:

    Scope, time, cost, and quality

    Stakeholders expectations Requirements (needs) vs. unidentified requirements

    (expectations)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    7/284

    Chapter 1 - Introduction Programs are groups of projects managed in a

    coordinated way to obtain benefits not availablefrom managing the projects individually

    Most programs have elements of ongoingoperations Series of repetitive or cyclical undertakings

    Projects are often divided into subprojects formore manageability Often contracted out to external organizations

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    8/284

    Chapter 2

    Project Management Context Project Phases are marked by the completion of a

    deliverable Tangible, verifiable work product

    Review of deliverables and approval/denial are phaseexits, stage gates, or kill points

    Phases are collected into the Project Life Cycle Set of defined work procedures to establish

    management control

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    9/284

    Chapter 2

    Project Management Context Project Life Cycle defines:

    Technical work performed in each phase

    Who is involved in each phase

    Project Phases can overlap Fast Tracking Common Characteristics of Project Life Cycles:

    Cost and Staffing levels are low at start and move higher towardsthe end

    Probability of successfully completing project is low at beginning,higher towards the end as project continues

    Stakeholder influence is high at the beginning and progressivelylowers as project continues

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    10/284

    Chapter 2

    Project Management Context Stakeholders: individuals and organizations who

    are actively involved in the project

    Often have conflicting expectations and objectives In general, differences should be resolved in favor of the

    customer individual(s) or organization(s) that will usethe outcome of the project

    Stakeholder management is a proactive task Project Mangers must determine all stakeholders and incorporate

    their needs into the project

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    11/284

    Chapter 2

    Project Management Context Stakeholders are:

    Project Managers

    Customers

    Performing Organizations, owners

    Sponsor

    Team

    Internal/External

    End User

    Society, citizens

    Others: owner, funders, supplier, contractor

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    12/284

    Chapter 2

    Project Management Context Organizational Systems: Project based vs. Non-Project

    Based

    Project Based derive revenues from performingprojects for others (consultants,contractors),management by projects

    Non-Project Based seldom have management systemsdesigned to support project needs (manufacturing,

    financial services)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    13/284

    Chapter 2

    Project Management Context Organizational Cultures and Styles:

    Entrepreneurial firms more likely to adopt highlyparticipative Project Manager accept higherrisk/reward

    Hierarchical firms less likely to adopt participativeProject Manager take fewer risks

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    14/284

    Chapter 2

    Project Management Context Organizational Structures

    Functional (classical) marked by identifiable superiors.Staff grouped by specialty . Perceived scope of project

    limited by function (Engineering, HR). Typically havepart-time Project Manager

    Projectized Organization blend functional andprojectized characteristics. Mix cross-departmentpersonnel with full-time Project Manger

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    15/284

    Chapter 2

    Project Management Context Project Management Skills

    General Business Management (consistently producing resultsexpected by stakeholders)

    Leading (establishing direction, aligning resources, motivating) Communicating (clear, unambiguous, and complete)

    Negotiating (conferring with others to reach an agreement)

    Problem Solving (definition and decision making)

    Distinguish causes and symptoms Identify viable solutions

    Influencing Organization (understanding power and politics)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    16/284

    Chapter 2

    Project Management Context Socioeconomic Influences

    Standards document approved that provides common,repeated use, rules and guidelines Compliance is not mandatory

    Regulations document that identifies products,services or characteristics Compliance is mandatory

    Standards often become de facto regulations Internationalization

    Cultural Influences

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    17/284

    Chapter 2

    Project Management Context Organization Structure Pros and Cons

    Projectized Efficient Organization No home

    Loyalty Lack of Professionalism Effective Communication Duplication of functions, less

    efficient resource usage

    Matrix Visible Objectives not cost effective

    PM Control More than 1 boss

    More support More complex to control

    Utilize scarce resources Tough resource allocation

    Information distribution Competition of priorities

    Coordination Policies & Procedures Home based Potential for conflict

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    18/284

    Chapter 2

    Project Management Context Functional Organization

    Specialists More emphasis on functions

    1 supervisor No career path in PM

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    19/284

    Chapter 3

    Project Management Processes Project Management requires active management of

    Project Processes

    Series of actions that achieve a result

    Project Management Processes

    Describing and organizing the work

    Product-Oriented Processes

    Specifying and creating the product

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    20/284

    Chapter 3

    Project Management Processes Process Groups:

    Initiating processes: recognizing a project or phaseshould begin

    Planning processes: devising and maintaining aworkable plan

    Executing processes: coordinating resources to executethe plan

    Controlling processes: ensuring project objectives aremet; monitoring, correcting and measuring progress

    Closing processes: formalized acceptance

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    21/284

    Chapter 3

    Project Management Processes Process Groups are linked by the results each

    produces Process Groups are overlapping activities with

    various levels of intensity Process Group interactions cross phases rolling

    wave planning Provides details of work to complete current phase and

    provide preliminary description of work for subsequentphases

    Individual processes have inputs, tools andtechniques, and outputs (deliverables)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    22/284

    Chapter 3

    Project Management Processes Initiating and Planning Processes Committing the organization to begin

    Initiation, High-level planning, Charter

    Amount of planning proportional to the scope ofthe project Core Planning Scope Planning written statement Scope Definition subdividing major deliverables into

    more manageable units Activity Definition determine specific tasks needed to

    produce project deliverables Activity Sequencing plotting dependencies

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    23/284

    Chapter 3

    Project Management Processes Core Planning (continued)

    Activity Duration Estimating determine amount of work neededto complete the activities

    Schedule Development analyze activity sequences, duration, andresource requirements

    Resource Planning identify what and how many resources areneeded to perform the activities

    Cost Estimating develop resource and total project costs

    Cost Budgeting allocating project estimates to individual workitems

    Project Plan Development taking results from other planningprocesses into a collective document

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    24/284

    Chapter 3

    Project Management Processes Planning/Facilitating Processes manage the

    interaction among the planning processes Quality Planning standards that are relevant to the

    project and determining how to meet standards Organizational Planning identify, document, and

    assigning project roles and responsibilities

    Staff Acquisition obtaining the human resources

    Communications Planning determining rules andreporting methods to stakeholders

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    25/284

    Chapter 3

    Project Management Processes Planning/Facilitating Processes (continued)

    Risk Identification determining what is likely to affect theproject and documenting these risks

    Risk Quantification evaluating risks and interactions toaccess the possible project outcomes

    Risk Response Development defining enhancement stepsand change control measures

    Procurement Planning determining what to buy and when

    Solicitation Planning documenting product requirementsand identifying possible sources

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    26/284

    Chapter 3

    Project Management Processes Planning/Facilitating Processes (continued)

    Order of events: Scope Statement Create Project Team Work Breakdown Structure

    WBS dictionary Finalize the team Network Diagram Estimate Time and Cost Critical Path Schedule Budget Procurement Plan

    Quality Plan Risk Identification, quantification and response development Change Control Plan Communication Plan Management Plan Final Project Plan Project Plan Approval Kick off

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    27/284

    Chapter 3

    Project Management Processes Executing Processes

    Project Plan Execution performing the activities Complete Tasks/Work Packages

    Information Distribution Scope Verification acceptance of project scope Quality Assurance evaluating overall project

    performance on a regular basis; meeting standards Team Development developing team and individual

    skill sets to enhance the project Progress Meetings

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    28/284

    Chapter 3

    Project Management Processes Executing Processes (continued)

    Information Distribution making project informationavailable in a timely manner

    Solicitation obtaining quotes, bids, proposals asappropriate

    Source Selection deciding on appropriate suppliers

    Contract Administration managing vendor

    relationships

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    29/284

    Chapter 3

    Project Management Processes Controlling Processes needed to regularly

    measure project performance and to adjust projectplan

    Take preventive actions in anticipation of possibleproblems Change Control coordinating changes across the entire

    project plan

    Scope Change Control controlling scope creep Schedule Control adjusting time and project schedule

    of activities

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    30/284

    Chapter 3

    Project Management Processes Controlling Processes (continued)

    Cost Control managing project budget

    Quality Control monitoring standards and specific

    project results; eliminating causes of unsatisfactoryperformance

    Performance Reporting status, forecasting, andprogress reporting schedule

    Risk Response Control responding to changes in riskduring the duration of the project

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    31/284

    Chapter 3

    Project Management Processes Closing Processes

    Administrative Closure generating necessaryinformation to formally recognize phase or project

    completion Contract Close-out completion and delivery of projectdeliverables and resolving open issues Procurement Audits Product Verification Formal Acceptance Lessons Learned Update Records Archive Records Release Team

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    32/284

    Chapter 3

    Project Management Processes Overall Processes

    Influencing the organization

    Leading

    Problem Solving

    Negotiating

    Communicating

    Meetings

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    33/284

    Chapter 3

    Project Management Processes Project Selection Techniques

    Comparative Approach (similar projects)

    Benefit measurement method

    Constrained Optimization (mathematical approach)

    Key aspect of scope verification is customer acceptance

    Only 26 % of projects succeed

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    34/284

    Chapter 4 Project Integration

    Management Project Integration Management

    Ensures that the project processes are properly coordinated Tradeoffs between competing objectives and alternatives in order to meet

    stakeholder approval Project Plan Development

    Project Plan Execution Overall Change Control

    These processes may occur repeatedly over the project duration Historical Records are needed to perform project management well, they are inputs

    to continuous improvement Files Lessons Learned Actual Costs Time Estimates WBS Benchmarks Risks

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    35/284

    Chapter 4 Project Integration

    Management Project Plan Development

    Uses outputs from other planning processes to createconsistent document to guide project execution and

    control Iterated several times

    Documents planning assumptions

    Documents planning decisions that are chosen

    Facilitates communication Defines key management reviews

    Provides a baseline to track progress measurement andproject control

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    36/284

    Chapter 4 Project Integration

    Management Project Plan Development Inputs

    Other planning outputs: primarily the planning processoutputs (WBS, base documents, application area inputs)

    Historical information verify assumptions, records ofpast project performance

    Organizational policies quality management,personnel administration, Financial controls

    Constraints factors that limit performance, contractualprovisions, budget

    Assumptions risk factors

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    37/284

    Chapter 4 Project Integration

    Management Tools & Techniques for Plan Development

    Project Planning Methodology any structuredapproach (software, templates, forms, start-up meetings

    Stakeholder Skills & Knowledge tap into plandevelopment; use expertise for reasonableness

    PMIS Out of the box approach to support all projectaspects through closure

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    38/284

    Chapter 4 Project Integration

    Management Project Plan Development Outputs

    Project Plan is a collection that changes over time as moreinformation about the project becomes available

    Baseline will change only in response to approved scope change

    Project Plan includes some or all of the following: Project Charter

    Project Management approach or strategy

    Scope statement

    Work Breakdown Structure (WBS)

    Budget, schedule, risks Key Staff, Major Milestones

    Change Control Plan, Management and Communications Plan

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    39/284

    Chapter 4 Project Integration

    Management Project Plan Components (continued)

    Cost Estimates, scheduled start dates and responsibilityassignments

    Performance measurement baselines Major milestones and target dates

    Required Staff

    Risks, constraints and assumptions

    Subsidiary management plans (scope, schedule) Open Issues

    Pending Decisions

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    40/284

    Chapter 4 Project Integration

    Management Supporting Details to the Project Plan

    Outputs from planning processes

    Technical documentation

    Business requirements, specifications, and designs

    Relevant standards

    Additional information not previously known

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    41/284

    Chapter 4 Project Integration

    Management Project Plan Execution

    Primary process for carrying out the project plan

    Most costly aspect of project management

    Direction of organizational resources and interfaces

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    42/284

    Chapter 4 Project Integration

    Management Project Plan Execution Inputs:

    Project Plan

    Supporting Detail

    Organizational Policies

    Corrective Action anything to bring expectedperformance in line with the project plan

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    43/284

    Chapter 4 Project Integration

    Management Tools & Techniques for Plan Execution

    General Management Skills

    Product Skills and Knowledge defined as part of

    planning, provided by staffing Work Authorization System formal procedure for

    sanctioning work to ensure completion written orverbal authorization

    Status review meetings regular exchanges ofinformation

    Project Management Information System

    Organizational Procedures

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    44/284

    Chapter 4 Project Integration

    Management Project Plan Execution Outputs

    Work results the outcome of activities performed isfed into the performance reporting process

    Change Requests expand/shrink project scope, modifycosts and schedule estimates

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    45/284

    Chapter 4 Project Integration

    Management Overall Change Control

    Influencing factors that create change to ensure beneficial results;ensure that change is beneficial

    Determining that change has occurred

    Managing actual changes as they occur Evaluate impact of change Meet with team to discuss alternatives Meet with management to present decision

    Change control requires Maintaining integrity of performance measurement baselines

    (project plan) Ensuring changes to scope are accurately recorded Coordinating changes across knowledge areas (scheduling, risk,

    cost, quality, etc.) Determine all factors that control change and pro-actively

    preventing the occurrence; evaluate the impact of change

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    46/284

    Chapter 4 Project Integration

    Management Inputs to Change Control

    Project Plan baseline performance

    Performance Reports issue tracking, risk management

    Change Requests orally or written, externally orinternally initiates, legally mandated or optional

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    47/284

    Chapter 4 Project Integration

    Management Change Control Tools & Techniques

    All Changes must be evaluated before a decision can bereached

    Change Control System collection of formalprocedures, paperwork, tracking systems, approvallevels

    Change Control Board decision making authority

    Configuration Management documented procedure toapply technical and administrative direction ID and document functional and physical characteristics

    Control changes to these characteristics

    Record and report change and implementation status

    Audit items and system to verify requirements

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    48/284

    Chapter 4 Project Integration

    Management Change Control Tools & Techniques

    Performance Measurement earned value, plan varianceanalysis

    Additional Planning revised cost estimates, modifyactivity sequences, plan adjustments Project Management Information System Change Control System may have

    Change Control Plan

    Change Control Board Change Control Procedures, Corrective Action plans Performance Statistics, Reports, Change forms Specification reviews, Demonstrations, Testing, Meetings

    Configuration Management

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    49/284

    Chapter 4 Project Integration

    Management Change Control Outputs

    Project Plan Updates

    Corrective Actions

    Lessons Learned variance causes and reasoningdocumented for historical purposes

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    50/284

    Chapter 4 Project Integration

    Management Configuration Management

    Rigorous Change Management as it relates to scope Subset of the change control system

    Work Authorization System

    Controls gold plating; defines what task is/is not

    Meetings

    Most are inefficient; keep minutes Status can be determined without meeting

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    51/284

    Chapter 4 Project Integration

    Management Lessons Learned

    Project is not complete until a Lessons Learned iscompleted

    What have we done, how can we do it better Technical Aspects of the project

    Project Management (WBS, plans, etc.)

    Overall Management (communications, leadership)

    Best to have whole team complete and made available Also called Post Mortem

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    52/284

    Chapter 4 Project Integration

    Management Integration is a result of need for communication

    within a project

    Primary responsibility to decide what changes arenecessary is Management

    Project Managers must pro-actively define and solveproblems before reporting to superiors

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    53/284

    Chapter 5

    Project Scope Management Project Scope Management

    Processes required to ensure that the project includesall, and only, work required

    Defining what is/is not included in the project

    Project scope work that must be done measuredagainst project plan

    Product scope features and functions included in theproduct or service measured against requirements

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    54/284

    Chapter 5

    Project Scope Management Initiation process of formally recognizing that a

    new project exists, or an existing project continueto next phase

    Involves feasibility study, preliminary plan, orequivalent analysis

    Authorized as a result of: Market Demand

    Business Need

    Customer Request

    Technological Advance

    Legal Requirement

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    55/284

    Chapter 5

    Project Scope Management Initiation Inputs:

    Product Description characteristics of theproduct/service that the project was to create Less detail in early phases, more comprehensive in latter

    Relationship between product/service and business need

    Should support later project planning

    Initial product description is usually provided by the buyer

    Strategic Plan supportive of the organization's goals

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    56/284

    Chapter 5

    Project Scope Management Initiation Inputs (continued)

    Project Selection Criteria defined in terms of theproduct and covers range of management concerns

    (finance, market) Historical Information results of previous project

    decisions and performance should be considered

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    57/284

    Chapter 5

    Project Scope Management Tools & Techniques for Initiation

    Project Selection Methods: Benefit measurement models comparative approaches, scoring

    models, economic models Murder Boards

    Peer Review

    Scoring Models

    Economic Models

    Benefits compared to costs

    Constrained operation models programming mathematical Linear Programming

    Integer Programming

    Dynamic Programming

    Multi-objective programming

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    58/284

    Chapter 5

    Project Scope Management Tools & Techniques for Initiation

    Project Selection Methods: Decision models generalized and sophisticated techniques

    Expert judgment Business Units with specialized skills

    Consultant

    Professional and Technical Associations

    Industry Groups

    Delphi Technique obtain expert opinions on technical issues,scope of work and risks Keep experts identities anonymous

    Build consensus

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    59/284

    Chapter 5

    Project Scope Management Outputs from Initiation:

    Project Charter formally recognizes project, created bysenior manager, includes: Business need/Business Case Product description & title Signed contract Project Manager Identification & Authority level Senior Management approval Projects Goals and Objectives - Constraints factors that limit project management teams

    options Assumptions factors that are considered true for planning

    purposes. Involve a degree of risk

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    60/284

    Chapter 5

    Project Scope Management Scope Planning process of developing a written

    statement as basis for future decisions

    Criteria to determine if the project or phase is successful

    Scope Planning Inputs:

    Product description

    Project Charter

    Constraints Assumptions

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    61/284

    Chapter 5

    Project Scope Management Scope Planning Tools & Techniques

    Product Analysis - - developing a better understandingof the product of the project

    Cost/Benefit Analysis estimating tangible/intangiblecosts and returns of various project alternatives andusing financial measures (R.O.I.) to assess desirability

    Alternatives Identification generate different

    approaches to the project; brainstorming Expert Judgment

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    62/284

    Chapter 5

    Project Scope Management Scope Planning Outputs

    Scope Statement documented basis for making projectdecisions and confirming understanding among

    stakeholders. Includes: Project justification business need, evaluating future trade-offs

    Project Product summary of project description

    Project Deliverables list of summary of delivery items markingcompletion of the project

    Project Objectives quantifiable criteria met for success.Addresses cost, schedule and metrics unqualified objectivesindicate high risk (customer satisfaction)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    63/284

    Chapter 5

    Project Scope Management Scope Planning Outputs (continued)

    Supporting detail includes documentation of allassumptions and constraints

    Scope Management Plan how project scope ismanaged, change control procedure, expected stability,change identification and classification Control what is/is not in the project; prevents delivering

    extra benefits to the customer that were not

    specified/required

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    64/284

    Chapter 5

    Project Scope Management Scope Definition subdividing major deliverables

    into smaller, manageable components Improve accuracy of cost, time, and resource estimates

    Define a baseline for performance measurement Clear responsibility assignments Critical to project success reduces risk of higher cost,

    redundancy, time delays, and poor productivity Defines what you are doing; WBS is the tool

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    65/284

    Chapter 5

    Project Scope Management Scope Definition Inputs:

    Scope Statement

    Constraints consider contractual provisions

    Assumptions

    Other Planning Outputs

    Historical Information

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    66/284

    Chapter 5

    Project Scope Management Scope Definition Tools & Techniques

    Work Breakdown Structure templates from previousprojects

    Decomposition subdividing major deliverables intomanageable components: Major elements project deliverables and project management

    approach

    Decide cost and duration estimates are appropriate at level of

    detail Constituent elements tangible verifiable results to enable

    performance management, how the work will be accomplished

    Verify correctness of decomposition All items necessary and sufficient?

    Clearly and completely defined?

    Appropriately scheduled, budgeted, assigned?

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    67/284

    Chapter 5

    Project Scope Management Scope Definition Outputs

    Work Breakdown Structure (WBS) a deliverable-oriented grouping of project assignments that organizes

    and defines the scope of the project Each descending level represents further detail; smaller and more

    manageable pieces

    Each item is assigned a unique identifier collectively known ascode of accounts

    Work element descriptions included in a WBS dictionary (work,schedule and planning information)

    Other formats: Contractual WBS seller provides the buyer

    Organizational (OBS) work elements to specific org. units

    Resource (RBS) work elements to individuals

    Bill of Materials (BOM) hierarchical view of physical resources

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    68/284

    Chapter 5

    Project Scope Management Scope Definition Outputs

    Work Breakdown Structure (WBS) First Level is commonly the same at the Project Life Cycle (requirements,

    design, coding, testing, conversion and operation)

    First level is completed before the project is broken down further

    Each level of the WBS is a smaller segment of level above

    Work toward the project deliverables

    Break down project into tasks that Are realistically and confidently estimable

    Cannot be logically divided further Can be completed quickly (under 80 hours rule of thumb)

    Have a meaningful conclusion and deliverable

    Can be completed without interruption

    Provides foundation for all project planning and control

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    69/284

    Chapter 5

    Project Scope Management Scope Definition Outputs

    Work Breakdown Structure (WBS) - Benefits Prevent work slippage

    Project team understands how their tasks fit into the overall project andtheir impact upon the project

    Facilitates communication and cooperation between project team andstakeholders

    Helps prevent changes

    Focuses team experience into what needs to be done results in higher

    quality Basis and proof for estimating staff, cost and time

    Gets team buy-in, role identification

    Graphical picture of the project hierarchy

    Identifies all tasks, project foundation

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    70/284

    Chapter 5

    Project Scope Management WBS phrases

    Graphical hierarchy of the project

    Identifies all tasks

    Foundation of the project

    Very important

    Forces thought of all aspects of the project

    Can be re-used for other projects

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    71/284

    Chapter 5

    Project Scope Management Scope Definition Outputs

    Work Breakdown Structure (WBS) Dictionary Designed to control what work is done and when

    Also known as a task description Puts boundary on what is included in a task and what is not included

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    72/284

    Chapter 5

    Project Scope Management Scope Verification Inputs

    Work results partially/completed deliverables, costs todate

    Product documentation description available forreview (requirements)

    Scope Verification Tools & Techniques Inspection measuring, examining, testing to

    determine if results conform to requirements Scope Verification Outputs

    Formal acceptance documentation identifying clientand stakeholder approval, customer acceptance ofefforts

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    73/284

    Chapter 5

    Project Scope Management Scope Change Control:

    Influencing factors to ensure that changes are beneficial

    Determining scope change has occurred

    Managing changes when they occur

    Thoroughly integrated with other control processes

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    74/284

    Chapter 5

    Project Scope Management Scope Change Control Inputs:

    Work Breakdown Structure

    Performance Reports- issues reported

    Change Requests expansion/shrink of scope derivedfrom : External events (government regulations)

    Scope definition errors of product or project

    Value adding change new technology

    Scope Management Plan

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    75/284

    Chapter 5

    Project Scope Management Scope Change Control Tools & Techniques

    Scope Change Control System defines procedures howscope change can occur All paperwork, tracking systems, approval levels Integrated with overall change control procedures

    Performance Measurement determine what is causingvariances and corrective actions

    Additional Planning

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    76/284

    Chapter 5

    Project Scope Management Scope Change Control Outputs:

    Scope Changes fed back through planning processes,revised WBS

    Corrective Actions Lessons Learned cause and reasoning for variances

    documented for historical purposes

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    77/284

    Chapter 5

    Project Scope Management Management By Objectives (MBO)

    Philosophy that has 3 steps:

    Establish unambiguous and realistic objectives

    Periodically evaluate if objectives are being met Take corrective action

    Project Manager must know that if project is not aligned orsupport corporate objectives, the project is likely to loseresources, assistance and attention.

    MBO only works if management supports it

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    78/284

    Chapter 6

    Project Time Management Project Time Management

    Processes required to ensure timely completion of theproject

    No consensus concerning differences between activitiesand tasks

    Activities seen as composed of tasks most commonusage

    Other disciplines have tasks composed of activities

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    79/284

    Chapter 6

    Project Time ManagementActivity Definition: identifying and documenting

    specific activities to produce project deliverablesidentified in the WBS

    Must be defined to meet the project objectives

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    80/284

    Chapter 6

    Project Time ManagementActivity Definition Inputs

    WBS primary input

    Scope Statement project justification & project

    objectives Historical Information

    Constraints

    Assumptions

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    81/284

    Chapter 6

    Project Time ManagementActivity Definition Tools & Techniques

    Decomposition outputs are expressed as activitiesrather than deliverables

    Templates reuse from previous projects

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    82/284

    Chapter 6

    Project Time ManagementActivity Definition Outputs

    Activity List all to be performed; extension to the WBSand includes description to ensure team members

    understand work to be performed Supporting Detail organized as needed and include all

    assumptions and constraints

    WBS Updates identify missing deliverables and clarify

    deliverable descriptions. WBS updates often calledrefinements; more likely using new technologies inproject

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    83/284

    Chapter 6

    Project Time ManagementActivity Sequencing identifying and documenting

    interactive dependencies among activities. Supportlater development of a realistic schedule

    Project Management software often used

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    84/284

    Chapter 6

    Project Time ManagementActivity Sequencing Inputs:

    Activity List

    Product Description product characteristics often affect activitysequencing

    Mandatory Sequencing physical limitations, hard logic,prototypes needed; inherent in nature of work being done

    Discretionary Dependencies defined by project managementteam; best practices or unusual aspects of project soft logic,preferred logic, preferential logic

    External Dependencies relationship between project activities andnon-project activities (company policies, procurement, etc.)

    Constraints

    Assumptions

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    85/284

    Chapter 6

    Project Time Management Network Diagrams

    Shows how the project tasks will f low from beginning to end

    Proves how long the project will take to complete

    Takes project tasks from low levels of WBS and placing them intotheir order of completion (beginning to end)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    86/284

    Chapter 6

    Project Time ManagementActivity Sequencing Tools & Techniques

    Precedence Diagramming Method (PDM) constructing network diagram using nodes to represent

    activities and arrows to indicate dependencies; alsocalled Activity On Node (AON)

    Most project management software uses

    Includes 4 types of dependencies: Finish to Start from activity must finish before to activity can begin; most

    commonly used Finish to Finish from activity must finish before the next may finish

    Start to Start from activity must start before next to activity can start

    Start to Finish task must start before next activity can finish

    Use caution with last 3 techniques - logical relationships often notconsistently implemented with project management software

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    87/284

    Chapter 6

    Project Time ManagementActivity Sequencing Tools & Techniques (continued)

    Arrow Diagramming Method (ADM) uses arrows torepresent activities and connecting at nodes to illustrate

    dependencies Also called Activity On Arrow (AOA)

    Only uses finish to start dependencies

    PERT and CPM only can be drawn using AOA

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    88/284

    Chapter 6

    Project Time ManagementActivity Sequencing Tools & Techniques (continued)

    Conditional diagramming methods

    GERT (Graphical Evaluation and Review Technique)

    System Dynamic Models Allow for non-sequential activities (loops) or conditional

    branches not provided by PDM or ADM methods

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    89/284

    Chapter 6

    Project Time ManagementActivity Sequencing Tools & Techniques (continued)

    Network Templates standardized networks can beused. Composed of subnets, or fragnets

    Subnets are several nearly identical portions of a network(floors on a building, clinical trials, program modules)

    Useful for several identical processes (clinical trials,programming modules).

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    90/284

    Chapter 6

    Project Time ManagementActivity Sequencing Outputs:

    Project Network Diagram schematic display of projectactivities and relationships (dependencies). Should be

    accompanied by a summary narrative that describes thediagram approach

    Activity List Updates

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    91/284

    Chapter 6

    Project Time ManagementActivity Duration Estimating

    Involves assessing number of work periods needed tocomplete identified activities

    Requires consideration of elapsed time, calendars,weekends, and day of week work starts

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    92/284

    Chapter 6

    Project Time ManagementActivity Duration Estimating Inputs:

    Activity Lists

    Constraints

    Assumptions Resource Requirements amount of labor assigned to

    activity

    Resource Capabilities human and material resources,

    expertise Historical Information

    Project Files, or records of previous project results

    Commercial Duration Estimates useful when durations are notdriven by actual work (approval periods, material resources)

    Project Team Knowledge

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    93/284

    Chapter 6

    Project Time ManagementActivity Duration Estimating Tools & Techniques

    Expert Judgment guided by historical informationshould be used whenever possible; high risk without

    expertise avail. Simulation using different sets of assumptions (Monte

    Carlo Analysis) to drive multiple durations

    Analogous Estimating top down estimating useactual, similar, previous known durations as basis for

    future activity duration. Used when limited knowledgeis available. Form of expert judgment

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    94/284

    Chapter 6

    Project Time ManagementActivity Duration Outputs:

    Activity Duration Estimates quantitative assessmentsof work periods to complete an activity. Should indicate

    a range +/- of possible results Basis of Estimates all assumptions should be

    documented

    Activity List Updates

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    95/284

    Chapter 6

    Project Time Management Schedule Development

    Determining start and finish dates for project activities

    Without realistic dates, project unlikely to be finished as

    scheduled Schedule development process often iterates as more

    information becomes available (process inputs)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    96/284

    Chapter 6

    Project Time Management Schedule Development Inputs:

    Project Network Diagram

    Activity Duration Estimates

    Resource Requirements

    Resource Pool Description availability patterns; sharedresources are highly variable

    Calendars define eligible work periods Project Calendars affect all resources

    Resource Calendars affect specific resource pools or individuals

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    97/284

    Chapter 6

    Project Time Management Schedule Development Inputs (continued):

    Constraints Imposed Dates may be required

    Key events or milestones are initially requested and becomeexpected during project

    Assumptions

    Lead and Lag Time dependencies may specify time in

    order to satisfy relationship (example 2 weeks toreceive order)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    98/284

    Chapter 6

    Project Time Management Schedule Development Tools & Techniques

    Mathematical Analysis calculating theoreticalearly/late finish and start dates without regard for

    resource pool limitations; indicate time periods whichactivity should be scheduled given resource limits andother constraints: Critical Path Method (CPM) single early/late start and finish date for all

    activities. Based on specified, sequential network and single duration estimate.Calculates float to determine flexibility

    Graphical Evaluation and Review Technique (GERT) probabilistic treatment ofnetwork and activity duration estimates

    Program Evaluation and Review Technique (PERT)- sequential network andweighted average duration to calculate project duration differs from CPM byusing mean (expected value) instead of most-likely estimate in CPM

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    99/284

    Chapter 6

    Project Time Management Schedule Development Tools & Techniques

    Critical Path Method: refers to estimating based on one timeestimate per activity One time estimate per task (Most Likely)

    Emphasis on controlling cost and leaving schedule flexible Drawn using AOA diagrams

    Can have dummy task

    PERT (Program Review and Estimating Technique) 3 Time estimates per activity

    Optimistic Pessimistic

    Most Likely

    Emphasis on meeting schedule, flexibility with costs

    Drawn on AOA diagrams

    Can have dummy tasks

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    100/284

    Chapter 6 Project Time Management

    Schedule Development Tools & Techniques Monte Carlo Analysis

    Uses a computer with PERT values and network diagram

    Tells Probability of completing a project on any specific day

    Probability of completing a project for any specific amount of cost

    Probability of any task actually being on the critical path

    Overall Project Risk

    Suggests that Monte Carlo simulation will create a projectduration that is closer to reality than CPM or PERT

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    101/284

    Chapter 6 Project Time Management

    Schedule Development Tools & Techniques(continued)

    Duration Compression look to shorten project

    schedule without affecting scope Crashing cost and schedule trade-offs to determine greatest

    amount of compression for least incremental cost often resultsin higher costs

    Fast Tracking performing activities in parallel that normallywould be sequenced often results in re-work and usuallyincreases risk

    Simulation

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    102/284

    Chapter 6 Project Time Management

    Schedule Development Tools & Techniques(continued)

    Resource Leveling Heuristics leveling resources that

    apply to critical path activities a.k.a. resourceconstrained scheduling when limitation on quantityof available resources; sometimes called ResourceBased Method often increases project duration

    Project Management Software

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    103/284

    Chapter 6 Project Time Management Schedule Development Tools & Techniques (continued)

    Project Mangers role Provide the team with the necessary information to properly estimate

    the task

    Complete a sanity check of the estimate Formulate a reserve

    Project Team should be involved; determine task estimates Historical Records

    Guesses

    Actual Costs Benchmarks

    CPM and PERT

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    104/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    105/284

    Chapter 6 Project Time Management Schedule Development Outputs:

    Project Schedule includes planned start and finishdates for each activity; remains preliminary untilresources assignments are approved. Usually in

    following formats: Project Network Diagrams (with date information added) show

    logical and critical path activities Bar or Gantt charts activity start and end dates, expected

    durations Milestone Charts identifies key deliverables and interfaces Time-scaled network diagrams blend of project network and

    bar charts

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    106/284

    Chapter 6 Project Time Management

    Schedule Development Outputs (continued): Supporting Detail all assumptions and constraints.

    May also include:

    Resource requirement by time period (resource histogram) Alternative schedules (best/worst case)

    Schedule reserve/risk assessments

    Schedule Management Plan how updates are managed

    Resource requirement updates leveling and activity

    impact

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    107/284

    Chapter 6 Project Time Management

    Schedule Control: Influencing factors which create schedule changes to

    ensure changes are beneficial

    Determining that schedule has changed Managing actual changes as they occur

    Inputs to Schedule Control Project Schedule baseline approved, measure against

    project performance Performance Reports planned dates met, issues

    Change Requests

    Schedule Management Plan

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    108/284

    Chapter 6 Project Time Management Schedule Control Tools & Techniques

    Schedule Change Control System defines proceduresfor schedule changes, paperwork, approval, trackingsystems

    Performance Measurement assess magnitude ofvariations to baseline; determine if corrective action isneeded

    Additional Planning

    Project Management Software

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    109/284

    Chapter 6 Project Time Management Schedule Control Outputs:

    Schedule Updates any modifications, stakeholdernotification Revisions change scheduled start and finish dates generally

    in response to scope changes. Re-baselining may be neededin drastic situations

    Corrective Action re-align performance with projectplan

    Lessons Learned

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    110/284

    Chapter 6 Project Time Management Key knowledge points not in PMBOK

    Need to know manual calculations of network diagrams Created after project charter and WBS (task estimates and

    dependencies are determined) Mandatory dependencies (Hard Logic) inherent in nature of

    work

    Discretionary dependencies (Soft Logic) based onexperience, desire or results

    External dependencies based on needs and desires of

    organizations outside the project

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    111/284

    Chapter 6 Project Time Management

    Methods to draw network diagrams

    Activity on Node (AON) or Precedence DiagrammingMethod (PDM)

    Boxes represent tasks Arrows show task dependencies

    4 types of task relationships

    Finish to Start (task must finish before next can start)

    Finish to Finish (task must finish before next can finish)

    Start to Start (task must start before next can start)

    Start to Finish (task must start before the next can finish)

    No dummy tasks used

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    112/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    113/284

    Chapter 6 Project Time Management

    Methods to draw network diagrams

    Activity on Arrow (AOA or Arrow Diagramming Method(ADM) continued:

    PERT (Program Evaluation and Review technique) 3 time estimates per activity: Optimistic (O), Most Likely (M),

    Pessimistic (P)

    Emphasizes meeting schedule, flexibility with cost

    Can have dummy tasks

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    114/284

    Chapter 6 Project Time Management Methods to draw network diagrams

    PERT (Program Evaluation and Review technique) Estimating based on 3 formulas:

    PERT Duration: (P + 4M + O)/6 Standard Task Deviation: (P O)/6 Task Variance:

    Total project estimate: Add up all Optimistic, Most Likely and Pessimistic values of the critical path

    tasks and apply P + 4M + O/6

    Total project variance (+/-): Add up the individual task variances and take the square root of the value. Use

    the value as a +/- figure to compute the Optimistic and Pessimistic values. Thetotal project estimate will serve as the basis.

    [PO]26

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    115/284

    Chapter 6 Project Time Management

    Monte Carlo Simulation:

    Uses a computer with PERT values (P, M, O) and anetwork diagram but does not use the PERT formula

    Indicates Probability of completing project on a specific day

    Probability of completing project for any specific amount of cost

    Probability of any task actually being on critical path

    Overall project risk

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    116/284

    Chapter 6 Project Time Management

    Estimating techniques in general:

    Should be performed by entire project team Project manager needs to provide information to allow team to

    create estimates; sanity check; formulate reserve Estimates are:

    Guesses, Historical Records, Actual Costs, Benchmarks, CPM,PERT

    Critical paths determines the earliest completion date and identifies

    tasks that need monitoring Can be obtained by CPM, PERT and Monte Carlo estimating

    techniques

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    117/284

    Chapter 6 Project Time Management

    Key Definitions: Slack (Float): the amount of time a task can be delayed

    without delaying the entire project. Tasks on criticalpath have no slack. Slack is calculated by the difference between Early Start and Late

    Start of a task Free Slack (Float): the amount of time a task can be delayed without

    delaying the early start date of its successor

    Total Slack (Float): the amount of time a task can be delayed without

    delaying the project completion date Lag: inserted waiting time between tasks

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    118/284

    Chapter 6 Project Time Management General Comments:

    Projects can have more than 1 critical path (increases risk) and caninvolve dummy tasks

    Negative float indicates that you are behind Resource Leveling involves possibly letting schedule and cost slip Heuristics just means rule of thumb e.g. 80/20 rule Schedules are calendar based makes this different than a time

    estimate Bar Chart a.k.a. Gantt chart (track progress, report to entire team

    including stakeholders, control tool)

    Network Diagram (to show task inter-dependencies, show projectorganization, basis for project control) Milestone chart (report to Senior management, shows major events)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    119/284

    Chapter 6 Project Time Management General Comments:

    To shorten project schedule examine the critical path Crashing add more resources to the critical path tasks

    Usually results in increased cost Fast Tracking performing tasks in parallel

    Can result in re-work and increased risk

    Best to select method that has least impact on theproject (is the importance on cost, risk or schedule?)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    120/284

    Chapter 6 Project Time Management General Comments:

    Bar (Gantt) Charts Weak Planning Tool, effective progress and reporting tool Does not show interdependencies of tasks Does not help organize the project more effectively

    Network Diagrams (PERT, CPM, PDM) Shows task interdependencies Aids in effectively planning and organizing work Provides a basis for project control

    Milestone Charts Only shows major events Good for reporting to management and customer

    Flow Charts Depicts workflow and not commonly used for project management

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    121/284

    Chapter 6 Project Time Management General Comments:

    Free Slack (Float) amount of time a task can be delayed without delaying the earlystart date of its successor

    Total Slack (Float) amount of time a task can be delayed without delaying theproject completion date

    Lag inserted waiting time between tasks Resource Leveling level peaks of resource usage; stable number of resources

    allows schedule and cost slip in favor of leveling resources Heuristic rule of thumb (80/20 rule)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    122/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    123/284

    Chapter 7 Project Cost Management Project Cost Management

    Estimating should be based on WBS to improve accuracy

    Estimating should be done by the person performing the work

    Having historical records is key to improving estimates

    Costs (schedule, scope, resources) should be managed to estimates A cost (schedule, scope, baseline) should be kept and not changed

    Plans should be revised as necessary during completion of work

    Corrective action should be taken when cost problems (schedule,scope and resources) occur.

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    124/284

    Chapter 7 Project Cost Management

    Resource Planning: Determining what physical resources and quantities are

    needed to perform work

    Inputs to Resource Planning: Work Breakdown Structure

    Historical Information

    Scope Statement justification & objectives

    Resource Pool Description what resources arepotentially available for resource planning

    Organizational Policies staffing, procurement

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    125/284

    Chapter 7 Project Cost Management

    Inputs to Resource Planning: Work Breakdown Structure

    Network Diagram

    Schedule Risks

    Historical Information

    Scope Statement justification & objectives

    Resource Pool Description what resources arepotentially available for resource planning

    Organizational Policies staffing, procurement

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    126/284

    Chapter 7 Project Cost Management

    Resource Planning Tools & Techniques

    Expert Judgment

    Alternatives Identification

    Resource Planning Outputs: Resource Requirements what type & how many

    resources are needed for each activity in the WorkBreakdown Structure

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    127/284

    Chapter 7 Project Cost Management

    Cost Estimating:

    Develop approximate costs of resources

    Distinguish estimating from pricing

    Estimating likely amount Pricing business decision

    Identify alternatives and consider realigning costs inphases to their expected savings

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    128/284

    Chapter 7 Project Cost Management

    Cost Estimating Inputs:

    Work Breakdown Structure

    Resource Requirements

    Resource Rates (if known) Activity Duration Estimates

    Historical Information (project files, commercial costdatabases, team knowledge

    Chart Of Accounts coding structure for accounting;general ledger reporting

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    129/284

    Chapter 7 Project Cost Management

    Cost Estimating Tools & Techniques Analogous Estimating top down; using actual costs

    from previous project as basis for estimate Reliable when previous projects are similar and individuals have

    expertise form of expert judgment

    Parametric Modeling uses project characteristics inmathematical models to predict costs (e.g.buildinghouses)

    Reliable when historical information is accurate, parameters arequantifiable, and model is scalable 2 types: Regression analysis, Learning Curve

    Bottom Up Estimating rolling up individual activitiesinto project total smaller work activities have more

    accuracy -

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    130/284

    Chapter 7 Project Cost Management

    Cost Estimating Tools & Techniques Pros and Cons

    Analogous Estimating

    Quick - Less Accurate Tasks dont need to be identified Estimates prepared with little

    detail and understanding of project

    Less costly Requires considerable experience to do well

    Gives PM idea of management expectations Infighting at highlevels of organization

    Overall project costs are capped Difficult for projects withuncertainty

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    131/284

    Chapter 7 Project Cost Management

    Cost Estimating Tools & Techniques Pros and Cons

    Bottom Up Estimating

    More Accurate Takes time and expense Gains buy-in from the team Tendency for team to pad estimates

    Based on detailed analysis of project Requires that project bedefined and understood

    Provides a basis for monitoring and control Team infighting toget biggest piece of pie

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    132/284

    Chapter 7 Project Cost Management Outputs from Cost Estimating

    Cost estimates quantitative assessments of likely costs of resourcesrequired to complete tasks For all resources of the project (labor, materials, supplies, inflation allowance,

    reserve) Expressed in units of currency

    Supporting Detail Description of scope (reference to the WBS) Documentation how estimate was developed Indication of range of possible results Assumptions

    Cost Management Plan how cost variances will be managed

    Cost Risk: associated to seller for Fixed Price; associated to buyer for Timeand Materials budget

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    133/284

    Chapter 7 Project Cost Management

    Cost Budgeting Involves allocation of total estimate to individual work

    to establish a cost baseline to measure performance

    Cost Budgeting Inputs Cost Estimate

    Work Breakdown Structure

    Project Schedule includes planned start and finish

    dates for items costs are allocated to Needed to assign costs during the time period when the actual

    cost will be incurred

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    134/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    135/284

    Chapter 7 Project Cost Management Cost Control

    Concerned with influencing factors that create changes to the costbaseline that are beneficial

    Determining that the cost baseline has changed

    Managing actual changes as they occur Monitor cost performance to detect variances

    Record all appropriate changes accurately in the cost baseline

    Preventing incorrect, unauthorized changes being included in the costbaseline

    Informing stakeholders of authorized changes Determine the whys of positive and negative variances

    Integrated will all other control processes (scope, change, schedule, quality)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    136/284

    Chapter 7 Project Cost Management Inputs to Cost Control

    Cost Baseline Performance Reports meet, exceed budget

    50/50 Rule task is considered 50% complete when it begins and gets credit for remainder50% only when completed

    20/80 Rule - task is considered 20% complete when it begins and gets credit for remainder80% only when completed

    0/100 Rule task only credited when fully completed

    Change Requests Cost Management Plan

    Tools & Techniques of Cost Control Cost Change Control System defines the procedures by which the cost baseline may

    be changed

    Performance Measurement assess magnitude of cost variations (Earned ValueAnalysis) and what is causing the variance Additional Planning examine alternatives Computerized Tools forecast planned costs, track actual costs, forecast effect of

    cost changes

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    137/284

    Chapter 7 Project Cost Management Cost Control Outputs

    Revised Cost Estimate Modifications to cost information; require stakeholder approval and adjustments

    to other project areas

    Budget Updates changes to approved cost baseline; revised in response toscope changes

    Corrective Action Estimate at completion (EAC) forecast of total expenditures

    Actual to date plus remaining budget modified by a factor (cost performanceindex) Current variances are seen to apply to future variances

    Actual to date plus new estimate for remaining work

    Original estimates are flawed, or no longer relevant Actual to date plus remaining budget

    Current variances are typical and similar variances will not occur in the future

    Lessons Learned

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    138/284

    Chapter 7 Project Cost Management

    Earned Value Analysis Integrates cost, schedule and scope

    Better that comparing projected vs. actual because time

    and cost are analyzed separately Terms:

    BCWS Budgeted Cost of Work Scheduled (how much workshould be done)

    BCWP Budgeted Cost of Work Performed a.k.a. Earned Value

    (how much work is budgeted, how much did we budget) ACWP Actual Cost of Work Performed (how much did the

    completed work cost)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    139/284

    Chapter 7 Project Cost Management Earned Value Analysis

    Terms: BAC Budget at Completion (how much did you budget for

    the total job)

    EAC Estimate at Completion (what do we expect the totalproject to cost)

    ETC Estimate to Completion (how much more do we expectto spend to finish the job)

    VAC Variance at Completion (how much over/under budget

    do we expect to be)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    140/284

    Chapter 7 Project Cost Management Earned Value Analysis

    Formulas Variance (Plan Actual)

    Cost Variance (CV): BCWP ACWP; negative is over budget

    Schedule Variance (SV): BCWP BCWS; negative is behindschedule

    Cost Performance Index (CPI): BCWP

    ACWP

    I am only getting x out of every $ BCWPACWP

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    141/284

    Chapter 7 Project Cost Management Earned Value Analysis

    Formulas Schedule Performance Index (SPI): BCWP

    BCWS

    I am only progressing x % of the planned rate

    Estimate at Completion (EAC): BACCPI

    As of now we expect the total project to cost x$

    Estimate to Complete (ETC): EAC ACWP; how much will it costfrom now to completion

    Variance at Completion: BAC EAC; when the project is over howmuch more or less did we spend (most common way ofcalculating EVA

    BCWP

    BCWS

    BAC

    CPI

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    142/284

    Chapter 7 Project Cost Management

    Earned Value Analysis

    BCWP comes first in most formulas

    If it is a variance, BCWP comes first

    If it is an index, BCWP is divided by If the formula relates to cost, use AWCP

    If the formula related to schedule, use BWCP

    Negative is bad; positive results are good

    ETC refers to this point on; EAC refers to when job iscompleted

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    143/284

    Chapter 7 Project Cost Management

    Accuracy of Estimates

    Order of Magnitude Estimate: -25% - 75%; usually madeduring Initiation Phase

    Budget Estimate: -10% - 25%; usually made during thePlanning phase

    Definitive Estimate: -5% - 10%; usually made during thePlanning phase

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    144/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    145/284

    Chapter 7 Project Cost Management Accounting Standards

    Net Present Value: total benefits (income or revenue) less the costs.NPV is the sum of each present value of each income/revenue item

    Internal Rate of Return (IRR): company may select project based onhighest IRR

    Payback Period: number of time periods it takes to recover theinvestment in the project before generating revenues

    Benefit Cost Ratio (BCR): compares costs to the benefits of differentprojects Greater than 1 means benefits are greater than costs Less than 1 means costs are greater than benefits

    Opportunity Cost: opportunity given up by selecting one projectover another

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    146/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    147/284

    Chapter 7 Project Cost Management

    Accounting Standards Depreciation: assets lose value over time

    Straight Line depreciation: same amount is taken each year

    Accelerated Depreciation: 2 forms Double Declining Balance

    Sum of the Years Digits

    Life Cycle Costing: includes operations andmaintenance phases

    Value Analysis: find a less costly way to do same work

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    148/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    149/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    150/284

    Chapter 7 Project Cost Management Accounting Standards

    Definitive Estimate most precise/accurate estimate fordetermining project costs

    Management Reserve over time PM wants no change to reserve;

    customers wants $ back Cost and Schedule Data predicts future performance

    ROI, Nest Present Value and Discounted Cash Flow all can beused to measure total income vs. total $ expended

    Undistributed budget budget that contains approved scopechanges but are not planned yet

    Depreciation is not a measurement of profitability

    Pay Back Period - # of periods required to recover the initialinvestment

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    151/284

    Management Project Quality Management

    Processes required to ensure that the project will satisfythe needs for which it was designed

    Includes all activities of the overall managementfunction that determine the quality policy, objectives,and responsibilities. These are implemented by qualityplanning, quality control, quality assurance, and qualityimprovement

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    152/284

    Management 3 major processes:

    Quality Planning identifying quality standards that are relevant tothe project (Plan); Project Manager, Project Owner

    Quality Assurance evaluating overall project performance toprovide confidence that project will satisfy relevant quality

    standards (Implement or Execution); Project Team Quality Control monitoring specific results to comply with quality

    standards and eliminating unsatisfactory performance causes(Check or Control); Project Manager, Project Team Compatible with ISO 9000 and 10000 series Proprietary and non-proprietary approaches (total quality management

    Must address the management of the project and the product of theproject

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    153/284

    Management Quality the totality of characteristics of an entity that bear on its

    ability to satisfy stated or implied needs Critical aspect is to turn implied needs into stated needs through project

    scope management Do not confuse with grade category or rank given to entities having the

    same functional use but different requirements for quality Customer satisfaction conformance to specifications (must produce what

    is stated) and fitness for use (must satisfy real needs) Prevention avoid mistakes vs. cost of correction Management responsibility requires participation of team; responsibility

    of management to provide resources Processes within phases plan-do-check-act cycle

    Recognize that the investment in product quality improvements may be borne bythe performing organization since the project may not last long enough to reapreward

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    154/284

    Management Quality Planning

    Identify quality standards are relevant and how to satisfy

    Inputs to Quality Planning Quality Policy the overall intentions and direction of an

    organization with regard to quality as expressed by management Scope Statement

    Product Description

    Standards and Regulations

    Other Process Outputs processes from other knowledge areas

    (procurement planning)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    155/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    156/284

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    157/284

    Management

    Quality Assurance

    All planned and systematic activities implementedwithin the quality system to provide confidence that the

    project will satisfy quality standards Inputs to Quality Assurance

    Quality Management Plan

    Results of quality control measurements (testing)

    Operational definitions

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    158/284

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    159/284

    Management Quality Control monitoring specific results to determine

    if they comply with quality standards and identifying waysto eliminate causes of unsatisfactory results Includes project (deliverables) and management (cost and schedule

    performance) results Awareness of statistical quality control

    Prevention (keep errors out of process) and inspection (keep errors fromcustomers)

    Attribute sampling (result conforms) and variable sampling

    Special Causes (unusual events) and random causes

    Tolerances (acceptable range) and control limits (result falls withinrange)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    160/284

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    161/284

    Management Tools & Techniques for Quality Control

    Inspection activities such as testing to determine if results comply withrequirements

    Control Charts plot results over time Pareto diagrams frequency of occurrence that identifies type or category

    of result (80/20 rule) guides corrective action Statistical sampling select population of interest for inspection Flowcharting Trend Analysis forecast future outcomes based on historical results

    Technical performance (# of errors identified; # of errors that remain) Cost and Schedule performance (activities per period with significant variances)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    162/284

    Chapter 8 Project Quality

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    163/284

    Management

    Tips from the Review Guide Philosophy: definition of quality, avoidance of gold plating

    giving customer extras, prevention over inspection

    Conformance to requirements, specifications and fitness of use

    Quality Management processes required to ensure that the projectwill satisfy the needs for which it was undertaken

    Continuous Improvement - small improvements to reduce costsand ensure consistency

    Marginal Analysis optimal quality is reached at the point whenrevenue from improvement equals the costs to secure it

    Just in Time - decrease amount of inventory/decrease investment

    Chapter 8 Project QualityM

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    164/284

    Management

    Tips from the Review Guide ISO 9000 or 10000 standards to ensure that

    corporations follow their own quality procedures

    Total Quality Management continuous improvementin business practices

    Normal Distribution most common probability usedto measure variations

    Standard deviation (sigma) measure how far away

    from the mean (dotted vertical line) 3 or 6 sigma represents level of quality

    +/- 1 sigma equal to 68.26%

    +/- 2 sigma equal to 95.46%

    +/- 3 sigma equal to 99.73%

    Chapter 8 Project QualityM

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    165/284

    Management

    Tips from the Review Guide

    Responsibility to quality entire organization

    Ultimate employee

    Overall or Primary Project Manager Design and Test Specifications engineer

    Prevention over inspection quality must be planned innot inspected in

    Chapter 8 Project QualityM t

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    166/284

    Management

    Tips from the Review Guide Cost of conformance vs. non-conformance

    Quality Training vs. rework

    Studies vs. Scrap

    Surveys vs. Inventory Costs and warranty costs

    Quality Planning (Plan) determine what will bequality on project and how quality will be measured done during Planning Phases

    Identifying which standards are relevant to project how tosatisfy them

    Benchmarking look at past projects to determine ideas forimprovement

    Cost Benefit Analysis

    Flowcharts (fishbone)

    Chapter 8 Project QualityM t

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    167/284

    Management

    Tips from the Review Guide

    Quality Assurance (Implement) determine if yourmeasurement of quality is appropriate done duringExecution phases

    Process of evaluating overall performance on a regular basis

    Quality Audits structured review of quality activities thatidentify lessons learned

    Chapter 8 Project QualityM t

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    168/284

    Management Tips from the Review Guide

    Quality Control (Check) perform the measurementand compare to the quality plan done during Controlphases Process of monitoring specific project results to determine if

    they comply with relevant quality standards and identify waysof eliminating unsatisfactory performance

    Performance of the measurement or process, using qualitycontrol tools checking work

    Chapter 8 Project QualityM t

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    169/284

    Management Tips from the Review Guide

    Quality Control Tools

    Pareto Diagrams 80/20 rule the chart presents theinformation being examined in its order of priority and helps

    focus attention on the most critical issues Fishbone diagram (Cause and Effect)

    A creative way to look at the causes or potential causes of aproblem

    Helps stimulate thinking, organizes thoughts and generatesdiscussion

    Can be used to explore a desired future outcome and thefactors to which it relates

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    170/284

    Chapter 8 Project QualityM t

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    171/284

    Management Tips from the Review Guide

    Quality Control Tools

    Out of Control process is out of control when:

    A data point falls outside of the upper or lower control limit

    Non-random data points are within the upper control andlower control limits

    Rule of 7 non-random points outside the mean - processshould be investigated

    Assignable Cause data point the requires investigation to

    determine the cause of the variation

    Chapter 8 Project QualityM t

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    172/284

    Management PMI and Deming

    Cost of conformance 85% of costs of quality areresponsibility of Management Quality Training Rework

    Studies Scrap Surveys Inventory and Warranty costs

    Crosby absolutes of quality Performance standard is zero defects; measurement

    system is cost of non-conformanceContinuous Improvement

    Japanese (Kaizen)

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    173/284

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    174/284

    Chapter 8 Project Quality

    Management

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    175/284

    Management Review Guide Tips

    Marginal Analysis: optimal quality is reached whenincremental revenue from improvement equals theincremental cost to secure

    Standard Deviation: how far away from mean Variable: characteristic you want to measure

    Attribute: measurement (subjective or objective)

    Ultimate Responsibility Employee

    Overall Responsibility PM Design/Test Specifications - Engineer

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    176/284

    Chapter 8 Project Quality

    Management

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    177/284

    Management Review Guide Tips

    Quality objectives are approved in conceptual stage byproject owner

    QA auditing function that provides feedback to teamand client about quality of output being produced

    If sample size is a constant and acceptance numbersincrease, the producers risk decreases and consumer riskincreases

    85% of costs of quality are direct responsibility ofmanagement

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    178/284

    Chapter 9 Human Resource

    Management

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    179/284

    Management Project Human Resource Management

    1,9 manager = good relationship with team

    Project Organization Conflict between PM and Functional Managers

    Dual allegiance of team members Complex prioritization of resources

    Loss of developed procedures on project dissolution

    Compromise = both sides will lose

    Delegation Defer the decision

    Interpreted as passive

    Emphasize task vs. personnel

    Can be frequently used

    Chapter 9 Human Resource

    Management

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]

    180/284

    Management Project Human Resource Management

    If there is a team of experts, PM decisions will promotehigh satisfaction

    Functional/Project Managers likely to exercise: Power

    Authority

    Influence

    Traditional organization forms have no single point ofcontact for client/sponsor

    Chapter 9 Human ResourceManagement

  • 7/27/2019 Project Management Professional (PMP) Study Guide[1]