Upload
nermeen-soliman-elnahas
View
219
Download
1
Embed Size (px)
Citation preview
7/27/2019 Project Management Professional (PMP) Study Guide[1]
1/284
Certification Study Guide
7/27/2019 Project Management Professional (PMP) Study Guide[1]
2/284
PMI Certification Materials To assist PMI candidates for completing the PMI
certification exam administered by the ProjectManagement Institute
Content is from A Guide To The Project ManagementBody Of Knowledge (PMBOK)
www.pmi.org
7/27/2019 Project Management Professional (PMP) Study Guide[1]
3/284
Recurring Themes Historical Records need to collect and use for planning,
estimating and risk
Kickoff meetings are important
Work Breakdown Structures Do not introduce benefits that are not stated in
requirements
Needs of all stakeholders should be taken into account
during all projects Team Members must be involved in project planning
Project Mangers must be pro-active
7/27/2019 Project Management Professional (PMP) Study Guide[1]
4/284
Chapter 1
Introduction Project temporary endeavor undertaken to create
a unique product or service
Has a definite beginning and end and interrelatedactivities
Programs adopt new set of objectives and continueto work; projects ceasewhen declared objectives
have been attained
7/27/2019 Project Management Professional (PMP) Study Guide[1]
5/284
Chapter 1
Introduction Projects are unique characteristics are progressively
elaborated
Progressively: proceeding in steps
Elaborated: worked with care and detail
Scope of project should remain constant even ascharacteristics are progressively elaborated
7/27/2019 Project Management Professional (PMP) Study Guide[1]
6/284
Chapter 1 - Introduction Project Management: the application of
knowledge, skills, tools and techniques to project
activities in order to meet or exceed stakeholderneeds and expectations from a defined project balancing the following:
Scope, time, cost, and quality
Stakeholders expectations Requirements (needs) vs. unidentified requirements
(expectations)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
7/284
Chapter 1 - Introduction Programs are groups of projects managed in a
coordinated way to obtain benefits not availablefrom managing the projects individually
Most programs have elements of ongoingoperations Series of repetitive or cyclical undertakings
Projects are often divided into subprojects formore manageability Often contracted out to external organizations
7/27/2019 Project Management Professional (PMP) Study Guide[1]
8/284
Chapter 2
Project Management Context Project Phases are marked by the completion of a
deliverable Tangible, verifiable work product
Review of deliverables and approval/denial are phaseexits, stage gates, or kill points
Phases are collected into the Project Life Cycle Set of defined work procedures to establish
management control
7/27/2019 Project Management Professional (PMP) Study Guide[1]
9/284
Chapter 2
Project Management Context Project Life Cycle defines:
Technical work performed in each phase
Who is involved in each phase
Project Phases can overlap Fast Tracking Common Characteristics of Project Life Cycles:
Cost and Staffing levels are low at start and move higher towardsthe end
Probability of successfully completing project is low at beginning,higher towards the end as project continues
Stakeholder influence is high at the beginning and progressivelylowers as project continues
7/27/2019 Project Management Professional (PMP) Study Guide[1]
10/284
Chapter 2
Project Management Context Stakeholders: individuals and organizations who
are actively involved in the project
Often have conflicting expectations and objectives In general, differences should be resolved in favor of the
customer individual(s) or organization(s) that will usethe outcome of the project
Stakeholder management is a proactive task Project Mangers must determine all stakeholders and incorporate
their needs into the project
7/27/2019 Project Management Professional (PMP) Study Guide[1]
11/284
Chapter 2
Project Management Context Stakeholders are:
Project Managers
Customers
Performing Organizations, owners
Sponsor
Team
Internal/External
End User
Society, citizens
Others: owner, funders, supplier, contractor
7/27/2019 Project Management Professional (PMP) Study Guide[1]
12/284
Chapter 2
Project Management Context Organizational Systems: Project based vs. Non-Project
Based
Project Based derive revenues from performingprojects for others (consultants,contractors),management by projects
Non-Project Based seldom have management systemsdesigned to support project needs (manufacturing,
financial services)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
13/284
Chapter 2
Project Management Context Organizational Cultures and Styles:
Entrepreneurial firms more likely to adopt highlyparticipative Project Manager accept higherrisk/reward
Hierarchical firms less likely to adopt participativeProject Manager take fewer risks
7/27/2019 Project Management Professional (PMP) Study Guide[1]
14/284
Chapter 2
Project Management Context Organizational Structures
Functional (classical) marked by identifiable superiors.Staff grouped by specialty . Perceived scope of project
limited by function (Engineering, HR). Typically havepart-time Project Manager
Projectized Organization blend functional andprojectized characteristics. Mix cross-departmentpersonnel with full-time Project Manger
7/27/2019 Project Management Professional (PMP) Study Guide[1]
15/284
Chapter 2
Project Management Context Project Management Skills
General Business Management (consistently producing resultsexpected by stakeholders)
Leading (establishing direction, aligning resources, motivating) Communicating (clear, unambiguous, and complete)
Negotiating (conferring with others to reach an agreement)
Problem Solving (definition and decision making)
Distinguish causes and symptoms Identify viable solutions
Influencing Organization (understanding power and politics)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
16/284
Chapter 2
Project Management Context Socioeconomic Influences
Standards document approved that provides common,repeated use, rules and guidelines Compliance is not mandatory
Regulations document that identifies products,services or characteristics Compliance is mandatory
Standards often become de facto regulations Internationalization
Cultural Influences
7/27/2019 Project Management Professional (PMP) Study Guide[1]
17/284
Chapter 2
Project Management Context Organization Structure Pros and Cons
Projectized Efficient Organization No home
Loyalty Lack of Professionalism Effective Communication Duplication of functions, less
efficient resource usage
Matrix Visible Objectives not cost effective
PM Control More than 1 boss
More support More complex to control
Utilize scarce resources Tough resource allocation
Information distribution Competition of priorities
Coordination Policies & Procedures Home based Potential for conflict
7/27/2019 Project Management Professional (PMP) Study Guide[1]
18/284
Chapter 2
Project Management Context Functional Organization
Specialists More emphasis on functions
1 supervisor No career path in PM
7/27/2019 Project Management Professional (PMP) Study Guide[1]
19/284
Chapter 3
Project Management Processes Project Management requires active management of
Project Processes
Series of actions that achieve a result
Project Management Processes
Describing and organizing the work
Product-Oriented Processes
Specifying and creating the product
7/27/2019 Project Management Professional (PMP) Study Guide[1]
20/284
Chapter 3
Project Management Processes Process Groups:
Initiating processes: recognizing a project or phaseshould begin
Planning processes: devising and maintaining aworkable plan
Executing processes: coordinating resources to executethe plan
Controlling processes: ensuring project objectives aremet; monitoring, correcting and measuring progress
Closing processes: formalized acceptance
7/27/2019 Project Management Professional (PMP) Study Guide[1]
21/284
Chapter 3
Project Management Processes Process Groups are linked by the results each
produces Process Groups are overlapping activities with
various levels of intensity Process Group interactions cross phases rolling
wave planning Provides details of work to complete current phase and
provide preliminary description of work for subsequentphases
Individual processes have inputs, tools andtechniques, and outputs (deliverables)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
22/284
Chapter 3
Project Management Processes Initiating and Planning Processes Committing the organization to begin
Initiation, High-level planning, Charter
Amount of planning proportional to the scope ofthe project Core Planning Scope Planning written statement Scope Definition subdividing major deliverables into
more manageable units Activity Definition determine specific tasks needed to
produce project deliverables Activity Sequencing plotting dependencies
7/27/2019 Project Management Professional (PMP) Study Guide[1]
23/284
Chapter 3
Project Management Processes Core Planning (continued)
Activity Duration Estimating determine amount of work neededto complete the activities
Schedule Development analyze activity sequences, duration, andresource requirements
Resource Planning identify what and how many resources areneeded to perform the activities
Cost Estimating develop resource and total project costs
Cost Budgeting allocating project estimates to individual workitems
Project Plan Development taking results from other planningprocesses into a collective document
7/27/2019 Project Management Professional (PMP) Study Guide[1]
24/284
Chapter 3
Project Management Processes Planning/Facilitating Processes manage the
interaction among the planning processes Quality Planning standards that are relevant to the
project and determining how to meet standards Organizational Planning identify, document, and
assigning project roles and responsibilities
Staff Acquisition obtaining the human resources
Communications Planning determining rules andreporting methods to stakeholders
7/27/2019 Project Management Professional (PMP) Study Guide[1]
25/284
Chapter 3
Project Management Processes Planning/Facilitating Processes (continued)
Risk Identification determining what is likely to affect theproject and documenting these risks
Risk Quantification evaluating risks and interactions toaccess the possible project outcomes
Risk Response Development defining enhancement stepsand change control measures
Procurement Planning determining what to buy and when
Solicitation Planning documenting product requirementsand identifying possible sources
7/27/2019 Project Management Professional (PMP) Study Guide[1]
26/284
Chapter 3
Project Management Processes Planning/Facilitating Processes (continued)
Order of events: Scope Statement Create Project Team Work Breakdown Structure
WBS dictionary Finalize the team Network Diagram Estimate Time and Cost Critical Path Schedule Budget Procurement Plan
Quality Plan Risk Identification, quantification and response development Change Control Plan Communication Plan Management Plan Final Project Plan Project Plan Approval Kick off
7/27/2019 Project Management Professional (PMP) Study Guide[1]
27/284
Chapter 3
Project Management Processes Executing Processes
Project Plan Execution performing the activities Complete Tasks/Work Packages
Information Distribution Scope Verification acceptance of project scope Quality Assurance evaluating overall project
performance on a regular basis; meeting standards Team Development developing team and individual
skill sets to enhance the project Progress Meetings
7/27/2019 Project Management Professional (PMP) Study Guide[1]
28/284
Chapter 3
Project Management Processes Executing Processes (continued)
Information Distribution making project informationavailable in a timely manner
Solicitation obtaining quotes, bids, proposals asappropriate
Source Selection deciding on appropriate suppliers
Contract Administration managing vendor
relationships
7/27/2019 Project Management Professional (PMP) Study Guide[1]
29/284
Chapter 3
Project Management Processes Controlling Processes needed to regularly
measure project performance and to adjust projectplan
Take preventive actions in anticipation of possibleproblems Change Control coordinating changes across the entire
project plan
Scope Change Control controlling scope creep Schedule Control adjusting time and project schedule
of activities
7/27/2019 Project Management Professional (PMP) Study Guide[1]
30/284
Chapter 3
Project Management Processes Controlling Processes (continued)
Cost Control managing project budget
Quality Control monitoring standards and specific
project results; eliminating causes of unsatisfactoryperformance
Performance Reporting status, forecasting, andprogress reporting schedule
Risk Response Control responding to changes in riskduring the duration of the project
7/27/2019 Project Management Professional (PMP) Study Guide[1]
31/284
Chapter 3
Project Management Processes Closing Processes
Administrative Closure generating necessaryinformation to formally recognize phase or project
completion Contract Close-out completion and delivery of projectdeliverables and resolving open issues Procurement Audits Product Verification Formal Acceptance Lessons Learned Update Records Archive Records Release Team
7/27/2019 Project Management Professional (PMP) Study Guide[1]
32/284
Chapter 3
Project Management Processes Overall Processes
Influencing the organization
Leading
Problem Solving
Negotiating
Communicating
Meetings
7/27/2019 Project Management Professional (PMP) Study Guide[1]
33/284
Chapter 3
Project Management Processes Project Selection Techniques
Comparative Approach (similar projects)
Benefit measurement method
Constrained Optimization (mathematical approach)
Key aspect of scope verification is customer acceptance
Only 26 % of projects succeed
7/27/2019 Project Management Professional (PMP) Study Guide[1]
34/284
Chapter 4 Project Integration
Management Project Integration Management
Ensures that the project processes are properly coordinated Tradeoffs between competing objectives and alternatives in order to meet
stakeholder approval Project Plan Development
Project Plan Execution Overall Change Control
These processes may occur repeatedly over the project duration Historical Records are needed to perform project management well, they are inputs
to continuous improvement Files Lessons Learned Actual Costs Time Estimates WBS Benchmarks Risks
7/27/2019 Project Management Professional (PMP) Study Guide[1]
35/284
Chapter 4 Project Integration
Management Project Plan Development
Uses outputs from other planning processes to createconsistent document to guide project execution and
control Iterated several times
Documents planning assumptions
Documents planning decisions that are chosen
Facilitates communication Defines key management reviews
Provides a baseline to track progress measurement andproject control
7/27/2019 Project Management Professional (PMP) Study Guide[1]
36/284
Chapter 4 Project Integration
Management Project Plan Development Inputs
Other planning outputs: primarily the planning processoutputs (WBS, base documents, application area inputs)
Historical information verify assumptions, records ofpast project performance
Organizational policies quality management,personnel administration, Financial controls
Constraints factors that limit performance, contractualprovisions, budget
Assumptions risk factors
7/27/2019 Project Management Professional (PMP) Study Guide[1]
37/284
Chapter 4 Project Integration
Management Tools & Techniques for Plan Development
Project Planning Methodology any structuredapproach (software, templates, forms, start-up meetings
Stakeholder Skills & Knowledge tap into plandevelopment; use expertise for reasonableness
PMIS Out of the box approach to support all projectaspects through closure
7/27/2019 Project Management Professional (PMP) Study Guide[1]
38/284
Chapter 4 Project Integration
Management Project Plan Development Outputs
Project Plan is a collection that changes over time as moreinformation about the project becomes available
Baseline will change only in response to approved scope change
Project Plan includes some or all of the following: Project Charter
Project Management approach or strategy
Scope statement
Work Breakdown Structure (WBS)
Budget, schedule, risks Key Staff, Major Milestones
Change Control Plan, Management and Communications Plan
7/27/2019 Project Management Professional (PMP) Study Guide[1]
39/284
Chapter 4 Project Integration
Management Project Plan Components (continued)
Cost Estimates, scheduled start dates and responsibilityassignments
Performance measurement baselines Major milestones and target dates
Required Staff
Risks, constraints and assumptions
Subsidiary management plans (scope, schedule) Open Issues
Pending Decisions
7/27/2019 Project Management Professional (PMP) Study Guide[1]
40/284
Chapter 4 Project Integration
Management Supporting Details to the Project Plan
Outputs from planning processes
Technical documentation
Business requirements, specifications, and designs
Relevant standards
Additional information not previously known
7/27/2019 Project Management Professional (PMP) Study Guide[1]
41/284
Chapter 4 Project Integration
Management Project Plan Execution
Primary process for carrying out the project plan
Most costly aspect of project management
Direction of organizational resources and interfaces
7/27/2019 Project Management Professional (PMP) Study Guide[1]
42/284
Chapter 4 Project Integration
Management Project Plan Execution Inputs:
Project Plan
Supporting Detail
Organizational Policies
Corrective Action anything to bring expectedperformance in line with the project plan
7/27/2019 Project Management Professional (PMP) Study Guide[1]
43/284
Chapter 4 Project Integration
Management Tools & Techniques for Plan Execution
General Management Skills
Product Skills and Knowledge defined as part of
planning, provided by staffing Work Authorization System formal procedure for
sanctioning work to ensure completion written orverbal authorization
Status review meetings regular exchanges ofinformation
Project Management Information System
Organizational Procedures
7/27/2019 Project Management Professional (PMP) Study Guide[1]
44/284
Chapter 4 Project Integration
Management Project Plan Execution Outputs
Work results the outcome of activities performed isfed into the performance reporting process
Change Requests expand/shrink project scope, modifycosts and schedule estimates
7/27/2019 Project Management Professional (PMP) Study Guide[1]
45/284
Chapter 4 Project Integration
Management Overall Change Control
Influencing factors that create change to ensure beneficial results;ensure that change is beneficial
Determining that change has occurred
Managing actual changes as they occur Evaluate impact of change Meet with team to discuss alternatives Meet with management to present decision
Change control requires Maintaining integrity of performance measurement baselines
(project plan) Ensuring changes to scope are accurately recorded Coordinating changes across knowledge areas (scheduling, risk,
cost, quality, etc.) Determine all factors that control change and pro-actively
preventing the occurrence; evaluate the impact of change
7/27/2019 Project Management Professional (PMP) Study Guide[1]
46/284
Chapter 4 Project Integration
Management Inputs to Change Control
Project Plan baseline performance
Performance Reports issue tracking, risk management
Change Requests orally or written, externally orinternally initiates, legally mandated or optional
7/27/2019 Project Management Professional (PMP) Study Guide[1]
47/284
Chapter 4 Project Integration
Management Change Control Tools & Techniques
All Changes must be evaluated before a decision can bereached
Change Control System collection of formalprocedures, paperwork, tracking systems, approvallevels
Change Control Board decision making authority
Configuration Management documented procedure toapply technical and administrative direction ID and document functional and physical characteristics
Control changes to these characteristics
Record and report change and implementation status
Audit items and system to verify requirements
7/27/2019 Project Management Professional (PMP) Study Guide[1]
48/284
Chapter 4 Project Integration
Management Change Control Tools & Techniques
Performance Measurement earned value, plan varianceanalysis
Additional Planning revised cost estimates, modifyactivity sequences, plan adjustments Project Management Information System Change Control System may have
Change Control Plan
Change Control Board Change Control Procedures, Corrective Action plans Performance Statistics, Reports, Change forms Specification reviews, Demonstrations, Testing, Meetings
Configuration Management
7/27/2019 Project Management Professional (PMP) Study Guide[1]
49/284
Chapter 4 Project Integration
Management Change Control Outputs
Project Plan Updates
Corrective Actions
Lessons Learned variance causes and reasoningdocumented for historical purposes
7/27/2019 Project Management Professional (PMP) Study Guide[1]
50/284
Chapter 4 Project Integration
Management Configuration Management
Rigorous Change Management as it relates to scope Subset of the change control system
Work Authorization System
Controls gold plating; defines what task is/is not
Meetings
Most are inefficient; keep minutes Status can be determined without meeting
7/27/2019 Project Management Professional (PMP) Study Guide[1]
51/284
Chapter 4 Project Integration
Management Lessons Learned
Project is not complete until a Lessons Learned iscompleted
What have we done, how can we do it better Technical Aspects of the project
Project Management (WBS, plans, etc.)
Overall Management (communications, leadership)
Best to have whole team complete and made available Also called Post Mortem
7/27/2019 Project Management Professional (PMP) Study Guide[1]
52/284
Chapter 4 Project Integration
Management Integration is a result of need for communication
within a project
Primary responsibility to decide what changes arenecessary is Management
Project Managers must pro-actively define and solveproblems before reporting to superiors
7/27/2019 Project Management Professional (PMP) Study Guide[1]
53/284
Chapter 5
Project Scope Management Project Scope Management
Processes required to ensure that the project includesall, and only, work required
Defining what is/is not included in the project
Project scope work that must be done measuredagainst project plan
Product scope features and functions included in theproduct or service measured against requirements
7/27/2019 Project Management Professional (PMP) Study Guide[1]
54/284
Chapter 5
Project Scope Management Initiation process of formally recognizing that a
new project exists, or an existing project continueto next phase
Involves feasibility study, preliminary plan, orequivalent analysis
Authorized as a result of: Market Demand
Business Need
Customer Request
Technological Advance
Legal Requirement
7/27/2019 Project Management Professional (PMP) Study Guide[1]
55/284
Chapter 5
Project Scope Management Initiation Inputs:
Product Description characteristics of theproduct/service that the project was to create Less detail in early phases, more comprehensive in latter
Relationship between product/service and business need
Should support later project planning
Initial product description is usually provided by the buyer
Strategic Plan supportive of the organization's goals
7/27/2019 Project Management Professional (PMP) Study Guide[1]
56/284
Chapter 5
Project Scope Management Initiation Inputs (continued)
Project Selection Criteria defined in terms of theproduct and covers range of management concerns
(finance, market) Historical Information results of previous project
decisions and performance should be considered
7/27/2019 Project Management Professional (PMP) Study Guide[1]
57/284
Chapter 5
Project Scope Management Tools & Techniques for Initiation
Project Selection Methods: Benefit measurement models comparative approaches, scoring
models, economic models Murder Boards
Peer Review
Scoring Models
Economic Models
Benefits compared to costs
Constrained operation models programming mathematical Linear Programming
Integer Programming
Dynamic Programming
Multi-objective programming
7/27/2019 Project Management Professional (PMP) Study Guide[1]
58/284
Chapter 5
Project Scope Management Tools & Techniques for Initiation
Project Selection Methods: Decision models generalized and sophisticated techniques
Expert judgment Business Units with specialized skills
Consultant
Professional and Technical Associations
Industry Groups
Delphi Technique obtain expert opinions on technical issues,scope of work and risks Keep experts identities anonymous
Build consensus
7/27/2019 Project Management Professional (PMP) Study Guide[1]
59/284
Chapter 5
Project Scope Management Outputs from Initiation:
Project Charter formally recognizes project, created bysenior manager, includes: Business need/Business Case Product description & title Signed contract Project Manager Identification & Authority level Senior Management approval Projects Goals and Objectives - Constraints factors that limit project management teams
options Assumptions factors that are considered true for planning
purposes. Involve a degree of risk
7/27/2019 Project Management Professional (PMP) Study Guide[1]
60/284
Chapter 5
Project Scope Management Scope Planning process of developing a written
statement as basis for future decisions
Criteria to determine if the project or phase is successful
Scope Planning Inputs:
Product description
Project Charter
Constraints Assumptions
7/27/2019 Project Management Professional (PMP) Study Guide[1]
61/284
Chapter 5
Project Scope Management Scope Planning Tools & Techniques
Product Analysis - - developing a better understandingof the product of the project
Cost/Benefit Analysis estimating tangible/intangiblecosts and returns of various project alternatives andusing financial measures (R.O.I.) to assess desirability
Alternatives Identification generate different
approaches to the project; brainstorming Expert Judgment
7/27/2019 Project Management Professional (PMP) Study Guide[1]
62/284
Chapter 5
Project Scope Management Scope Planning Outputs
Scope Statement documented basis for making projectdecisions and confirming understanding among
stakeholders. Includes: Project justification business need, evaluating future trade-offs
Project Product summary of project description
Project Deliverables list of summary of delivery items markingcompletion of the project
Project Objectives quantifiable criteria met for success.Addresses cost, schedule and metrics unqualified objectivesindicate high risk (customer satisfaction)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
63/284
Chapter 5
Project Scope Management Scope Planning Outputs (continued)
Supporting detail includes documentation of allassumptions and constraints
Scope Management Plan how project scope ismanaged, change control procedure, expected stability,change identification and classification Control what is/is not in the project; prevents delivering
extra benefits to the customer that were not
specified/required
7/27/2019 Project Management Professional (PMP) Study Guide[1]
64/284
Chapter 5
Project Scope Management Scope Definition subdividing major deliverables
into smaller, manageable components Improve accuracy of cost, time, and resource estimates
Define a baseline for performance measurement Clear responsibility assignments Critical to project success reduces risk of higher cost,
redundancy, time delays, and poor productivity Defines what you are doing; WBS is the tool
7/27/2019 Project Management Professional (PMP) Study Guide[1]
65/284
Chapter 5
Project Scope Management Scope Definition Inputs:
Scope Statement
Constraints consider contractual provisions
Assumptions
Other Planning Outputs
Historical Information
7/27/2019 Project Management Professional (PMP) Study Guide[1]
66/284
Chapter 5
Project Scope Management Scope Definition Tools & Techniques
Work Breakdown Structure templates from previousprojects
Decomposition subdividing major deliverables intomanageable components: Major elements project deliverables and project management
approach
Decide cost and duration estimates are appropriate at level of
detail Constituent elements tangible verifiable results to enable
performance management, how the work will be accomplished
Verify correctness of decomposition All items necessary and sufficient?
Clearly and completely defined?
Appropriately scheduled, budgeted, assigned?
7/27/2019 Project Management Professional (PMP) Study Guide[1]
67/284
Chapter 5
Project Scope Management Scope Definition Outputs
Work Breakdown Structure (WBS) a deliverable-oriented grouping of project assignments that organizes
and defines the scope of the project Each descending level represents further detail; smaller and more
manageable pieces
Each item is assigned a unique identifier collectively known ascode of accounts
Work element descriptions included in a WBS dictionary (work,schedule and planning information)
Other formats: Contractual WBS seller provides the buyer
Organizational (OBS) work elements to specific org. units
Resource (RBS) work elements to individuals
Bill of Materials (BOM) hierarchical view of physical resources
7/27/2019 Project Management Professional (PMP) Study Guide[1]
68/284
Chapter 5
Project Scope Management Scope Definition Outputs
Work Breakdown Structure (WBS) First Level is commonly the same at the Project Life Cycle (requirements,
design, coding, testing, conversion and operation)
First level is completed before the project is broken down further
Each level of the WBS is a smaller segment of level above
Work toward the project deliverables
Break down project into tasks that Are realistically and confidently estimable
Cannot be logically divided further Can be completed quickly (under 80 hours rule of thumb)
Have a meaningful conclusion and deliverable
Can be completed without interruption
Provides foundation for all project planning and control
7/27/2019 Project Management Professional (PMP) Study Guide[1]
69/284
Chapter 5
Project Scope Management Scope Definition Outputs
Work Breakdown Structure (WBS) - Benefits Prevent work slippage
Project team understands how their tasks fit into the overall project andtheir impact upon the project
Facilitates communication and cooperation between project team andstakeholders
Helps prevent changes
Focuses team experience into what needs to be done results in higher
quality Basis and proof for estimating staff, cost and time
Gets team buy-in, role identification
Graphical picture of the project hierarchy
Identifies all tasks, project foundation
7/27/2019 Project Management Professional (PMP) Study Guide[1]
70/284
Chapter 5
Project Scope Management WBS phrases
Graphical hierarchy of the project
Identifies all tasks
Foundation of the project
Very important
Forces thought of all aspects of the project
Can be re-used for other projects
7/27/2019 Project Management Professional (PMP) Study Guide[1]
71/284
Chapter 5
Project Scope Management Scope Definition Outputs
Work Breakdown Structure (WBS) Dictionary Designed to control what work is done and when
Also known as a task description Puts boundary on what is included in a task and what is not included
7/27/2019 Project Management Professional (PMP) Study Guide[1]
72/284
Chapter 5
Project Scope Management Scope Verification Inputs
Work results partially/completed deliverables, costs todate
Product documentation description available forreview (requirements)
Scope Verification Tools & Techniques Inspection measuring, examining, testing to
determine if results conform to requirements Scope Verification Outputs
Formal acceptance documentation identifying clientand stakeholder approval, customer acceptance ofefforts
7/27/2019 Project Management Professional (PMP) Study Guide[1]
73/284
Chapter 5
Project Scope Management Scope Change Control:
Influencing factors to ensure that changes are beneficial
Determining scope change has occurred
Managing changes when they occur
Thoroughly integrated with other control processes
7/27/2019 Project Management Professional (PMP) Study Guide[1]
74/284
Chapter 5
Project Scope Management Scope Change Control Inputs:
Work Breakdown Structure
Performance Reports- issues reported
Change Requests expansion/shrink of scope derivedfrom : External events (government regulations)
Scope definition errors of product or project
Value adding change new technology
Scope Management Plan
7/27/2019 Project Management Professional (PMP) Study Guide[1]
75/284
Chapter 5
Project Scope Management Scope Change Control Tools & Techniques
Scope Change Control System defines procedures howscope change can occur All paperwork, tracking systems, approval levels Integrated with overall change control procedures
Performance Measurement determine what is causingvariances and corrective actions
Additional Planning
7/27/2019 Project Management Professional (PMP) Study Guide[1]
76/284
Chapter 5
Project Scope Management Scope Change Control Outputs:
Scope Changes fed back through planning processes,revised WBS
Corrective Actions Lessons Learned cause and reasoning for variances
documented for historical purposes
7/27/2019 Project Management Professional (PMP) Study Guide[1]
77/284
Chapter 5
Project Scope Management Management By Objectives (MBO)
Philosophy that has 3 steps:
Establish unambiguous and realistic objectives
Periodically evaluate if objectives are being met Take corrective action
Project Manager must know that if project is not aligned orsupport corporate objectives, the project is likely to loseresources, assistance and attention.
MBO only works if management supports it
7/27/2019 Project Management Professional (PMP) Study Guide[1]
78/284
Chapter 6
Project Time Management Project Time Management
Processes required to ensure timely completion of theproject
No consensus concerning differences between activitiesand tasks
Activities seen as composed of tasks most commonusage
Other disciplines have tasks composed of activities
7/27/2019 Project Management Professional (PMP) Study Guide[1]
79/284
Chapter 6
Project Time ManagementActivity Definition: identifying and documenting
specific activities to produce project deliverablesidentified in the WBS
Must be defined to meet the project objectives
7/27/2019 Project Management Professional (PMP) Study Guide[1]
80/284
Chapter 6
Project Time ManagementActivity Definition Inputs
WBS primary input
Scope Statement project justification & project
objectives Historical Information
Constraints
Assumptions
7/27/2019 Project Management Professional (PMP) Study Guide[1]
81/284
Chapter 6
Project Time ManagementActivity Definition Tools & Techniques
Decomposition outputs are expressed as activitiesrather than deliverables
Templates reuse from previous projects
7/27/2019 Project Management Professional (PMP) Study Guide[1]
82/284
Chapter 6
Project Time ManagementActivity Definition Outputs
Activity List all to be performed; extension to the WBSand includes description to ensure team members
understand work to be performed Supporting Detail organized as needed and include all
assumptions and constraints
WBS Updates identify missing deliverables and clarify
deliverable descriptions. WBS updates often calledrefinements; more likely using new technologies inproject
7/27/2019 Project Management Professional (PMP) Study Guide[1]
83/284
Chapter 6
Project Time ManagementActivity Sequencing identifying and documenting
interactive dependencies among activities. Supportlater development of a realistic schedule
Project Management software often used
7/27/2019 Project Management Professional (PMP) Study Guide[1]
84/284
Chapter 6
Project Time ManagementActivity Sequencing Inputs:
Activity List
Product Description product characteristics often affect activitysequencing
Mandatory Sequencing physical limitations, hard logic,prototypes needed; inherent in nature of work being done
Discretionary Dependencies defined by project managementteam; best practices or unusual aspects of project soft logic,preferred logic, preferential logic
External Dependencies relationship between project activities andnon-project activities (company policies, procurement, etc.)
Constraints
Assumptions
7/27/2019 Project Management Professional (PMP) Study Guide[1]
85/284
Chapter 6
Project Time Management Network Diagrams
Shows how the project tasks will f low from beginning to end
Proves how long the project will take to complete
Takes project tasks from low levels of WBS and placing them intotheir order of completion (beginning to end)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
86/284
Chapter 6
Project Time ManagementActivity Sequencing Tools & Techniques
Precedence Diagramming Method (PDM) constructing network diagram using nodes to represent
activities and arrows to indicate dependencies; alsocalled Activity On Node (AON)
Most project management software uses
Includes 4 types of dependencies: Finish to Start from activity must finish before to activity can begin; most
commonly used Finish to Finish from activity must finish before the next may finish
Start to Start from activity must start before next to activity can start
Start to Finish task must start before next activity can finish
Use caution with last 3 techniques - logical relationships often notconsistently implemented with project management software
7/27/2019 Project Management Professional (PMP) Study Guide[1]
87/284
Chapter 6
Project Time ManagementActivity Sequencing Tools & Techniques (continued)
Arrow Diagramming Method (ADM) uses arrows torepresent activities and connecting at nodes to illustrate
dependencies Also called Activity On Arrow (AOA)
Only uses finish to start dependencies
PERT and CPM only can be drawn using AOA
7/27/2019 Project Management Professional (PMP) Study Guide[1]
88/284
Chapter 6
Project Time ManagementActivity Sequencing Tools & Techniques (continued)
Conditional diagramming methods
GERT (Graphical Evaluation and Review Technique)
System Dynamic Models Allow for non-sequential activities (loops) or conditional
branches not provided by PDM or ADM methods
7/27/2019 Project Management Professional (PMP) Study Guide[1]
89/284
Chapter 6
Project Time ManagementActivity Sequencing Tools & Techniques (continued)
Network Templates standardized networks can beused. Composed of subnets, or fragnets
Subnets are several nearly identical portions of a network(floors on a building, clinical trials, program modules)
Useful for several identical processes (clinical trials,programming modules).
7/27/2019 Project Management Professional (PMP) Study Guide[1]
90/284
Chapter 6
Project Time ManagementActivity Sequencing Outputs:
Project Network Diagram schematic display of projectactivities and relationships (dependencies). Should be
accompanied by a summary narrative that describes thediagram approach
Activity List Updates
7/27/2019 Project Management Professional (PMP) Study Guide[1]
91/284
Chapter 6
Project Time ManagementActivity Duration Estimating
Involves assessing number of work periods needed tocomplete identified activities
Requires consideration of elapsed time, calendars,weekends, and day of week work starts
7/27/2019 Project Management Professional (PMP) Study Guide[1]
92/284
Chapter 6
Project Time ManagementActivity Duration Estimating Inputs:
Activity Lists
Constraints
Assumptions Resource Requirements amount of labor assigned to
activity
Resource Capabilities human and material resources,
expertise Historical Information
Project Files, or records of previous project results
Commercial Duration Estimates useful when durations are notdriven by actual work (approval periods, material resources)
Project Team Knowledge
7/27/2019 Project Management Professional (PMP) Study Guide[1]
93/284
Chapter 6
Project Time ManagementActivity Duration Estimating Tools & Techniques
Expert Judgment guided by historical informationshould be used whenever possible; high risk without
expertise avail. Simulation using different sets of assumptions (Monte
Carlo Analysis) to drive multiple durations
Analogous Estimating top down estimating useactual, similar, previous known durations as basis for
future activity duration. Used when limited knowledgeis available. Form of expert judgment
7/27/2019 Project Management Professional (PMP) Study Guide[1]
94/284
Chapter 6
Project Time ManagementActivity Duration Outputs:
Activity Duration Estimates quantitative assessmentsof work periods to complete an activity. Should indicate
a range +/- of possible results Basis of Estimates all assumptions should be
documented
Activity List Updates
7/27/2019 Project Management Professional (PMP) Study Guide[1]
95/284
Chapter 6
Project Time Management Schedule Development
Determining start and finish dates for project activities
Without realistic dates, project unlikely to be finished as
scheduled Schedule development process often iterates as more
information becomes available (process inputs)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
96/284
Chapter 6
Project Time Management Schedule Development Inputs:
Project Network Diagram
Activity Duration Estimates
Resource Requirements
Resource Pool Description availability patterns; sharedresources are highly variable
Calendars define eligible work periods Project Calendars affect all resources
Resource Calendars affect specific resource pools or individuals
7/27/2019 Project Management Professional (PMP) Study Guide[1]
97/284
Chapter 6
Project Time Management Schedule Development Inputs (continued):
Constraints Imposed Dates may be required
Key events or milestones are initially requested and becomeexpected during project
Assumptions
Lead and Lag Time dependencies may specify time in
order to satisfy relationship (example 2 weeks toreceive order)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
98/284
Chapter 6
Project Time Management Schedule Development Tools & Techniques
Mathematical Analysis calculating theoreticalearly/late finish and start dates without regard for
resource pool limitations; indicate time periods whichactivity should be scheduled given resource limits andother constraints: Critical Path Method (CPM) single early/late start and finish date for all
activities. Based on specified, sequential network and single duration estimate.Calculates float to determine flexibility
Graphical Evaluation and Review Technique (GERT) probabilistic treatment ofnetwork and activity duration estimates
Program Evaluation and Review Technique (PERT)- sequential network andweighted average duration to calculate project duration differs from CPM byusing mean (expected value) instead of most-likely estimate in CPM
7/27/2019 Project Management Professional (PMP) Study Guide[1]
99/284
Chapter 6
Project Time Management Schedule Development Tools & Techniques
Critical Path Method: refers to estimating based on one timeestimate per activity One time estimate per task (Most Likely)
Emphasis on controlling cost and leaving schedule flexible Drawn using AOA diagrams
Can have dummy task
PERT (Program Review and Estimating Technique) 3 Time estimates per activity
Optimistic Pessimistic
Most Likely
Emphasis on meeting schedule, flexibility with costs
Drawn on AOA diagrams
Can have dummy tasks
7/27/2019 Project Management Professional (PMP) Study Guide[1]
100/284
Chapter 6 Project Time Management
Schedule Development Tools & Techniques Monte Carlo Analysis
Uses a computer with PERT values and network diagram
Tells Probability of completing a project on any specific day
Probability of completing a project for any specific amount of cost
Probability of any task actually being on the critical path
Overall Project Risk
Suggests that Monte Carlo simulation will create a projectduration that is closer to reality than CPM or PERT
7/27/2019 Project Management Professional (PMP) Study Guide[1]
101/284
Chapter 6 Project Time Management
Schedule Development Tools & Techniques(continued)
Duration Compression look to shorten project
schedule without affecting scope Crashing cost and schedule trade-offs to determine greatest
amount of compression for least incremental cost often resultsin higher costs
Fast Tracking performing activities in parallel that normallywould be sequenced often results in re-work and usuallyincreases risk
Simulation
7/27/2019 Project Management Professional (PMP) Study Guide[1]
102/284
Chapter 6 Project Time Management
Schedule Development Tools & Techniques(continued)
Resource Leveling Heuristics leveling resources that
apply to critical path activities a.k.a. resourceconstrained scheduling when limitation on quantityof available resources; sometimes called ResourceBased Method often increases project duration
Project Management Software
7/27/2019 Project Management Professional (PMP) Study Guide[1]
103/284
Chapter 6 Project Time Management Schedule Development Tools & Techniques (continued)
Project Mangers role Provide the team with the necessary information to properly estimate
the task
Complete a sanity check of the estimate Formulate a reserve
Project Team should be involved; determine task estimates Historical Records
Guesses
Actual Costs Benchmarks
CPM and PERT
7/27/2019 Project Management Professional (PMP) Study Guide[1]
104/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
105/284
Chapter 6 Project Time Management Schedule Development Outputs:
Project Schedule includes planned start and finishdates for each activity; remains preliminary untilresources assignments are approved. Usually in
following formats: Project Network Diagrams (with date information added) show
logical and critical path activities Bar or Gantt charts activity start and end dates, expected
durations Milestone Charts identifies key deliverables and interfaces Time-scaled network diagrams blend of project network and
bar charts
7/27/2019 Project Management Professional (PMP) Study Guide[1]
106/284
Chapter 6 Project Time Management
Schedule Development Outputs (continued): Supporting Detail all assumptions and constraints.
May also include:
Resource requirement by time period (resource histogram) Alternative schedules (best/worst case)
Schedule reserve/risk assessments
Schedule Management Plan how updates are managed
Resource requirement updates leveling and activity
impact
7/27/2019 Project Management Professional (PMP) Study Guide[1]
107/284
Chapter 6 Project Time Management
Schedule Control: Influencing factors which create schedule changes to
ensure changes are beneficial
Determining that schedule has changed Managing actual changes as they occur
Inputs to Schedule Control Project Schedule baseline approved, measure against
project performance Performance Reports planned dates met, issues
Change Requests
Schedule Management Plan
7/27/2019 Project Management Professional (PMP) Study Guide[1]
108/284
Chapter 6 Project Time Management Schedule Control Tools & Techniques
Schedule Change Control System defines proceduresfor schedule changes, paperwork, approval, trackingsystems
Performance Measurement assess magnitude ofvariations to baseline; determine if corrective action isneeded
Additional Planning
Project Management Software
7/27/2019 Project Management Professional (PMP) Study Guide[1]
109/284
Chapter 6 Project Time Management Schedule Control Outputs:
Schedule Updates any modifications, stakeholdernotification Revisions change scheduled start and finish dates generally
in response to scope changes. Re-baselining may be neededin drastic situations
Corrective Action re-align performance with projectplan
Lessons Learned
7/27/2019 Project Management Professional (PMP) Study Guide[1]
110/284
Chapter 6 Project Time Management Key knowledge points not in PMBOK
Need to know manual calculations of network diagrams Created after project charter and WBS (task estimates and
dependencies are determined) Mandatory dependencies (Hard Logic) inherent in nature of
work
Discretionary dependencies (Soft Logic) based onexperience, desire or results
External dependencies based on needs and desires of
organizations outside the project
7/27/2019 Project Management Professional (PMP) Study Guide[1]
111/284
Chapter 6 Project Time Management
Methods to draw network diagrams
Activity on Node (AON) or Precedence DiagrammingMethod (PDM)
Boxes represent tasks Arrows show task dependencies
4 types of task relationships
Finish to Start (task must finish before next can start)
Finish to Finish (task must finish before next can finish)
Start to Start (task must start before next can start)
Start to Finish (task must start before the next can finish)
No dummy tasks used
7/27/2019 Project Management Professional (PMP) Study Guide[1]
112/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
113/284
Chapter 6 Project Time Management
Methods to draw network diagrams
Activity on Arrow (AOA or Arrow Diagramming Method(ADM) continued:
PERT (Program Evaluation and Review technique) 3 time estimates per activity: Optimistic (O), Most Likely (M),
Pessimistic (P)
Emphasizes meeting schedule, flexibility with cost
Can have dummy tasks
7/27/2019 Project Management Professional (PMP) Study Guide[1]
114/284
Chapter 6 Project Time Management Methods to draw network diagrams
PERT (Program Evaluation and Review technique) Estimating based on 3 formulas:
PERT Duration: (P + 4M + O)/6 Standard Task Deviation: (P O)/6 Task Variance:
Total project estimate: Add up all Optimistic, Most Likely and Pessimistic values of the critical path
tasks and apply P + 4M + O/6
Total project variance (+/-): Add up the individual task variances and take the square root of the value. Use
the value as a +/- figure to compute the Optimistic and Pessimistic values. Thetotal project estimate will serve as the basis.
[PO]26
7/27/2019 Project Management Professional (PMP) Study Guide[1]
115/284
Chapter 6 Project Time Management
Monte Carlo Simulation:
Uses a computer with PERT values (P, M, O) and anetwork diagram but does not use the PERT formula
Indicates Probability of completing project on a specific day
Probability of completing project for any specific amount of cost
Probability of any task actually being on critical path
Overall project risk
7/27/2019 Project Management Professional (PMP) Study Guide[1]
116/284
Chapter 6 Project Time Management
Estimating techniques in general:
Should be performed by entire project team Project manager needs to provide information to allow team to
create estimates; sanity check; formulate reserve Estimates are:
Guesses, Historical Records, Actual Costs, Benchmarks, CPM,PERT
Critical paths determines the earliest completion date and identifies
tasks that need monitoring Can be obtained by CPM, PERT and Monte Carlo estimating
techniques
7/27/2019 Project Management Professional (PMP) Study Guide[1]
117/284
Chapter 6 Project Time Management
Key Definitions: Slack (Float): the amount of time a task can be delayed
without delaying the entire project. Tasks on criticalpath have no slack. Slack is calculated by the difference between Early Start and Late
Start of a task Free Slack (Float): the amount of time a task can be delayed without
delaying the early start date of its successor
Total Slack (Float): the amount of time a task can be delayed without
delaying the project completion date Lag: inserted waiting time between tasks
7/27/2019 Project Management Professional (PMP) Study Guide[1]
118/284
Chapter 6 Project Time Management General Comments:
Projects can have more than 1 critical path (increases risk) and caninvolve dummy tasks
Negative float indicates that you are behind Resource Leveling involves possibly letting schedule and cost slip Heuristics just means rule of thumb e.g. 80/20 rule Schedules are calendar based makes this different than a time
estimate Bar Chart a.k.a. Gantt chart (track progress, report to entire team
including stakeholders, control tool)
Network Diagram (to show task inter-dependencies, show projectorganization, basis for project control) Milestone chart (report to Senior management, shows major events)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
119/284
Chapter 6 Project Time Management General Comments:
To shorten project schedule examine the critical path Crashing add more resources to the critical path tasks
Usually results in increased cost Fast Tracking performing tasks in parallel
Can result in re-work and increased risk
Best to select method that has least impact on theproject (is the importance on cost, risk or schedule?)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
120/284
Chapter 6 Project Time Management General Comments:
Bar (Gantt) Charts Weak Planning Tool, effective progress and reporting tool Does not show interdependencies of tasks Does not help organize the project more effectively
Network Diagrams (PERT, CPM, PDM) Shows task interdependencies Aids in effectively planning and organizing work Provides a basis for project control
Milestone Charts Only shows major events Good for reporting to management and customer
Flow Charts Depicts workflow and not commonly used for project management
7/27/2019 Project Management Professional (PMP) Study Guide[1]
121/284
Chapter 6 Project Time Management General Comments:
Free Slack (Float) amount of time a task can be delayed without delaying the earlystart date of its successor
Total Slack (Float) amount of time a task can be delayed without delaying theproject completion date
Lag inserted waiting time between tasks Resource Leveling level peaks of resource usage; stable number of resources
allows schedule and cost slip in favor of leveling resources Heuristic rule of thumb (80/20 rule)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
122/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
123/284
Chapter 7 Project Cost Management Project Cost Management
Estimating should be based on WBS to improve accuracy
Estimating should be done by the person performing the work
Having historical records is key to improving estimates
Costs (schedule, scope, resources) should be managed to estimates A cost (schedule, scope, baseline) should be kept and not changed
Plans should be revised as necessary during completion of work
Corrective action should be taken when cost problems (schedule,scope and resources) occur.
7/27/2019 Project Management Professional (PMP) Study Guide[1]
124/284
Chapter 7 Project Cost Management
Resource Planning: Determining what physical resources and quantities are
needed to perform work
Inputs to Resource Planning: Work Breakdown Structure
Historical Information
Scope Statement justification & objectives
Resource Pool Description what resources arepotentially available for resource planning
Organizational Policies staffing, procurement
7/27/2019 Project Management Professional (PMP) Study Guide[1]
125/284
Chapter 7 Project Cost Management
Inputs to Resource Planning: Work Breakdown Structure
Network Diagram
Schedule Risks
Historical Information
Scope Statement justification & objectives
Resource Pool Description what resources arepotentially available for resource planning
Organizational Policies staffing, procurement
7/27/2019 Project Management Professional (PMP) Study Guide[1]
126/284
Chapter 7 Project Cost Management
Resource Planning Tools & Techniques
Expert Judgment
Alternatives Identification
Resource Planning Outputs: Resource Requirements what type & how many
resources are needed for each activity in the WorkBreakdown Structure
7/27/2019 Project Management Professional (PMP) Study Guide[1]
127/284
Chapter 7 Project Cost Management
Cost Estimating:
Develop approximate costs of resources
Distinguish estimating from pricing
Estimating likely amount Pricing business decision
Identify alternatives and consider realigning costs inphases to their expected savings
7/27/2019 Project Management Professional (PMP) Study Guide[1]
128/284
Chapter 7 Project Cost Management
Cost Estimating Inputs:
Work Breakdown Structure
Resource Requirements
Resource Rates (if known) Activity Duration Estimates
Historical Information (project files, commercial costdatabases, team knowledge
Chart Of Accounts coding structure for accounting;general ledger reporting
7/27/2019 Project Management Professional (PMP) Study Guide[1]
129/284
Chapter 7 Project Cost Management
Cost Estimating Tools & Techniques Analogous Estimating top down; using actual costs
from previous project as basis for estimate Reliable when previous projects are similar and individuals have
expertise form of expert judgment
Parametric Modeling uses project characteristics inmathematical models to predict costs (e.g.buildinghouses)
Reliable when historical information is accurate, parameters arequantifiable, and model is scalable 2 types: Regression analysis, Learning Curve
Bottom Up Estimating rolling up individual activitiesinto project total smaller work activities have more
accuracy -
7/27/2019 Project Management Professional (PMP) Study Guide[1]
130/284
Chapter 7 Project Cost Management
Cost Estimating Tools & Techniques Pros and Cons
Analogous Estimating
Quick - Less Accurate Tasks dont need to be identified Estimates prepared with little
detail and understanding of project
Less costly Requires considerable experience to do well
Gives PM idea of management expectations Infighting at highlevels of organization
Overall project costs are capped Difficult for projects withuncertainty
7/27/2019 Project Management Professional (PMP) Study Guide[1]
131/284
Chapter 7 Project Cost Management
Cost Estimating Tools & Techniques Pros and Cons
Bottom Up Estimating
More Accurate Takes time and expense Gains buy-in from the team Tendency for team to pad estimates
Based on detailed analysis of project Requires that project bedefined and understood
Provides a basis for monitoring and control Team infighting toget biggest piece of pie
7/27/2019 Project Management Professional (PMP) Study Guide[1]
132/284
Chapter 7 Project Cost Management Outputs from Cost Estimating
Cost estimates quantitative assessments of likely costs of resourcesrequired to complete tasks For all resources of the project (labor, materials, supplies, inflation allowance,
reserve) Expressed in units of currency
Supporting Detail Description of scope (reference to the WBS) Documentation how estimate was developed Indication of range of possible results Assumptions
Cost Management Plan how cost variances will be managed
Cost Risk: associated to seller for Fixed Price; associated to buyer for Timeand Materials budget
7/27/2019 Project Management Professional (PMP) Study Guide[1]
133/284
Chapter 7 Project Cost Management
Cost Budgeting Involves allocation of total estimate to individual work
to establish a cost baseline to measure performance
Cost Budgeting Inputs Cost Estimate
Work Breakdown Structure
Project Schedule includes planned start and finish
dates for items costs are allocated to Needed to assign costs during the time period when the actual
cost will be incurred
7/27/2019 Project Management Professional (PMP) Study Guide[1]
134/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
135/284
Chapter 7 Project Cost Management Cost Control
Concerned with influencing factors that create changes to the costbaseline that are beneficial
Determining that the cost baseline has changed
Managing actual changes as they occur Monitor cost performance to detect variances
Record all appropriate changes accurately in the cost baseline
Preventing incorrect, unauthorized changes being included in the costbaseline
Informing stakeholders of authorized changes Determine the whys of positive and negative variances
Integrated will all other control processes (scope, change, schedule, quality)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
136/284
Chapter 7 Project Cost Management Inputs to Cost Control
Cost Baseline Performance Reports meet, exceed budget
50/50 Rule task is considered 50% complete when it begins and gets credit for remainder50% only when completed
20/80 Rule - task is considered 20% complete when it begins and gets credit for remainder80% only when completed
0/100 Rule task only credited when fully completed
Change Requests Cost Management Plan
Tools & Techniques of Cost Control Cost Change Control System defines the procedures by which the cost baseline may
be changed
Performance Measurement assess magnitude of cost variations (Earned ValueAnalysis) and what is causing the variance Additional Planning examine alternatives Computerized Tools forecast planned costs, track actual costs, forecast effect of
cost changes
7/27/2019 Project Management Professional (PMP) Study Guide[1]
137/284
Chapter 7 Project Cost Management Cost Control Outputs
Revised Cost Estimate Modifications to cost information; require stakeholder approval and adjustments
to other project areas
Budget Updates changes to approved cost baseline; revised in response toscope changes
Corrective Action Estimate at completion (EAC) forecast of total expenditures
Actual to date plus remaining budget modified by a factor (cost performanceindex) Current variances are seen to apply to future variances
Actual to date plus new estimate for remaining work
Original estimates are flawed, or no longer relevant Actual to date plus remaining budget
Current variances are typical and similar variances will not occur in the future
Lessons Learned
7/27/2019 Project Management Professional (PMP) Study Guide[1]
138/284
Chapter 7 Project Cost Management
Earned Value Analysis Integrates cost, schedule and scope
Better that comparing projected vs. actual because time
and cost are analyzed separately Terms:
BCWS Budgeted Cost of Work Scheduled (how much workshould be done)
BCWP Budgeted Cost of Work Performed a.k.a. Earned Value
(how much work is budgeted, how much did we budget) ACWP Actual Cost of Work Performed (how much did the
completed work cost)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
139/284
Chapter 7 Project Cost Management Earned Value Analysis
Terms: BAC Budget at Completion (how much did you budget for
the total job)
EAC Estimate at Completion (what do we expect the totalproject to cost)
ETC Estimate to Completion (how much more do we expectto spend to finish the job)
VAC Variance at Completion (how much over/under budget
do we expect to be)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
140/284
Chapter 7 Project Cost Management Earned Value Analysis
Formulas Variance (Plan Actual)
Cost Variance (CV): BCWP ACWP; negative is over budget
Schedule Variance (SV): BCWP BCWS; negative is behindschedule
Cost Performance Index (CPI): BCWP
ACWP
I am only getting x out of every $ BCWPACWP
7/27/2019 Project Management Professional (PMP) Study Guide[1]
141/284
Chapter 7 Project Cost Management Earned Value Analysis
Formulas Schedule Performance Index (SPI): BCWP
BCWS
I am only progressing x % of the planned rate
Estimate at Completion (EAC): BACCPI
As of now we expect the total project to cost x$
Estimate to Complete (ETC): EAC ACWP; how much will it costfrom now to completion
Variance at Completion: BAC EAC; when the project is over howmuch more or less did we spend (most common way ofcalculating EVA
BCWP
BCWS
BAC
CPI
7/27/2019 Project Management Professional (PMP) Study Guide[1]
142/284
Chapter 7 Project Cost Management
Earned Value Analysis
BCWP comes first in most formulas
If it is a variance, BCWP comes first
If it is an index, BCWP is divided by If the formula relates to cost, use AWCP
If the formula related to schedule, use BWCP
Negative is bad; positive results are good
ETC refers to this point on; EAC refers to when job iscompleted
7/27/2019 Project Management Professional (PMP) Study Guide[1]
143/284
Chapter 7 Project Cost Management
Accuracy of Estimates
Order of Magnitude Estimate: -25% - 75%; usually madeduring Initiation Phase
Budget Estimate: -10% - 25%; usually made during thePlanning phase
Definitive Estimate: -5% - 10%; usually made during thePlanning phase
7/27/2019 Project Management Professional (PMP) Study Guide[1]
144/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
145/284
Chapter 7 Project Cost Management Accounting Standards
Net Present Value: total benefits (income or revenue) less the costs.NPV is the sum of each present value of each income/revenue item
Internal Rate of Return (IRR): company may select project based onhighest IRR
Payback Period: number of time periods it takes to recover theinvestment in the project before generating revenues
Benefit Cost Ratio (BCR): compares costs to the benefits of differentprojects Greater than 1 means benefits are greater than costs Less than 1 means costs are greater than benefits
Opportunity Cost: opportunity given up by selecting one projectover another
7/27/2019 Project Management Professional (PMP) Study Guide[1]
146/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
147/284
Chapter 7 Project Cost Management
Accounting Standards Depreciation: assets lose value over time
Straight Line depreciation: same amount is taken each year
Accelerated Depreciation: 2 forms Double Declining Balance
Sum of the Years Digits
Life Cycle Costing: includes operations andmaintenance phases
Value Analysis: find a less costly way to do same work
7/27/2019 Project Management Professional (PMP) Study Guide[1]
148/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
149/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
150/284
Chapter 7 Project Cost Management Accounting Standards
Definitive Estimate most precise/accurate estimate fordetermining project costs
Management Reserve over time PM wants no change to reserve;
customers wants $ back Cost and Schedule Data predicts future performance
ROI, Nest Present Value and Discounted Cash Flow all can beused to measure total income vs. total $ expended
Undistributed budget budget that contains approved scopechanges but are not planned yet
Depreciation is not a measurement of profitability
Pay Back Period - # of periods required to recover the initialinvestment
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
151/284
Management Project Quality Management
Processes required to ensure that the project will satisfythe needs for which it was designed
Includes all activities of the overall managementfunction that determine the quality policy, objectives,and responsibilities. These are implemented by qualityplanning, quality control, quality assurance, and qualityimprovement
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
152/284
Management 3 major processes:
Quality Planning identifying quality standards that are relevant tothe project (Plan); Project Manager, Project Owner
Quality Assurance evaluating overall project performance toprovide confidence that project will satisfy relevant quality
standards (Implement or Execution); Project Team Quality Control monitoring specific results to comply with quality
standards and eliminating unsatisfactory performance causes(Check or Control); Project Manager, Project Team Compatible with ISO 9000 and 10000 series Proprietary and non-proprietary approaches (total quality management
Must address the management of the project and the product of theproject
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
153/284
Management Quality the totality of characteristics of an entity that bear on its
ability to satisfy stated or implied needs Critical aspect is to turn implied needs into stated needs through project
scope management Do not confuse with grade category or rank given to entities having the
same functional use but different requirements for quality Customer satisfaction conformance to specifications (must produce what
is stated) and fitness for use (must satisfy real needs) Prevention avoid mistakes vs. cost of correction Management responsibility requires participation of team; responsibility
of management to provide resources Processes within phases plan-do-check-act cycle
Recognize that the investment in product quality improvements may be borne bythe performing organization since the project may not last long enough to reapreward
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
154/284
Management Quality Planning
Identify quality standards are relevant and how to satisfy
Inputs to Quality Planning Quality Policy the overall intentions and direction of an
organization with regard to quality as expressed by management Scope Statement
Product Description
Standards and Regulations
Other Process Outputs processes from other knowledge areas
(procurement planning)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
155/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
156/284
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
157/284
Management
Quality Assurance
All planned and systematic activities implementedwithin the quality system to provide confidence that the
project will satisfy quality standards Inputs to Quality Assurance
Quality Management Plan
Results of quality control measurements (testing)
Operational definitions
7/27/2019 Project Management Professional (PMP) Study Guide[1]
158/284
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
159/284
Management Quality Control monitoring specific results to determine
if they comply with quality standards and identifying waysto eliminate causes of unsatisfactory results Includes project (deliverables) and management (cost and schedule
performance) results Awareness of statistical quality control
Prevention (keep errors out of process) and inspection (keep errors fromcustomers)
Attribute sampling (result conforms) and variable sampling
Special Causes (unusual events) and random causes
Tolerances (acceptable range) and control limits (result falls withinrange)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
160/284
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
161/284
Management Tools & Techniques for Quality Control
Inspection activities such as testing to determine if results comply withrequirements
Control Charts plot results over time Pareto diagrams frequency of occurrence that identifies type or category
of result (80/20 rule) guides corrective action Statistical sampling select population of interest for inspection Flowcharting Trend Analysis forecast future outcomes based on historical results
Technical performance (# of errors identified; # of errors that remain) Cost and Schedule performance (activities per period with significant variances)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
162/284
Chapter 8 Project Quality
7/27/2019 Project Management Professional (PMP) Study Guide[1]
163/284
Management
Tips from the Review Guide Philosophy: definition of quality, avoidance of gold plating
giving customer extras, prevention over inspection
Conformance to requirements, specifications and fitness of use
Quality Management processes required to ensure that the projectwill satisfy the needs for which it was undertaken
Continuous Improvement - small improvements to reduce costsand ensure consistency
Marginal Analysis optimal quality is reached at the point whenrevenue from improvement equals the costs to secure it
Just in Time - decrease amount of inventory/decrease investment
Chapter 8 Project QualityM
7/27/2019 Project Management Professional (PMP) Study Guide[1]
164/284
Management
Tips from the Review Guide ISO 9000 or 10000 standards to ensure that
corporations follow their own quality procedures
Total Quality Management continuous improvementin business practices
Normal Distribution most common probability usedto measure variations
Standard deviation (sigma) measure how far away
from the mean (dotted vertical line) 3 or 6 sigma represents level of quality
+/- 1 sigma equal to 68.26%
+/- 2 sigma equal to 95.46%
+/- 3 sigma equal to 99.73%
Chapter 8 Project QualityM
7/27/2019 Project Management Professional (PMP) Study Guide[1]
165/284
Management
Tips from the Review Guide
Responsibility to quality entire organization
Ultimate employee
Overall or Primary Project Manager Design and Test Specifications engineer
Prevention over inspection quality must be planned innot inspected in
Chapter 8 Project QualityM t
7/27/2019 Project Management Professional (PMP) Study Guide[1]
166/284
Management
Tips from the Review Guide Cost of conformance vs. non-conformance
Quality Training vs. rework
Studies vs. Scrap
Surveys vs. Inventory Costs and warranty costs
Quality Planning (Plan) determine what will bequality on project and how quality will be measured done during Planning Phases
Identifying which standards are relevant to project how tosatisfy them
Benchmarking look at past projects to determine ideas forimprovement
Cost Benefit Analysis
Flowcharts (fishbone)
Chapter 8 Project QualityM t
7/27/2019 Project Management Professional (PMP) Study Guide[1]
167/284
Management
Tips from the Review Guide
Quality Assurance (Implement) determine if yourmeasurement of quality is appropriate done duringExecution phases
Process of evaluating overall performance on a regular basis
Quality Audits structured review of quality activities thatidentify lessons learned
Chapter 8 Project QualityM t
7/27/2019 Project Management Professional (PMP) Study Guide[1]
168/284
Management Tips from the Review Guide
Quality Control (Check) perform the measurementand compare to the quality plan done during Controlphases Process of monitoring specific project results to determine if
they comply with relevant quality standards and identify waysof eliminating unsatisfactory performance
Performance of the measurement or process, using qualitycontrol tools checking work
Chapter 8 Project QualityM t
7/27/2019 Project Management Professional (PMP) Study Guide[1]
169/284
Management Tips from the Review Guide
Quality Control Tools
Pareto Diagrams 80/20 rule the chart presents theinformation being examined in its order of priority and helps
focus attention on the most critical issues Fishbone diagram (Cause and Effect)
A creative way to look at the causes or potential causes of aproblem
Helps stimulate thinking, organizes thoughts and generatesdiscussion
Can be used to explore a desired future outcome and thefactors to which it relates
7/27/2019 Project Management Professional (PMP) Study Guide[1]
170/284
Chapter 8 Project QualityM t
7/27/2019 Project Management Professional (PMP) Study Guide[1]
171/284
Management Tips from the Review Guide
Quality Control Tools
Out of Control process is out of control when:
A data point falls outside of the upper or lower control limit
Non-random data points are within the upper control andlower control limits
Rule of 7 non-random points outside the mean - processshould be investigated
Assignable Cause data point the requires investigation to
determine the cause of the variation
Chapter 8 Project QualityM t
7/27/2019 Project Management Professional (PMP) Study Guide[1]
172/284
Management PMI and Deming
Cost of conformance 85% of costs of quality areresponsibility of Management Quality Training Rework
Studies Scrap Surveys Inventory and Warranty costs
Crosby absolutes of quality Performance standard is zero defects; measurement
system is cost of non-conformanceContinuous Improvement
Japanese (Kaizen)
7/27/2019 Project Management Professional (PMP) Study Guide[1]
173/284
7/27/2019 Project Management Professional (PMP) Study Guide[1]
174/284
Chapter 8 Project Quality
Management
7/27/2019 Project Management Professional (PMP) Study Guide[1]
175/284
Management Review Guide Tips
Marginal Analysis: optimal quality is reached whenincremental revenue from improvement equals theincremental cost to secure
Standard Deviation: how far away from mean Variable: characteristic you want to measure
Attribute: measurement (subjective or objective)
Ultimate Responsibility Employee
Overall Responsibility PM Design/Test Specifications - Engineer
7/27/2019 Project Management Professional (PMP) Study Guide[1]
176/284
Chapter 8 Project Quality
Management
7/27/2019 Project Management Professional (PMP) Study Guide[1]
177/284
Management Review Guide Tips
Quality objectives are approved in conceptual stage byproject owner
QA auditing function that provides feedback to teamand client about quality of output being produced
If sample size is a constant and acceptance numbersincrease, the producers risk decreases and consumer riskincreases
85% of costs of quality are direct responsibility ofmanagement
7/27/2019 Project Management Professional (PMP) Study Guide[1]
178/284
Chapter 9 Human Resource
Management
7/27/2019 Project Management Professional (PMP) Study Guide[1]
179/284
Management Project Human Resource Management
1,9 manager = good relationship with team
Project Organization Conflict between PM and Functional Managers
Dual allegiance of team members Complex prioritization of resources
Loss of developed procedures on project dissolution
Compromise = both sides will lose
Delegation Defer the decision
Interpreted as passive
Emphasize task vs. personnel
Can be frequently used
Chapter 9 Human Resource
Management
7/27/2019 Project Management Professional (PMP) Study Guide[1]
180/284
Management Project Human Resource Management
If there is a team of experts, PM decisions will promotehigh satisfaction
Functional/Project Managers likely to exercise: Power
Authority
Influence
Traditional organization forms have no single point ofcontact for client/sponsor
Chapter 9 Human ResourceManagement
7/27/2019 Project Management Professional (PMP) Study Guide[1]