    Construction of New Hostel

    Block in IIM Shillong 

    Project Management Final Report  

    Detailed project management report on construction of a new hostel block with an indoor sport

    complex within the existing IIM Shillong Campus in 18 months to accommodate 84 students within a

    budget of 2.5 Crores.

    Submitted by:

    Project Controller- Pillutla Anirudha Asish (2012PG

    Project Manager- Manan Chandna (2012PG

    Project Engineer- Ganesh Shanker (2012PG

    Procurement Manager- Sajal Goel (2012PG

    HR & Legal Officer- Sushree Tripathy (2012PG

  • 8/9/2019 Project Management_Final Report (1)

    2/18

    Page | 1

    Contents1. Executive Summary ............................................................................................................................... 2

    2. Introduction .......................................................................................................................................... 2

    3. Project Scope and Basic Assumption .................................................................................................... 3

    4. Technical Know-How Requirements ..................................................................................................... 4

    5. Foreseeable Difficulties and Constraints .............................................................................................. 5

    5.1. Financial Difficulties .......................................................................................................................... 5

    5.2. Political difficulties ............................................................................................................................ 5

    5.3. Construction difficulties .................................................................................................................... 5

    5.4. Other difficulties ............................................................................................................................... 5

    6. Risk Register .......................................................................................................................................... 6

    7. Work Breakdown Structure .................................................................................................................. 78. Milestone PERT Chart of the Proposed Project .................................................................................... 7

    9. Project Duration and Project Budget .................................................................................................... 8

    9.1. Project Milestones ............................................................................................................................ 8

    9.2. Resource Requirements .................................................................................................................... 8

    9.3. Construction phase – external and internal ..................................................................................... 9

    9.4. Resource cost planning ................................................................................................................... 10

    9.5. Assumptions .................................................................................................................................... 11

    9.6. Total cost of project ........................................................................................................................ 11

    10. Social costs, Risks and Expected Benefits of the Proposed Project ................................................ 11

    10.1. Social cost-benefit analysis ......................................................................................................... 11

    10.2. Risk & mitigations strategies of our project ............................................................................... 12

    11. Critical Success Factors for our project: .......................................................................................... 13

    12. Limitations and future scope of research ....................................................................................... 13

    13. Lessons Learnt and key difficulties faced while preparing the project plan ................................... 14

    13.1. Lessons Learned .......................................................................................................................... 14

    13.2. Difficulties Faced ......................................................................................................................... 15

    14. Annexures ....................................................................................................................................... 16

  • 8/9/2019 Project Management_Final Report (1)

    3/18

    Page | 2

    1.  Executive SummaryThis project report summarizes in detail the planning behind the construction of a new hostel block with

    an indoor sport complex within the existing IIM Shillong Campus in 18 months to accommodate 84

    students within a budget of 2.5 crores.

    The project is proposed to be completed in three phases namely, planning, site development andconstruction. In the planning phase the major deliverables will be the construction blueprint and

    completion of legal formalities which would include permission for erecting a new building within the

    campus. In the site development stage, we need to lay a foundation for the building at the proposed

    site. The major and final phase of construction will have deliverables such as the completed hostel and

    the indoor sports complex on the ground floor.

    Once the blueprint was prepared and approved through consultation with the client, the cost estimate

    was prepared and scheduling was done consequently. The social costs and risks involved in the project

    were accounted for. The benefits of undertaking the construction were outlined with special focus on

    the critical success factors. Finally at the end of the report, the limitations are enlisted and learningsderived from this project are outlined.

    2.  Introduction and Study RationaleThe project is aimed at the construction of a new hostel block in the premises of IIM Shillong in a span of

    18 months from the start of the project. The project has been taken up due to the increasing batch size

    that is being admitted into the institute year after year as well as a diverse set of programs being added

    to the institute’s offerings. This has led to a growing demand for a new residential complex for students.

    The new hostel block is also envisaged to include an indoor sports complex as the current facility is

    operating under overcapacity. Also, the plan for the new building has been endorsed by our institute’sDirector during an open house discussion, which reinforces the management’s will to take the project

    forward. The capacity of the new hostel block is planned to be for 84 rooms along with an indoor sports

    complex. The location of the hostel would be in the area adjacent to the admin building, on the other

    side of the road (on the way to barracks), where clearing of trees is already underway. This report

    discusses in detail the planning, deliverables, resource requirements, budget, risks and benefits of the

    project within its defined scope.

    The study rationale behind taking up this project is as follows:

      The current hostel facility in the institute is operating under overcapacity and the number of

    students being inducted every year is on the rise

      The sports facility present also needs to be improved to provide the right infrastructure for

    students in a premium management institute

      The project deals with identification and scheduling of resources to complete the task in a given

    time and resource frame

      To determine the various types of risks, costs and constraints that could be associated with

    managing a project as well as how to mitigate and manage the same

  • 8/9/2019 Project Management_Final Report (1)

    4/18

    Page | 3

      It is an opportunity to apply the principles of project management learnt in class as well as the

    tools for the same

    3.  Project Scope and Basic Assumption

    3.1. 

    Scope

    The scope of our work would include:

     

    Selecting builder for the construction of new hostel block with indoor sports facility

      Floating of the Bid

      Evaluating EOI

      Floating RFPs

     

    Evaluation and Final selection of Vendor

      Design of the new hostel block with an indoor sports complex

     

    Exact location of the building in the college premises

      Layout of the entire building

     

    Construction of the building

     

    Procuring resources like labor, raw material etc.

      Providing basic amenities like provision for lights/ fans/ heaters, fully-equipped bathrooms,

    drinking water facility, common room with LCD television, gym, squash facility, indoor

    badminton court, table tennis etc. to the students of IIM Shillong

      After the construction of the facilities it is important to regularly perform maintenance

    activities on all the facilities. Understanding the maintenance requirements from the builder

    and accordingly allocate resources for maintenance activities

     

    Providing good quality fresh basic eatables and energy drinks through an automatic vending

    machine that requires only limited space for installation

      Keeping the sports facility open 24 hours at the hostel on all the days, as required by the

    Institute

    3.2.  Limits and Exclusion:

     

    Plumbing and electrical work for the building will be taken care by the contractor

     

    Our job is only the felicitation of the hostel block, day to day job will be carried out by

    the contractor

     

    The overseeing of the day to day operations and quality assurance will be done by

    Hostel Committee along with a team of experts

    3.3.  Basic Assumption:

  • 8/9/2019 Project Management_Final Report (1)

    5/18

    Page | 4

      The legal and other approvals for hostel block will be taken by the college

    administration and not by us

      The location of the hostel block will be in the space where TV room, gym, badminton

    court are currently located. The space adjacent to the guest house can also be used

     

    We will construct the hostel block and hand it over to the college administration. Day today operations post completion will not be our responsibility

    4.  Technical Know-How Requirements

    The technical know-how requirement would need a skilled workforce. The organization has

    the policy of employing skilled workforce from internal the organization. Hence the skilled

    workforce requirement would be:

      Project Manager-1

      Chief Strategy and Marketing Officer

     

    Chief Finance and Purchase Officer

     

    Chief Operations Manager

      Chief HR Manager

      Electrical Engineers -2

      Civil engineers -3

      Mechanical Engineer – 3

      Architectures - 2

    4.1. 

    Technical Specifications

     

    The intake of students at IIM Shillong is set to increase in the next few years and hence

    there is a need for new hostel block to accommodate the increasing strength

      Creation of EOI in a standard format so as to invite qualified builders and contractors

      Associate with the most renowned construction player in the region and establish final

    deal with them

      Location Specification:

      A room which has the potential for setting up required technical infrastructure

    i.e. plumbing, electricity supply and other basic infrastructure

      Room should be big enough to accommodate 1 student

     

    Contractor Specification:

     

    Contractor should have minimum work experience in similar domain in

    Meghalaya for at least 2 years

    The major specifications that we propose for this hostel building and indoor sports complex are:

    Deliverables Technical Specifications

  • 8/9/2019 Project Management_Final Report (1)

    6/18

    Page | 5

    Size (of the building) Ground Floor + 4 floors + one-mess on each floor for cooking and dining

    Construction Material Standard building format (Brick & Mortar)

    Recreational Facilities Ground floor consists of Table Tennis, Indoor Badminton Court, Gymnasium

    and Squash Room

    Hostel Capacity 84 rooms

    Room specifications Cement Flooring + Provision for 2 tube-lights + 1 fan. The room size and

    design will be same as the existing new boy’s hostel rooms.

    Floor Specifications Tiled-flooring in the corridors

    Bathrooms One bathroom for every 2 rooms

    Utilities Connecting the entire building to the main power grid of the campus +

    Earthing + Drainage Facility + Automatic vending machine in sports complex

    Building construction CDEF concept

    5. 

    Foreseeable Difficulties and ConstraintsThe various difficulties and constrains in the construction of the building and setting up sports facilitieswhich may appear are as follows:

    5.1. 

    Financial Difficulties

      The funds for construction of new buildings within the campus have to come through the

    Central govt. It may not be obtained on time and might delay the start of the project.

      As a government organization we need to follow the tender process which may lead to change

    in the proposed budget if the parties are not ready to work at the amount specified in the

    tender.

    5.2.  Political difficulties

      The whole of Meghalaya is suffering from strikes and bandhs because of the current political

    scenario and the demand for ILP. This may lead to laborers not reporting on time or unable to

    work freely.

      The schedule might get hampered and it might take more number of days to finish the project.

      Also if ILP issue comes into effect, getting manpower from outside might be a problem 

    5.3. 

    Construction difficulties

      Timely procurement of raw materials due to location of Shillong

     

    Risk of non-compliance from supplier’s end may pose a problem for the timely finish of the

    project

    5.4.  Other difficulties

      Design variations after the initiation of the project

      Price inflation of construction materials

  • 8/9/2019 Project Management_Final Report (1)

    7/18

    Page | 6

      Implementation of various project management tool could be of problem as the labor

    contractor and other involved parties can be categorized as level 1 organization where these

    people might not be well versed with project management control frameworks

      Excessive approval procedures in administrative government departments

      Low management competency of subcontractors

     

    Unsuitable construction program planning

      General safety accident occurrence

      Unavailability of sufficient professionals and managers

    Various difficulties and constrains mentioned above may pose following problems in the proposed

    project:

      Late delivery of the project;

      Increases in operating costs

      Design and construction defects impacting upon the operation of the completed project;

     

    Deficiencies in other infrastructure or services upon which the successful operation of theproject depends, e.g. sports facilities as they require accurate measurements of the area

    6.  Risk RegisterIt acts as a central repository for all risks identified by the project or organization and, for each risk,

    includes information such as risk probability, impact, counter-measures, and risk owner and so on.

    Post identification of the risk, risk register has been created to know the exact probability and their

    impact on the project

    Risk Event  Likelihood  Impact  DetectionDifficulty 

    Stage of the Project 

    Delay of Design and construction 2 4 2 Start-up and ongoing

    Release of funds not on time 2 3 2 Start-up and ongoing

    Delay of interior setup like room

    furnishing and sports facilities

    1 1 1 After completion of

    construction

    Inaccurate estimations of time

    and money

    2 4 2 Ongoing, throughout the

    project

    Delay in site clearance and

    Permission from local authorities

    2 4 1 Start-up

    Errors and omissions in

    construction

    3 4 4 Final Stages of construction

    Fluctuation of estimated prices of

    raw materials

    4 4 1 Construction

    Labor issues 3 3 4 During construction

  • 8/9/2019 Project Management_Final Report (1)

    8/18

    Page | 7

    7.  Work Breakdown Structure

    8.  Milestone PERT Chart of the Proposed Project

    The project consists of the following milestones:

    1.  Getting legal approval: This milestone indicates the readiness of the team for going for the next

    phase of the project which is to begin the preparation of site and the construction phase. This task is

    a milestone since it signifies the end of the preparation phase for the project and starts with the

    implementation of the same.

    2.  Site development: This is a milestone since it signifies the readiness of site so that the construction

    work can start on it properly.

    3.  Completion of external construction: It involves the finishing of construction of all the 4 floors and

    signifies the readiness of the building to start with internal furnishing and layout of the sports

    utilities in the same.

    4. 

    Completion of sports utilities and ready for handover: This milestone signifies the completion of the

    project and is ready to be open for the students.

    All the 4 of the milestones along with the expected timeline is shown in the images below:

  • 8/9/2019 Project Management_Final Report (1)

    9/18

    Page | 8

    9.  Project Duration and Project Budget

    9.1.  Project Milestones

    Milestones  Day of Completion 

    Construction Blueprint Day 45

    Completion of Legal formalities Day 60

    Excavation of site Day 100

    Laying of Foundation and surface drainage Day 150

    Completion of indoor sports complex ( ground floor ) Day 280

    Completion of First floor Day 330

    Completion of Second floor Day 380

    Completion of Third floor Day 430

    Completion of Fourth floor Day 480

    Completion of additional infrastructure Day 520

    Project Handover Day 540

    9.2. 

    Resource Requirements

    Resource 

    Purpose 

    Procurement  

    Cost per

    unit/resource 

    Total cost

    in project  

    HumanResource

    Six people forworking on the

    project design and

    handling interaction

    with the client

    Internal to theorganization  –  5

    External consultant

    -1

    For the internalworkforce the salary

    per month is Rs.30000

    per person. External

    consultant charges

    Rs.5000 per design

    sanctioned

    180000

  • 8/9/2019 Project Management_Final Report (1)

    10/18

    Page | 9

    Human

    Resource

    For clerical jobs like

    applying for permits

    and receiving them

    External resources Average salary would

    be Rs. 10000 pm ( for 2

    months only )

    40000

    Miscellaneous

    Cost

    Stationary Cost along

    with other amenities

    and utilities

    To be obtained

    from suppliers

    --

    200000

    Total budget = Rs.420000; Contingency margin = 10% 

    Total Budget (with contingency margin) = Rs.462000

    9.3. 

    Construction phase – external and internal

    This phase consists of calculating the cost required for acquiring material (raw material and finished

    goods).

    Resource Purpose Procurement Cost per

    unit/resource

    Total cost in

    project

    Steel Frames &

    Rods

    Construction From supplier Rs. 44200 per unit

    available

    442000

    Cement Construction From supplier 50 kg sacks @

    RS.275 per sack

    144375

    Sand Construction From supplier RS.43 per cubic

    feet of river sand

    303709

    Bricks Construction From supplier Rs.19000 for 3000

    bricks

    660739

    Plaster Construction Contract given to

    vendor

    Rs.50 per sq.m of

    wall area

    42017

    Paint Internal and

    external

    Contract given to

    vendor

    300000

    Sanitary fixtures Internal to

    building

    From supplier 150000

    Plumbing and

    sewage facility

    Internal and

    external to

    building

    Contract given 1200000

    PVC Pipes Construction From supplier 20000

    Electrical System

    (Excluding

    Lighting,

    including HVAC)

    Internal Contract given 5800000

  • 8/9/2019 Project Management_Final Report (1)

    11/18

    Page | 10

    Generators

    (Diesel Operated)

    Back Up Power

    system

    From supplier-

    1000kVA x 4

    $95000 per

    generator

    2470000

    Manpower

    Requirement

    Labor work,

    plumbing,

    electrical fixing

    and carpentry

    Daily workforce for

    masonry : 25

    Workforce for

    plumbing : 15

    Workforce for

    electrical System: 7

    Workforce for

    painting : 12

    Masonry @ Rs.300

    per person per day

    Plumbing @ Rs.450

    per person per day

    Electrical @ Rs.450

    per person per day

    Painting @ Rs.250

    per person per day

    Flooring and other

    internal civil works

    @ Rs.350 per

    person per day

    220300

    Tiles and mosaic

    flooring

    Interior to the

    building

    From supplier Kajaria tiles @

    Rs.95 for 1x1sq.ft

    tiles

    225000

    Total Budget = Rs. 11978140

    Taking into consideration 10% contingency, the total budget becomes = Rs. 13176000 

    9.4. 

    Resource cost planning 

    The completion phase includes the final touches required for the completion of the building including,

    internal decorations like standardized lighting and fixtures and glass fixtures.

    Resource Purpose Procurement Cost per

    unit/resource

    Total cost in

    project

    Electrical

    lighting fixtures

    Standardized

    lighting in the

    shopping complex

    From supplier

    --

    700000

    Glass fixtures to

    provide the

    aesthetic look

    Both internal and

    external to the

    shopping complex

    Procured from

    supplier but fixed

    by contractor

    --

    2000000

    Fire-fighting

    system

    installation

    As directed by

    government to

    get certified for

    safe operation

    Procured from

    supplier

    Fire extinguishers

    @ Rs.2000 per

    unit and other

    equipment

    100000

  • 8/9/2019 Project Management_Final Report (1)

    12/18

    Page | 11

    9.5. 

     Assumptions

    The salary of permanently hired employees has not been considered in the budget calculation as the

    organization has separate salary account to handle the same and this cost is taken care of in the overall

    company expenses and is not specific to the project alone.

    9.6.  Total cost of project

    The total project cost comes out to be approximately Rs. 2.25 crores 

    Considering contingency cost of 10%, and rounding off the value obtained, the cost of the project stands

    to be Rs. 25000000. (Rs. 2.5 Crores) 

    10.  Social costs, Risks and Expected Benefits of the Proposed Project

    10.1. 

    Social cost-benefit analysis

    A social cost-benefit analysis aims to chart all of the effects that would influence the welfare of society

    on account of constructing the stadium. It is a systematic and cohesive method to survey all the impacts

    caused by the urban development project. It comprises not just the financial effects (investment costs,

    direct benefits like tax and fees etc.), but all the social effects, like: pollution, safety, indirect (labor)

    market, legal aspects etc.

    The social cost-benefit analysis calculates the direct (primary), indirect (secondary) and external effects:

     

    Direct effects  are the costs and benefits that can be directly linked to the owners/users of theproject properties (e.g., the users and the owner of stadium).

      Indirect effects  are the costs and benefits that are passed on to the producers and consumers

    outside the market with which the project is involved (e.g., the owner of shops outside the campus )

      External effects are the costs and benefits that cannot be passed on to any existing markets because

    they relate to issues like the environment (noise, emission of CO2, etc.), safety (traffic, external

    security) and nature (biodiversity, dehydration, etc.).

    The social cost-benefits associated are as follows: 

    10.1.1. 

    Direct Effects  Construction of the new hostel will provide accommodation to the additional students who will be

     joining the institute next year.

      The indoor sports complex will ensure that students get access to better recreational facilities. 

    10.1.2. 

    Indirect Effects

      The shops around the college will benefit due to the increase in the number of students.

  • 8/9/2019 Project Management_Final Report (1)

    13/18

    Page | 12

      The noise level would increase during construction phase and might disturb the nearby residents.

    10.1.3. 

    External Effects

      The effect on environment would be significant during construction phase

    10.2. 

    Risk & mitigations strategies of our project

    Types of Risk Risk Identification Risk Mitigation

    Financial Risk Firstly, the funds for construction of new

    buildings within the campus have to come

    from the Central govt. It may not be

    obtained on time and might delay the start

    of the project.

    Secondly, as a government organization weneed to follow the tender process which

    may lead to change in the proposed budget

    if the parties are not ready to work at the

    amount specified in the tender.

    A few other risks which has a direct impact

    on the cost of the project

      Design variations after the initiation of

    the project

     

    Price inflation of construction materials  Excessive approval procedures in

    administrative government

    departments

    Project should be initiated with the IIM

    Shillong corpus after a written

    confirmation by the central govt. that the

    funds will be moved to IIM Shillong in

    due course of time.

    Understanding the cost of such projectsin Shillong, a good estimate of the

    amount to be paid to potential

    contractors should be done so that

    parties don’t leave the tender process.

    Usually if the parties find that the

    venture is not profitable, all of them

    leave.

    Contract should strictly not allow any

    design variations.

    Price inflation is not in our control but

    the proposed budget usually considers

    the possibility of price rise of raw

    materials

    Political Risk The whole of Meghalaya is suffering from

    strikes and bandhs because of the current

    political scenario and the demand for ILP.

    This may lead to laborers not reporting on

    time or unable to work freely. The schedule

    might get hampered and it might take more

    number of days to finish the project.

    Measures can be taken to house laborers

    within the campus so that work is not

    hampered. As far as raw materials

    procurement is considered, buffer stock

    would need to be purchased

    Risks associated

    with supply

    chain

    The two major risks identified under this

    head are: Non-availability of resources and

    risk of non-compliance from supplier’s end 

    Enter into strictly defined contracts with

    the suppliers

  • 8/9/2019 Project Management_Final Report (1)

    14/18

    Page | 13

    Safety related

    risks

      Low management competency of

    subcontractors

      Unsuitable construction program

    planning

      General safety accident occurrence

     

    Lack of coordination between

    project participants

      Unavailability of sufficient amount

    of skilled labor

      Unavailability of sufficient

    professionals and managers

    Subcontractors are not in our direct

    control but while contractors previous

    work can be checked to understand the

    kind of subcontractor they use.

    Skilled labor scouting should be done well

    in advance to avoid such problems.

    Usually there are intermediary players

    who help in getting the skilled labor. Such

    people should be approached if such an

    issue arises

    11.  Critical Success Factors for our project:The key success factors of our project are listed below:

      Schedule:  It is important for the project to meet the schedule and the proposed timelines. So

    the critical success factor is to meet or beat established project milestones

      Safety:  It is important that all the safety guidelines are followed and thus the success factor in

    this case will be- no recordable or lost time injuries and reportable injuries lower than the

    industry average

      Budget:  There are a lot of risks involved in this project. It is imperative that we manage risks to

    contain costs within the estimated budget

     

    Quality:  Conform to project requirements and quality without adverse effects on milestones orbudget. None of the above success factors should be achieved at the cost of quality

      Environmental & Regulation Compliance: Complete project without any violations conforming

    to the standards and regulations

      Operational and construction standards- Education, implementation and consistency of

    standards

    12.  Limitations and future scope of research

    The proposed hostel block will not include any changes in the plan/design at a later stage due to thestrict timelines. The design of the block and the room specifications will be similar to the existing new

    hostel blocks.

    There will be just cement flooring (cement) to ensure timely completion. There will be no additional

    classrooms or study rooms in this hostel.

  • 8/9/2019 Project Management_Final Report (1)

    15/18

    Page | 14

    We have not taken into account risks associated with the external factors like weather, terrain and

    natural disasters. With Shillong being an area affected by extreme climate and prone to natural disasters

    like mild earthquakes etc., the ideal project plan should also have strategies to mitigate these risks and

    have contingencies planned to meet the success factors.

    Taking into account all the above factors are out the scope of the current project plan and are topics forfuture scope of research.

    13.  Lessons Learnt and Key Difficulties Faced

    13.1. 

    Lessons Learned 

      Importance of minutes of meetings was established while working on the project. It was

    observed that referring past decisions and the discussions becomes important for taking future

    decisions and hence for future reference minutes of meetings play a very crucial role. Keeping

    track of allocated tasks and responsibilities became much easier with the help of minutes of

    meetings. 

      While managing a project, preparing timeline and budget are not the only key areas. There are

    many other important things, like work breakdown structure, know-how of the domain to some

    extent for efficient scheduling budget management, social cost-benefit analysis, anticipation of

    possible risks and measures to mitigate them etc., which needs to be considered while planning

    for any project. 

      Importance of consensus and discussions between client and project management team is

    another key area which was observed. The discussions brought out many new ideas on table but

    at the same time it was realized that unnecessary discussions may be time consuming without

    adding value to the project. Similarly, agreeing to a point is very important for the project to

    proceed further effectively. All of this is accomplished through clear and consistent

    communication.

      Good project management involves no shortage of dialogue between team members, clients,

    and anyone else that should be in the loop. Constructive criticism pushes your team to do their

    best and makes expectations clear. If someone is already producing phenomenal work, be sure

    to recognize it and let them know. It is important to cultivate creativity whenever possible.

     

    Another aspect to bear in mind throughout the life of a project is that changes will be made.Turning change into an opportunity is important; re-evaluation of the state of project and using

    it to motivate the team should be the step forward. That way, even if drastic changes come up —

    your project will end a success.

      Also a key learning is that good project management doesn’t end when a project is completed.

    Evaluating the results of the team’s hard work is an integral step in the process. Obviously t he

  • 8/9/2019 Project Management_Final Report (1)

    16/18

    Page | 15

    views of client about team’s efforts will be communicated by them but a personal introspection

    becomes important for future improvement.

    13.2.  Difficulties Faced

      Without clear knowledge about the actual resources and schedule involved in a construction

    project it was difficult to figure out things at many points in time. With the help of online

    resources and batch mates with prior experience in this field, this difficulty was tackled to some

    extent. 

      The team involved people with varied backgrounds who have their own understanding about

    various topics. Hence, it became difficult in certain discussions to reach on consensus timely.

    Thus meetings sometimes became a time consuming affair but this has its own positives and

    negatives. Also dividing the roles as project manager, HR manager, communications manager

    etc. helped in dealing with this issue to some extent as the concerned person was the one who

    led the discussion of his/her domain, brining everyone on same page and helping in reaching a

    consensus.

      Lack of proper communication sometimes in the initial phase proved to be bottleneck hindering

    the project. But gradually as the project planning continued the team developed a co-ordination

    and this issue was addressed soon.

      Timely follow-up, which is an important step in project management, was in some points not

    adequate and hence revising the points discussed in the past meetings consumed a lot of time

    but minutes of meetings came to rescue to a large extent.

  • 8/9/2019 Project Management_Final Report (1)

    17/18

    Page | 16

     Annexure

     Annexure 1: Expression of Interest

    Sl. No.  Particulars  Details 

    1 Profile of Builder

    2 Name

    3 Address in full

    4 Telephone /Mobile No.

    5 Fax, Email

    6 Month and year of establishment

    7 Name of Proprietor /Partner

    8 Annual turnover during the last 3

    Years.

    9 Whether the firm is income-tax

    Assesse?

    If Yes please give the details of PAN

    No. and copy of the latest

    Assessment order.10 Registration No., if applicable

    11 EPF No. , if applicable

    12 Details of Infrastructure, persons 

    employed, No. of offices/branches

    available with the service provider

    13 Service Tax No., if applicable

    14 VAT No. , if applicable

    15 TIN No. , if applicable

    16

    Name of at least 2 References of

    repute with address and telephone

    Numbers (Enclose their Certificates)

    Note: Attach extra sheet if required.

  • 8/9/2019 Project Management_Final Report (1)

    18/18

    Page | 17

    Place: Signature of the

    Date: Caterer/Hotelier

     Annexure 2: Details of Previous Contracts

    Period of Contract Name & address of Type of

    Contract

    undertaken

    Number of Value of

    Organization Parties contract

    From To serviced (annual)

     Annexure 3: Details of Present Contracts if any, of similar nature being rendered by

    you (that will be available for inspection by our officials)

    Period of Contract Name & address of Type of Number of Value of

    Organization contract persons contract

    From To  undertaken serviced (annual)