Mining Projects from (Un)Structured Data Project mining Saimir Bala, WU (Vienna University of Economics and Business) 12 JUNE 2017

Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining Projects from (Un)Structured Data

Project mining

Saimir Bala, WU (Vienna University of Economics and Business)

12 JUNE 2017

Page 2: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

You the manager of a software development company

You are applying best practices, established project management guidelines and tools

But…

What is really going on in your software development project?

Why are deadlines not met? Why are the costs superior to the planned?

Why is does the your software product require more maintenance than what you thought?

PAGE 2

Motivation

Page 3: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Software processes are carried out in a project-oriented fashion

Goal is a release of a software product

Artifact-centric processes

Software development methodology (e.g., Scrum, Waterfall)

Artifacts are tracked by means of Version Control Systems

Should follow best practices (e.g. Principles of good modularization)

PAGE 3

About software projects

Q: How can we help the manager to gain transparency on the software project?

Page 4: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 4

Project-Oriented Business Processes

Page 5: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Project-Oriented Classic Processes

Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN)

One time (fixed goal and resources)

Recursive, Cyclic

Single instance Many instances

Workpackages, Modules, Units Activities

Subworkpackages, Submodules Suprocesses

PAGE 5

Project-Oriented vs. Classic Business Processes

Page 6: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Project-Oriented Classic Processes

Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN)

One time (fixed goal and resources)

Recursive, Cyclic

Single instance Many instances

Workpackages, Modules, Units Activities

Subworkpackages, Submodules Suprocesses

PAGE 6

Project-Oriented vs. Classic Business Processes

?

Page 7: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Software projects are supported by a variety of tools

Examples

Project management, Bug-tracking

Development

Dependency management

Testing

Continuous integration

Documentation

Version Control System

PAGE 7

Software Projects Data

Page 8: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 8

State of the Art: Activity Mining

Kindler et al. 2006

Page 9: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 9

State of the Art: Dotted Chart

Song and van der Aalst. 2007

Page 10: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 10

State of the Art: Evolution Storylines

Ogawa and Ma 2010

Page 11: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 11

State of the Art: Visual Software Analytics

Wettel and Lanza 2007

Page 12: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Identification of the problem

Objectives of the artifact

Artifact Development

DemonstrationEvaluationCommunication

PAGE 12

Methodology: DSR

Peffers 2007

Page 13: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining the Real Gantt Chart

PAGE 13

Page 14: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining the Gantt Chart of a Project

14

Page 15: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Example from the SHAPE project

“pm” work package

“example” work package

single events within files

Associated information:

1. User2. Type of change

3. Comment

Project structure

Activity inferred from single events1. Threshold based

2. Activated when a tree node in the

project structure is collapsed3. Decomposed when node is

expanded15

Page 16: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Indicators

Data from the VCS

Authors

Files

Type of change, Etc

Coverage, i.e. work-intensity

the ratio between active working periods (i.e., the time spans of activities) and the total work package duration

Expected active time between commits (tc)

average work speed (commit frequency) during active times

16

Page 17: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

The following assumptions are made:

1. Meaningful file structure

Project participants organize the files in a representative (e.g., spatially separating documentation from testing into different folders).

2. Regular commits

Project participants systematically commit their changes in the VCS

3. Descriptive comments.

Project participants write descriptive comments that allow others members to understand the changes made to the software

PAGE 17

Assumptions

Page 18: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Resource Classification from Commit Messages

18

Page 19: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 19

Resource Classification from Commit Messages

Page 20: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Developer

PAGE 20

Resource Classification from Commit Messages: Developer vs. Tester

Tester

Page 21: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 21

Learning Decision Trees from Projects

Page 22: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining Hidden Work Dependencies

22

Page 23: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 23

Artifact Evolution as Time Series

Are they similar?

Correlation!

Page 24: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 25

Characterization of Projects wrt Dependencies

Page 25: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Bala, S., Cabanillas, C., Mendling, J., Rogge-Solti, A., Polleres, A.: Mining Project-Oriented Business Processes. In: BPM. pp. 425–440 (2015).

Agrawal, K., Aschauer, M., Thonhofer, T., Tomsich, N., Bala, S., Rogge-Solti, A.: Resource Classification from Version Control System Logs. In: EDOC Workshops (2016).

Bala, S., Havur, G., Sperl, S., Steyskal, S., Haselböck, A., Mendling, J., Polleres, A.: SHAPEworks: A BPMS Extension for Complex Process Management. In: BPM (Demos). pp. 50–55. (2016).

Bala, S., Revoredo, K., Mendling, J., Santoro, F.: Uncovering the Hidden Co-Evolution in the Work History of Software Projects. In: BPM. 2017 (conditionally accepted)

PAGE 26

Publications

Page 26: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Identification of the problem

Objectives of the artifact

Artifact Development

DemonstrationEvaluationCommunication

PAGE 27

Next steps

Peffers 2007

Page 27: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Identification of the problem

Objectives of the artifact

Artifact Development

DemonstrationEvaluationCommunication

PAGE 28

Next steps

Peffers 2007

Page 28: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Identification of the problem

Objectives of the artifact

Artifact Development

DemonstrationEvaluationCommunication

PAGE 29

Next steps

Peffers 2007

Page 29: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

DEPARTMENT OF INFORMATION SYSTEMS AND OPERATIONSINSTITUTE FOR INFORMATION BUSINESS

Welthandelsplatz 1, D2/1.0261020 Vienna, Austria

M.SC. SAIMIR BALA

T +43-1-313 36-5304F +43-1-313 [email protected]

PAGE 32

Questions?

Page 30: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Backup slides

PAGE 33

Page 31: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 34

Data Model for SQL Querying VCS logs

Page 32: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining the Real Gantt Chart

PAGE 35

Page 33: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining the Gantt Chart of a Project

36

Page 34: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Example from the SHAPE project

“pm” work package

“example” work package

single events within files

Associated information:

1. User2. Type of change

3. Comment

Project structure

Activity inferred from single events1. Threshold based

2. Activated when a tree node in the

project structure is collapsed3. Decomposed when node is

expanded37

Page 35: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Indicators

Data from the VCS

Authors

Files

Type of change, Etc

Coverage, i.e. work-intensity

the ratio between active working periods (i.e., the time spans of activities) and the total work package duration

Expected active time between commits (tc)

average work speed (commit frequency) during active times

38

Page 36: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

The following assumptions are made:

1. Meaningful file structure

Project participants organize the files in a representative (e.g., spatially separating documentation from testing into different folders).

2. Regular commits

Project participants systematically commit their changes in the VCS

3. Descriptive comments.

Project participants write descriptive comments that allow others members to understand the changes made to the software

PAGE 39

Assumptions

Page 37: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Some Real World Projects

Project Description Commits Users Files Duration tc coverage

Opendata bot Open Data AT Assistant: Data

Pioneers Create Camp project28 1 3507 16 0 100.00%

MiningVCS Gantt chart visualization of projects 84 1 111 61 1.9 87.00%

MSR paper Writing a conference paper 35 2 78 44 12.8 70.00%

Progit2 Pro Git 2nd Edition 1292 134 955 481 118.6 60.00%

GHDiscovery GitHub Activities Discovery

repository.11 1 97 29 6.6 53.00%

SHAPE Joint research project on railway

automation624 13 6470 1127 21.8 38.00%

papers from

siemens

Repository form Siemens to keep

track of paper writing processes649 5 1791 1853 26.4 23.00%

Facebook-ads-

java-sdk

Java SDK for Facebook Ads APIs 38 8 428 324 18.2 22.00%

Biglist-of-

naughty-strings

Strings which have a high probability

of causing issues when used as user-

input data.

202 60 15 530 53.3 10.00%

We set the aggregation threshold to 7 days (i.e. two events belong to the same activity only if their temporal distance is one week or less)

40

Page 38: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Open-Data Helper Bot

Open Data AT Assistant: Data Pioneers Create Camp project

Helps search for an open dataset

28 commits, 1 user 3507 files, 16 days

0 tc, 100% coverage

41

Page 39: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining VCS Software

This software project

84 commits, 1 user, 111 files, 62 days

tc 1.9 hours, coverage 87%

42

Page 40: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

MSR Paper

Preparation of a conference paper

35 commits, 2 users, 78 files, 44 days

12.8 tc, 70% coverage

43

Page 41: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Book Writing Project

Progit book 2nd edition

1292 commits, 134 users, 955 files, 481 days

tc 118.6 hours, coverage 60%

44

Page 42: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Students Project: Disovering Github Activities

Student class project 1 user, 72 files, duration

29 days tc 8.8 hours, coverage

59%45

Page 43: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

SHAPE Project

Joint research project on railway automation

6470 files, 13 users, duration 1127 days

tc 21.8 hours, coverage = 38%

46

Page 44: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Writing Papers Project (from Industry)

Repository for papers writing process taken from SHAPE project

649 commits, 5 users, 1791 files, 1853 days duration tc 26.4 hours, coverage 23%

47

Page 45: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Facebook ads java sdk

Java development kit for Facebook ads 38 commits, 8 users, 428 files, 324 days 18.2 tc, 22% coverage

48

Page 46: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Big List of Naughty Strings

An evolving list of strings which have a high probability of causing issues when used as user-input data.

202 commits, 15 files, 51 users, 531 days tc 53.3 hours, coverage 10%

No activities found in the subdirectories, i.e. no continuous work for in the same subdirectory within the given aggregation threshold

49

Page 47: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Uncovering the Hidden Co-Evolution in the Work History of Software Projects

PAGE 50

Page 48: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 51

Requirements

How can we use data generated from the software project to help gaining transparency on the status and work history?

R1 (Extract the work history)

•Discover the process of how artifacts evolve in the project as a labeled set of steps

R2 (Uncover Work-Related Dependencies)

•Identify that parts of the work are connected to other parts co-evolution of two artifacts?

R3 (Measure Dependencies)

•How strongly depend two artifacts on one another?

Page 49: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 52

State of the Art

MSR

• Mostly solving R2 (Uncover work-related dependencies and R3 (Measure dependencies)

• Zaidman et al. 2008, Zimmerman et al. 2008, D‘Ambros et al. 2009, Lindeberg et al. 2016

Process Mining

• Mostly addressing R1 (Extract the work history)

• Kindler et al. 2006, Goncalves et al. 2011, Poncin et al. 2011, Bala et al. 2015

Visualization

• No approach addressing R1, R2, and R3 simultaneously

• Voinea and Telea 2006, Ripley et al. 2007, Greene and Fischer 2015

Page 50: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 53

Approach

Page 51: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

How to capture events?

How to obtain the work history from the events?

What are important informations we need to consider in order to identify dependencies?

How to analyze the data?

How to measure work-dependency?

PAGE 54

Challenges

Page 52: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

The following assumptions are made:

1. Meaningful file structure

Project participants organize the files in a representative (e.g., spatially separating documentation from testing into different folders).

2. Regular commits

Project participants systematically commit their changes in the VCS

3. Descriptive comments.

Project participants write descriptive comments that allow others members to understand the changes made to the software

PAGE 55

Assumptions

Page 53: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 56

Concepts

Artifact evolution

• Changes made to an artifact during its lifetime, meaured in Lines of Code

Dependency• High similarity in the evolution of two

software artifacts

Page 54: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 57

Metrics

Degree of Co-

Evolution

•Strength of the connection. A value in the interval [0,1], where 1 is the highest degree of co-evolution

File Distance

•Distance between two files in the file tree. Equal to the length of the path traversing the least common ancestor.

Page 55: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Generate events from software repository data into a log file

Preprocess log data

Compute artifact evolution

Compute Dependencies

Compute MetricsSelect set of

highly dependent & distant files

Potential wok-dependencies

PAGE 58

Method

Page 56: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 59

Computing Dependencies

Are they similar?

Correlation!

Page 57: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 60

Results

Page 58: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 61

Co-Evolution versus Distance

Page 59: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 62

Characterization of Projects wrt Dependencies

Page 60: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 63

Zipf law on real projects: 100%

Camunda Operationcode Caret

Page 61: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 64

Zipf law on real projects: top 80%

Camunda Operationcode Caret

Page 62: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 65

Zipf law on real projects: top 50%

Camunda Operationcode Caret

Page 63: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

PAGE 66

Stories

Are they similar?

Page 64: Project mining Mining Projects from (Un)Structured …Project-Oriented Classic Processes Plan (e.g. Gantt, PERT) Process Model (e.g. Petri Net, BPMN) One time (fixed goal and resources)

Mining project-oriented business process is difficult

Provide hints for the project manager

Work dependencies not easy to be seen without analysing the work history

Future work:

Improve method for comparting time series

Semantic analysis of process labels

PAGE 67

Conlusion