Project Report on Manufacturing of Engineering Fabrication &
Machinery Components for EOT Cranes, Valves, Pressure
Vessel, Conveyors & Rollers.
Process Flow Diagram :
The following process flow diagram is followed for the unit operations as per
sequences.
Cutting of MS/SS Plate,
Round, Rolled Section.
Bending
Grinding
Power Press
Drilling
Grinding
Lathe Machining
For Components
Machining
Assemble
Testing
7/30/2019 Project of Manufacturing of Engg Fabrication
2/5
II PLANT & MACHINERY
Plant & Machinery Quantity Amount (Rs.)
Electrical Welding Set 8 no 5,40,000/
Tig & CO, Welding Machine 1 no 80,000/
Mig Welding Machine I no 1.35,000/Line Cutter 1 no 10.000/
Drilling - Machine 2 no 5O.OO0/-
Gas Cutting Set 5 no 20,000/-
Hyd. Press 70 MT Cap X 1 Mt Gap 1 no 80.000/
Grind inn M/c 1 no 4,500/
Bench Drilling M/c 1 no 22,000/
Magnetic Drilling Machine 3 No 60,000/
Hand Grinder 6 no 15,000/
Total 10.16,500/-
Heavy Duty Power Press 500 Ton capacity with motor and
Electrical accessories X 3 Mts Gap
1 no 13,50,000/-
Welding Rectifier I No 1,00.000/
Plasma (air) Cutting Machine 1 no 1,65,000/-
Plate Rolling Machine capacity up to 50 mm with MotorElectrical accessories
1no 9,00,000/-
Lathe Machine 10 Length, Free chuck and Electrical panel
board
1 No 2,10.000/
Lathe Machine 8.5 Ft Length, Free Chuck and Electricalpanel board
1No 2,10,000/-
Lathe Machine 6 Ft length, Free Chuck and Electrical
panel board
1 no 1,90,000/-
C.N.C Lathe Machine 1 no 10,00,000/-
Hydraulic Operated Surface Grinding Machine 1N0 4,00,000/-Vertical Milling Machine 1 No 3,50,000/-
Universal Milling Machine 4,50,000/-
Radial Drilling Machine 1 Capacity 1 No 2,50,000/-
Magnetic Drilling Machine 1 No 35,000/-
Bench Grinding Machine 1 No 5.000/-
Handing Grinding Machine 2 No 20,000/-
Electrical Hacksaw 12" Capacity 1 No 30,000/-
AirConipressor3HP 1 No 35,000/-
Height Gauge 12" 12,000/-
Height Gauge 24" 1 No 20,000/-
Inspection Surface Plate 1 No 1,20,0011/-
Micro Meter 0 mm to ISO mm 1 No 9,500/-Dial Indicator 1 No 4,500/-
Total 58,66,000/-
Add VAT@ 4 % against C Form 2,34,500/-
Total Proposed Machinery 61,00,500/-
Total Plant & Machinery 71,17,000/-
7/30/2019 Project of Manufacturing of Engg Fabrication
3/5
7. Cost of the project : Amount
I) Land & Building : Rented
II) Plant & Machinery : Rs.71,17,000/-
III) Working Capital Requirement Rs 35,65,000/-
Total Rs. 105,82,000/-
Sources of Finance (Proposed) :
I) a) Promoter's Contribution on Fixed Capital : Rs. 10,16,500/-
b) Term Loan for Plant & Machinery (Proposed) : Rs. 61,00,500/-
II) a) Working Capital Margin @ 10 % : Rs. 3.45 Lakhs
b) Working Capital Loan (CC Loan) :Rs. 31.20 Lakhs
Total Rs. 105.82 Lakhs10 Subsidy from State Govt. on Plant & Machinery Investment @ 25%
Rs. 15,25,000/-
Calculation of Recurring Expenses
a) Cost of Manpower ( Per Month)
Particulars Number wage/Salary Amount(Rs.)
Manager 1 10,000/- 10,000/-
Skilled Worker 10 5000/- 50,000/-
Un skilled Worker 10 4500/- 45,000/-
Accountant/Sales
Personnel/Office Assistant
2 5000/- 10,000/-
Watchman / Assistant 2 4,000/- 8,000/-
Total 25 1,23,000/-
b) Utility Expenses : ( Per Month)
Electricity & water Ks. 63,000/-
( 75X25X8X.70X6.0/-)
c) Raw Materials (( Per Month)
Items Quantity Rate Amount(Rs.)
MS / SS Plate, Round & Rolled
Including Transportation & Duty.
20 MT Rs. 60/- average 12,00,000/-
Total Rs. 12,00,000/-
d) Miscellaneous other Expenses (Per Month):
Items Amount(Rs)
Rent for Sheds Y-73 & Y-76 21,665/-
Telephones/Postage/Stationery 2000/-
Repair/ Maintenance 4,000/-
Consumables 4,000/-
Transportation/Travel Charges 3,000/-
Insurance Premium/Audit Fee/Tax 3,000/-
7/30/2019 Project of Manufacturing of Engg Fabrication
4/5
Packaging & Forwarding 3,000/-
Selling & Advertisement 3,000/-
Misc. Other Contingency Expenses 3,345/-
Total 47,000/-
e) Total Recurring Expenditure ( Per Month)
a) Raw Materials Rs. 12,00,000/-
b) Manpower Rs. 1,23,000/-
c) Utility Rs. 63,000/-
d ) Misc Other Expenses Rs. 47,000/-
Total Rs. 14,33,000/-
V) Working Capital Assessment: ( at 70% Capacity Utilization)-
Particulars Requirement (
Rs. In Lakhs)of working
capitals
Working
capitalCycle
Working
CapitalMargin @
10%
Amount of
Working capitalLoan (Rs in
Lakhs)
Raw material 12.00 1 Months 1.20 10.80
Work In Progress(WIP) 7.16 2 weeks 072 6.44
Finished Goods Stock 8 96 1/2 Month 0.90 8.06
Bills Receivable 6.55 1/2 month 0.66 5.89
Total 34.05 ------ 3 45 31.20
Considerations:
Finished Goods Stock - Recurring Expenses X 1.25 ( At 25% Higher Margin)
Bills Receivable = Recurring Expenses excluding manpower expenses
Interest Calculation on Working Capital Loan :
i) Total Loan : Rs. 31.20 Lakhs
ii) Rate of Interest @ 11.00%
iii) Total Loan Interest Rs. 3 43 Lakhs
PROJECTED BREAK EVEN POINT (B.E.P.)
YEAR1 II III IV V
A VARIABLE COSTTOTAL DIRECT OFPROCESSING(80%)
A 132.80 147.45 157 87 158 28 158 2S
MANUFACTURING (ANNEX
5. K)
B GROSS RECIEPTSA/INCOME TOTAL B 209.52 224.486 239.451 239.451 239.451
7/30/2019 Project of Manufacturing of Engg Fabrication
5/5
(ANNEX 5. B)C CONTRIBUTION C (B-A) 76.72 77.04 81.58 81.17 81.17
CI CONTRIBUTION @ 100% C.U. C1 109.6 102.718 101.975 101.465 101 465D FIXED COST
(i) TOTAL INDIRECT COST 29.16 31.21 3326 33 26 33.26(ii) TOTAL DEPRECIATION (W.D.V.) 9.15 7.78 6.61 5.62 4.78
(iii) INTEREST ON T.L 6.62 5.40 3.88 2.41 092
(iv) INTEREST ON W.C.LOAN 3.43 343 3.43 3.43 343
TOTAL D 48.36 47.82 47.18 44.72 42.39
BREAK EVEN POINT : D/C1 %AGE E 44.12 46.55 46.26 44.07 41.78
AVERAGE B.E.P. 44.56%
BREAK EVEN SALES 93.357 RS. LAKH PER ANNUM
AVERAGE MONTHLY SALES (B.E.P) RS. 7.78 Lakhs
CALCULATION OF RETURN ON CAPITALINVESTMENT
YEAR
I II III IV V
A RETURN ON CAPITAL EMPLOYED1 NET PROFIT AFTER TAX 17.15 17.10 20.59 22.22 24.062 Depreciation on Fixed asset added 9.15 7.78 6.61 5.62 4.7
826.30 24.88 27.20 27.84 28.84
B CAPITAL EMPLOYED
2 FIXED CAPITAL 61 54.20 40.60 27.00 26.50
3 Shared capital 12.29 12.29 12.29 12.29 12.29Total of 2*3 73.29 66.49 52.89 39.29 38.79
C RETURN ON CAPITAL EMPLOYED 35.89 37.42 51.42 70.85 74.34
D AVERAGE RETURN ONCAPITAL EMPLOYED - % AGE 53.9838