Project Orion Progress and Challenges
Mark GeyerOrion Project Manager
February 26, 2008
Constellation Program Components
Ares V -Heavy Lift
LaunchVehicle
Ares I -Crew
LaunchVehicle
EarthDeparture
Stage
Orion - CrewExploration
Vehicle
Altair-Lunar
Lander
Orion-CEV Expanded View
Launch Abort Systememergency escape during launch
Crew Modulecrew and cargo transport
Service Modulepropulsion, electrical power,
fluids storage
Spacecraft Adapterstructural transition toAres launch vehicle
44
• 5 meter diameter capsule – Apollo shape
• Significant increase in volume from Apollo (3.9 meter)
• Proven safe technique to withstand extreme heating loads
• Able to leverage Apollo performance data
• Reduced development time and risk
• Larger Crew Accommodations
• Lunar missions: 4 crew
• Space Station missions: 6 crew
• Expanded Mission Capabilities
• Long Duration (6 months)
• State-of-the-Art Materials, Systems
3.9 M 5.0 M
Orion Design and Operational Heritage
Orion Earth Orbital Mission
• Capable of supporting ISSmissions
• Transport up to 6 crewmembers on Orion for crewrotation
• 210 day stay time
• Emergency lifeboat forentire ISS crew
• Deliver limited pressurizedcargo for ISS resupply
Orion Lunar Mission
• Orion and Lunar Landerboosted to lunar orbit
– Up to 4 crew onboard
• Lander descends to lunarsurface
• Orion is uninhabited duringlunar surface operations
• Lander upper stage returnsto Orion in lunar orbit
• Orion returns crew to Earth
Orion/Ares Flight Schedule Overview
FY06
SRR
Project
Requirements Prime Award
CDR
SDR
PDR
Development / Qual
Testing
Flight Article
Production
InitialOperationalCapability
9/2013
Project Design
Integrated ARES-
Orion Launches
FY07 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15
TransonicAbort
Max qNom Abort
Devt.LASPA
ProtoLASPA
Ares I-XFT
(1st stage test)
Ares 1-YHi Alt Abort
Orion 1OrbitFlight
Tumble Abort
O-2 O-3 O-4 O-5
FullOperationalCapability(6-Crew)
Lunar Sortie Mission
Video
Orion Project Driving Challenges
• Expect to fly Orion for a generation
• Mission adaptability as explorationevolves
• Block upgrades to capability asexperience gained
– First major upgrade for lunar capability
• Invest in safety – “Liftoff to Landing”
• Design for low operations cost –Invest in life cycle efficiency and lowesttotal ownership cost as basis ofsustainability
• Leverage experienced workforce andindustrial capability
Recent Orion Accomplishments
Facility Renovation–
GRC IET Facility
Wind Tunnel Testing
LAS Abort Motor Test Firing
Abort Test Launch Complex - WSMR
Pad Abort Test #1 – Crew Module
Boilerplate Test Article