Project Planning Mclean Farms Pvt. Ltd.

Project Planning TJ 23 June

Embed Size (px)

Citation preview

Page 1: Project Planning TJ 23 June

Project PlanningMclean Farms Pvt. Ltd.

Page 2: Project Planning TJ 23 June

Upcoming ProjectsUpcoming Projects

1. MF Labelling System2. Moba Integration

Moba Client Data Import to PFMS Database Import Cracked, Dirt and licker data to PFMS

Database Off grade Alert & tracking system

3. Supervisor’s Performance Tracking System

Page 3: Project Planning TJ 23 June

MF Labelling SystemMF Labelling System

1. TUN Labelling System2. Pallet tag Labeling System

Regular Pallet tag Promo Pallet tag 1st/2nd grade Pallet tag Pulp vats Pallet tag

3. Settings Printer Settings Barcode detail settings

Page 4: Project Planning TJ 23 June

1. TUN Labelling System1. TUN Labelling System

Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary and Tejas

Design Specification 1 Days Rosemary and Tejas

Approval 1 Day Rosemary

Development 5 Days Rosemary & TJ

Testing 1 Day Tejas & Rosemary

Create User Guide 1 Day Tejas

Total Estimate Time 10 DaysLive Environment: Install Application on Front Room PC

Training 5 Day Tejas and Supervisors

Total Project time including Training: 15 Days (3 Weeks)

Project Estimate TimeProject Estimate Time

Page 5: Project Planning TJ 23 June

2. Pallet tag labelling System2. Pallet tag labelling System

TASK DURATION in Days (7Hr/Day) Total Working

Days

Team Member

sREGULAR

PROMO 2ND RADE

PULP VATS

Settings

Roughly Design Planning

1 1 1/2 1/2 1 4 RG, TJ, Byron

Design Specification

1 1 1 1 1 4 RG & TJ

Approval 1 12 1/2 1/2 1/2 3 RG

Development

10 8 3 3 5 29 RG & TJ

Testing 1 1 1 1 1 5 RG & TJ

User Guide

1 1 1 1 1 5 TJ

Total Estimate Time: 50 Working Days

Training 5 5 5 5 20 RG & TJ

Total estimate Project time including Training: 70 Working Days (3 Month + 2 Weeks)

Project Estimate TimeProject Estimate Time

Page 6: Project Planning TJ 23 June

2. MOBA Integration

Page 7: Project Planning TJ 23 June

Off Grade Tracking & Alert SystemOff Grade Tracking & Alert System

• What is Off grade eggs? If MOBA system detects eggs with …..

Cracked Blood Dirt

called Off grade eggs.

Machine Speed: Nearly 3 Dozen per Second (36 Eggs)

Page 8: Project Planning TJ 23 June

Off Grade Track & Alert SystemOff Grade Track & Alert System

Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary, Byron and

Tejas

Design Specification 1 Days Rosemary and Tejas

Approval 1 Day Rosemary

Development 10 Days Rosemary & Tejas

Testing 1 Day Rosemary & Tejas

Create User Guide 1 Day TejasTotal Estimate Time 15 Days

Live Environment: Install Application on Spare TV (PC) on PF

Training 5 Day Tejas and Maintenance

Total Project time including Training: 20 Days (4 Weeks)

Project Estimate TimeProject Estimate Time

Page 9: Project Planning TJ 23 June

3. Performance Tracking System

Task Duration (7Hr/Day) Team member Roughly Design Planning 1 Day Rosemary, Byron and

Tejas

Design Specification 1 Days Rosemary and Tejas

Approval 1 Day Rosemary

Development 20 Days Rosemary & Tejas

Testing 1 Day Rosemary & Tejas

Create User Guide 1 Day Tejas

Total Estimate Time 25 DaysLive Environment: Install Application on Byron’s PC

Training 1 Day Tejas

Total Project time including Training: 26 Days (5 Weeks)

Project Estimate TimeProject Estimate Time

Page 10: Project Planning TJ 23 June

SummarySummary

Projects DurationMF Labelling System 17 Weeks (4 Months + 1 Week)

MOBA: Off grade Tracking & Alert System 04 Weeks (1 Month)

Performance Tracking system 05 Weeks (1 Month + 1 Week)

Total Estimate Development time: 6 Month + 2 Weeks (910 Hours)