1 | Projects Portfolio Navu Memafu - Pacific Palms Property 1. WINDWARD EAST – Port Moresby, NCD Project Description: Windward East Apartments is a 14-storey executive apartments building comprises of total of 40 units which includes 24x3 bedrooms, 12x2 bedrooms, 2x2 bedroom penthouses, 1x4 bedroom penthouse and 1x5 bedroom penthouse, all penthouses have two levels. The apartment is enhanced with amenities including swimming pool, gymnasium facility, tennis, pool tables, kids’ playground, squash and BBQ area. The building has 3 levels of basement car parking and a visitor car park at Ground Floor. Architect: Cullen Feng Architects (Australia) Contractor: China Railway Construction Group (CRCG) Construction Cost: K89, 648,000.00 Construction Duration: 2010 – October 2014 Roles in the Project Assist the superintendent (project manager) with the daily supervision of the construction work by the main contractor and subcontractors. Assist the superintendent (project manager) with the daily project administration work. Carry out daily inspections on construction work to make sure the contractor(s) comply with the approved standards and the project requirements. Liaise with the project consultants (architect, consultant engineers, etc.) to make sure their system(s) are installed correctly and as per the engineering design. Coordinated the defect liability period (DLP) by liaising with the main contractor during the defects rectification work.

Project Portfoilio

Embed Size (px)

Citation preview

Page 1: Project Portfoilio

1 | P r o j e c t s P o r t f o l i o Navu Memafu - Pacific Palms Property

1. WINDWARD EAST – Port Moresby, NCD Project Description: Windward East Apartments is a 14-storey executive apartments building comprises of total of 40 units which includes 24x3 bedrooms, 12x2 bedrooms, 2x2 bedroom penthouses, 1x4 bedroom penthouse and 1x5 bedroom penthouse, all penthouses have two levels. The apartment is enhanced with amenities including swimming pool, gymnasium facility, tennis, pool tables, kids’ playground, squash and BBQ area. The building has 3 levels of basement car parking and a visitor car park at Ground Floor. Architect: Cullen Feng Architects (Australia) Contractor: China Railway Construction Group (CRCG) Construction Cost: K89, 648,000.00 Construction Duration: 2010 – October 2014 Roles in the Project

Assist the superintendent (project manager) with the daily supervision of the construction work by the main contractor and subcontractors.

Assist the superintendent (project manager) with the daily project administration work.

Carry out daily inspections on construction work to make sure the contractor(s) comply with the approved standards and the project requirements.

Liaise with the project consultants (architect, consultant engineers, etc.) to make sure their system(s) are installed correctly and as per the engineering design.

Coordinated the defect liability period (DLP) by liaising with the main contractor during the defects rectification work.

Page 2: Project Portfoilio

2 | P r o j e c t s P o r t f o l i o Navu Memafu - Pacific Palms Property

2. PENTHOUSE 2 REFURBISHMENT – Port Moresby, NCD Project Description: Major refurbishment work for the double storey Penthouse 2 suite at the top level of Windward West. The Penthouse 2 refurbishment was part of the property upgrade for the Windward West Apartments. Interior Designer: Space Studio NZ (New Zealand) Contractor: Pacific Structure Limited Project Cost: K1 million Construction Duration: February 2014 – May 2014 Roles in the Project

Oversaw the overall construction work and progress of the project undertaking by the main contractor and subcontractors.

Liaised with interior designer (Space Studio from New Zealand) to make sure the contractor comply with the design requirements and standards.

Carried out daily inspections to make sure the work is done properly and correctly.

Managed client supply items for the project to make sure they are ordered and supplied in a timely manner.

Prepared weekly progressive reports for senior management information and update.

Page 3: Project Portfoilio

3 | P r o j e c t s P o r t f o l i o Navu Memafu - Pacific Palms Property

3. WINDWARD WEST RENOVATION – Port Moresby, NCD Project Description: Windward West is a 14-storey Apartment building which completed construction in 1987 by Fletcher Morobe Construction Limited in 1985. After over 30 years, the building has gone through it first ever major renovation. The apartment comprise of 12 x 2 bedroom unit with ensuites, 12 x 3 bedroom with ensuites and 2 x double storey penthouses. Architect: Pacific Palms Property – In house Contractor: Pacific Palms Property – In house Project Cost: K8 million Construction Duration: October 2014 – April 2016 Roles in the Project

Construction Manager to manage day to day operations of the construction work on site.

Managed and supervised a team of construction workers including builders, carpenters, joiners, plumbers, electricians, plasterers, painters, etc…

Supervised all specialist contractors undertaking works with the major renovation project.

Managed building materials and equipment procurement from local and overseas suppliers to make sure the materials ordered are correct and deliver to the project site in a timely manner.

Prepared and submitted monthly progress status report to the Property Development Manager for senior management update.

Page 4: Project Portfoilio

4 | P r o j e c t s P o r t f o l i o Navu Memafu - Pacific Palms Property

4. HARBOURSIDE DEVELOPMENT – Port Moresby, NCD Project Description: Steamships Harbourside Development project has been the first post-industrial portside development in Port Moresby and it consists of two, six and seven storey buildings respectively. The buildings cater for office spaces, professional suites, basement parking, ground floor retail as well as restaurants over the water-edge and boat moorings. The esplanade and water front building façade are composed of glazed curtain walls and perforated sun shading. The building forms have the slight angular geometry typical of the steel coastal ship hulls that have used the site for many years. Architect: Cullen Feng Architect (Australia) Construction Manager: China Railway Construction Group (CRCG) Project Cost: K180 million Construction Duration: March 2012 – June 2015 Roles in the Project

Assisted superintendent (project manager) with the daily supervision of the construction work by the main contractor and subcontractors.

Liaised with consultants (architect, services, structural, mechanical, etc.) to make sure their system(s) are correctly and properly done.

Oversaw fit-out works by tenants’ contractors to make sure they comply with our company’s requirements and building regulations.

Coordinated the defect liability period by liaising with the main contractor to fixing the defects identified.

Page 5: Project Portfoilio

5 | P r o j e c t s P o r t f o l i o Navu Memafu - Pacific Palms Property

5. CASSOWAY HOTEL – Kiunga, Western Province Project Description: Cassowary Hotel in Kiunga, Western Province is a joint venture project between Ok Tedi Development Foundation (OTDF) through CMCA and Steamships Trading Company Limited (STC) in which Pacific Palms Property (PPP) was nominated as the project manager to manager the project from initial design to completion of construction. The hotel is modular system manufactured in Thailand and shipped to PNG and it comprises of 45 guest rooms, staff accommodations, restaurant, dining, lounge and enzo’s pizza outlet and has total of 4 levels from Ground Floor to Level 3 and laundry at the basement area. Architect: Thomson Adsett Architects (Australia) Construction Manager: The George Group – TGG (PNG) Limited Project Cost: K32 million Construction Duration: May 2016 – April 2017 (ongoing) Roles in the Project

Client’s representative at construction site as the Site Architect and Project Administrator.

Oversee the overall construction of the hotel undertaken by the construction manager.

Provide contract admin work for the project (review, verify and recommend contractor’s claims) before approval is given by the client.

Carry out daily site inspection to make sure the works are done in accordance with the requirements in the contract.

Prepare and submitted progressive site inspection reports for the senior management and the client.