Project Report and Appraisal

Embed Size (px)

Citation preview

  • 8/13/2019 Project Report and Appraisal

    1/26

    CA Day July 01 20071

    Project Report and AppraisalPreparation of a Project Report

    and appraisal thereof

  • 8/13/2019 Project Report and Appraisal

    2/26

    CA Day July 01 2007CA Debasish Banerjee2

    Introduction

    Project finance is providing financefor particular projects, which is later

    repaid from cash flows generated bythose specific projects.

    Importance of risk management inproject finance

  • 8/13/2019 Project Report and Appraisal

    3/26

    CA Day July 01 2007CA Debasish Banerjee3

    Agenda

    Today we are going to discuss the methodof preparing a Project Report and its

    appraisal

    Preparing of Schemes for SSI Registration

  • 8/13/2019 Project Report and Appraisal

    4/26

    CA Day July 01 2007CA Debasish Banerjee4

    OverviewProject Report preparation involvesFixation of Cost of Project

    Fixation of Means of FinancingPreparation of Financial StatementsAssessing Financial viability

    Assessing Economic viability

  • 8/13/2019 Project Report and Appraisal

    5/26

    CA Day July 01 2007CA Debasish Banerjee5

    Fixation of cost of Project

    Great care should be takenEvery item is properly scrutinized by financer

    Over-invoice to be avoided and creditability ofthe promoters retainedOmission to be financed by promoterTime schedule fixed byBar-Chart ( < 5 crores)PERT or CPM method

  • 8/13/2019 Project Report and Appraisal

    6/26

    CA Day July 01 2007CA Debasish Banerjee6

    Fixation of cost of Project

    The Cost of ProjectLand and Site developmentBuilding and civil woksPlant & MachineryEscalation & contingenciesOther Fixed AssetsTechnical know-how feesInterest during constructionPreliminary & Preoperative expensesMargin Money for working capital

  • 8/13/2019 Project Report and Appraisal

    7/26CA Day July 01 2007CA Debasish Banerjee7

    Land and site development

    Basic Cost of landConveyancing charges and other allied charges

    Levelling of the plotLaying of the internal roadLaying of the approach roadConstruction of the Boundary WallsConstruction of the main gateTube-well digging cost

  • 8/13/2019 Project Report and Appraisal

    8/26CA Day July 01 2007CA Debasish Banerjee8

    Building and civil works

    Main factory BuildingAllied civil structure

    There is a tendency of over stating this costThere is a tendency for over-run due to increase in

    the area and / or cost of construction

  • 8/13/2019 Project Report and Appraisal

    9/26CA Day July 01 2007CA Debasish Banerjee

    9

    Plant & Machinery

    Evaluation of technologiesIncreased Profitability

    Saving of labourBetter consumption normsLesser requirement of PlantsEase in availability of raw material

    Selection of plant & machinery

  • 8/13/2019 Project Report and Appraisal

    10/26CA Day July 01 2007CA Debasish Banerjee

    10

    Escalation and contingencies

    Takes care of escalation which may take placeduring the actual implementation of the project.

  • 8/13/2019 Project Report and Appraisal

    11/26CA Day July 01 2007CA Debasish Banerjee

    11

    Miscellaneous Fixed Assets

    There are other items of machinery whichdo not form part of the direct

    manufacturing process

    These should be supported with quotations

  • 8/13/2019 Project Report and Appraisal

    12/26CA Day July 01 2007CA Debasish Banerjee

    12

    Technical know-how fees

    Fees for technical consultancy

  • 8/13/2019 Project Report and Appraisal

    13/26CA Day July 01 2007CA Debasish Banerjee

    13

    Interest during construction

    periodThe promoter is required to pay the interestduring the period and depends on

    Quantum of loanDuration for which the loan will remain

    outstanding

  • 8/13/2019 Project Report and Appraisal

    14/26

    CA Day July 01 2007CA Debasish Banerjee14

    Preliminary & preoperative

    expensesExpenses which are not directly relatedwith any of the above expenses and are

    required to be incurred

  • 8/13/2019 Project Report and Appraisal

    15/26

    CA Day July 01 2007CA Debasish Banerjee15

    Margin money for working

    capitalEssential requirement of any project is theWorking Capital

    Assessment of W.C. requirement20% of TurnoverCA-CL=WC & then 25% margin

    MPBF (Maximum Permissible BankFinance)

  • 8/13/2019 Project Report and Appraisal

    16/26

    CA Day July 01 2007CA Debasish Banerjee16

    Fixation of Means of Financing

    Debt Equity Ratiomaximum permissible is 3:1 for small scale unit

    And 2:1 for other unitsPromoters contribution Unsecured Loan

    Debt Service Coverage Ratio Repaymentcapacity

  • 8/13/2019 Project Report and Appraisal

    17/26

    CA Day July 01 2007CA Debasish Banerjee17

    Debt Service Coverage Ratio

    Should be in the vicinity of 1.5. Earlier it was 2.High DSCR can be reduced by

    Reducing cash accrualsBy lower Capacity UtilizationMore Pessimistic Approach

    Altering the Interest

    Increasing the Instalment of the loanLow DSCR can be reviewed alternatively byreversed remedy

  • 8/13/2019 Project Report and Appraisal

    18/26

    CA Day July 01 2007CA Debasish Banerjee18

    Preparation of financial

    statementfor the period of atleast the tenure of the term

    loan

    Cost of production and profitabilityCash Flow StatementBalance Sheet

  • 8/13/2019 Project Report and Appraisal

    19/26

    CA Day July 01 2007CA Debasish Banerjee19

    Preparation of financial

    statement for existing Unitsfor the period of atleast the tenure of the term

    loan

    Cost of production and profitabilityIncrease in Sale above 20% should be properly

    explained

    Cash Flow StatementBalance Sheet

  • 8/13/2019 Project Report and Appraisal

    20/26

    CA Day July 01 2007CA Debasish Banerjee20

    Performance Ratios

    Share Capital Reserve NET WORTHProfitability ratios

    Analysis of Cash AccrualsAnalysis of SalesAnalysis of the Working CapitalAnalysis of Debtorsmore than 6 months may be considered not

    recoverable

  • 8/13/2019 Project Report and Appraisal

    21/26

    CA Day July 01 2007CA Debasish Banerjee21

    Break Even Point

    Fixed CostVariable Cost

    ContributionBreak Even Point

  • 8/13/2019 Project Report and Appraisal

    22/26

    CA Day July 01 2007CA Debasish Banerjee22

    Internal Rate of Return

    Return on Investment methodPay back method criteria

    Net present value criteria ( discounted)Internal Rate of return

  • 8/13/2019 Project Report and Appraisal

    23/26

    CA Day July 01 2007CA Debasish Banerjee23

    Internal Rate of Return

    Internal Rate of returnThe cash flow are total ( Rs 35,000)

    The average cash flow calculated ( Rs 35000/5= Rs7000)The initial investment is divided by the average Cash

    flow to 3 decimal places (Rs 20000/7000=2.856)

    This figure is matched with the annuity table and theclosed rate for the number of years ( 5 yrs) for whichthe project is expected to have economic life isevaluated. It works out to 22.1%

  • 8/13/2019 Project Report and Appraisal

    24/26

  • 8/13/2019 Project Report and Appraisal

    25/26

    CA Day July 01 2007CA Debasish Banerjee 25

    Additional Formats

    Preparation of a Project ReportPreparation of the CMA Data for the Bank

    (Format enclosed)Appraisal Report of the Banker (Formatenclosed)

    Credit rating Norms ( details enclosed )Preparation of Schemes ( Format enclosed)

  • 8/13/2019 Project Report and Appraisal

    26/26

    CA Day July 01 2007CA Debasish Banerjee 26

    More Information

    For those who love to readGuide to Project Finance enclosed in CD

    (downloaded from Net)Project Reports and Appraisals byH.P.S.Pahwa (Bharat Law House Pvt Ltd)

    Credit Appraisal of any Bank