Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
1
http
://pm
sym
posiu
m.u
md.
edu
Mairav Mintz, PE, CCMSagar Khadka, DRMP, FAACE
2018 Project Management SymposiumFriday, May 11, 20189:45am to 10:15am
PROJECT RISK MANAGEMENT: CONTEXT, TOOLS AND REAL WORLD APPLICATIONS
2
Project Risk Management: Perspective– Construction Projects: On Time within Budget?– Industry Trend: Current Practice of Risk Management
Project Risk Management: Practical Tools for Any Project– Risk Management Overview– Schedule Risk Analysis– Cost Risk Analysis– Integrated Cost-Schedule Risk Analysis (ICSRA)
Real World Example– GAO Mandated ICSRA: Multi-Phase, Historic Renovation
Outline
3
• In a study of 258 transportation infrastructure projects*– Completed between 1927 and 1998– On five continents– In 20 countries– $90 Billion in (1995 prices)
• Cost overruns were prevalent –– 9 out of 10 projects– Affected projects in all 20 countries
• In MBP’s own research from a review of over 2,500 schedules –– No instance of cost >100% and time <100%– Cost overruns correlate with schedule delays
*Bent Flyvbjerg, Mette Skamris Holm, and Søren BuhlJournal of the American Planning Association,
Vol. 68, No. 3, Summer 2002
Project Risk Management: PerspectiveConstruction Projects: On Time within Budget?
4
• In a 2017 Dodge Data & Analytics Study** -– Data gathered from over 500 respondents– Owners, general contractors, trade contractors– Examined 25 different risk factors and 10 different risk evaluation and
mitigation approaches• 75% of respondents reported experiencing a dispute or claim in
the last five years– For transportation projects, that number was over 80%
• Dodge reported that the construction industry has seen a shift from recession to higher levels of activity, but the risk landscape has just changed, not declined
**“Managing Risk in the Construction Industry”Dodge Data & Analytics SmartMarket Report, 2017
Project Risk Management: Perspective
5
• GAO is responsible for assisting Congress in the oversight of federal agencies including their stewardship of public funds
• GAO has established best practice guides– GAO Cost Estimating and Assessment Guide - Best
Practices for Developing and Managing Capital Program Costs, GAO-09-3SP, March 2009
– GAO Schedule Assessment Guide – Best Practices for Project Schedules, GAO-16-89G, December 2015
• GAO mandates that project budget and duration consider risks and uncertainty
• GAO mandates agencies incorporate and implement a rigorous risk management program
Industry Trend: Current Practice of Risk Management
Project Risk Management: Perspective
6
Tools
Schedule Risk Analysis Cost Risk Analysis
Integrated Cost-Schedule Risk Analysis
Tools
Contract Documents, Plans & Specs
Risk Management
• Bonds, Insurance & Warranties• Safety & Accident Prevention• Dispute Resolution Provisions• Scope Creep, Force Majeure• Default, Professional Liability ….
• Incomplete Design• Defective Plans & Specification• Inadequate Site Investigation• Unrealistic Schedule, Budget• Unforeseen conditions ….
Traditional Risk Management Project Risk Management
Risk Management Overview
Risk Register & On-going Project Risk Management
Known and Insurable Known and Unknown
7
Project Risk Management Model
14
8
An active and forward looking tool to:
– Identify foreseeable risk events
– Analyze the potential impact of each risk event on the project
– Prioritize risks based on the severity of impact through the use of a Risk Matrix and Risk Register
– Create problem solving strategies to mitigate risk impacts
– Keep an eye on each risk until it has been averted, mitigated or resolved
Project risk management is a continuous effort
Project Risk Management
Risk Matrix and Project Risk Register
9
Will my project complete on
time?Tools
Schedule Risk Analysis Cost Risk Analysis
Integrated Cost-Schedule Risk Analysis
Project Risks
Project Risk Management
Risk Register & Ongoing Project Risk Management
Schedule Risk Analysis
10
MobilizationDemolition
Excavation
Concrete StructureInterior/MEP/Cx/Accreditation
Demobilization
Permit
NTP
ProjectCompletion
Conceptual Project Schedule
In quantitative risk analysis “Risk and Uncertainty” are applied to the CPM schedule activities to assess their impact on project schedule
Schedule Risk Analysis
11
(Inherent variability in activity duration, cost estimates)
35 Days (most likely)
30 Days (min) 45 Days (max)
Schedule Risk Analysis - Uncertainty
15%
10%
0%
12
(External factors that affect estimates, duration)
Risk Driver as Threat pushes cost, schedule duration
35 Days (most likely)
30 Days (min) 55 Days (max)
Schedule Risk Analysis – Uncertainty & Risks
15%
10%
0%
13
15%
10%
0%
(External factors that affect estimates, duration)
Risk Driver as Opportunity improves cost, schedule duration
35 Days (most likely)
20 Days (min) 45 Days (max)
Schedule Risk Analysis - Opportunity
14
MobDemolition
Excavation
Concrete StructureInterior/MEP/Cx/Accreditation Demob
PermitNTP
ProjectCompletion
Conceptual Project Schedule
NTPPermit
MobDemolition
Concrete StructureInterior/MEP/Cx/Accreditation
Conceptual Project Schedule(with uncertainty and risks)Risk: Unforeseen conditions, rock,
ExcavationRisk: batching plant, excessive heat, steel delivery, skilled laborRisk: difficulty
getting permit
Risk: difficulty getting workers screened
Schedule Risk Analysis
Demob
ProjectCompletion
Risk: Availability of MEP trade
Project Delay
15
2016-05-01 2016-06-20 2016-08-09 2016-09-28
Distribution (start of interval)
0
100
200
300
400
500
600
700
800
Hits
0% 2016-05-13
5% 2016-06-20
10% 2016-06-25
15% 2016-06-29
20% 2016-07-02
25% 2016-07-05
30% 2016-07-08
35% 2016-07-11
40% 2016-07-13
45% 2016-07-15
50% 2016-07-18
55% 2016-07-20
60% 2016-07-22
65% 2016-07-25
70% 2016-07-28
75% 2016-07-30
80% 2016-08-03
85% 2016-08-06
90% 2016-08-12
95% 2016-08-19
100% 2016-10-11
Cum
ulat
ive
Freq
uenc
y
Schedule Risk AnalysisEntire Plan : Finish Date
Schedule Time Contingency
(P80) or 80% Confidence
Deterministic Date
Schedule Risk Analysis and Time Contingency
Schedule Risk Analysis
16
Will my project complete
within budget?Tools
Schedule Risk Analysis Cost Risk Analysis
Integrated Cost-Schedule Risk Analysis
Risk Register & Ongoing Project Risk Management
Project Risks
Project Risk Management
Cost Risk Analysis
17
Will my project complete
within budget and on time?
Tools
Schedule Risk Analysis Cost Risk Analysis
Integrated Cost-Schedule Risk Analysis
Project Risks
Project Risk Management
Risk Register & Ongoing Project Risk Management
Integrated Cost-Schedule Risk Analysis
18
Schedule Time Contingency
(P80) or 80% Confidence
Deterministic Date
Why perform an integrated cost-schedule risk analysis?
Cost Contingency
Deterministic Cost
(P80) or 80% Confidence
Integrated Cost-Schedule Risk Analysis
– Cost risk analysis calculates a cost contingency but does not account for the cost impact associated with schedule overrun
– Schedule risk analysis calculates a time contingency but does not consider the cost overrun associated with schedule slippage
19
Process OverviewProject Execution Plan (Baseline Schedule, Plans and Specs)
Cost-Loaded CPM Summary Schedule
Individual Risk Interviews
Pre-Mitigated Risk Modeling and Analysis
Pre-Mitigated Risk Results
Group Risk Mitigation Workshop
Draft Risk Results
Post-Mitigated Risk Modeling and Analysis
Finalize Schedule
Evaluation of Cost-Loaded CPM Schedule against
GAO’s Ten Best Practices
Mitigated Risk Data
19
20
• Characteristics of Integrated Cost-Schedule Risk Analysis– Utilizes a cost-loaded CPM schedule, which includes:
• Direct costs
• Time dependent costs
– Excludes estimated contingencies
– Risk driver method considers:• Uncertainty
• External risks
• Results of this Analysis– Quantifies the impact of schedule slippage on project cost
– Identifies the top schedule and cost risk drivers
– Can develop risk mitigation strategies for top risks
Integrated Cost-Schedule Risk Analysis
21
– Complete building interior and exterior restoration including infrastructure
– Removal/replacement of building’s top floor– Five-phase, 10-year construction effort– Fully occupied building; VIP occupants– Secured access– Urban setting with no laydown areas– Situated in a residential neighborhood– Historic renovation– $750 million budget– Intractable completion dates for each phase
Case Study: GAO Mandated ICS Risk Analysis
Multi-Phase Historic Renovation
22
UNIQUE PHASING CONSIDERATIONS
Jan 2015 Jan 2017 Jan 2019 Jan 2021 Jan 2023 Jan 2025
Pre-Phase 1
Mov
e
Pre-Phase 2 Pre-Phase 3 Pre-Phase 4
Phase 0 Phase 1 Phase 2 Phase 3 Phase 4
• Completion Date: December 2024• Project Total Budget: $752.7 million
Mov
e
Mov
e
Mov
e
Mov
e
Mov
e
Mov
e
Mov
e
Case Study: GAO Mandated ICS Risk Analysis
Multi-Phase Historic Renovation
23
UNIQUE PHASING CONSIDERATIONS
Failure to complete a phase on time would result in missing a move cycle and an immediate two year delay
Jan 2017 Jan 2019 Jan 2021
Dec 1st
Phase 1 Move-In
Dec 1st
2 Year Delay
Phase 2
Pre-Phase 2 Move-Out Pre-Phase 3Move-Out
Move-In
Case Study: GAO Mandated ICS Risk Analysis
Multi-Phase Historic Renovation
24
Results with risk from pre-mitigated simulation, at the 80th percentile:• Projected to miss move cycle for all of Phases 1 - 4• Projected finish date of 2035, 11 years beyond the required completion date• Cost, with inflation including contingency, rises to $1 billion, $250 million above
budget
Jan 2017 Jan 2019 Jan 2021Dec 1st
Phase 1 Move-In
Dec 1st
2 Years Delay
Phase 2
Pre-Phase 2 Move-Out Pre-Phase 3Move-Out
Move-In
Case Study: GAO Mandated ICS Risk Analysis Multi-Phase Historic Renovation
Results from the initial Cost-Schedule Risk Analysis - prior to the risk mitigation workshop - were not acceptable
25
Project Team worked hard during the Risk Mitigation Workshops:• Reviewed Risk Parameters
• Probability• Duration Impact Parameters• Cost Impact Parameters
• Developed Mitigation Strategies• Agree on Mitigation Strategies• Make commitments• Create Action Items (for follow through)
• Revised Risk Parameters based on the Mitigation Strategies Selected• Probability• Duration Impact Parameters• Cost Impact Parameters
Case Study: GAO Mandated ICS Risk Analysis Multi-Phase Historic Renovation
26
Three risk mitigation workshops were required before arriving at mitigations that achieved project objectives:
• In lieu of acceleration to gain back time, the Project Team elected to proceed with an early start process to allow for:– Early bid package buyout– Early start of key submittals– Early start of long lead item procurement
• This achieved the necessary schedule objectives• Also, the cost savings associated with the early start scenario vs mandated
acceleration was significant
Case Study: GAO Mandated ICS Risk Analysis Multi-Phase Historic Renovation
27
Multiple tools are available to manage project risk:– Will my project finish on time? Consider schedule risk
analysis– Will my project stay within budget? Consider cost risk
analysis– How will risk and uncertainty impact my project’s cost
and schedule objectives? Consider integrated cost-schedule risk analysis
– How do I keep my project on track? Consider a risk matrix and risk register as part of a regular risk management program• Plan, identify, analyze, monitor, and mitigate risks• Prioritize and allocate resources where they are needed most
Recap