Project Risks

Embed Size (px)

Citation preview

  • 7/31/2019 Project Risks

    1/28

    Project Risks

    Anil Agashe

  • 7/31/2019 Project Risks

    2/28

    Risks in Projects

    What is Risk? Probability or chance that a thing will not turn out as

    planned

    High certainty of outcome means less risk and vice

    versaWhy analyze and quantify risk? Since large sums of money (or effort converted to

    money) over a period of time are involved in Projects;

    Many Projects embody a firms strategic intent;

    Lenders are interested in the Projects ability toservice the debt.

  • 7/31/2019 Project Risks

    3/28

    Risks in Projects

    Risks in Projects stem from

    Technical uncertainties/ constraints

    Schedule uncertainties

    Cost uncertainties

  • 7/31/2019 Project Risks

    4/28

    Risks in Projects

    High certainty of outcome depends on

    knowledge and experience in prior

    projects

    Unique or first time projects have higher

    element of risk

  • 7/31/2019 Project Risks

    5/28

    Risk Management

    Risk is a fact of life in Projects. Itsreduction by anticipation and contingencyplanning is the objective of Risk

    ManagementRisk Management Main elements

    Risk identification

    Risk assessment Risk response planning

  • 7/31/2019 Project Risks

    6/28

    Risk Identification

    Sources of risk

    Internal. Originating inside the project- Hencesome measure of control possible

    Two types of internal risks Market risk- Risk of not meeting market requirements

    or that of Customers due to inadequately defined

    Customer needs, failure to identify changing needs,

    unreliable forecast

    Technical risk Risk of not meeting time, cost andperformance requirements due to technical problems

  • 7/31/2019 Project Risks

    7/28

    Risk Identification

    Source of risk External- Originating external to the project. PM s

    have no control over this. Typical risks are changesin: (All these are situation specific!)

    Market conditions

    Competitor actions

    Government regulations/ Political risks

    Interest rates

    Exchange rate risk (for projects involving foreign exchange)

    Resource risk- availability of material and labour

    Customer needs and behaviour

    Supplier relations

    Nature (weather, natural calamities..)

  • 7/31/2019 Project Risks

    8/28

    How to identify risks?

    Reports from past projects

    List of user needs and requirements- more

    clarity, the better

    Risk check lists and levels of risk thought

    to be associated with risk sources

    Collective experience sharing of projectteam members by brain storming

  • 7/31/2019 Project Risks

    9/28

    Risk Assessment

    Once the risks have been identified, risk

    assessment is done in terms of

    Risk likelihood

    Risk impact

    Risk consequence

  • 7/31/2019 Project Risks

    10/28

    Risk Likelihood

    Probability that risk will materialize.

    Expressed as a numerical factor between

    0 ( impossible to happen) to 1 (certain to

    happen)

    Low risk Risk likelihood Value 0-0.2

    Medium risk Risk likelihood value 0.2-0.5High risk Risk likelihood value 0.5 - 1

    Risk likelihood values are assigned based on the

    collective judgement and experience of project personnel

  • 7/31/2019 Project Risks

    11/28

    Risk Impact

    If a risk materializes, the result is Risk

    impact. In project, risk impact is specified

    in terms of Excess Time (weeks or

    months), Excess Cost (Rupees) andReduction/ degradation in Performance

  • 7/31/2019 Project Risks

    12/28

    Risk Consequence

    Risk consequence is a function of Risk

    likelihood and Risk Impact

    Risk Consequence (Expected Value)= Risk Likelihood x Risk Impact

    Example : Say, the Risk Likelihood is 0.4 . If the risk materializes,

    it would delay the project by 3 months and increase the cost byRs. 200,000.

    The expected value of Risk consequences are

    Risk Consequence Time (RT) = 0.4x 3= 1.2 months

    Risk Consequence cost (RC) = 0.4x 200,000= Rs 80,000

  • 7/31/2019 Project Risks

    13/28

    Risk Priority

    The Project may contain many activities

    with risk.

    The risk consequence values for these

    activities are computed and ranked.

    Higher the value, more the priority

    Those with higher risk consequence

    values are given special attention

  • 7/31/2019 Project Risks

    14/28

    Risk Response Planning

    After Risk Identification and Risk

    Assessment , Risk Response Planning

    addresses the issue of how to deal with

    risk

  • 7/31/2019 Project Risks

    15/28

    Types of Risk Response

    PlanningTransfer the Risk

    Risk transferred in part or in full between Customer to

    Contractor or Third Party by means of Contract

    incentives, Contract Penalties, Contract Warrantiesattached to Project Cost, Schedules or Performance

    or by Insurance

    Penalties for delay and degraded performance

    Insurance for covering risks

  • 7/31/2019 Project Risks

    16/28

    Types of Risk Response

    PlanningReduce Risk (of technical performance)

    Minimize System complexity

    Employ best technical team

    Perform extensive tests and evaluations of

    system

    Use ofproven technology

    Use of Outside specialists and experts forreview and assessment of work

  • 7/31/2019 Project Risks

    17/28

    Types of Risk Response

    PlanningReduce risk ( associated with schedules)

    Create Master project schedule and follow it strictly

    Schedule most risky tasks as early as possible to

    allow time for catching up Close monitoring of critical tasks

    Deploy best workers on time critical tasks

    As far as possible, schedule high risk activities in

    parallel rather than in series Provide incentives for over time work

  • 7/31/2019 Project Risks

    18/28

    Types of Risk Response

    PlanningContingency Planning

    Identify risks

    Anticipate what ever might happen

    Prepare a detailed plan to cope with it

    Accept Risk (Do nothing)

    If the cost of avoiding risk exceeds the

    benefits then do nothing is a better option.

    Mostly for non severe risks

  • 7/31/2019 Project Risks

    19/28

  • 7/31/2019 Project Risks

    20/28

    Risk Analysis Method

    Risk Consequence (Expected Value)=

    Risk likelihood x Risk impact (outcome)

    Risk Consequence Time (RT)= Corrective

    Time x Likelihood

    Risk Consequence Cost= Corrective cost

    x Likelihood

  • 7/31/2019 Project Risks

    21/28

    Example

    Suppose the Base line Time Estimate (BTE)(Time estimate without any buffer) for projectcompletion is 30 weeks and Base line CostEstimate (with no buffer cost) is 800000Rs,. Ifthe risk likelihood is 0.3 for the project and if itmaterializes, the project delay is 5 weeks (riskimpact for time) and increase cost by 100000Rs(risk impact for cost ) , find out RT, RC and

    Expected Time of Completion & Expected costof Completion

  • 7/31/2019 Project Risks

    22/28

    Example

    RT= 5x 0.3 =1.5 weeks

    RC= 0.3x 100000= 30000Rs

    RT and RC are included as buffer or risk reservein the project schedule and cost

    After considering risk, the excepted projectcompletion time (ET) = 30+1.5= 31.5 weeks

    After considering risk, the expected projectcompletion cost (EC)= 800000+ 30000=830000Rs

  • 7/31/2019 Project Risks

    23/28

    Example

    When the corrective time and cost cannot

    be realistically established,

    ET= BTE (1+ likelihood)= 30 (1+0.3)= 39

    weeks (from previous example)

    EC= BCE (1+likelihood)= 800000(1+0.3)=

    1040000Rs

  • 7/31/2019 Project Risks

    24/28

    ExampleA project involves following activities. Against the activities are mentioned their

    respective Baseline Cost estimate and Baseline Time estimates , the corrective

    cost and time and the likelihood of risk.

    Activity Predecessor BCE BTE Corrective Cost Corr. Time Risk

    Rs Weeks Rs Weeks likelihood

    L - 20000 9 4000 2 0.2

    V L 16000 8 4000 2 0.3

    S L 16000 3 4000 1 0.3

    T S 32000 5 8000 2 0.1

    J V 18000 3 4000 1 0.1

    R V 10000 4 4000 3 0.3U J,T 20000 7 12000 3 0.2

    C J,R 15000 6 5000 2 0.3

    Calculate the Risk Time and Risk Cost for activities

    What is the Expected Time of completion of the project and Expected cost of

    completion?

  • 7/31/2019 Project Risks

    25/28

    Completion & Closing of

    Projects

  • 7/31/2019 Project Risks

    26/28

  • 7/31/2019 Project Risks

    27/28

    Action items for PM in this phase

    1. Documentation

    For the customer this is necessary to operate and

    maintain the item provided as a result of theproject

    For the Project executing team this is a record of

    events, experiences , hurdles and corrective

    actions taken to build a knowledge data base forfuture projects of similar nature

  • 7/31/2019 Project Risks

    28/28

    Action items for PM in this phase-

    Contd

    2. Closing down Project accounting system

    3. Conducting Project review

    Assess the performance of project team members,

    procedures for improvement action4. Disposal of Assets

    Surplus equipment and materials not needed

    anymore

    5. Ensuring that all stake holders are satisfied