Project Scheduling and Resource Management PPT (Dinesh K. C.)

Embed Size (px)

Citation preview

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    1/31

    Project Scheduling and

    Resource Management

    Presentation by:

    Dinesh K. C.III semester, MBA

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    2/31

    In this Presentation

    What is scheduling?

    Project Scheduling.

    Importance of Project Scheduling.Methods of Scheduling

    Resource

    Resource ManagementImportance of resource management

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    3/31

    Introduction

    A project is a collection of tasks that mustbe completed in minimum time or at

    minimal cost.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    4/31

    Project Schedule

    Split project into tasks and estimate timeand resources required to complete eachtask

    Organize tasks concurrently to makeoptimal use of workforce

    Minimize task dependencies to avoid

    delays caused by one task waiting foranother to complete

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    5/31

    Contd..

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    6/31

    Contd..

    Objectives of Project Scheduling

    Completing the project as early as possible by

    determining the earliest start and finish of

    each activity.

    Calculating the likelihood a project will be

    completed within a certain time period.

    Finding the minimum cost schedule needed tocomplete the project by a certain date.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    7/31

    Scheduling problems

    Estimating the difficulty of problems and hence the

    cost of developing a solution is hard

    Common myth: If we fall behind schedule, we can

    always add more programmers and catch up later in

    the project Productivity is not proportional to the number of people

    working on a task

    Adding people to a late project makes it later because of

    communication overheads

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    8/31

    OBJECTIVES FOR SCHEDULING

    EFFECTIVE TIME MANAGEMENT

    OPTIMZE SEQUENCE OF EVENTS

    DEFINE NECESSARY RESOURCES

    MONITOR PROJECT PROGRESS

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    9/31

    PRIMARY COMPONENTS IN A

    PROJECT SCHEDULE

    ACTIVITIES

    SPECIFIC FUNCTION

    FINITE DURATION

    DETERMINE LINKAGE SPECIFY RESOURCE REQUIREMENTS

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    10/31

    The PERT/CPM Approach for

    Project Scheduling

    The PERT/CPM approach to project

    scheduling uses network presentation of

    the project to

    Reflect activity precedence relations

    Activity completion time

    PERT/CPM is used for scheduling

    activities such that the projects completiontime is minimized.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    11/31

    Gantt Charts

    Gantt charts are used as a tool to monitor andcontrol the project progress.

    A Gantt Chart is a graphical presentation that

    displays activities as follows: Time is measured on the horizontal axis. A horizontal

    bar is drawn proportionately to an activity s expectedcompletion time.

    Each activity is listed on the vertical axis.

    In an earliest time Gantt chart each bar beginsand ends at the earliest start/finish the activitycan take place.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    12/31

    Gantt Charts-

    Monitoring Project Progress

    Graphical notations used to illustrate theproject schedule

    Show project breakdown into tasks. Tasks

    should not be too small. They should takeabout a week or two

    Activity charts show task dependencies

    and the critical path Activity Bar charts show schedule against

    calendar time

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    13/31

    Gantt Charts

    Advantages and DisadvantagesAdvantages. Easy to construct

    Gives earliest completion date.

    Provides a schedule of earliest possible start and finishtimes of activities.

    Disadvantages Gives only one possible schedule (earliest).

    Does not show whether the project is behind schedule.

    Does not demonstrate the effects of delays in any oneactivity on the

    start of another activity, thus on the project completion

    time.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    14/31

    Contd..

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    15/31

    Benefits of Resource Scheduling

    If project delay is unacceptable, it allowssufficient time for considering alternativessuch as cost-time trade-offs and changing

    of priorities.Provides information to prepare time-phased work package budgets with dates

    Enables project managers to determinethe amount of flexibility they have overcertain resources.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    16/31

    Resource Allocation Problem

    A shortcoming of most scheduling

    procedures is that they do not address the

    issues of resource utilization and

    availability.

    Scheduling procedures tend to focus on

    time rather than physical resources.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    17/31

    Resource Allocation Problem

    Schedules should be evaluated not merelyin terms of meeting project milestones, butalso in terms of the timing and use ofscarce resources.

    A fundamental measure of the projectmanagers success in project

    management is the skill with which thetrade-offs among performance, time, andcost are managed.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    18/31

    Resource Management in Projects

    Resource management is one of the keycorner stones of project management. If aproject manager excels in resource

    management, then he has 50% of projectmanagement challenges solved, and theproject manager needs to concentrate on theremaining 50% to get the project completed

    on time & on budget.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    19/31

    Importance of resource

    managementResources cost money, and not having the rightresources at the right time upsets the schedule.

    In complex projects - especially non-IT projects, thereare several types of resources that needs to bemanaged: Equipment, supplies, machinery, people,land, clearances etc. These resources cost money toprocure.

    If the lead times are too short, it costs more money toget the resources. So it pays to look ahead in the project

    planning stage and make proper plans to procure therequired resources in a timely manner for the lowestcost.

    Changes to the cost of the resources has a big impacton the viability of the project, therefore resource

    management also impacts cost management.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    20/31

    Components of Resource

    management

    1. Effort Estimation

    2. Resource Identification

    3. Lead time to get required resources4. Resource Utilization

    5. Resource Tracking

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    21/31

    Effort Estimation

    Effort Estimation is the first step in projectplanning. Essentially the project has to be broken

    into smallest possible work packages and a project

    plan is made based to meet the delivery date.Project manager needs to know the type of efforts

    involved & the resources needed for that to start

    the estimation process. Next step is to prepare the

    estimates. The best way to get the estimate is to

    talk to the actual persons who will be doing the

    work. Talk to the people and ask for three

    estimates: average, pessimistic & optimistic.

    To Summarize the exercise of

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    22/31

    To Summarize the exercise of

    resource estimation is as

    follows:1. Break the project down into smallest possible setof tasks - also called work packages.

    2. Talk to the persons who will be doing the work to

    get a range of estimates3. Validate the estimate with experts & historical data

    4. Determine the way the estimates are recordedand presented to customers & stake holders

    5. Roll up all the estimates and present thepessimistic estimate to customers

    6. Hammer all the caveats and assumptions into

    customer's mind along with the estimates

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    23/31

    Resource Identification

    Every single work package in the project

    should have resources identified with. In

    the initial stage of the project, if resources

    for each work package is not identified andassigned for that, then that's a major gap

    in project planning, and the project plan is

    not complete nor it should be sharedoutside to customers.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    24/31

    Contd..

    It is the role of the project manager to work

    with the stake holders to get resources for

    each work package. In most cases, not all

    the resources are identified and allocatedat the start of project, so from planning

    perspective this denotes a risk & hence a

    contingency resource identification mustalso be done during the planning stage.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    25/31

    Lead Time for Resources

    Resources are always scarce and must be

    carefully used. In most cases, resources

    will be committed to the project at the

    beginning of the project, but it is the dutyof the project manager to know the lead

    time needed to get the required resources

    and plan things accordingly.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    26/31

    The resource schedule should

    list the following:

    1. Resources needed

    2. Duration of the need

    3. Lead time for procuring/booking the

    resources

    4. Remainders/reconfirmations schedule forensuring that resources to be made available.

    5. Cost of resources & cost variations ofresources.

    6. Ramp-up time for the resources - i.e, time

    needed for the resource to be fully effective

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    27/31

    Resource Utilization

    Resource utilization refers to the plan on how the

    allocated/available resources are utilized in the

    project. Often times people succumb to the

    pressure and get into over utilization of resources:i.e., make people work overtime to complete the

    tasks, overload/overuse machinery etc.

    Over utilization of a given resource is not astandard plan. No project manger should plan for

    overloading of resources in the initial project plan.

    The project plan must account for normal usage of

    the resource.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    28/31

    Resource Tracking

    Once the resource planning, resource schedule is doneand the project is under way, the project manager musttrack the actual usage/consumption of the resources andcompare against the plan. The actual usage must be

    captured into the system and this helps in refinement offuture project plans.

    During the project estimation time, people have a

    tendency to tell things which their managers like to hear- thus giving an overtly aggressive estimate or aconservative estimate. But when the actual efforts aretracked against the initial estimate and the variances arediscussed openly in the project meetings, people tend to

    become more realistic in the future projects.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    29/31

    Contingency Planning

    Resources are always scarce & hence there isalways a possibility of required resources not beingavailable to the project. It is therefore a goodpractice to add resource contingency into the

    resource estimates to guard against resourcescarcity.

    Resource contingency is something that's added tothe initial estimates to guard against things

    requiring more work than expected or simply toreflect the fact that the estimate is not reliable. It isgood practice to add contingency to individual workpackages. In some cases, contingency is added enbloc in form of additional work packages.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    30/31

    Toconclude

    Project managers are measured primarily on

    the delivery of projects. To deliver projects on

    time and on budget, one needs to have a very

    tight control on the resources and time scales.Resource management is the key for

    successful projects delivery and resource

    utilization tracking is a key metric in measuringthe quality of the project plan, monitoring the

    project status and this helps in taking any

    corrective steps.

  • 7/28/2019 Project Scheduling and Resource Management PPT (Dinesh K. C.)

    31/31

    References

    John M. Nicholas, Project Management for

    Business and Technology, II ed., Pearson

    Education, New Delhi, 2002.

    Prasanna Chandra, Projects, V ed.,

    McGraw Hill, New Delhi, 2004.

    http://en.wikipedia.org/wiki/Schedule_proje

    ct_management

    http://mba.tuck.dartmouth.edu