14
7/28/2019 Project Scheduling Crashing26042007 http://slidepdf.com/reader/full/project-scheduling-crashing26042007 1/14 Step By Step Step By Step Crash Project Crash Project

Project Scheduling Crashing26042007

Embed Size (px)

Citation preview

Page 1: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 1/14

Step By StepStep By Step

Crash ProjectCrash Project

Page 2: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 2/14

2

Techniques for Shortening aTechniques for Shortening a

Project ScheduleProject Schedule  Add people to the schedule. Add people to the schedule.

Work longer hoursWork longer hours (Over Time).(Over Time). 

Improve productivity.Improve productivity.

Overlap tasks or make serial tasks simultaneous or Overlap tasks or make serial tasks simultaneous or 

parallel activitiesparallel activities (Fast Track).(Fast Track).

Remove or delay features or functionality from theRemove or delay features or functionality from the

project critical pathproject critical path (Cut Scope)(Cut Scope)

Consider innovative approaches such as a differentConsider innovative approaches such as a different

development methodology / alternative technologies.development methodology / alternative technologies.

Out-sourcing options.Out-sourcing options.

Page 3: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 3/14

3

Crashing PrioritiesCrashing Priorities

► Critical Path’s activities (Starting withCritical Path’s activities (Starting with

lowest crash cost / day)lowest crash cost / day)

► Near critical activities with lowest floatNear critical activities with lowest float(Slack).(Slack).

► In case of equals. Start with lowest activityIn case of equals. Start with lowest activity

ID numbers.ID numbers.

Page 4: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 4/14

4

CAUTIONSCAUTIONS

► Shortening or lengthening tasks on the critical path directlyShortening or lengthening tasks on the critical path directlyaffects project finish time.affects project finish time.

► Duration of “non-critical” task is irrelevant.Duration of “non-critical” task is irrelevant.► ““Crashing” all jobs is ineffective, focus on the few % of Crashing” all jobs is ineffective, focus on the few % of 

 jobs that are on the Critical Path (s). jobs that are on the Critical Path (s).► ““Crashing” task can cause shifting the Critical Path to aCrashing” task can cause shifting the Critical Path to adifferent Paths (Tasks).different Paths (Tasks).

► Shortening task- technical and economical challenge.Shortening task- technical and economical challenge.► Previous non-critical task can become critical.Previous non-critical task can become critical.

► Lengthening of non-critical task can also shift the criticalLengthening of non-critical task can also shift the criticalpath.path.

► Project length should be reduced as long as crashing costsProject length should be reduced as long as crashing costsare less than indirect cost.are less than indirect cost.

Page 5: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 5/14

5

Cost TypesCost TypesIndirect Cost Indirect Cost :: Costs related proportionally Costs related proportionally with the duration of the project - (Shared with the duration of the project - (Shared cost with other projects or company units) - Whencost with other projects or company units) - When activities areactivities arecrashed crashed these tend tothese tend to decrease the Indirect cost of The project:decrease the Indirect cost of The project:

Overheads : Admin. ExpensesOverheads : Admin. Expenses Office Rental Office Rental 

SupervisionSupervision

ConsultantsConsultants Interest Interest 

Direct Cost Direct Cost ::Costs related directly Costs related directly with the duration of the project - Whenwith the duration of the project - When activitiesactivitiesare crashed are crashed these tend tothese tend to increase the direct cost of The project.increase the direct cost of The project.  

Labor Labor  Equipment Equipment  MaterialsMaterials Sub-contractorsSub-contractors

Page 6: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 6/14

6

Time-Cost Trade-off Time-Cost Trade-off 

Indirect cost - DecreasedIndirect cost - Decreased

   C  o  s   t   (   $   )

   C  o  s   t   (   $   )

CrashingCrashing

Direct cost - IncreasedDirect cost - Increased

Minimum Cost = Optimal Project Time / CostMinimum Cost = Optimal Project Time / Cost

Minimum Cost = Optimal Project Time / CostMinimum Cost = Optimal Project Time / Cost

TimeTime

TotalTotal

Project DurationProject Duration

Project DurationProject Duration

CostCost

 Non - Linear Cost  Non - Linear Cost 

 Distribution Distribution

Optimal Project TimeOptimal Project Time

Optimal Project costOptimal Project cost

Page 7: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 7/14

7Cost ( X $100 )Cost ( X $100 )

2020

1818

1616

1414

1212

1010

88

66

44

22

5 10 15 20 25 30 35 40 455 10 15 20 25 30 35 40 45

Crash This Activity 4 Days FromCrash This Activity 4 Days From 2020 ToTo 1616

MarginalMarginal

CostCost

=

CC – NCCC – NC

NT – CTNT – CT

=

4000 –4000 –20002000

20 – 1220 – 12

$ 250 / Day$ 250 / Day=

CrashingCrashing

CT = 12 daysCT = 12 days

CC = $4000CC = $4000

NormalNormal

NT = 20 daysNT = 20 days

NC = $2000NC = $2000

 Job time = 16 days Job time = 16 days

Total Cost = $3000Total Cost = $3000

ActivityActivity

DurationDuration

DaysDays

Time-Cost Time-Cost  Trade-off Trade-off 

Crashing Cost = 4 * $ 250 +Crashing Cost = 4 * $ 250 + $$ 2000 = $ 30002000 = $ 3000 

   N   T

 –   C   T

   N   T

 –   C   T

CC – NCCC – NC

 Linear Cost Distribution Linear Cost Distribution

Page 8: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 8/14

8

Time-Cost Trade-off Time-Cost Trade-off ExampleExample

A $20 1

B $40 2

C $30 1

D $25 4

E $30 2

F $30 1

G $0 0

ACTIVITY

ID

CRASH

COST PER

DAY

MAXIMUM

CRASH

TIMETIME COST TIME COST

3 $50 2 $70

6 $80 4 $160

10 $60 9 $90

11 $50 7 $150

8 $100 6 $160

5 $40 4 $70

6 $70 6 $70

NORMAL

DIRECT COSTS

CRASH

INITIAL TOTAL DIRECT COSTS = $450INITIAL TOTAL DIRECT COSTS = $450INITIAL TOTAL INDIRECT COSTS = $400INITIAL TOTAL INDIRECT COSTS = $400

SAVING INDIRECT COST PER CRASHED DAY = $50/DAY.SAVING INDIRECT COST PER CRASHED DAY = $50/DAY.

Page 9: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 9/14

9

Original NetworkOriginal Network

1 B E

 A $20 6 8

B $40 A C G

C $303 10 6

D $25 D F

E $30 11 5

F $30

CRASHING COST = $0CRASHING COST = $0

INITIAL TOTAL DIRECT COSTS = $450INITIAL TOTAL DIRECT COSTS = $450

INITIAL TOTAL INDIRECT COSTS = $400INITIAL TOTAL INDIRECT COSTS = $400

INITIAL TOTAL COSTS = $450 + $400 = $850INITIAL TOTAL COSTS = $450 + $400 = $850

PROJECT DURATION = 25 DAYS.PROJECT DURATION = 25 DAYS.

A-B-E-G = 23 DAYS

A-C-F-G = 24 DAYS

A-D-F-G = 25 DAYS

Page 10: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 10/14

10

2 B E

 A $20 6 8

B $40 A C G

C $30 2 X 10 6

D $25 D F

E $30 11 5

F $30

TOTAL CRASHING COST = $20TOTAL CRASHING COST = $20

INITIAL TOTAL DIRECT COSTS = $450 + $20 = $470INITIAL TOTAL DIRECT COSTS = $450 + $20 = $470

INITIAL TOTAL INDIRECT COSTS = $400 - $50 = $350INITIAL TOTAL INDIRECT COSTS = $400 - $50 = $350

INITIAL TOTAL COSTS = $470 + $350 = $820INITIAL TOTAL COSTS = $470 + $350 = $820

PROJECT DURATION = 24 DAYS.PROJECT DURATION = 24 DAYS.

Crash “ A ”Crash “ A ”

$20$20

A-B-E-G = 22 DAYS

A-C-F-G = 23 DAYS

A-D-F-G = 24 DAYS

Page 11: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 11/14

11

Crash “ D ”Crash “ D ”

3 B E

 A $20 6 8

B $40 A C G

C $30 2 X 10 6

D $25 D F

E $30 10 5

F $30

TOTAL CRASHING COST = $20 + $25 = $45TOTAL CRASHING COST = $20 + $25 = $45

INITIAL TOTAL DIRECT COSTS = $450 + $45 = $495INITIAL TOTAL DIRECT COSTS = $450 + $45 = $495

INITIAL TOTAL INDIRECT COSTS = $400 - $100 = $300INITIAL TOTAL INDIRECT COSTS = $400 - $100 = $300

INITIAL TOTAL COSTS = $495 + $300 = $795INITIAL TOTAL COSTS = $495 + $300 = $795

PROJECT DURATION = 23 DAYS.PROJECT DURATION = 23 DAYS.

$20$20

$25$25

A-B-E-G = 22 DAYS

A-C-F-G = 23 DAYS

A-D-F-G = 23 DAYS

Page 12: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 12/14

12

Crash “ F ”Crash “ F ”

4 B E

 A $20 6 8

B $40 A C G

C $30 2 X 10 6

D $25 D F

E $30 10 4X

F $30

TOTAL CRASHING COST = $20 + $25 + $30 = $75TOTAL CRASHING COST = $20 + $25 + $30 = $75

INITIAL TOTAL DIRECT COSTS = $450 + $75 = $525INITIAL TOTAL DIRECT COSTS = $450 + $75 = $525

INITIAL TOTAL INDIRECT COSTS = $400 - $150 = $250INITIAL TOTAL INDIRECT COSTS = $400 - $150 = $250

INITIAL TOTAL COSTS = $525 + $250 = $775INITIAL TOTAL COSTS = $525 + $250 = $775

PROJECT DURATION = 22 DAYS.PROJECT DURATION = 22 DAYS.

$20$20

$25$25 $30$30

A-B-E-G = 22 DAYS

A-C-F-G = 22 DAYS

A-D-F-G = 22 DAYS

Page 13: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 13/14

13

5 B E

 A $20 6 7

B $40 A C G

C $30 2 X 9X 6

D $25 D F

E $30 9 4X

F $30

TOTAL CRASHING COST = $20 + $25 + $30 + $25+ $30 + $30 = $160TOTAL CRASHING COST = $20 + $25 + $30 + $25+ $30 + $30 = $160

INITIAL TOTAL DIRECT COSTS = $450 + $160 = $610INITIAL TOTAL DIRECT COSTS = $450 + $160 = $610

INITIAL TOTAL INDIRECT COSTS = $400 - $200 = $200INITIAL TOTAL INDIRECT COSTS = $400 - $200 = $200

INITIAL TOTAL COSTS = $610 + $200 = $810INITIAL TOTAL COSTS = $610 + $200 = $810

PROJECT DURATION = 21 DAYS.PROJECT DURATION = 21 DAYS.

$20$20

$25$25 $30$30

Crash “ D,C and E ”Crash “ D,C and E ”

$25$25

$30$30

$30$30

A-B-E-G = 21 DAYS

A-C-F-G = 21 DAYS

A-D-F-G = 21 DAYS

Page 14: Project Scheduling Crashing26042007

7/28/2019 Project Scheduling Crashing26042007

http://slidepdf.com/reader/full/project-scheduling-crashing26042007 14/14

14

Time-Cost Trade-off Time-Cost Trade-off 

Crash ResultCrash Result

PROJECT DURATIONTOTAL DIRECT COS TOTAL INDIRECT COS TOTAL PROJECT COSTCRASHING COST

25 450 400 850 0

24 470 350 820 20

23 495 300 795 45

22 525 250 775 75

21 610 200 810 160

CRASH PROJECT

  $  8   5  0

  $  8  2  0

  $   7  9   5

  $   7   7   5

  $  8  1  0

0

100

200

300

400

500

600

700

800

900

25 24 23 22 21

PROJECT DURATION

    C    O

    S

TOTAL

PROJECT

COST

TOTAL

DIRECT

COST

TOTALINDIRECT

COST

CRASHING

COST

OPTIMUMOPTIMUM

COST – TIME POINTCOST – TIME POINT

OPTIMUMOPTIMUM

PROJECT DURATIONPROJECT DURATION