DIVISI 1. UMUM
Start: Mon 18/08/14ID: 2
Finish: Sun 28/09/14Dur: 42 days
Comp: 0%
Pek. Mobilisasi dan Demobilisasi
Start: 18/08/14 ID: 3
Finish: 24/08/14 Dur: 7 days
Res:
Pek. Direksi keet
Start: 18/08/14 ID: 4
Finish: 31/08/14 Dur: 14 days
Res:
Pek. Papan Nama Proyek
Start: 18/08/14
Finish: 24/08/14
Res:
Pek. Pengaturan lalu lintas dan Pagar Pengaman
Start: 22/08/14
Finish: 28/08/14
Res:
Pek. Pengukuran Site
Start: 18/08/14
Finish: 24/08/14
Res:
DIVISI 3. PEKERJAAN TANAH
Start: Mon 01/09/14ID: 20
Finish: Sun 12/10/14Dur: 42 days
Comp: 0%
DIVISI 4. Pekerjaan Aspal
Start: Mon 29/09/14ID: 26
Finish: Thu 23/10/14Dur: 25 days
Comp: 0%
DIVISI 5. PERKERASAN BERBUTIR
Start: Tue 14/10/14ID: 31
Finish: Mon 03/11/14Dur: 21 days
Comp: 0%
DIVISI 2. DRAINASE
Start: Mon 15/09/14ID: 13
Finish: Fri 24/10/14Dur: 40 days
Comp: 0%
PEMBANGUNAN JALAN TEMBUS SHOLEH
Start: Thu 24/07/14ID: 1
Finish: Thu 20/11/14Dur: 120 days
Comp: 0%
Page 1
DIVISI 7. STRUKTUR
Start: Mon 29/09/14ID: 33
Finish: Thu 20/11/14Dur: 53 days
Comp: 0%
DIVISI 8. PEKERJAAN MINOR
Start: Thu 24/07/14ID: 45
Finish: Sun 10/08/14Dur: 18 days
Comp: 0%
Pek. Tactile Surface
Start: 24/07/14 ID: 46
Finish: 30/07/14 Dur: 7 days
Res:
Pek. Grill Besi Plat
Start: 28/07/14 ID: 47
Finish: 03/08/14 Dur: 7 days
Res:
Pek. Pembongkaran Beton
Start: 28/07/14
Finish: 03/08/14
Res:
Page 2
Pek. Papan Nama Proyek
Start: 18/08/14 ID: 5
Finish: 24/08/14 Dur: 7 days
Res:
Pek. Pengaturan lalu lintas dan Pagar Pengaman
Start: 22/08/14 ID: 6
Finish: 28/08/14 Dur: 7 days
Res:
Pek. Pengukuran Site
Start: 18/08/14 ID: 7
Finish: 24/08/14 Dur: 7 days
Res:
Pek. Bouplank
Start: 25/08/14 ID: 8
Finish: 14/09/14 Dur: 21 days
Res:
Pek. Los Kerja / Bahan
Start: 25/08/14 ID: 9
Finish: 07/09/14 Dur: 14 days
Res:
Pek. Pembersihan Damija
Start: 08/09/14 ID: 10
Finish: 14/09/14 Dur: 7 days
Res:
Pek. Pengujian Lapangan
Start: 15/09/14 ID: 11
Finish: 28/09/14 Dur: 14 days
Res:
Pek. Galian Tanah
Start: 01/09/14 ID: 21
Finish: 21/09/14 Dur: 21 days
Res:
Pek. Galian Tanah Keras Oprit
Start: 15/09/14 ID: 22
Finish: 21/09/14 Dur: 7 days
Res:
Pek. Urugan Tanah Kembali Bekas Galian (dipadatkan)
Start: 06/10/14 ID: 23
Finish: 12/10/14 Dur: 7 days
Res:
Pek. Penyiapan badan jalan
Start: 15/09/14 ID: 24
Finish: 28/09/14 Dur: 14 days
Res:
Page 3
Pek. Pembongkaran Beton
Start: 28/07/14 ID: 48
Finish: 03/08/14 Dur: 7 days
Res:
Pek. Pemasangan Kerb
Start: 28/07/14 ID: 49
Finish: 10/08/14 Dur: 14 days
Res:
Pek. Paving Block
Start: 28/07/14 ID: 50
Finish: 10/08/14 Dur: 14 days
Res:
Page 4
Pek. Pengujian Lapangan
ID: 11
Dur: 14 days
Res:
Pek. Normalisasi Saluran
Start: 15/09/14 ID: 12
Finish: 21/09/14 Dur: 7 days
Res:
Pek. Pasangan batu dengan mortar
Start: 15/09/14 ID: 14
Finish: 12/10/14 Dur: 28 days
Res:
Pek. Buis Beton Bulat Dia 30
Start: 19/09/14 ID: 15
Finish: 16/10/14 Dur: 28 days
Res:
Pek. Drainase U-Ditch (U-800)
Start: 23/09/14
Finish: 20/10/14
Res:
Pek. Penyiapan badan jalan
ID: 24
Dur: 14 days
Res:
Pek. Buangan tanah bekas galian
Start: 08/09/14 ID: 25
Finish: 28/09/14 Dur: 21 days
Res:
Pek. Pondasi Agregat Kelas A
Start: 29/09/14 ID: 27
Finish: 05/10/14 Dur: 7 days
Res:
Pek. Lapis Resap Pengikat
Start: 06/10/14 ID: 28
Finish: 12/10/14 Dur: 7 days
Res:
Pek. Laston Lapis Pondasi (AC-Base) levelling (crossing)
Start: 06/10/14
Finish: 19/10/14
Res:
Page 5
Pek. Lantai kerja Ready mix K-125 (Box Utilitas, U-Ditch, Box Culvert)
Start: 29/09/14 ID: 37
Finish: 12/10/14 Dur: 14 days
Res:
Pek. Bekisting (2x pakai)
Start: 03/10/14
Finish: 23/10/14
Res:
Page 6
Pek. Drainase U-Ditch (U-800)
Start: 23/09/14 ID: 16
Finish: 20/10/14 Dur: 28 days
Res:
Pek. Cover Drainase U-Ditch (U-800)
Start: 27/09/14 ID: 17
Finish: 24/10/14 Dur: 28 days
Res:
Pek. Box Culvert HD BC 800x800
Start: 01/10/14 ID: 18
Finish: 14/10/14 Dur: 14 days
Res:
Pek. Box Culvert HD BC 800x800 BM
Start: 05/10/14 ID: 19
Finish: 18/10/14 Dur: 14 days
Res:
Pek. Laston Lapis Pondasi (AC-Base) levelling (crossing)
Start: 06/10/14 ID: 29
Finish: 19/10/14 Dur: 14 days
Res:
Pek. Laston Lapis Pondasi (AC-Base) levelling (oprit)
Start: 10/10/14 ID: 30
Finish: 23/10/14 Dur: 14 days
Res:
Pek. Limestone tebal 30 cm
Start: 14/10/14 ID: 32
Finish: 03/11/14 Dur: 21 days
Res:
Page 7
Pek. Beton K-250 (ready mix) Block Beton 54 cm x 60 cm
Start: 28/10/14 ID: 34
Finish: 03/11/14 Dur: 7 days
Res:
Pek. Beton K-250 (ready mix) Block Beton 56 cm x 60 cm
Start: 04/11/14 ID: 35
Finish: 10/11/14 Dur: 7 days
Res:
Pek. Bekisting (2x pakai)
Start: 03/10/14 ID: 38
Finish: 23/10/14 Dur: 21 days
Res:
Pek. Beton K-225 (site mix, exclude formwork) + pipa pvc dia.2"
Start: 07/10/14 ID: 39
Finish: 13/10/14 Dur: 7 days
Res:
Pek. Beton K-250 (ready mix) Blox Utilitas + Bak Kontrol
Start: 14/10/14 ID: 40
Finish: 20/11/14 Dur: 38 days
Res:
Pek. Besi tulangan polos U24
Start: 07/10/14 ID: 41
Finish: 13/11/14 Dur: 38 days
Res:
Pek. Beton Struktur FS-45 Tb. 25 cm (28 hari)
Start: 16/10/14 ID: 42
Finish: 05/11/14 Dur: 21 days
Res:
Pek. Beton Struktur FS-45 Tb. 20 cm (Jalan Cilubut,7 hari)
Start: 16/10/14 ID: 43
Finish: 05/11/14 Dur: 21 days
Res:
Page 8
Page 9
Pek. Beton Jepit Ready Mix K-250
Start: 11/11/14 ID: 36
Finish: 17/11/14 Dur: 7 days
Res:
Pek. Wet lean concrete tebal 10 cm (ready mix K-125)
Start: 20/10/14 ID: 44
Finish: 02/11/14 Dur: 14 days
Res:
Page 10
Critical
Noncritical
Critical Milestone
Milestone
Critical Summary
Summary
Critical Inserted
Inserted
Critical Marked
Marked
Critical External
External
Project Summary
Highlighted Critical
Highlighted Noncritical
Page 11
Project: C:\Users\yurisdal\Docu
Date: Thu 24/07/14