DIVISI 1. UMUM Start: Mon 18/08/1 ID: 2 Finish: Sun 28/09/1 Dur: 42 days Comp: 0% Pek. Mobilisasi dan Demobilisasi Start: 18/08/14 ID: 3 Finish: 24/08/14 Dur: 7 days Res: Pek. Direksi keet Start: 18/08/14 ID: 4 Finish: 31/08/14 Dur: 14 days Res: Pek. P Start: Finish Res: Pek. P Start: Finish Res: Pek. P Start: Finish Res: DIVISI 3. PEKERJAAN TANAH Start: Mon 01/09/1 ID: 20 Finish: Sun 12/10/1 Dur: 42 days Comp: 0% DIVISI 4. Pekerjaan Aspal Start: Mon 29/09/1 ID: 26 Finish: Thu 23/10/1 Dur: 25 days Comp: 0% DIVISI 5. PERKERASAN BERBUTIR Start: Tue 14/10/14 ID: 31 Finish: Mon 03/11/1 Dur: 21 days Comp: 0% DIVISI 2. DRAINASE Start: Mon 15/09/1 ID: 13 Finish: Fri 24/10/14Dur: 40 days Comp: 0% PEMBANGUNAN JALAN TEMBUS S Start: Thu 24/07/14 ID: 1 Finish: Thu 20/11/1 Dur: 120 days Comp: 0% Page 1

Project Tembus Sholeh NP

Embed Size (px)

DESCRIPTION

Proyek Jalan

Citation preview

Page 1: Project Tembus Sholeh NP

DIVISI 1. UMUM

Start: Mon 18/08/14ID: 2

Finish: Sun 28/09/14Dur: 42 days

Comp: 0%

Pek. Mobilisasi dan Demobilisasi

Start: 18/08/14 ID: 3

Finish: 24/08/14 Dur: 7 days

Res:

Pek. Direksi keet

Start: 18/08/14 ID: 4

Finish: 31/08/14 Dur: 14 days

Res:

Pek. Papan Nama Proyek

Start: 18/08/14

Finish: 24/08/14

Res:

Pek. Pengaturan lalu lintas dan Pagar Pengaman

Start: 22/08/14

Finish: 28/08/14

Res:

Pek. Pengukuran Site

Start: 18/08/14

Finish: 24/08/14

Res:

DIVISI 3. PEKERJAAN TANAH

Start: Mon 01/09/14ID: 20

Finish: Sun 12/10/14Dur: 42 days

Comp: 0%

DIVISI 4. Pekerjaan Aspal

Start: Mon 29/09/14ID: 26

Finish: Thu 23/10/14Dur: 25 days

Comp: 0%

DIVISI 5. PERKERASAN BERBUTIR

Start: Tue 14/10/14ID: 31

Finish: Mon 03/11/14Dur: 21 days

Comp: 0%

DIVISI 2. DRAINASE

Start: Mon 15/09/14ID: 13

Finish: Fri 24/10/14Dur: 40 days

Comp: 0%

PEMBANGUNAN JALAN TEMBUS SHOLEH

Start: Thu 24/07/14ID: 1

Finish: Thu 20/11/14Dur: 120 days

Comp: 0%

Page 1

Page 2: Project Tembus Sholeh NP

DIVISI 7. STRUKTUR

Start: Mon 29/09/14ID: 33

Finish: Thu 20/11/14Dur: 53 days

Comp: 0%

DIVISI 8. PEKERJAAN MINOR

Start: Thu 24/07/14ID: 45

Finish: Sun 10/08/14Dur: 18 days

Comp: 0%

Pek. Tactile Surface

Start: 24/07/14 ID: 46

Finish: 30/07/14 Dur: 7 days

Res:

Pek. Grill Besi Plat

Start: 28/07/14 ID: 47

Finish: 03/08/14 Dur: 7 days

Res:

Pek. Pembongkaran Beton

Start: 28/07/14

Finish: 03/08/14

Res:

Page 2

Page 3: Project Tembus Sholeh NP

Pek. Papan Nama Proyek

Start: 18/08/14 ID: 5

Finish: 24/08/14 Dur: 7 days

Res:

Pek. Pengaturan lalu lintas dan Pagar Pengaman

Start: 22/08/14 ID: 6

Finish: 28/08/14 Dur: 7 days

Res:

Pek. Pengukuran Site

Start: 18/08/14 ID: 7

Finish: 24/08/14 Dur: 7 days

Res:

Pek. Bouplank

Start: 25/08/14 ID: 8

Finish: 14/09/14 Dur: 21 days

Res:

Pek. Los Kerja / Bahan

Start: 25/08/14 ID: 9

Finish: 07/09/14 Dur: 14 days

Res:

Pek. Pembersihan Damija

Start: 08/09/14 ID: 10

Finish: 14/09/14 Dur: 7 days

Res:

Pek. Pengujian Lapangan

Start: 15/09/14 ID: 11

Finish: 28/09/14 Dur: 14 days

Res:

Pek. Galian Tanah

Start: 01/09/14 ID: 21

Finish: 21/09/14 Dur: 21 days

Res:

Pek. Galian Tanah Keras Oprit

Start: 15/09/14 ID: 22

Finish: 21/09/14 Dur: 7 days

Res:

Pek. Urugan Tanah Kembali Bekas Galian (dipadatkan)

Start: 06/10/14 ID: 23

Finish: 12/10/14 Dur: 7 days

Res:

Pek. Penyiapan badan jalan

Start: 15/09/14 ID: 24

Finish: 28/09/14 Dur: 14 days

Res:

Page 3

Page 4: Project Tembus Sholeh NP

Pek. Pembongkaran Beton

Start: 28/07/14 ID: 48

Finish: 03/08/14 Dur: 7 days

Res:

Pek. Pemasangan Kerb

Start: 28/07/14 ID: 49

Finish: 10/08/14 Dur: 14 days

Res:

Pek. Paving Block

Start: 28/07/14 ID: 50

Finish: 10/08/14 Dur: 14 days

Res:

Page 4

Page 5: Project Tembus Sholeh NP

Pek. Pengujian Lapangan

ID: 11

Dur: 14 days

Res:

Pek. Normalisasi Saluran

Start: 15/09/14 ID: 12

Finish: 21/09/14 Dur: 7 days

Res:

Pek. Pasangan batu dengan mortar

Start: 15/09/14 ID: 14

Finish: 12/10/14 Dur: 28 days

Res:

Pek. Buis Beton Bulat Dia 30

Start: 19/09/14 ID: 15

Finish: 16/10/14 Dur: 28 days

Res:

Pek. Drainase U-Ditch (U-800)

Start: 23/09/14

Finish: 20/10/14

Res:

Pek. Penyiapan badan jalan

ID: 24

Dur: 14 days

Res:

Pek. Buangan tanah bekas galian

Start: 08/09/14 ID: 25

Finish: 28/09/14 Dur: 21 days

Res:

Pek. Pondasi Agregat Kelas A

Start: 29/09/14 ID: 27

Finish: 05/10/14 Dur: 7 days

Res:

Pek. Lapis Resap Pengikat

Start: 06/10/14 ID: 28

Finish: 12/10/14 Dur: 7 days

Res:

Pek. Laston Lapis Pondasi (AC-Base) levelling (crossing)

Start: 06/10/14

Finish: 19/10/14

Res:

Page 5

Page 6: Project Tembus Sholeh NP

Pek. Lantai kerja Ready mix K-125 (Box Utilitas, U-Ditch, Box Culvert)

Start: 29/09/14 ID: 37

Finish: 12/10/14 Dur: 14 days

Res:

Pek. Bekisting (2x pakai)

Start: 03/10/14

Finish: 23/10/14

Res:

Page 6

Page 7: Project Tembus Sholeh NP

Pek. Drainase U-Ditch (U-800)

Start: 23/09/14 ID: 16

Finish: 20/10/14 Dur: 28 days

Res:

Pek. Cover Drainase U-Ditch (U-800)

Start: 27/09/14 ID: 17

Finish: 24/10/14 Dur: 28 days

Res:

Pek. Box Culvert HD BC 800x800

Start: 01/10/14 ID: 18

Finish: 14/10/14 Dur: 14 days

Res:

Pek. Box Culvert HD BC 800x800 BM

Start: 05/10/14 ID: 19

Finish: 18/10/14 Dur: 14 days

Res:

Pek. Laston Lapis Pondasi (AC-Base) levelling (crossing)

Start: 06/10/14 ID: 29

Finish: 19/10/14 Dur: 14 days

Res:

Pek. Laston Lapis Pondasi (AC-Base) levelling (oprit)

Start: 10/10/14 ID: 30

Finish: 23/10/14 Dur: 14 days

Res:

Pek. Limestone tebal 30 cm

Start: 14/10/14 ID: 32

Finish: 03/11/14 Dur: 21 days

Res:

Page 7

Page 8: Project Tembus Sholeh NP

Pek. Beton K-250 (ready mix) Block Beton 54 cm x 60 cm

Start: 28/10/14 ID: 34

Finish: 03/11/14 Dur: 7 days

Res:

Pek. Beton K-250 (ready mix) Block Beton 56 cm x 60 cm

Start: 04/11/14 ID: 35

Finish: 10/11/14 Dur: 7 days

Res:

Pek. Bekisting (2x pakai)

Start: 03/10/14 ID: 38

Finish: 23/10/14 Dur: 21 days

Res:

Pek. Beton K-225 (site mix, exclude formwork) + pipa pvc dia.2"

Start: 07/10/14 ID: 39

Finish: 13/10/14 Dur: 7 days

Res:

Pek. Beton K-250 (ready mix) Blox Utilitas + Bak Kontrol

Start: 14/10/14 ID: 40

Finish: 20/11/14 Dur: 38 days

Res:

Pek. Besi tulangan polos U24

Start: 07/10/14 ID: 41

Finish: 13/11/14 Dur: 38 days

Res:

Pek. Beton Struktur FS-45 Tb. 25 cm (28 hari)

Start: 16/10/14 ID: 42

Finish: 05/11/14 Dur: 21 days

Res:

Pek. Beton Struktur FS-45 Tb. 20 cm (Jalan Cilubut,7 hari)

Start: 16/10/14 ID: 43

Finish: 05/11/14 Dur: 21 days

Res:

Page 8

Page 9: Project Tembus Sholeh NP

Page 9

Page 10: Project Tembus Sholeh NP

Pek. Beton Jepit Ready Mix K-250

Start: 11/11/14 ID: 36

Finish: 17/11/14 Dur: 7 days

Res:

Pek. Wet lean concrete tebal 10 cm (ready mix K-125)

Start: 20/10/14 ID: 44

Finish: 02/11/14 Dur: 14 days

Res:

Page 10

Page 11: Project Tembus Sholeh NP

Critical

Noncritical

Critical Milestone

Milestone

Critical Summary

Summary

Critical Inserted

Inserted

Critical Marked

Marked

Critical External

External

Project Summary

Highlighted Critical

Highlighted Noncritical

Page 11

Project: C:\Users\yurisdal\Docu

Date: Thu 24/07/14