Project to Do

Embed Size (px)

Citation preview

  • 8/3/2019 Project to Do

    1/4

    Tempe PRS regulator/instrumentation UpgradePrimary Regulatory Sets (PRSs) are gas pressure reduction, metering and filtration facilitieslocated at each off-take on primary mains, reducing the pressure from a MAOP of 3,500 kPa tosupply the secondary network with a MAOP of 1,050 kPa. Construction, operation andmaintenance of PRS are managed in accordance with the safety and operating plan (SAOP) andAS2885 suite of pipeline standards. Compliance with AS2885 is a regulatory requirement (NSW

    Gas Supply [Safety Management] Regulation 2002).

    14 PRS are installed and there are three main groups or categories as follows:Group 1 Sites commissioned in 1976 when natural gas was introduced to the Sydney market.Includes Tempe PRS.Group 1a Sites commissioned as part of organic growth post 1976. Includes Horsley Park,Haberfield, Wollongong (Cringila) and Willoughby PRS. Group 2 Sites commissioned as part of the construction of the Eastern Creek to Penrithprimary main Penrith PRS.Group 3 The Moorebank PRS was commissioned in 2007 (part of the Sydney Primary Loop).Most PRSs are located in Sydney and are situated on public land. Due to limited abovegroundspace, most PRS are installed in underground concrete pits with lockable lids and alarms. The

    Supervisory Control and Data Acquisition (SCADA) system remotely monitors these facilities. Nineof the 14 PRS are between 31 and 35 years old. Tempe PRS is 33 years old.

    Drivers (need or justification) for upgrading Tempe PRSThe Primary Facilities section of the Asset Management Plan (AMP) indicates Jemena AssetManagement (JAM) expects the design life of PRSs to be 40 years (the same section also refersto 30 to 35 years). PRS are subject to planned (or preventive) maintenance regimes howeverunlike pipe assets, PRS comprise different components including regulators, meters, valves,filters, pipes and instrumentation, all of which can have different lives. Individual soft components(e.g. associated with filters and regulators) need to be replaced at regular intervals irrespective ofthe asset life.

    Details pertaining to a number of PRS issues which impact upon Lifecycle Management areprovided in the AMP. These issues are summarised as follows:

    Many PRSs are over 30 years old. The original Fisher pressure control valves areexcessively noisy and resulting vibration has the potential over time to cause serious damageas it did in 2007 when a weldolet on the Auburn PRS failed due to fatigue. The excessivenoise level presents an OH&S risk for service personnel and also breaches EPA Guidelinesfor allowable noise levels in adjacent residential/commercial areas. Temporary noisemitigation modifications have been made however they are ineffective when maintenanceactivities are carried out.

    Operation of the Fisher pressure control valves relies on compressed air and failure rateof the instrument air systems is increasing. Reliance on electricity supply is also provingproblematic. In the event of a power failure, bleeding of natural gas to atmosphere can occur.This is environmentally undesirable.

    Due to the age of the assets, vendors are withdrawing technical and spare parts support.Depending on its condition, redundant equipment is used for spare parts. However this has

    practical limitations. A number of installations do not meet mandatory hazardous area standards.

    Many PRS are installed below ground in concrete pits which inherently provide a dampenvironment.

    Corrosion of pipework and PRS components is an ongoing problem as various measurestaken to eliminate dampness have been unsuccessful.

    Below ground pits are classified as confined spaces which require special access/egressmeasures. Grates are fitted as a precaution against trips and falls during maintenanceoperations.

    JGN completed a comprehensive Lifecycle Management study in 2008. Risk analyses inaccordance with AS/NZS 4630 were conducted as follows:

    asset risk (levels of service, maintainability, asset lifecycle-end of life).

    technical risk (asset variation [standardization], maintenance costs, special issues).

    financial risk.

    compliance risks (standards, OHS, environmental).

  • 8/3/2019 Project to Do

    2/4

  • 8/3/2019 Project to Do

    3/4

    Project driversThe AMP and the Lifecycle Management Report comprehensively outline the need for, and thebasis of the project. The engineering assessment (EA) assumes it is not a capacity driven project.Although primary gas facilities have a nominal asset life of 30-40 years, it is widely accepted withinthe gas industry that it is more likely that major facilities (or their components), such as PRS, willrequire changes or replacement much more frequently due to changing capacity requirementsand/or technological obsolescence. Technological obsolescence includes unavailability of spareparts and lack of manufacturer support. It is considered that JAM and JGN should adopt astandard nominal asset life for PRS. The period nominated for this class of asset is not criticallyimportant; however, the recommendation is made for consistency reasons. Currently the AMPrefers to 30-35 years and 40 years. The Lifecycle Management Report refers to 30 years. Differentfigures have the potential to create reader doubt and/or present unanswered questions. JGNsdecision to upgrade Tempe PRS is soundly based on formal technical and financial riskassessments in accordance with the appropriate Australian Standard. The decision is also basedon a pressing need to eliminate equipment vibration and to reduce noise levels to within limits

    specified by EPA Guidelines and OH&S legislation. There is also a pressing need for mandatoryhazardous area standards to be met.

    Options investigatedIt is apparent that JAM has considered a wide range of options before selecting Option 2 (upgradeusing existing concrete pit) as the preferred option. While an aboveground option could satisfy allspecified criteria, the Tempe PRS EA clearly demonstrates this is not technically or economicallyfeasible.

    JAM has not limited its investigations to known/proven technology, but has considered newtechnology Cocon 6 which is undergoing trials overseas.

    Third party reviewer understands the pressure regulating equipment with this technology is locatedin a below ground surface mounted box accessible via ground level box lids. These boxes are

    not classified as confined spaces and service/maintenance tasks can be performed at groundlevel. Furthermore, there are other important considerations and reviewer agrees it is premature tointroduce this new technology. It may be more suited to new PRS installations that do not involvecostly retrofitting.

    Proposed project scopeThe overall project scope is to upgrade Tempe PRS to mitigate current risks and ensure continuedsafe and reliable operation. Table 6-8 indicates key assumptions and constraints.

  • 8/3/2019 Project to Do

    4/4