Project Umpqua Electric Vehicle Drive System
Team Abdullah Binsaeed
Dustin Buscho
Steven Arlint
AdvisorDr. Albright
Industry RepresentativeMr. Menig
Freightliner
Overview
• Introduction
• Scorecard
• Plans
• Milestones
• Issues/Concerns
• Conclusions
Introduction
• Light electric vehicle drive system– Driver and vehicle weight of approximately 450
lbs.– Commuters will benefit.– Main emphasis on the motor control and feedback– Displays data analogous to cars RPM and fuel
gauge
Control Logic
Regenerative Control
Gate Drive
Speed Control Gate Drive
MOSFET70A 500V x1
MOSFET 70A 500V x2
Current Sensor
Free Wheeling
DiodeDC
Permanent Magnet Motor
Ground
High Voltage(DC)
Sensor Logic
LCD Display
Digital Tachometer
User Input
Scorecard (DEC 05 plans)
• Test regenerative braking
• Full load test the forward drive mode of the motor controller
• Construct current sensing system
• Program PIC microcontroller to recognize the current sensing system
• Complete design review process
• (All of this has been completed)
Plans
• Finish PIC microcontroller programming for data acquisition
• Interface LCD display
• Complete Theory of Operations Document
• Test regenerative braking under load
MilestonesNumber Description Original
10/13/05Previous11/8/05
Present11/15/05
1 Product Pre-Approval 09/13/05 09/13/05 09/13/05
2 Functional Spec Approval (Product Approval)
10/4/05 11/3/05 11/10/05
3 Project Plan Approval 11/11/05 11/18/05 10/18/05
4 Completion of draft circuit design
10/31/05 10/31/05 10/31/05
5 Motor and chassis tested 10/31/05 10/31/05 10/31/05
6 Parts Ordered 11/15/05 11/15/05 11/15/05
7 Design Release 12/9/05 12/9/05 12/9/05
8 Power electronics module completed
12/9/05 12/9/05 12/9/05
9 Analog devices interfaced to digital system
1/16/05 1/16/05 1/16/05
10 Final circuits assembled 02/24/06 02/24/-6 02/24/06
11 TOP’s Approval 02/24/06 02/24/06 02/24/06
12 Testing under load 03/28/06 03/28/06 03/28/06
13 Prototype Release 04/07/06 04/07/06 04/07/06
Concerns/Issues
• Main issues: – Safety (real world)
• Solutions: – Product testing and documenting results– Using caution when operating with high
voltage, high current cases. Gloves, first aid, and a cell phone is always present.
Conclusions
• Introduction
• Scorecard
• Additional Accomplishments
• Plans
• Issues/Concerns
• Conclusions
Questions?