3
DEC 05, 2014 Projects Brief July 2007- Feb 2011 Turner International (Project & Construction Managers), 1- Project: Doha Convention Center & Tower. Client: Real Estate Investment. Developer: Qatari Diar Real Estate Investment. Current Project Cost Estimate: (Approx.) 8.642 Billion Qatari Riyals - 2.368 Billion $. Consultant, Contactors & Suppliers: Murphy / Jahn (Main Consulting – Architects). Hyder Consulting (Supervision Consulting). STS & GHD Consulting (Durability & Geotechnical Consulting). DG Jones & Partners (DGJ) (Cost Consulting & QS). Six Construct JV Midmac (Main contractor – Sub & Super-structure Convention Center). Ammico (Main contractor – Enabling & Piling Package). ACTS, Gulf Labs, Body Coat, ACES & LOADTEST (Concrete & Foundation Test Services Agencies). Untied Equipment (Sub-contractor - Dewatering System). Qatar, United & Watanya Ready Mix. (Concrete Supplier). BMC / SIKA (Sub-contractor / Supplier for Water Proof). Merco & Lion Qatar (Sub-contractor / Supplier for RFT & steel sections). ARUP (MEP-AV/ IT Consulting). Diwan (Local Consulting – Architects) Magnusson Klemencic Associates (MKA) (Structure Consulting). Thornton Tomasetti Group (TTG) (Structure Designer). Wrner Sobek Ingfnieurf (Special Structure Consulting). Rainer Schmidt (Landscape Consulting – Architects). HSBC (Insurance Consulting). Schirmer Engineering Group (Life Safety & Fire Protection). Curtain Wall Design & Consulting (CDC) (Building Cladding Consulting). Semaan & Soberman (Vertical Transportation Engineer). Al Huda (Sub-contractor - Utilities). Project Introduction for DCC&T: The Doha Convention Center & Tower is located in a prime location on the Corniche Road adjacent to the Doha City Center with a mixed use development including Hotel, Office, Residential and Retail. Mohamed Ismail Deputy Project Manager Qatar Olympic Committee Page | 1

Projects Brief - M Ismail - Qatar Olympic - March 2015

Embed Size (px)

Citation preview

Page 1: Projects Brief - M Ismail - Qatar Olympic -  March 2015

DE

C

05

,

20

14

Projects Brief

July 2007- Feb 2011 Turner International (Project & Construction Managers),

1- Project: Doha Convention Center & Tower. Client: Real Estate Investment. Developer: Qatari Diar Real Estate Investment. Current Project Cost Estimate: (Approx.) 8.642 Billion Qatari Riyals - 2.368 Billion $.

Consultant, Contactors & Suppliers:

Murphy / Jahn (Main Consulting – Architects). Hyder Consulting (Supervision Consulting). STS & GHD Consulting (Durability & Geotechnical Consulting). DG Jones & Partners (DGJ) (Cost Consulting & QS). Six Construct JV Midmac (Main contractor – Sub & Super-structure Convention Center). Ammico (Main contractor – Enabling & Piling Package). ACTS, Gulf Labs, Body Coat, ACES & LOADTEST (Concrete & Foundation Test Services Agencies). Untied Equipment (Sub-contractor - Dewatering System). Qatar, United & Watanya Ready Mix. (Concrete Supplier). BMC / SIKA (Sub-contractor / Supplier for Water Proof). Merco & Lion Qatar (Sub-contractor / Supplier for RFT & steel sections). ARUP (MEP-AV/ IT Consulting). Diwan (Local Consulting – Architects) Magnusson Klemencic Associates (MKA) (Structure Consulting). Thornton Tomasetti Group (TTG) (Structure Designer). Wrner Sobek Ingfnieurf (Special Structure Consulting). Rainer Schmidt (Landscape Consulting – Architects). HSBC (Insurance Consulting). Schirmer Engineering Group (Life Safety & Fire Protection). Curtain Wall Design & Consulting (CDC) (Building Cladding Consulting). Semaan & Soberman (Vertical Transportation Engineer). Al Huda (Sub-contractor - Utilities).

Project Introduction for DCC&T:

The Doha Convention Center & Tower is located in a prime location on the Corniche Road adjacent to the Doha City Center with a mixed use development including Hotel, Office, Residential and Retail.

Project Total Gross Floor Area: Tower, Retail, Ballroom, Convention Center & Below Grade Areas: 671,716 m2

Convention Center – Below Grade, Retail & Ballroom Gross Floor Area: 346,605 m2 Total number of car parking spaces: 5,062 spaces. Overall Tower building height above Ground Level (meters): 551.20 m Total number of tower floors above Ground Level : 112 floors Tower Gross Floor Area : 218,979 m2

2- Project: Museum of Islamic Art. (M.I.A.) Client: Qatar Petroleum. (Q.P.) End User: Qatar Museum Authority (Q.M.A.) Project Cost Estimate: (Approx.) 12.641 Billion Qatari Riyals – 3.463 Billion $.

Consultant, Contactors & Suppliers: I M Pei (Architect Designer).

Mohamed Ismail

Deputy Project Manager

Qatar Olympic Committee

Page | 1

Page 2: Projects Brief - M Ismail - Qatar Olympic -  March 2015

DE

C

05

,

20

14

Wilmotte & Associates (Interior Architect). Hyder Consulting (Supervision Consulting). Halcrow Consulting (Landscape Consulting). Quadrant Security Group (Security Designer). Baytur. (Main contractor - Substructure & Superstructure). Mevian Depa (Main contractor - Galleries). Al Huda (Main contractor – Facilities & Exterior landscape). Mercury (Sub-contractor MEP). Click (Sub-contractor for showcases). Cassina (Main contractor – Furniture & Signage). SIS (subcontractor for security) &Tech-q (Supplier multimedia) Haz Marbel (stones supplier) & Al Nakeal (subcontractor for plantation). Qatari Engineer & Associates (Local Associate Architect). LESLIE E ROBERTSON Associations, NY (Structure Engineer). Davis Langdon France (Quality Surveyor Consultant). Jaros Baum & Bolles (MEP Engineer). Rolf Jensen & Associates (Fire Protection / Life Safety Designer). Fisher Marantz Stone, NY (Light Designer). Fountain People (Fountain Designer). Plan Consultant (Kitchen Designer). Clean zone & Diplomatic Club (subcontractor for cleaning)

Project Introduction:

Qatar Museum Authority approached the master of modernism (I M Pei) about design the Qatar Geometric Trade Mark.

The Museum ultimately built on its own reclaimed island (376,740 ft2) and to be centerpiece of the Doha Corniche.

At the top of atrium in the highest point inside (50 m), an oculus captures and reflect patterned light around stainless steel dome which transforms the architecture into a showcase of light and shadow.

Total building: 35,500 m2 Total gallery space: 4225 m2.

Education Wing: 2700 m2 Collection Storage: 1800 m2

Library: 820 m2 Conservation Lab: 400 m2

Auditorium (197 seats): 430 m2 Ceremony Entrance Bridge: 280 m Restaurant: 380 m2 Gift Shop: 300 m2

Aug 2006-Feb 2007 Doha Asian Games Organizing Committee 2006 (DAGOC),

Directorate: Venues Directorate, Doha Asian Game Olympic Committee. Department: Development and Overlays.

Projects: Asian Games Terminal Airport (AGT) & Back of House for Doha Airport. Games Motor Pool around DOHA. Two Athletic Village Bus Depots. Five Residential Towers for Media & Technical Officials Accommodation. Central Production Unit for Catering. Officials Hotels (Sheraton-Four Season-Ritz Carlton).

Consultant, Contactors & Suppliers:

SIEMENS Portugal, Germany, India (terminal airport & PSS. fens). G.E (generators and cabling). TFCN (the look company). PICO& EL-BADAD (tents).

Mohamed Ismail

Deputy Project Manager

Qatar Olympic Committee

Page | 2

Page 3: Projects Brief - M Ismail - Qatar Olympic -  March 2015

DE

C

05

,

20

14

TRAGS (infrastructural & civil work). GULF HOUSING (civil work). BYRNE & SPACE MAKERS (port cabin, container& toilet). BOOM (road and pavement work). COMPASS, DIPLOMATIC CLUB, QATAR STAR (catering). TMS & KARWA (transportation). KAHRAMMA (water and elec.), ASHGAL (civil works), Doha Municipality & other government authorities.

Mohamed Ismail

Deputy Project Manager

Qatar Olympic Committee

Page | 3