Projects currently Under Construction Lewisville High School Auditorium Westside Aquatics Center Flower Mound High School 9 th Grade Campus Marcus

Embed Size (px)

Citation preview

  • Slide 1
  • Slide 2
  • Projects currently Under Construction Lewisville High School Auditorium Westside Aquatics Center Flower Mound High School 9 th Grade Campus Marcus High School 9 th Grade Campus
  • Slide 3
  • Lewisville H.S. Renovation and Rebuild Project Contractor: Balfour Beatty Construction Architect: SHW Group Project started: September, 2010 Project completion: November, 2013
  • Slide 4
  • Contractor: Balfour Beatty Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Lewisville High School Auditorium Purdue
  • Slide 5
  • Lewisville High School Auditorium
  • Slide 6
  • Slide 7
  • Slide 8
  • Contractor: Adolfson and Peterson Construction Architect: SHW Group Project started: November, 2012 Project completion: November, 2013 Westside Aquatics Center
  • Slide 9
  • Slide 10
  • Slide 11
  • Slide 12
  • Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall 2014 Flower Mound H.S. 9 th Grade Campus
  • Slide 13
  • Slide 14
  • Slide 15
  • Marcus H.S. 9 th Grade Campus Contractor: Satterfield & Pontikes Construction Architect: PBK Project started : May, 2013 Project completion: Fall, 2014
  • Slide 16
  • Marcus H.S. 9 th Grade Campus
  • Slide 17
  • Slide 18
  • Projects Pending Construction Camey Elementary Open Bids: September 2013 Board Approval; November 2013 Start Construction: November 2013 Substantial Completion: November 2014 Griffin Middle School Open Bids: November, 2013 Board Approval: December, 2013 Start Construction: December, 2013 Substantial Completion: June, 2015
  • Slide 19
  • Construction Schedule: Project to start: October, 2013 Project Completion: November, 2014 Main Entry Camey Elementary Rebuild
  • Slide 20
  • Slide 21
  • Slide 22
  • Griffin Middle School Rebuild Construction Schedule: Project to start: Fall, 2013 Project Completion: June, 2015
  • Slide 23
  • Griffin Middle School Rebuild
  • Slide 24
  • Projects Currently Under Warranty: Marcus HS Athletic Package Under Warranty until April, 2014 Flower Mound HS Athletic Package Under Warranty Until October, 2014
  • Slide 25
  • Contractor: Pogue Construction Architect: PBK Project under warranty until April, 2014 Marcus High School Athletic Package
  • Slide 26
  • Flower Mound H.S. Sports Package Contractor: Satterfield & Pontikes Construction Architect: PBK Project under warranty until October 2014