Projects currently Under Construction Lewisville High School
Auditorium Westside Aquatics Center Flower Mound High School 9 th
Grade Campus Marcus High School 9 th Grade Campus
Slide 3
Lewisville H.S. Renovation and Rebuild Project Contractor:
Balfour Beatty Construction Architect: SHW Group Project started:
September, 2010 Project completion: November, 2013
Slide 4
Contractor: Balfour Beatty Construction Architect: SHW Group
Project started: November, 2012 Project completion: November, 2013
Lewisville High School Auditorium Purdue
Slide 5
Lewisville High School Auditorium
Slide 6
Slide 7
Slide 8
Contractor: Adolfson and Peterson Construction Architect: SHW
Group Project started: November, 2012 Project completion: November,
2013 Westside Aquatics Center
Slide 9
Slide 10
Slide 11
Slide 12
Contractor: Satterfield & Pontikes Construction Architect:
PBK Project started : May, 2013 Project completion: Fall 2014
Flower Mound H.S. 9 th Grade Campus
Slide 13
Slide 14
Slide 15
Marcus H.S. 9 th Grade Campus Contractor: Satterfield &
Pontikes Construction Architect: PBK Project started : May, 2013
Project completion: Fall, 2014
Slide 16
Marcus H.S. 9 th Grade Campus
Slide 17
Slide 18
Projects Pending Construction Camey Elementary Open Bids:
September 2013 Board Approval; November 2013 Start Construction:
November 2013 Substantial Completion: November 2014 Griffin Middle
School Open Bids: November, 2013 Board Approval: December, 2013
Start Construction: December, 2013 Substantial Completion: June,
2015
Slide 19
Construction Schedule: Project to start: October, 2013 Project
Completion: November, 2014 Main Entry Camey Elementary Rebuild
Slide 20
Slide 21
Slide 22
Griffin Middle School Rebuild Construction Schedule: Project to
start: Fall, 2013 Project Completion: June, 2015
Slide 23
Griffin Middle School Rebuild
Slide 24
Projects Currently Under Warranty: Marcus HS Athletic Package
Under Warranty until April, 2014 Flower Mound HS Athletic Package
Under Warranty Until October, 2014
Slide 25
Contractor: Pogue Construction Architect: PBK Project under
warranty until April, 2014 Marcus High School Athletic Package
Slide 26
Flower Mound H.S. Sports Package Contractor: Satterfield &
Pontikes Construction Architect: PBK Project under warranty until
October 2014