Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
Specialist study: Hydrology and Flood Evaluation
Prepared by: A C Muir
August 2012
PROPOSED FLOOD MITIGATION MEASURES TO
BE IMPLEMENTED FOR THE
OSHAKATI/ONGWEDIVA AREA
Environmental Impact Assessment (EIA)
COPYRIGHT ©
PROJECT NAME
Environmental Impact Assessment for the Proposed
Mitigation Measures to be implemented for the
Oshakati/Ongwediva area
STAGE OF REPORT Final Draft
CLIENT Emviro Dynamics
LEAD SPECIALIST A C Muir
DATE OF RELEASE August, 2012
CONTRIBUTORS TO THE
REPORT A C Muir, L C Hattingh
DECLARATION
I ,A C Muir hereby declare that I do:
(a) have knowledge of and experience in conducting assessments (my area of expertise),
including knowledge of the Act, these regulations and guidelines that have relevance to the
proposed activity;
(b) perform the work relating to the application in an objective manner, even if this results in views
and findings that are not favourable to the applicant;
(c) comply with the Act, these regulations, guidelines and other applicable laws, as relevant to
my area of expertise.
I also declare that there is, to my knowledge, no information in my possession that reasonably has or
may have the potential of influencing –
(i) any decision to be taken with respect to the application in terms of the Act and the
regulations; or
(ii) the objectivity of this report, plan or document prepared in terms of the Act and these
regulations.
Signed: ___________________
ii
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
EXECUTIVE SUMMARY
In recent years, the central northern areas of Namibia have experienced heavy
flooding. The Town of Oshakati was severely affected by the floods, and the
Namibian Cabinet accepted a proposal for the implementation of a Concept
Master Plan for the Town. The main purpose of the Master Plan is to keep the
floodwaters out of Oshakati by constructing a flood protection dike around the
town.
The consultants appointed for the design of the flood protection dike, BAR Namibia,
developed a hydrology and hydraulic model to gauge the effect that the
construction of the dike may have on the areas susceptible to inundation through
flooding.
The EIA team carried out an evaluation of the work done by BAR and reached the
following conclusions:
Despite the lack of hydrology and flow data in the Cuvelai catchment the
consultant developed a realistic basis on which to generate rainfall data which is
acceptable taking into account the conservative approach adopted.
The flood flows generated from the hydrological model compare well with the
flows experienced in 2011 based on the modeled inundation compared to the
actual inundation in 2011.
The calibration of the model using actual inundation maps of 2011 plus measured
flood levels provide a measure of confidence in the hydraulic model.
The design of the flood diversion channel was based on the modeling objectives
of providing sufficient flow capacity such that the inundation before the channel
construction and after construction was similar. The design achieved this
objective.
The construction of the flood diversion channel will have no effect downstream of
Oshakati after the flow has merged with the natural oshanas flow. Taking the
footprint of Oshakati around which the flow will be diverted and comparing that
with the ex of the Cuvelai flow area, any local disruptions which may occur near
Oshakati are insignificant.
Construction of the dike and the flood diversion channel will affect certain
households that fall within the construction boundaries. It will also affect
traditional access routes into Oshakati. These are reported on in more detail in the
Social Impact report.
The following recommendations are therefore made:
The lack of rainfall, flow and water level data in the catchment of the Cuvelai is a
serious shortcoming that should be addressed as a matter of urgency, particularly
in light of similar developments which are likely to take place within the
catchment.
It is further recommended that funds should be made available on the budget of
the current project to design a strategy to implement the collection of critical
iii
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
data. This data should then be used to monitor future flood events and compare
actual measurements with the model results.
The construction programme and a flood management plan must be designed
for the construction phase when the town will be most susceptible to flooding.
The design of the dike should take into consideration the access of the rural
communities near Oshakati into the town.
iv
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
CONTENTS
EXECUTIVE SUMMARY ........................................................................................................... ii
CONTENTS ............................................................................................................................ iv
TABLES AND FIGURES ........................................................................................................... vi
APPENDICES ........................................................................................................................ vii
ABBREVIATIONS AND ACRONYMS.................................................................................... viii
1 INTRODUCTION ............................................................................................................. 1
1.1 BACKGROUND ........................................................................................................... 1
1.2 SPECIALIST STUDY LEADER ......................................................................................... 1
1.3 TERMS OF REFERENCE................................................................................................ 1
1.4 assumptions and limitations ..................................................................................... 2
1.5 METHODOLOGY ........................................................................................................ 3
1.5.1 Hydrological Model ............................................................................................ 3
1.5.2 Hydraulic Model.................................................................................................. 4
1.5.3 Design of the Flood Diversion Channel ........................................................... 5
1.5.4 Evaluation of Consultants Methods and Results ............................................ 6
2 PROJECT DESCRIPTION ................................................................................................. 7
3 LEGAL AND REGULATORY REQUIREMENTS ................................................................... 9
4 THE RECEIVING ENVIRONMENT .................................................................................. 10
4.1 INTRODUCTION ........................................................................................................ 10
5 IDENTIFICATION OF KEY IMPACTS .............................................................................. 14
5.1 KEY POTENTIAL IMPACTS TO BE ASSESSED............................................................. 14
6 IMPACT ASSESSMENT .................................................................................................. 15
6.1 METHODOLOGY FOR IMPACT ASSESSMENT ......................................................... 15
6.1.1 Description of impact ...................................................................................... 15
6.2 IMPACT ASSESSMENT ............................................................................................... 23
v
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
7 CONCLUSIONS AND RECOMMENDATIONS ............................................................... 24
8 REFERENCES ................................................................................................................ 25
vi
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
TABLES AND FIGURES
Table 1: Environmental sensitivity and the potential impact ....................................... 13
Table 2: Flood levels north and to the west of Oshakati ............................................... 17
Table 3: Flood levels within Oshakati ................................................................................... 17
Table 4: Inundation of rural households .............................................................................. 18
Table 5: Inundation of access routes .................................................................................. 18
Table 6: Changes in flow velocities ..................................................................................... 19
Table 7 Higher turbidity and salinity ..................................................................................... 19
Table 8: Flood levels north and to the west of Oshakati ............................................... 20
Table 9: Flood levels within Oshakati ................................................................................... 20
Table 10: Inundation of rural households ............................................................................ 21
Table 11: Inundation of access routes ................................................................................ 21
Table 12: Changes in flow velocities ................................................................................... 21
Table 13: Higher turbidity and salinity .................................................................................. 22
Table 14: Summary of impact assessment .................................................................... 23
Figure 1: Extent of hydraulic model ....................................................................................... 5
Figure 2: Overview of the Project Area showing the position of the Dyke ...................... 8
Figure 3: Flow of Oshanas through Oshakati ..................................................................... 11
Figure 4: Oshana flow intercepted by Diversion Channel ............................................... 12
Figure 5: Inundation map for pre and post dyke construction ....................................... 16
vii
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
APPENDICES
BAR Namibia, IMDC (2012). Design and Supervision of the Construction of the Dike
around Oshakati. Report on the Hydrological and Hydraulic Model
viii
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
ABBREVIATIONS AND ACRONYMS
1D 1 - dimensional
2D 2 - dimensional
BAR Namibia Buro of Architects Namibia
DTM Digital Terrain Model
EIA Environmental Impact Assessment
PDM model Probability Distributed Moisture model
PMF Probable Maximum Flood
RMF Regional Maximum Flood
UK United Kingdom
WCE Windhoek Consulting Engineers
1
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
1 INTRODUCTION
1.1 BACKGROUND
In recent years, the central northern areas of Namibia have experienced heavy
flooding. In 2008 the floods were considered the highest in living memory. However,
these floods were exceeded in 2009, and again in 2011.
The Town of Oshakati was severely affected by the floods, and the Namibian
Cabinet accepted a proposal for the implementation of a Concept Master Plan for
the Town. The main purpose of the Master Plan is to keep the floodwaters out of
Oshakati by constructing a flood protection dike around the town.
BAR Namibia has been appointed as the consultants on the project. IMDC was
appointed by BAR as sub-consultants to perform the hydrological and hydrodynamic
study. This specialist report forms part of the Environmental Impact Assessment and
will evaluate the work done on the hydrology and hydraulic modeling and will assess
the various impacts of the project on the environment.
1.2 SPECIALIST STUDY LEADER
Mr Muir trained as a Civil Engineer at the University of Cape Town, South Africa. After
graduation he joined the Department of Water Affairs, Namibia in 1974. During this
period he worked as a design engineer and also spent four years on site as a
construction engineer. He was promoted to head of the design office in 1981 and
thereafter promoted to Director of Works of the Department. He left the government
service in 1991 and joined Windhoek Consulting Engineers (WCE) as an Associate.
During his time with WCE he was involved in numerous flood investigations which
included both flood hydrology and hydraulic modeling.
His experience is also related to the design, construction and management of water
supply projects and township services as well as the investigation into water
resources. He also has experience in water and waste water treatment systems.
1.3 TERMS OF REFERENCE
The purpose of the hydrological and hydrodynamic study is to provide the basis for
the design of the flood protection measures with all necessary hydraulic information.
For this, a detailed hydrodynamic model was developed, that allows the impact of
flooding due to the construction of a dyke around Oshakati to be assessed. To
deliver input to this hydrodynamic model, a hydrological model was first developed.
With the model, changes in water levels and flows in and around Oshakati can be
2
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
calculated. Hence design variables, such as dyke crown height, culvert capacity
and bridge width, can be determined. This will then divert floodwater around the
town. The dike will extend from the north of Okatana and will divert the floodwaters
around Oshakati, to the west. The floodwater will then join with the natural drainage
system south of Oshakati.
The EIA component of this study will evaluate the methods used, the model
calibration techniques applied and the level of confidence that can be attributed to
the results. Impacts on the environment of the construction of the dike will also be
assessed.
1.4 ASSUMPTIONS AND LIMITATIONS
A major limitation in conducting a study of the hydrology and flow regime of the
Cuvelai catchment is a serious lack of records. This includes rainfall records, flow
data and flood levels
Although the Namibia met office has rainfall records at a few stations in the Cuvelai,
some of which go back to 1913, many have not been updated for some time and
there are significant gaps in the records. Very little data is available on surface water
flows in the catchment. There are 13 gauging stations located south of the border
which measure water levels, but no flow data are available. These flow gauging
stations were installed prior to the 2008 floods at Shakambebe and Shanalumono just
south of the Angola border. No depth-discharge curves exist, which renders it
impossible to convert the stage records into flow records.
No data is available for the major part of the catchment which lies north of the
Namibia/Angola border.
The lack of data has made the hydrological study a challenging task and the level of
accuracy of the results should be seen in this context. For this reason a conservative
approach was adopted in determining the flows in the catchment.
Flow data are available in the adjoining catchments of the Kunene River at
Ruacana and the Okavango River at Rundu. However, this information was not used
in estimating the flows in the Cuvelai catchment.
The limitations imposed on the methodology and accuracy of the study can thus be
summarized as follows:
No flow records exist for the Cuvelai catchment;
The catchment of the Cuvelai is extremely flat – an average slope of less than
0.1%;
3
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
The conventional methods for determining flood peaks are not applicable to
these very flat catchments – this was confirmed by some control calculations
done by the EIA team using deterministic methods for the Kunene as well as
Okavango catchments. It was clear from the results of these deterministic
methods that the attenuation effect of the oshanas cannot be effectively
modeled by the use of conventional methods as the results tend to give
extremely unrealistically high flood peaks;
Previous hydrology calculations for the Cuvelai catchment (KPE: 2009) used
the results of extremely conservative empirical calculations to determine flood
peaks for different sub-catchments assuming that the use of the RMF and PMF
of the Kunene River with probabilities of exceedance of less than 10-9 is of
relevance. This is considered to be overly conservative and not realistic;
1.5 METHODOLOGY
1.5.1 Hydrological Model
The following methodology was applied by the consultants, BAR Namibia, in
generating the flood data for the hydrological model. For detailed information on
the techniques used to generate the modeling data for the catchment area, refer to
the BAR report on the hydrology and hydraulic model.
i. A DTM of the catchment area was compiled from available data.
ii. Rainfall data was generated for the Cuvelai catchment using available
rainfall records and satellite imagery.
iii. Time series evaporation data was derived based on the average potential
evaporation rate per year (i.e. 2800-3000 mm).
iv. Additional modeling parameters such as soil storage capacity, reservoir time
constants and infiltration rate to groundwater were developed.
v. The above information was used to develop the hydrological model which
transforms rainfall and potential evaporation data to flow at the catchment
outlet.
vi. The model that was used for the study is the Probability Distributed Moisture
model (PDM model) which is a fairly general conceptual rainfall-runoff model
which was developed and is maintained by the UK Centre for Ecology and
Hydrology.
4
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
1.5.2 Hydraulic Model
The hydrodynamic model was developed using InfoWorks RS v10.5.12 (Innovyze Ltd,
UK). The program can model open channel flow and overbank flows in any network
of channels.
The program can be used to solve systems under both steady and unsteady flow
conditions, either flows with a pronounced 1D character or flows with no principal
component, i.e. 2D-flow can be modeled.
A digital terrain model (DTM), combined with on-site topographical measurements of
all relevant hydraulic structures, were used to define river cross sections, bridges,
culverts etc., as well as information on the bed characteristics which was modeled
using Manning’s coefficient.
Due to the very flat topography in the region, there is an exchange of flow between
the interconnected oshanas. The invert level of the oshanas is not constant, neither is
the water level constant during periods when there is flow in the oshanas, and also,
significantly, during times of high floods. The direction of the flow between the
interconnected oshanas depends on the difference in water levels between the
oshanas. The location of the interconnections were determined from the flood map
of April 5, 2011, while the flow between the oshanas was determined using the weir
flow equation.
After the initial modeling runs, the model was calibrated using the flood inundation
areas recorded in 2011. More detail of the calibration methods can be found in the
BAR report on the hydrology and hydraulic modeling. The flood levels obtained from
the model were also checked against measured flood levels in the area which
corresponded within acceptable limits taking into account the expected modeling
tolerances.
The extent of the model can be seen in Figure 1.
5
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Figure 1: Extent of hydraulic model
1.5.3 Design of the Flood Diversion Channel
The flood diversion channel has been designed to transfer flood waters arriving in the
oshanas north of Oshakati, flowing around the western side of Oshakati and joining
up again with the natural flow of the oshanas south of Oshakati. One of the aims of
the project is to ensure that the dike has a minimal impact on the inundation of the
area upstream and to the west of Oshakati. The effect of the inundation will be
reported on in more detail in the social impact study.
However, based on the method used to calibrate the hydraulic model, the effect of
further inundation should be limited.
6
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
1.5.4 Evaluation of Consultants Methods and Results
A number of discussions and meetings were held between the EIA team, the
Department of Water Affairs’ Hydrology Division and the consultants, BAR Namibia,
on the work undertaken in determining the flow magnitudes and flood inundation
areas. These discussions were held in Windhoek and Oshakati in January 2012. At
this stage the first draft of the hydrology and flood modeling report was available.
The EIA team’s initial comments were then addressed in the final model which was
presented in Windhoek in March 2012.
Taking into consideration the lack of rainfall, flow and flood level data in the Cuvelai
catchment, and considering also that the major part of the catchment falls in
Angola, where no data is available, the detail of the work done by BAR Namibia as
well as the techniques used to generate the flood data is noteworthy. It is the
opinion of the EIA team that the results of the hydrology and hydraulic modeling are
sufficiently accurate to be used in the design of the flood protection dike around
Oshakati.
7
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
2 PROJECT DESCRIPTION
The Town of Oshakati, the capital of the Oshana Region, has in recent years, been
severely affected by flooding. To make Oshakati flood free, a dyke will be
constructed, extending from the north of Okatana around the western edge of
Oshakati and joining up again with the natural flowing oshanas south of Oshakati.
This will divert the main flows arriving from the north, around Oshakati.
The proposed dyke for Oshakati will be approximately 26km long and 44m wide. The
height of the crest of the dyke will be between 2.2-2.5 m above the existing oshana
bed level. This level corresponds to the maximum water level of the design flood
(return period of 100 year). An additional freeboard of 500mm has also been
provided. The 100 year flood level has been determined using a hydrological and
hydraulic model which was developed by the4 consultants.
The dyke has been extended to the south to avoid backwater flowing into the town
from the south.
The dyke will have a slope protection such as grouted stone pitching at the water
side to avoid erosion, the details of which will be designed according to the soil
characteristics. At the land side a cemented gravel slope protection is foreseen.
All natural vegetation including large trees will be cleared from the footprint area of
the dyke to ensure a good foundation.
On top of the dyke a dual carriage way (60m road reserve) will be constructed
which will act as a bypass or ring road around Oshakati.
The ring road will have a limited access only at the intersections with the trunk roads
entering Oshakati. These intersections will be designed as roundabouts with a large
radius to avoid the need for and maintenance of robot controlled intersections. The
ring road is being considered in conjunction with the Roads Authority.
The dyke around Oshakati will be used to divert flood waters from the north around
the western side of the town. The diversion channel will use existing oshanas as far as
possible to convey the water around the town. However, where high ground
between these oshanas is encountered it will be excavated to form part of the
channel.
An overview of the project area is shown in Figure 2
8
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Figure 2: Overview of the Project Area showing the position of the Dyke
9
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
3 LEGAL AND REGULATORY REQUIREMENTS
The Local Authorities Act requires that no residential development is allowed below
the 1 in 50 year flood level.
A long period of relatively dry rain seasons has been experienced in the north of
Namibia between 1995 and 2008. This period coincided with rapid urbanization and
development, particularly informal housing, in Oshakati. This also resulted in large
low lying areas being used for the construction of residential units.
The project now being proposed will be based on keeping Oshakati flood free for
floods exceeding a return period on 1 in 100 years.
10
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
4 THE RECEIVING ENVIRONMENT
4.1 INTRODUCTION
The town of Oshakati lies within the area in the north of Namibia which is
characterized by very flat terrain and an ill-defined drainage network that originates
in Angola and converges into the Etosha Pan. The town was originally developed on
higher lying areas between oshanas. With the rapid urbanization that took place
after 1990 developed flowed over into the lower lying areas of Oshakati. These are
the areas most affected by flooding.
The ephemeral channels, or oshanas, in the Cuvelai Delta normally fill up from local
rains in the rainy season but with little continuous flow. In good rainy seasons,
floodwaters from the upper catchment in Angola reach Namibia, resulting in floods
known as the efundja. Under normal circumstances the local population welcomes
the efundjas because of the opportunity for fishing and because open water is
available for stock drinking.
Floods are mainly the results of local rainfall and rainfall just north of the border in
the Cuvelai Delta.
Efundja floods are mainly the result of a flood in the “main” Cuvelai River
spreading out over the full width of the Cuvelai Delta north of the border.
Floods in the Cuvelai Delta are often made worse by road embankments which
obstruct the flow of water in the oshanas.
Flooding in Oshakati is caused by the flow from a few major oshanas that flow from
the north. Currently this flow goes through the centre of Oshakati and causes serious
inundation of the low lying areas where a lot of informal settlement has occurred
over the last number of years.
Figure 3 provides an overview of the existing oshanas that flow into Oshakati and the
extent of the inundation that occurred in 2011.
11
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Figure 3: Flow of Oshanas through Oshakati
Flow from the major oshanas north of Oshakati will be combined. Atherse flows will
be intercepted by the dyke and diverted to the west of the town.
Figure 4 shows how these flows will be combined and intercepted by the diversion
channel.
12
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Figure 4: Oshana flow intercepted by Diversion Channel
Land use in the affected area is dominated by communal farming in the rural areas
and urban development within the Oshakati Townlands.
In Oshakati Town flooding takes place in the lower lying areas that have developed
following rapid urbanization over the last 20 years. This has been made worse by the
recent good rain seasons which caused major flows in the oshanas that flow through
and around the town.
The rural areas are less affected by the floods as development has traditionally taken
place on the higher lying ground next to the Oshanas. However, recent floods have
caused major problems with access where roads and other traditional access routes
have bee4n either breached or inundated.
13
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Table 1: Environmental sensitivity and the potential impact
ENVIRONMENTAL FEATURE SENSITIVITY POTENTIAL IMPACT
Low lying areas in Oshakati The floods cause major flooding
in the low lying areas
increasingly being used as
informal settlements
Positive as flood will be
diverted around the
town
Inundation of rural areas Changes in the flood regime
may inundate new areas.
If larger areas are
inundated, this will
affect rural residents.
Access from rural areas close to Oshakati
into the town
Rural residents current5ly use
numerous alternative, more
informal routes into Oshakati.
During times of flood
access will be
negatively affected as
the whole western side
of Oshakati will only be
accessed along major
roads.
14
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
5 IDENTIFICATION OF KEY IMPACTS
5.1 KEY POTENTIAL IMPACTS TO BE ASSESSED
The following are the key impacts related to the hydrology and hydraulic modeling
study:
Flood levels north and to the west of Oshakati
Flood levels within Oshakati
Inundation of rural households
Inundation of access routes.
Changes in flow velocities
Possible increase in turbidity and saline content of the oshanas water caused by
excavations required to construct the diversion channel
15
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
6 IMPACT ASSESSMENT
6.1 METHODOLOGY FOR IMPACT ASSESSMENT
The methodology followed in determining the impacts listed above is the same for all
impacts. All the impacts are affected by the flows in the oshanas and the flood
levels. The methodology is described in detail in paragraph 1.5:
6.1.1 Description of impact
The construction of the dike will have an effect on the flood levels north and to the
west of Oshakati. Although the diversion channel has been designed to be large
enough to divert the full incoming flow from the north there are still areas which will
now be inundated during the 1 in 100 year flood. The inundation of these areas will
only occur under extreme flood conditions and the impact is thus not considered to
be severe. Figure 5 below presents the inundated areas pre and post dyke
construction.
Flood levels within Oshakati will be reduced to the flooding that will take place from
local stormwater runoff. Flooding from the oshanas will not occur after construction
of the dike.
Inundation that can be expected of the rural households in the vicinity of Oshakati
should not increase since the hydraulic model was calibrated to ensure that the
areas inundated by floods are not greater after the construction of the dike.
Inundation of access routes to Oshakati will be affected during periods of flood and
the rural population will have to make use of the major roads to gain access to the
town. This may cause inconvenience since longer distances may have to be
traversed.
16
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Figure 5: Inundation map for pre and post dyke construction
17
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Table 2: Flood levels north and to the west of Oshakati
DESCRIPTION
EXTENT Site specific
A minimal
backwater effect
is created to the
north and west of
Oshakati under
extreme flood
conditions
Local
A minimal
backwater effect is
created to the
north and west of
Oshakati under
extreme flood
conditions
Regional
No impact
National
No impact
International
No impact
DURATION Very Short Term
≤ 1 week for local
flooding
Short term
For duration of
flood event
Medium term
No impact
Long term
No impact
Permanent
No impact
INTENSITY/
MAGNITUDE
No lasting effect
No environmental
functions and
process are
affected
Minor effects
Effect will depend
on accuracy of
model calibration
Moderate effects
No impact
Serious effects
No impact
Table 3: Flood levels within Oshakati
DESCRIPTION
EXTENT Site specific
Improvement
Local
Improvement
Regional
No impact
National
No impact
International
No impact
DURATION Very Short Term
No impact
Short term
No impact
Medium term
No impact
Long term
No impact
Permanent
No impact
INTENSITY/
MAGNITUDE
No lasting effect
No environmental
functions and
process are
affected
Minor effects
No
environmental
functions and
process are
affected
Moderate effects
No impact
Serious effects
No impact
18
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Table 4: Inundation of rural households
DESCRIPTION
EXTENT Site specific
Similar to previous
natural condition
Local
Similar to
previous natural
condition
Regional
No impact
National
No impact
International
No impact
DURATION Very Short Term
From local rain
Short term
For duration of
flood event
Medium term
No impact
Long term
No impact
Permanent
No impact
INTENSITY/
MAGNITUDE
No lasting effect
Minor
Minor effects
Minor
Moderate effects
No impact
Serious effects
No impact
Table 5: Inundation of access routes
DESCRIPTION
EXTENT Site specific
Inconvenience as
alternatives are
available
Local
Inconvenience
as alternatives
are available
Regional
No impact
National
No impact
International
No impact
DURATION Very Short Term
≤ 1 week for local
flooding
Short term
For duration of
flood event
Medium term
No impact
Long term
No impact
Permanent
No impact
INTENSITY/
MAGNITUDE
No lasting effect
Minor
Minor effects
Minor
Moderate effects
No impact
Serious effects
No impact
19
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Table 6: Changes in flow velocities
DESCRIPTION
EXTENT Site specific
Flow velocities are
on average
approximately 0.5
m/s and can
increase up to 0.8
m/s. This could be
dangerous for
people wanting to
cross an oshanas
during floods
Local
Could be
dangerous
during floods
Regional
No impact
National
No impact
International
No impact
DURATION Very Short Term
≤ 1 week for local
flooding
Short term
For duration of
flood event
Medium term
No impact
Long term
No impact
Permanent
No impact
INTENSITY/
MAGNITUDE
Will have a lasting
effect
Could be major
Will have a
lasting effect
Could be major
No impact No impact
Table 7 Higher turbidity and salinity
DESCRIPTION
EXTENT Site specific
Not expected to
be significant if
fish not affected
Local
Not expected to
be significant if
fish not affected
Regional
No impact
National
No impact
International
No impact
DURATION Very Short Term
≤ 1 week for local
flooding
Short term
For duration of
flood event
Medium term
No impact
Long term
No impact
Permanent
No impact
INTENSITY/
MAGNITUDE
Should find a
balance after a
few flood events
Could be major in
Should find a
balance after a
few flood events
Could be major
No impact No impact
20
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
DESCRIPTION
the short term in the short
term
Status and degree of confidence in predictions of the impact are described in the
table below :
Table 8: Flood levels north and to the west of Oshakati
NONE LOW MEDIUM HIGH
IMPACT
SIGNIFICANCE
The impact is expected
to be moderate as
relatively small areas
are affected and then
only under extreme
flooding conditions
Table 9: Flood levels within Oshakati
NONE LOW MEDIUM HIGH
IMPACT
SIGNIFICANCE
The situation of
flooding within
Oshakati will improve
with the construction
of the dyke
21
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Table 10: Inundation of rural households NONE LOW MEDIUM HIGH
IMPACT
SIGNIFICANCE
Rural households may
be affected by
inundating larger
areas. The impact can
be mitigated by
ensuring adequate
capacity in the
diversion channel to
pass all the flood
waters.
Table 11: Inundation of access routes
NONE LOW MEDIUM HIGH
IMPACT
SIGNIFICANCE
The impact is expected
to be low as there are
alternative routes into
town. The duration of
the impact is also
limited to the flood
events
Table 12: Changes in flow velocities
NONE LOW MEDIUM HIGH
IMPACT
SIGNIFICANCE
The impacts could be
serious if people try
and cross the diversion
channel during
flooding, particularly
young children.
22
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
Table 13: Higher turbidity and salinity NONE LOW MEDIUM HIGH
IMPACT
SIGNIFICANCE
The impact may cause
the normal behaviour
of fish to change. If
fish stay away from
the area it could affect
a source of food for
the local population.
23
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
6.2 IMPACT ASSESSMENT
Table 14: Summary of impact assessment
DURING CONSTRUCTION DURING OPERATION
NATURE OF THE IMPACT Care must be taken
when construction takes
place during the rain
season that temporary
protection is provided
against flooding of the
town
Maintenance must be
undertaken of the canal and
any signs of erosion must be
immediately attended to
EXTENT Could be major during
the rainy season
Very important
DURATION ± 3 months Permanent
INTENSITY High Medium
PROBABILITY High High
STATUS (+ OR -) - ve - ve
SIGNIFICANCE (NO
MITIGATION/ENHANCEMENT)
Enhancement Enhancement
MITIGATION Yes Yes
SIGNIFICANCE (WITH
MITIGATION/ENHANCEMENT)
High High
CONFIDENCE LEVEL High High
24
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
7 CONCLUSIONS AND RECOMMENDATIONS
With reference to the evaluation of the hydrology study and the hydraulic modeling
carried out by BAR Namibia. The following can be concluded:
Despite the lack of hydrology and flow data in the Cuvelai catchment the
consultant developed a realistic basis on which to generate rainfall data which is
acceptable taking into account the conservative approach adopted.
The flood flows generated from the hydrological model compare well with the
flows experienced in 2011 based on the modeled inundation compared to the
actual inundation in 2011.
The calibration of the model using actual inundation maps of 2011 plus measured
flood levels provide a measure of confidence in the hydraulic model.
The design of the flood diversion channel was based on the modeling objectives
of providing sufficient flow capacity such that the inundation before the channel
construction and after construction was similar. The design achieved this
objective.
The construction of the flood diversion channel will have no effect downstream of
Oshakati after the flow has merged with the natural oshanas flow. Taking the
footprint of Oshakati around which the flow will be diverted and comparing that
with the ex of the Cuvelai flow area, any local disruptions which may occur near
Oshakati are insignificant.
Construction of the dike and the flood diversion channel will affect certain
households that fall within the construction boundaries. It will also affect
traditional access routes into Oshakati. These are reported on in more detail in the
Social Impact report.
The following is recommended:
The lack of rainfall, flow and water level data in the catchment of the Cuvelai is a
serious shortcoming that should be addressed as a matter of urgency, particularly
in light of similar developments which are likely to take place within the
catchment.
It is further recommended that funds should be made available on the budget of
the current project to design a strategy to implement the collection of critical
data. This data should then be used to monitor future flood events and compare
actual measurements with the model results.
The construction programme and a flood management plan must be designed
for the construction phase when the town will be most susceptible to flooding.
The design of the dike should take into consideration the access of the rural
communities near Oshakati into the town.
25
Environmental Impact Assessment: Oshakati Flood Mitigation Project Specialist Study: Hydrology and Flood Evaluation Date July 2012
8 REFERENCES
Enviro Dynamics (2010). Environmental Impact Assessment and Environmental
Management Plan of Orange River Life of Mines Extension Project, Sendelingsdrift.
Oranjemund: NAMDEB.
Mendelsohn, J., Jarvis, A., Roberts, C., & Robertson, T. (2009). Atlas of Namibia: A
portrait of the land and its people. Cape Town, South Africa: Sunbird Publishers (PTY)
LTD.
BAR Namibia, IMDC (2012). Design and Supervision of the Construction of the Dike
around Oshakati. Report on the Hydrological and Hydraulic Model
G van Langenhove (2008). Hydrological Perspective on 2008 Floods in Northern
Namibia, with Special Reference to Cuvelai Area. Report Department of Water
Affairs
L C Hattingh (2012). Hydrology for the Omafo to Outapi Road (DR3608). Hydrology
report for the design of the upgrading of the road between Omafo and Outapi.
KPE Joint Venture (2008). Study Report on Flooding of Proclaimed Roads in North
Central Namibia (RA/CS-NP/04-2008). Report for the Roads Authority