27
Proposed Northwest Transmission Line Public open houses: Smithers March 31, 2009 – Hudson Bay Lodge Terrace April 1, 2009 – Coast Inn of the West Stewart April 2, 2009 – Al Lawrence Memorial Arena

Proposed Northwest Transmission Line - BC Hydro · Proposed Northwest Transmission Line Public open houses: Smithers March 31, 2009 – Hudson Bay Lodge ... • Hydrogeography: characteristics

Embed Size (px)

Citation preview

Proposed Northwest Transmission Line

Public open houses:

Smithers March 31, 2009 – Hudson Bay Lodge Terrace April 1, 2009 – Coast Inn of the West Stewart April 2, 2009 – Al Lawrence Memorial Arena

2

Overview• About BCTC• Proposed Northwest Transmission Line (NTL)

- Overview- Route options- Right-of-way and structures

• Consultation • Environmental studies• Milestones• Questions

3

About BCTC• Independent Crown Corporation

- Regulated by the BC Utilities Commission- Reports to the Ministry of Energy, Mines and Petroleum Resources

• Responsible for planning, building, operating and maintaining the Province’s grid in a safe, reliable and cost-effective manner

- $5.3 billion, 10-year capital plan- Long-Term Transmission Vision (30-year road map)

4

The Transmission SystemMore than 18,000 km oftransmission lines

75,000 hectares of ROW

Close to 300 stations

State of the art system control centre and backup facility

Interconnections to USAand Alberta

5

Key:Red: 500kvBlue: 287 kVGreen: 230 kVDark blue: 138 kVBlack: 69 kV

6

Potential NTL~ 335 km, 287 kV transmission line

Skeena substation (Terrace) to possible new substation near Bob Quinn Lake

Alternative routes being studied in some locations

~ $400 million (2007 estimate); private-public partnership

7

Right of way

ROW width: 38 m

Extra one-time clearing on each side for security of line

8

Possible structure types

9

Potential benefits• If NTL is constructed, it could provide:

- Reliable, clean electricity supply to attract and support new industrial developments – such as mines – which could support overall economic growth

- Secure grid connection to new sources of clean electricity (IPPs)- Potential to connect communities reliant on diesel generation to a cleaner

power supply, if they wish

10

Key dates to December 2007

• May 4, 2007: BCTC applied to BCEAO, requesting that NTL be accepted for review under the BC Environmental Assessment Act

• June 1, 2007: BCEAO accepted NTL for review and posted project description

• Nov 12, 2007: BCEAO issued Section 11 Order • Nov 13, 2007: BCEAO posted draft Terms of Reference (TOR)

for EA Application; public comment period startedNovember 26, 2007: NTL put on hold• Dec 5, 2007: Public comment period suspended

11

Current phase of NTL • Province announces funding Sept. 26, 2008, to continue the

environmental assessment and consultation processes

• This will lead to the preparation of an Application for an Environmental Assessment Certificate

• Province seeking a partner to contribute towards construction costs

• No plans to file the Application or to construct NTL until “funding gap” is addressed

12

Terms of Reference• Consultation with Nisga’a Nation, First Nations, agencies,

stakeholders and public

• Specifies studies to be conducted and information requirements to be provided in Application for an Environmental Assessment Certificate

• Assessment work has been contracted to Rescan Environmental Services Ltd., with professional and technical field assistance by First Nations and Nisga’a Nation

13

Nisga’a and First Nations consultation• Led by BC Hydro’s Aboriginal Relations and Negotiations

team

• First Nations with interests in NTL, and Nisga’a Nation, are encouraged to participate throughout the planning process, environmental assessment, and other regulatory or approval processes related to NTL

• First Nations and Nisga’a Nation participation facilitated through funding

14

First Nations consultation• First Nations participating in consultation process include:

- Kitselas First Nation- Kitsumkalum First Nation- Lax Kw’alaams First Nation- Metlakatla First Nation- Gitxsan - Skii km Lax Ha Nation- Tahltan - Gitanyow Hereditary Chiefs

15

Public consultation• Led by BCTC Community Relations. Goals:

- Provide information and receive feedback through meetings with stakeholders and public; web and email updates; and other communications materials

- Identify opportunities for public input into NTL and encourage public involvement in the EA process for NTL

• Going forward:- Continue to update and offer meetings to interested stakeholder groups- Arrange public meetings in support of EA process (e.g., during public

comment period for draft Terms of Reference)

16

Study topicsMeteorology & Air QualityNoiseVisual QualitySoilsGeotechnical & Natural HazardsPhysiography & TopographyGeology & GeochemistryHydrologyHydrogeologyArchaeologyTraditional Use

Traditional KnowledgeEcosystem MappingVegetation WildlifeFisheriesAquaticsWetlandsSocio-economicsLand UsePublic HealthTransportation & Utilities

17

Studies • Meteorology/Air quality:

historic and current conditions; potential impacts of weather and air quality on transmission line

• Visual quality: potential effect of project on visually sensitive areas, such as parks, communities, viewsheds, etc.

• Noise: existing noise levels and potential changes during project construction and operation

18

Studies (cont’d)

• Soils: determine which soils in project area are sensitive to degradation/erosion

• Geotechnical/Natural hazards:assess terrain stability in project area (e.g., seismic, volcanic, land movement, etc.)

• Physiography/Topography: key features in area, such as mountains, watercourses, wetlands, etc.

19

Studies (cont’d)

• Geology/geochemistry: characterization of representative rock types; determination of metal leaching/acid rock drainage

• Hydrology: surface water quantity conditions

• Hydrogeography:characteristics of any ground water aquifers, esp. at proposed substation and work camp sites

20

Studies (cont’d)

• Vegetation and Ecosystem mapping: inventory of plant species and ecosystems

• Wildlife: habitat mapping and surveys of ungulates, grizzly bear, birds, bats, species at risk

21

Studies (cont’d)

• Fisheries: fish presence and habitat quality for watercourses crossed by potential project

• Aquatics: aquatic communities and habitat in watercourses crossed by potential project

• Wetlands: types, sizes locations and functions; plant species, soil and water characteristics; reliant wildlife

22

Studies (cont’d)

• Public Health: audible noise, EMF, domestic water quality/supply, country foods

• Socio-economic: community well-being – economic, services, employment, infrastructure, etc.

• Land use: forestry, mining, traplines, fishing/angling, guide-outfitting, tourism, residential, etc.

• Transportation, Utilities air, land and water transportation corridors; utilities (gas, electric, sewers, etc.)

23

Studies (cont’d)• Archaeology: archaeological

overview assessment; based on AOA determine if archaeological impact assessment required in any portion of study area

• Traditional Knowledge & Use:First Nations with traditional territory in proposed project area hold unique knowledge

• Nisga’a Nation rights and interests: Nisga’a Nation has unique knowledge of Nisga’a lands, Nass area and Nass wildlife area

• BCTC working with First Nationsand Nisga’a Nation to support community-directed studies

24

Environmental Management Program

• BCTC Construction Environmental Management Plans and Operational Environmental Management Programs

- Construction EMPs describe the environmental practices and procedures to be applied during the construction of the project

- Operational EM Programs include existing provincial procedures, systems, principles and plans applied during operations and which may be periodically updated

25

Upcoming milestones

• June 2009: Finalize TOR; complete studies and effects assessments

• Sept 2009: Application for EA Certificate ready for filing

26

BCTC Project Delivery Team

PM(Tim Jennings)

BCTCSteering Committee

(David Emerson, Doug Little, John Irving, Bruce Barrett, Julius Pataky,

Janet Woodruff)

NTL ProjectOrganization Chart

Community Relations

(Lesley Wood)

Environmental Consultant

(Rescan – Rolf Schmitt)

Properties(BCH - Sharon

Szameit)

FN’s(BCH ARN –

Jeremy Higham)

BCTC System Planning

(Phil Park)

BCH Engineering(Pat Siega)

27

QUESTIONS?