Proposition 84 Project Status Round No. of Projects Progress Grant Amount Total Cost Round 1 13 Projects 7 Complete $12M $260M Round 2 18 Projects 0 Complete $14.5M $150M Drought 9 Participants 0 Complete $12M $23M Final 7 Participants 0 Complete $61M $237M

Proposition 84 Project Status - sawpa.org

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Proposition 84 Project Status - sawpa.org

Proposition 84 Project Status

Round 1 13 Projects, 7 Complete, $12M grants, $260M total Round 2 18 Projects, 0 Complete, $14.5M grants, $150M total Drought Round 9 Participants, 0 Complete, $12M grants, $23M total Final Round 7 Participants, 0 Complete, $61M grants, $237M total

Round No. of Projects Progress Grant Amount Total Cost

Round 1 13 Projects 7 Complete $12M $260M

Round 2 18 Projects 0 Complete $14.5M $150M

Drought 9 Participants 0 Complete $12M $23M

Final 7 Participants 0 Complete $61M $237M

Page 2: Proposition 84 Project Status - sawpa.org

Projected Watershed-Wide Benefits of All Four Rounds of OWOW Prop 84 IRWM Projects

• Reduces water demand by 18,000 AFY representing 36,000 households

• Captures 44,000 AFY of stormwater for beneficial use

• Recharges 180,000 AF of additional imported water

• Produces 18,000 AFY of desalted groundwater

• Removes 29,000 tons of salt from groundwater per year

• Creates 11,000 AFY of additional recycled water

• Restores 3,800 acres of environmental habitat

• Reduces nonpoint source pollution by 29,000 pounds per year

• Reduces flood risk damage by $91 million

• Creates about 11,000 construction related jobs

Page 3: Proposition 84 Project Status - sawpa.org

Round 1 Projects

Page 4: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required

Funding

Match

Add’l Cost

Share

Total Project

Cost

% Grant

Billed

% Project

Complete

Perris II Desalination

Facility

EMWD $ 1,000,000 $ 607,296

26.00%

$ 728,456 $ 2,335,752 100% 98%

GWRS Flow Equalization OCWD $ 1,000,000 $ 1,180,760

7.67%

$ 13,218,9201 $ 15,399,680 100% 100%

Alamitos Barrier

Improvement Project

OCWD $ 1,000,000 $ 650,600

5.61%

$ 9,956,0002 $ 11,606,600 100% 25%

Chino Creek Wellfield

Development Project

WMWD $ 1,000,000 $ 1,646,091

26.00%

$ 3,685,027 $ 6,331,118 100% 95%

Arlington Basin Water

Quality Improvement

Project

WMWD $ 1,000,000 $ 900,000

33.21%

$ 809,670 $ 2,709,670 0% 45%

Inland Empire Brine Line

Rehabilitation and

Enhancement

SAWPA $ 1,000,000 $ 698,153

10.07%

$ 5,234,5763 $ 6,932,729 100% 100%

Proposition 84 Round 1 Project Status Update

1 $ 13,218,920 in Other State Funds 2 $ 9,956,000 in Other State Funds 3 $ 5,234,576 in Other State Funds

Page 5: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required

Funding

Match

Add’l Cost

Share

Total Project

Cost

% Grant

Billed

% Project

Complete

Arlington Desalter

Interconnection Project

Corona $ 400,000 $ 350,493

26.00%

$ 597,556 $ 1,348,049 100% 100%

Impaired Groundwater

Recovery

IRWD $ 1,000,000 $ 20,148,848

53.99%

$ 16,173,122 $ 37,321,970 100% 100%

Sludge, Dewatering,

Odor Control & Primary

Sludge Thickening

OCSD $ 1,000,000 $ 36,638,218

26.00%

$ 103,278,005 $ 140,916,223 100% 92%

Mill Creek Wetlands* Ontario $ 1,000,000 $ 1,615,000

8.85%

$ 15,635,000 $ 18,250,0004 100% 100%

Santa Ana Watershed

Vireo Monitoring

SAWA $ 600,000 $ 225,994

26.00%

$ 43,213 $ 869,207 100% 100%

Cactus Basin SBCFCD $ 1,000,000 $ 4,427,155

29.96%

$ 9,350,026 $ 14,777,181 0% 40%

Proposition 84 Round 1 Project Status Update

4 $ 15,420,000 in Other State Funds

* Retention not paid yet

Page 6: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required

Funding

Match

Add’l Cost

Share

Total Project

Cost

% Grant

Billed

% Project

Complete

Perchlorate Wellhead

Treatment System

Pipelines

WVWD $ 1,000,000 $ 368,940

26.00%

$ 50,060 $ 1,419,000 100% 100%

Total $ 12,000,000 $ 69,457,548

26.62%

$ 179,419,635 $ 260,877,183 83.3% 83.7%

Proposition 84 Round 1 Project Status Update

Page 7: Proposition 84 Project Status - sawpa.org

Round 2 Projects

Page 8: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required

Funding

Match

Add’l Cost

Share

Total Project

Cost

% Grant

Billed

% Project

Complete

Perris Desalination

Program – Well 94

EMWD $ 1,000,000 $ 0

0.00%

$ 9,238,280 $ 10,238,280 0% 13%

Quail Valley Subarea 9

Phase I Sewer System

EMWD $ 1,930,000 $ 2,960,000

37.00%

$ 3,110,000 $ 8,000,000 19% 14%

Wineville Regional

Recycled Water Pipeline

and GW Recharge

System Upgrades

IEUA $ 1,000,000 $ 0

0.00%

$ 29,500,0001 $ 30,500,000 100% 74%

San Sevaine GW

Recharge Basin

IEUA $ 750,000 $ 925,001

32.34%

$ 1,184,999 $ 2,860,000 43% 48%

Regional Residential

Landscape Retrofit

IEUA $ 500,000 $ 370,000

37.00%

$ 130,000 $ 1,000,000 66% 95%

Lower Day Basin IEUA $ 750,000 $ 917,599

37.00%

$ 812,401 $ 2,480,000 0% 38%

Proposition 84 Round 2 Project Status Update

1 $29,500,000 in Other State Funds

Page 9: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required

Funding

Match

Add’l Cost

Share

Total Project

Cost

% Grant

Billed

% Project

Complete

Prado Basin Sediment

Mgmt Demonstration

OCWD $ 750,000 $ 2,910,050

37.00%

$ 4,204,950 $ 7,865,000 0% 18%

Enhanced Stormwater

Capture & Recharge

along SAR

SBVMWD $ 1,000,000 $ 11,581,000

37.00%

$ 18,719,000 $ 31,300,000 0% 25%

Customer Handbook to

Using Water Efficiently

WMWD $ 120,000 $ 42,000

25.93%

$ 0 $ 162,000 0% 45%

Corona/Home Gardens

Multi-Jurisdictional Water

Transmission Line

Corona $ 1,300,000 $ 2,327,494

37.00%

$ 2,663,031 $ 6,290,525 1% 38%

Peters Canyon Channel

Water Capture and

Reuse Pipeline

Irvine $ 1,000,000 $ 3,211,086

37.00%

$ 4,467,523 $ 8,678,609 100% 86%

Canyon Lake Hybrid

Treatment Process

LESJWA $ 500,000 $ 327,635

37.00%

$ 57,865 $ 885,500 62% 90%

Proposition 84 Round 2 Project Status Update

Page 10: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required

Funding

Match

Add’l Cost

Share

Total Project

Cost

% Grant

Billed

% Project

Complete

CII Performance Based

WUE Program

MWDOC $ 500,000 $ 898,179

37.00%

$ 1,029,333 $ 2,427,512 100% 33%

Recycled Water Project

Phase I

Riverside $ 1,000,000 $ 8,030,000

37.00%

$ 12,670,000 $ 21,700,000 0% 10%

Plunge Creek Water

Recharge and Habitat

Improvement

SBVWCD $ 500,000 $ 184,731

26.00%

$ 25,769 $ 710,500 21% 30%

Soboba Band of Lusieno

Indians Wastewater Prjct

Soboba $ 150,000 $ 53,000

26.11%

$ 0 $ 203,000 0% 45%

Forest First USFS $ 1,000,000 $ 2,055,039

37.00%

$ 2,499,121 $ 5,554,160 0% 49%

Wilson III Basins Project

and Wilson Basins/

Spreading Grounds

Yucaipa $ 750,000 $ 4,825,807

37.00%

$ 7,466,914 $ 13,042,721 0% 29%

Total $ 14,500,000 $ 40,151,571

26.67%

$ 95,279,236 $ 150,556,117 28% 43%

Proposition 84 Round 2 Project Status Update

Page 11: Proposition 84 Project Status - sawpa.org

Drought Round Projects

Page 12: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required Funding Match

Add’l Cost Share

Total Project Cost

% Grant Billed

% Project Complete

Conservation Based

Reporting Tools and Rate

Structure

SAWPA $ 6,662,610 $ 0

0.00%

$ 0 $ 6,662,610 26% 34%

High Visibility Turf

Removal & Retrofit

SARW

EMWD $ 906,800 $ 1,212,770 $ 600,830 $ 2,720,400 0% 57%

IEUA $ 807,564 $ 1,080,050 $ 535,077 $ 2,422,691 100% 100%

OCWD $ 880,894 $ 1,178,123 $ 583,666 $ 2,642,683 0.27% 57%

SBVMWD $ 828,499 $ 1,108,049 $ 548,949 $ 2,485,497 0% 13%

WMWD $ 851,243 $ 1,138,467 $ 564,019 $ 2,553,729 49% 78%

High Visibility Turf

Removal & Retrofit

USMW

EMWD $ 420,000 $ 561,715 $ 278,285 $ 1,260,000 0% 57%

WMWD $ 52,500 $ 70,214 $ 34,786 $ 157,500 0% 57%

RCWD $ 525,000 $ 702,145 $ 447,855 $ 1,675,000 47% 77%

Total $ 11,935,110 $ 7,051,533

31.23%

$ 3,593,467 $ 22,580,110 25% 58%

Proposition 84 Drought Round Project Status Update

Page 13: Proposition 84 Project Status - sawpa.org

2015 Round Projects

Page 14: Proposition 84 Project Status - sawpa.org

Project Name Agency Grant

Amount

Required Funding Match

Add’l Cost Share

Total Project Cost

% Grant Billed

% Project Complete

Newhope-Placentia

Trunk Sewer

Replacement Project

OCSD $ 1,000,000 $ 30,000,000

28.60%

$ 73,890,000 $ 104,890,000 0% 0%

Integrated Watershed

Protection Program

RCFC&

WCD

$ 5,054,302 $ 9,060,000

29.71%

$ 16,379,698 $ 30,494,000 0% 0%

SARCCUP Member

Agencies

$ 55,000,000 $ 30,500,000

30.12%

$ 15,772,899 $ 101,272,899 0% 0%

Total $ 61,054,302 $ 69,560,000

29.00%

$ 106,042,597 $ 236,656,899 0% 0%

Proposition 84 2015 Round Project Status Update

Page 15: Proposition 84 Project Status - sawpa.org

A Closer Look

Round 1

• Perris II Desalination Facility (EMWD)

• Alamitos Barrier Improvement Project (OCWD)

• Chino Creek Wellfield Development Project (WMWD)

• Arlington Basin Water Quality Improvement Project (WMWD)

• Cactus Basin (SBCFCD)

• Sludge Dewatering, Odor Control & Primary Sludge Thickening (OCSD)

Page 16: Proposition 84 Project Status - sawpa.org

Perris II Desalination Facility (EMWD)

Page 17: Proposition 84 Project Status - sawpa.org

• Description: Supply brackish feed water to the Perris II Desalter

• Overall Percent Complete : 98%

• Final Completion Report: August 22, 2016

• Benefits: Use of local degraded brackish groundwater supplies as a viable, long-term step in generating new local potable water resources.

Perris II Desalination Facility (EMWD)

Page 18: Proposition 84 Project Status - sawpa.org

Alamitos Barrier Improvement Project (OCWD)

Page 19: Proposition 84 Project Status - sawpa.org

Alamitos Barrier Improvement Project (OCWD)

Page 20: Proposition 84 Project Status - sawpa.org

Alamitos Barrier Improvement Project (OCWD)

• Description: Install injection wells, monitoring wells and piezometers

• Overall Percent Complete: 30%

• Estimated Completion: December 2017

• Benefits: Control seawater intrusion, augment injection capacity and protect nearby down gradient production wells for the City of Seal Beach & Golden State Water Company. Protect water quality of groundwater in Orange County Groundwater Basin.

Page 21: Proposition 84 Project Status - sawpa.org

Chino Creek Wellfield Development Project (WMWD)

Page 22: Proposition 84 Project Status - sawpa.org

Chino Creek Wellfield Development Project (WMWD)

Page 23: Proposition 84 Project Status - sawpa.org

Chino Creek Wellfield Development Project (WMWD)

• Description: Development of 3 production wells as part of the Chino Desalter Phase 3 Expansion; adding approximately 2,900 AFY

• Overall Percent Complete : 95%

• Estimated Completion: December 2016

• Benefits: Increase local supplies and facilitate responsible groundwater management, protect downstream users, and promote regional cooperation.

Page 24: Proposition 84 Project Status - sawpa.org

Arlington Basin Water Quality Improvement Project (WMWD)

Page 25: Proposition 84 Project Status - sawpa.org

Arlington Basin Water Quality Improvement Project (WMWD)

Page 26: Proposition 84 Project Status - sawpa.org

Arlington Basin Water Quality Improvement Project (WMWD)

• Description: Construct one new artificial recharge basin within the Arlington groundwater Basin

• Overall Percent Complete : 45%

• Estimated Completion: October 2017

• Benefits: Improve water supply reliability for Western Riverside County to meet future demands, and reduce dependence on imported water supply.

Page 27: Proposition 84 Project Status - sawpa.org

Cactus Basin (SBCFCD)

Page 28: Proposition 84 Project Status - sawpa.org

Mixing native & imported fines for dam

Dam soil spreading and compaction

Cactus Basin (SBCFCD)

Page 29: Proposition 84 Project Status - sawpa.org

Cactus Basin (SBCFCD)

Page 30: Proposition 84 Project Status - sawpa.org

Cactus Basin

• Description: Construct Cactus Basin No. 3

• Overall Percent Complete: 64%

• Estimated Completion: Feb 2017 (1 year)

• Benefits: Reduce local flooding, downstream flooding potential, and size and cost of downstream drainage facilities. Increase groundwater recharge and subsequently increase water supply.

Page 31: Proposition 84 Project Status - sawpa.org

Cactus Basin

• 280,000 CY – foundation (dam embankment)

• 84,820 CY – fine materials brought in from offsite (to make gradation more compact)

• 229,000 CY – dam embankment constructed

• 349,000 CY – excavated from basin

• 40,000 CY – blended materials placed into the basin embankment

• 261,400 CY of surplus dirt was disposed

Page 32: Proposition 84 Project Status - sawpa.org

Sludge Dewatering, Odor Control & Primary Sludge Thickening (OCSD)

Page 33: Proposition 84 Project Status - sawpa.org

Sludge Dewatering, Odor Control & Primary Sludge Thickening (OCSD)

Page 34: Proposition 84 Project Status - sawpa.org

Sludge Dewatering, Odor Control & Primary Sludge Thickening (OCSD)

Page 35: Proposition 84 Project Status - sawpa.org

Sludge Dewatering, Odor Control & Primary Sludge Thickening (OCSD)

Page 36: Proposition 84 Project Status - sawpa.org

Sludge Dewatering, Odor Control & Primary Sludge Thickening (OCSD)

• Description: Improvements to OCSD’s Plant No. 1

• Overall Percent Complete : 92%

• Estimated Completion: October 2017

• Benefits: Local, reliable supply of purified recycled water that is used to prevent seawater intrusion at the Talbert Barrier, and recharge OC Groundwater Basin.

Page 37: Proposition 84 Project Status - sawpa.org