Upload
floriane-martin
View
20
Download
1
Tags:
Embed Size (px)
DESCRIPTION
Proton Improvement Plan Keith Gollwitzer May 6th, 2013 All Experimenters’ Meeting. Thanks to F. Garcia for Linac slides. Overview of Status. RFQ Largely in operations mode – But… Still adjusting n ew s ources – spark rates and emittances have improved - PowerPoint PPT Presentation
Citation preview
1
Proton Improvement Plan
Keith Gollwitzer
May 6th, 2013All Experimenters’ Meeting
Thanks to F. Garcia for Linac slides
Gollwitzer AEM 2
Overview of Status • RFQ Largely in operations mode – But…
– Still adjusting new sources – spark rates and emittances have improved
• Second Source – with new hardware design has been tested• Linac Commissioning continues while improving
– Efficiency Improving: Up to 90% (current still lower than desired)
• Linac Beam Position Monitor system upgrade complete• Progress on developing Linac modulator for replacement/upgrade; both
in-house (AD/EE support) and by SLAC• Booster commissioning continues with many studies• Booster RF Solid State Upgrade completed• RF cavity refurbishment goes on• Progress in utilities replacement/upgrade
Linac Utilities
• Power Distribution– L1 transformer
• Continue with the prep work for the installation of L1 transformer. – Approval from FESS to
proceed - DP-18 complete
– Electrical conduit relocated to clear the area
– Quote on hand for hatch manufactured and installation
Linac L1 transformer – storage
Hatch location
• BPM Electronics Upgrade complete
Linac Instrumentation
Diagnostics Room Update existing RF Logamp electronics with
Digital electronics FPGA, ADC, Digital Signal Processing Long term stability Flexibility to modify system as needed
Linac - 200 MHz Rf Power System -1• Modulator Upgrade– 35kV, Marx-topology modulator to drive triode (or MBK)
– SLAC – Two cell test stand
Two vernier cells: ripple +/- 37VSpec:+/- 25V (F1-Marx design uses 10 main cells)
• Modulator Upgrade (cont.)– 35kV, Marx-topology modulator
to drive triode (or MBK)– AD/EE – One cell test stand– Test: Short circuit
» The Soft Shut Down circuit is used to softly shut down the IGBT if a fault occur
Contribution by: H. Pfeffer
Short circuit current1000A/
Load voltage & shortcollector 200V/
Load current 100A/
Linac - 200 MHz Rf Power System - 2
Gollwitzer AEM 7
Booster Aperture Scan
Booster Notch Beam Absorber
Last power supply/kicker system for beam notching system has been commissioned
Many Booster studiesAperture scansLattice Radiation studies
Gollwitzer AEM 8
Solid State RF Station in Gallery
New Power Amplifier
Booster Solid State Upgrade is complete!
9
Booster RF Work• Solid State Upgrade is complete
– Major benefits to reliability and the cost of operation• Refurbishment continues
– Un-certified a cavity due to RF leak
Booster Cavity WorkRefurbished (15Hz)
SS Prototype SS Upgraded
Cavity Removed
Gollwitzer AEM
10
We are now concerned about connection with outer flange
Gollwitzer AEM
Pulled one cavity and have started testing
RF leak from outer flange?
Gollwitzer AEM 11
Cavity RefurbishmentThere is always something unexpected: goop epoxy fix from some prior leak
Gollwitzer AEM 13
Near Term Plans• RFQ injector – Will be adding a new trim package (improve transmission)
• Installing Booster Utility Transformer• Installing Linac Roof access • Booster aperture studies• Booster Cogging studies• Booster Lattice Studies• Booster Cavity Refurbishment
• Operations:– Higher Intensity Tune-up– Address shielding assessment issues to allow for higher flux