Upload
tranngoc
View
215
Download
1
Embed Size (px)
Citation preview
1
Particle Swarm Optimization for
Voltage Stability Analysis
Dinesh Rangana Gurusinghe University of Manitoba, Canada
Weerakorn Ongsakul Asian Institute of Technolgy, Thailand
Electrical Power and Energy Conference 2012
Resilient Green Energy Systems for a Sustainable Society
October 12, 2012
2
Outline
• Introduction
• Objectives
• Concept of Particle Swarm Optimization (PSO)
• Methodology
• Results and Discussion
• Conclusion and Recommendations
• Areas for Improvements
3
Introduction
• Voltage collapse point (VCP) : following a disturbance there is a
time where power system voltages become uncontrollable and it
is known as VCP
• An effective approach to determine VCP greatly assists planning
and operation of power system
• Already establish methods, such as Multiple Power Flow (MPF)
and Continuation Power Flow (CPF) methods provides the
accurate VCP but relatively more time consuming as they
engaged with several power flow computations
• But effective optimization approaches can furnish the Optimal
Operating Condition (OOC) with adequate accuracy but less
computation effort
4
Objectives
The primary objective of the research is to introduce accurate,
but less time consuming PSO based novel approach to find
VCP in power system.
1. To develop an effective PSO based approach for determining
the VCP of power systems
2. To apply the proposed approach for analysing diverse
applications of VSA
3. To compare the effectiveness of the proposed approach
including different versions of PSO to CPF method and
eigenvalue analysis
5
Concept of Particle Swarm Optimization (PSO)
II IV
I
III
6
PSO Algorithm
Initialize Particles
Evaluate Particles’ Fitness
Update Particles
iter=iter+1
iter<iter_max
Stop
Yes
7
Methodology – Outlined Flow Chart
Determine the VCP point using
different versions of PSO, namely,
Basic PSO, TVIW and TVAC
8
Methodology – Problem Formulation
• Objective Function
• At the VCP point, active and reactive power at all load buses are
maximized
• In the study, active power at a random load bus is selected as the
objective function
9
Methodology – Problem Formulation (Cont…)
• Constraints
• The constraint related to the power factor at PQ buses
• The constraint related to the definite direction of power increase at
PQ buses (It is assumed that bus 1 is selected as the objective bus)
• The constraint related to the constant active power generation at PV
buses
10
Methodology – Problem Formulation (Cont…)
• Constraints – Cont…
• The constraint related to reactive power limit of the PV buses and
the slack bus
• The constraint related to active power limit of the PV buses and the
slack bus
11
Methodology – PSO
• Number of particles is set as d and each particle should have attributes
of voltage magnitudes of PQ buses and phase angles of both PQ and
PV buses
• Phase angles are randomly initialized in such a way that initialized
values should be lied within ±100 and voltage magnitudes for PQ buses
are initialized according to the modified constraint equation,
12
Methodology – PSO (Cont…)
• Active power adjustments (PV buses PQ buses except selected load
bus) to satisfy equality constraints,
• For PV buses if
• For PV buses if
• In PQ buses, phase angle should be adjusted in opposite way
• The phase angle adjustment process should be continued until the
residuals of active power differences within the specified accuracy limit.
i.e.
13
Methodology – PSO (Cont…)
• Particles can be represented as,
or
• The velocity vectors corresponding to the particles are randomly
initiated as represented as
• Generator reactive power limits can be handled with a Penalty function
14
Methodology – PSO Method (Cont…)
• Adjust voltage magnitudes of generation buses according to reactive
power injection,
• Adjust voltage magnitudes of voltage compensation buses according to
reactive power injection,
15
Methodology – PSO Method (Cont…)
• The best previous position of a particle is recorded and represented as,
• The best among all particles in the group so far, it is represented as,
• The particle positions are updated according to the velocity equation as,
• The new position of the particle can be obtained as,
16
Methodology – PSO Method (Cont…)
• In Basic PSO, all four parameters of the velocity equation are fixed
• In TVIW PSO,
• In TVAC PSO,
17
Test Results
Values for Tuning Parameters of Proposed PSO Versions
18
Test Results
There are four test cases, specifically,
• Determination the SNB point
• considering reactive power limits of generators
• optimal operating condition (OOC) considering both active and reactive power limits of generators
• Diverse applications of voltage stability analysis under optimal operating condition
• OOC under (N-1) contingency criterion
• OOC with a voltage compensation devices
19
NEW ANURADHAPURA
MAHO
HORANA
AMBALANGODA
PANNALA
ATURUGIRIYA
SAPUGASKANDA
PANNIPITIYA
ORUWALA
BIYAGAMA
VEYANGODA
MATUGAMA
KELANITISSA
COL-F
COL-E
COL-C
KELANITISSA
RATMALANA
KOLONNAWA
PANADURA
DEHIWALA
SRI J'PURA
KERAWALAPITIYA
KATUNAYAKE
KOTUGODA
BOLAWATTA
ANIYAKANDA
LAKDANAWI
ATURUGIRIYA
ORUWALA
SRI J'PURA
DEHIWALA
RATMALANA
COL-A
PANNIPITIYA
KHD
COL-I
KOLONNAWA
MADAMPE
NOROCHCHOLAI
PUTTALAM
RATNAPURA
MATARA
KUKULE
DENIYAYA
HAMBANTOTA
SAMANALAWEWA
UPPER KOTMALE
WIMALASURENDRA
KOTMALE
SEETHAWAKA
POLPITIYA
KOSGAMA
LAXAPANA
CANYON
LAXAPANA
NEW
KIRIBATHKUMBURA
THULHIRIYA
N'ELIYA
BALANGODA
BADULLA
RANDENIGALA
VICTORIA
PALLEKELE
RANTEMBE
KURUNEGALA
HABARANA
BOWATENNA
UKUWELA
NAULA
POLONNARUWA
MONARAGALA
INGINIYAGALA
AMPARA
PADDIRIPPU
VALACHCHANAI
CHUNNAKAM
KERAWALAPITIYA
BIYAGAMAKELANIYAS'KANDA
ANIYAKANDA
KOTUGODA
220/132 kV Sub Station
Thermal Power Station
Hydro Power Station
132kV GS
KAPPALTURAI
ANURADHAPURA
VAVUNIA
KILINOCHCHI
220kV Line
132kV : Line
132kV : Underground Cable
BEDDEGAMA
GALLE
MAHIYANGANA
NEW HABARANA
TRINCOMALEE PS
TRINCOMALEE
NEW CHILAW
BELIATTA
WELIGAMA
MORATUWA
KEGALLE
PILIYANDALA
COL-B
COL-K
KIRINDIWELA
KADAWATHA
ARANGALA
Test Results : Power System of Sri Lanka (182 buses)
20
• 1 : Considering Reactive Power Limit of Generators
Test Results : Power System of SL (Cont…)
21
• 2 : Optimal Operating Condition with Generator Limits
Test Results : Power System of SL (Cont…)
22
• 3 : OOC under (N-1) Contingency Criterion
Test Results : Power System of SL (Cont…)
23
• 3 : OOC under (N-1) Contingency Criterion (Cont…)
Test Results : Power System of SL (Cont…)
0.54
0.56
0.58
0.60
0.62
0.64
0.66
0.68
Base 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52
Contingency
Loa
ding
Fac
tor,
λc
24
• 4 : OOC with an installation of 100MVar SVC at bus 45 (JPURA_3)
Test Results : Power System of SL (Cont…)
25
• Summary results of Test System
Test Results : Power System of SL (Cont…)
26
• The study introduces a new optimization approach, which directly calculates the VCP without several power flow computations by PSO
• The effectiveness of the proposed approach has been tested on the power system of Sri Lanka. Test results are evaluated with the CPF method and the optimality is verified by eigenvalue analysis
• Results confirms that the proposed PSO based approach is very valuable as it produces accurate, technically feasible, optimal solution for the 182-bus power system of Sri Lanka
• It is recommended to install sufficient reactive power resources to most critical buses identified in (N-1) contingency criterion to enhance the VCP of the power system of Sri Lanka
Conclusion and Recommendations
27
• It is important to study the behaviour of OLTC and the optimal
tap setting, which furnishes the OOC
• It is better to check the performance of the proposed PSO based
approach with different types of voltage compensators other than
capacitors and SVC
• The study is limited to Basic PSO, TVIW PSO, and TVAC PSO
and they do not show a significant difference. However, it is vital
to consider other types of PSO versions
Areas for Improvements
28
Thank You and
Questions?
Acknowledgement
The Royal Thai Government
(HM Queen Scholarship Program)