PSS ARRA PROJECTS ROTA. Repairs and Renovations. Sinapalo Elementary School. Painting ( Misamis ) – Contract 70257-OC 100% Complete – Project Closed A/C Upgrade (Pacific Coop) – Contract 99079-OC 100% Complete – Project Closed General Repairs ( Misamis ) – Contract 99402-OC - PowerPoint PPT Presentation

Citation preview

Page 1: PSS  ARRA PROJECTS ROTA

PSS ARRA PROJECTSROTARepairs and Renovations

Page 2: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary School

Painting (Misamis) – Contract 70257-OC 100% Complete – Project Closed A/C Upgrade (Pacific Coop) – Contract 99079-OC 100% Complete – Project Closed General Repairs (Misamis) – Contract 99402-OC 100% Complete – Project Closed

Page 3: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolPainting

Page 4: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolPainting

Page 5: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolPainting

Page 6: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolA/C Units

Page 7: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolNew Covered Walkway

Page 8: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolNew Covered Walkway

Page 9: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolNew Covered Walkway

Page 10: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolADA Parking

Page 11: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolNew SPED Restroom

Page 12: PSS  ARRA PROJECTS ROTA

Sinapalo Elementary SchoolNew SPED Restroom

Page 13: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School

Roof Coating (Radiocom) – Contract 70398-OC 100% Complete – Project Closed A/C Upgrade (Pacific Coop) – Contract 99079-OC 100% Complete – Project Closed General Repairs (Misamis) – Contract 99402-OC 100% Complete – Project Closed Doors and Windows (Pacific Coop) – Contract 70205-OC 100% Complete – Project Closed

Page 14: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School Roof Coating

Page 15: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School A/C Upgrade

Page 16: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School Doors and Windows

Page 17: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School Renovated Restrooms

Page 18: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School Renovated Restrooms

Page 19: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School Fitness Room

Page 20: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School Fitness Room

Page 21: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School New Sidewalk

Page 22: PSS  ARRA PROJECTS ROTA

Rita Hocog Inos Junior Senior High School ADA Parking

Page 23: PSS  ARRA PROJECTS ROTA

Rota High School

Roof Coating (Radiocom) – Contract 70398-OC 100% Complete – Project Closed Painting (Misamis) – Contract 70257-OC 100% Complete – Project Closed A/C Upgrade (Pacific Coop) – Contract 99079-OC 100% Complete – Project Closed General Repairs (Misamis) – Contract 99402-OC 100% Complete – Project Closed Doors and Windows (Pacific Coop) – Contract 70205-OC 100% Complete – Project Closed Electrical Upgrade (DK Brothers) – Contract 70336-OC 100% Complete – Project Closed

Page 24: PSS  ARRA PROJECTS ROTA

Rota High School Roof Coating

Page 25: PSS  ARRA PROJECTS ROTA

Rota High SchoolPainting

Page 26: PSS  ARRA PROJECTS ROTA

Rota High SchoolPainting

Page 27: PSS  ARRA PROJECTS ROTA

Rota High School General Repair

Page 28: PSS  ARRA PROJECTS ROTA

Rota High SchoolRestroom Renovations

Page 29: PSS  ARRA PROJECTS ROTA

Rota High SchoolRestroom Renovations

Page 30: PSS  ARRA PROJECTS ROTA

Rota High SchoolDoors and Windows

Page 31: PSS  ARRA PROJECTS ROTA