PT INDONESIA POWER GAS (LNG) UTILIZATION FOR POWER GENERATION
4th Gas Forum Special Focus on Technology
JUDI WINARKO
Head of Primary Energy Division
DIVISI ENERGI PRIMER PT INDONESIA POWER
Overview 35.000 MW Electricity Projects
Indonesia Electricity System
PLN - 35.000 MW Electricity Program
New Additional Gas Power Plant (35.000 MW)
LOCATION GAS POWER PLANT
LNG Demand
KEY WORD : - LONG TERM SECURITY LNG SUPPLAY - LNG LOGISTIK SYSTEM & MID STREAM FACILITIES
Gas infrastructure for electricity
Indonesia Power
Contribution for 35.000 MW
Electricity Projects
PT Indonesia Power
Gas Supplier for IP Gas Power Plant (existing)
No Gas Power Plant Pipeline/LNG Gas Source (PSC) Contract Capacity
1. Priok CCGT Block 1-3 Pipeline Gas PHE ONWJ 100 bbtud
Pipeline Gas PGN 27-30 bbtud
LNG Bontang, Tangguh
150 bbtud
2. Tambak Lorok CCGT Pipeline Gas SPP/Pertamina EP
50 bbtud
Pipeline Gas KJG/PCML 116 bbtud
3. Grati CCGT Pipeline Gas Santos 75 bbtud
4. Dual Fuel Gas Engine Pesanggaran Bali
LNG PEL 40 bbtud
12
FSRU West Java operated by PT Nusarantara Regas, deliver gas supply for Muara Karang dan Priok CCPPs (4000 MW) around 27 cargo per year
CNG Plant, Compressed Natural Gas (250 bar) and deliver gas at pickload time : CNG Plant Grati, cap. 15 bbtud operate by PT Energi Transportir Indonesia CNG Plant Tambak Lorok, cap. 17 bbtud operate by PT Pertadaya Gas
IP Project in 35.000 MW Gas Power Plant
No Project Capacity (MW)
COD Remark
1. Perak CCGT (Peaker) DMN : 540 2019 21 BBTUD,Gas from Kangean Efficiency : 49.8 % - 60 %
2. Tambak Lorok Block III
700 2019 Gas from Kepodang (existing 116 BBTUD)
3. Grati Add on 150 2019 HRSG installment at Block II, Increase PP Efficiency from 32% - 48%
5. Clustering Barge Mounted Power Plant
350 (total) 2018 Cluster 1 : Sulbagsel, Lombok & Kalseltengtim • 1 Barge 120 MW • 3 Barge - @ 60 MW Cluster 2 : NTT, Maluku, Papua • 2 Barge - @ 25 MW
6. Tg Priok Block IV 740 2019 (est) O&M opportunity (PLN’s project)
7. Grati Block III 450 2019 (est) O&M opportunity (PLN’s project)
Cluster 1 : Sulbagsel, Lombok & Kalseltengtim • 1 Barge 120 MW • 3 Barge - @ 60 MW
Cluster 2 : NTT, Maluku, Papua • 2 Barge - @ 25 MW
GOALS : (i) High Utilisation & Flexible for multi system (ii) For Demand & Reserved Margin
Sumatera Kalimantan
Sulawesi
Maluku
Papua
Nusa Tenggara Java-Bali
1
2
CLUSTERING BARGE MOUNTED POWER PLANT (Total ± 350MW)
FSRU West Java operated by PT Nusarantara Regas, deliver gas supply for Muara Karang dan Priok CCPPs (4000 MW) around 27 cargo per year
CNG Plant, Compressed Natural Gas (250 bar) and deliver gas for pikeload time : - Grati, cap. 15 bbtud operate by PT
Energi Transportir Indonesia. - Tambak Lorok, cap. 17 bbtud operate
by PT Pertadaya Gas
Floating Storage, Regas & Terminal LNG Benoa Bali, operated by PT Pelindo Energi Logistik.
KONSEP FACILITAS MIDSTREAM GAS BALI
LNG Supplay Chain
1. LNG Plant Terminal • Size of Jetty • Facility Loading (Loading arm, Flexible hose) • LNG/Gas Quality
2. LNG Carrier • Vessel, Barge/LCT • Tank Type/Cargo Containment System
3. HUB • Size (standard, mini)
4. Receiving Terminal (Floating, Land base) • Size of Jetty • Unloading facility • Storage (Issotank, flat bottom) • Regas system (ambient, forced)
5. Gas Pipeline