Nepal: Enhanced Vocational Education and Training Project HImplementation Support Review
Novemberl2-16, 2018Aide Memoire
1. During November 12-16, 2018, a Bank Team' led by Sangeeta Goyal carried out anImplementation Support Review of the Enhanced Vocational Education and Training Project II(EVENT 11). This Aide Memoire (AM) summarizes the findings on the status of the projectimplementation, recommendations and agreements reached with the relevant agencies to take correctivemeasures and/or to expedite implementation. The AM was discussed at a wrap-up meeting onNovember 16, 2018 chaired by Mr. Baikuntha Prasad Aryal, Joint Secretary, Ministry of Education,Science and Technology (MOEST). The meeting was attended by Mr. Churamani Aryal, SectionOfficer, Ministry of Finance. As agreed with MOEST, the AM will be publicly disclosed as requiredby the Bank's Access to Information Policy.
OVERALL STATUS AND KEY PROJECT DATA
2. The Project is on track to achieve its Project Development Objective (PDO) of "improving
equitable access to market relevant training programs and strengthening the technical and vocationaleducation and training (TVET) sector service delivery in Nepal". The PDO is rated as satisfactory based
on the achievement against the first year key performance indicators (KPIs) and Disbursement Linked
Indictor (DLIs) targets. Most of the KPIs and DLIs for Year I have either been completed or
substantially achieved. The Project Implementation Committee (PIC) constituted on May 6, 2018, and
the Technical Advisory Committee (TAC) constituted on June 11, 2018, have been working closely
with the Project Secretariat (PS) in guiding implementation. The Project Implementation Manual (PIM)
for EVENT II was endorsed on June 29, 2018, thus completing this legal covenant. Overall
implementation progress is being rated Moderately Satisfactory due to delays in some prior activities
for the quality improvement grants and training of instructors and heads of institutions.
Table 1: Project DataProject Data Project Performance Ratings
Summary Ratings Previous Current
Board Approval September 29, 2017 Achievement of PDO S S
Signing January 21, 2018 Implementation Progress MS MS
Effectiveness Date February 23, 2018 Project Management S S
Closing date July 15, 2022 Procurement MS MS
IDA credit amount US$ 60 million Financial Management MS MS
Amount disbursed as of US$ 0.36 million Safeguards MS MS
Nov 30, 2018 (about 0.6% ofallocated amount)
M&E S SCounterpart Funding NA NA
Ratings: HS=Highly Satisfactory; S=Satisfactory; MS=Moderately Satisfactory; MU=ModeratelyUnsatisfactory; U=Unsatisfactory; IU=Highly Unsatisfactory; NA=Not Applicable; NR= Not Rated
IMPLEMENTATION STATUS UPDATE
3. DLI achievements for Year I and status of agreed actions from the previous consultations in
May 2018: The Bank has received Disbursement Linked Indicator (DLI) achievement reports including
]Sangeeta Goyal (TTL, Senior Economist), Maya Sherpa (co-TTL, Economist), Mohan Prasad Aryal (Senior Operations
Officer), Uttam Sharma (Economist), Jayakrishna Upadhya (Economist), Baburam Niraula (Economist), Yogesh B. Malla
(Financial Management Specialist), Annu Rajbhandari (Environmental Specialist), Jaya Sharma (Social Development
Specialist), Chandra Kishor Mishra (Procurement Specialist), Dron Pun (Consultant), Deepa Shakya (Consultant) and
Prakash Thapa (Consultant). Sunita Gurung (Program Assistant) provided all logistic support.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
EVENT II Project, Aide Memoire -2- December 4, 2018
evidence as per the agreed verification protocols for Disbursement linked results (DLRs) 2.1, 2,2, 3.1,
4.1, and 6.1, with reimbursement claims totaling NRS 267,314,445 (approximately US$ 2.26 million
based on the exchange rate of NRS 115 to a US$, as on November 15, 2018). Details of the
achievements are described below. Annex 3 of this AM provides a status update on agreed actions from
the last consultations. Most actions have been completed, and the remaining are nearing completion.
Component 1: Support to Results-based Financing, Results Area 1: Strengthening Service Delivery in
Technical Education
4. The draft of the quality assurance (QA) manual for technical school leaving certification
(TSLC) and Diploma offering institutions has been completed and is under review. It is expected to be
finalized and placed before the PIC for clearance by February 28, 2019 (DLR 1.1). The PS has received
interest from 152 public and private TSLC and Diploma offering institutions in response to the
Expression of Interest (EOI) for performance-based quality improvement-grants (QIG) (published in
August-September2018). It is expected that the PS will complete the selection of 100 eligible
institutions for receiving performance grants in two phases by May-June 2019. These 100 institutions
will sign Memoranda of Understandings (MOUs) with the PS for receiving grants (DLR 1.2). With
support from the PS, the selected institutions will prepare their institutional development plans for
achieving higher quality assurance standards as described in the QA manual.
5. Twenty heads/personnel in management positions of TSLC and Diploma offering institutions
have completed training in leadership and management (DLR 2.1) through Training Institute for
Technical Instruction (TITI). Likewise, 76 TSLC and Diploma instructors have also completed
occupational training (DLR 2.2). Focus group discussions were held with some beneficiaries of these
two training for feedback purposes.
6. The second set of MOUs between the PS and TITI and National Skills Testing Board (NSTB),
respectively, have been signed to cover activities for Year 2 of the project. As per their MOU, TITI will
train 60 heads/personnel in management positions of institutions in management and leadership
training, and 260 TSLC and Diploma instructors in occupational training, and NSTB will train 180
skills test assessors. TITI will conduct training during the off-peak season including the holiday period
so that the maximum number of interested candidates can participate in the training. The PS, TITI and
CTEVT will also strategize on outreach strategies for getting more participations for these training.
With regards to curriculum, the PS will support CTEVT in identifying curricula for
revision/development based on the demand from local, domestic and international employers. Such
needs analysis will be carried out by the CTEVT. The list of curricula to be so revised/developed will
be finalized by March 2019, before the preparation of budgetary requirements for the next fiscal year.
7. Results Area 2: Widening Access to TVET Programs: Four hundred and sixty-five
disadvantaged youths attending TSLC programs received scholarships in two installments (DLR 3.1)
under this activity, as per the first-year target. The remaining 35 scholarship recipients will be verified
for receiving their second installment by December 2018, after the completion of the verification of
attendance and other requirements. The selection of 2,000 disadvantaged youth for receiving
scholarships (target for the Year 2 of the project) is in progress. The PS is developing a mechanism to
strengthen verification process of scholarship applicants through close collaboration with Local
Governments and the Education Development and Coordination Unit (EDCU).
8. Training of 16,087 youth (11,841 for results-based short-term training or RBST and 4,246 for
voucher-based short-term training or VBST) in short-term training has been completed and income
verification activity is currently under progress. Of those who received the short-term training, 87.18%
were female and disadvantaged youth (against the Year 1 target of 50%; DLR 4.1). The PS has
published EOI for training providers to respond to for the short-term training activity to be carried out
for Year 2 of the Project for RBST of 19,000 youth, including 5,000 under women window, and VBST
of 5,000 youth. The PS has also planned to provide level 2 training to 750 youth in selected trades for
which cost estimation has been prepared and is in the process of approval. Regarding simplifying
procurement processes and selection of firms for RBST and VBST, the Bank may accept proposed
EVENT II Project, Aide Memoire -3- December 4, 2018
modalities (such as quality competition; direct bidding without the publication of EOI, etc.), providedtransparency and quality issues are not compromised. In addition, such decisions need to be endorsedby competent authorities.
9. The NSTB has completed the skills test of 6,902 youths (Level I - 1481, Level 2- 4674, Level3 - 740) against a target of 6,000 youths to be tested for prior skills (DLR 6.1). The PS has signed a newMOU with the NSTB for the skills test of 6,000 youth to be tested for prior skills in 2019 (Year 2 target).NSTB will make concerted efforts to enable migrants to access this opportunity.
10. Results Area 3: Pilots in Enabling Youth Transition to Work: Detailed consultations have been
held with other agencies (such as CTEVT's ENSSURE2 Project, funded by the Swiss DevelopmentCooperation (SDC)) active in the area of developing and offering apprenticeship programs. There have
been delays in the development of curricula for these programs. Additionally, the curricula that havebeen adapted for apprenticeships cover 24 months instead of the earlier envisaged 12-18 months. Thismeans that starting next year, only one cohort of apprentices can complete a full apprenticeship. Indiscussion with CTEVT including its Curriculum Development Division and NSTB, it was agreed thatthe PS will explore other options such as professional level and level 2 training with on-the-job trainingmodules (which are already established modalities in Nepal) that can also be considered as part of the
apprenticeships/work-place based training to be supported under the project. The evaluation of this pilotprogram can be expanded in scope to assess multiple models, and therefore provide a richer set of
learning. The PS with support from the Bank team is also putting together a design note for the jobplacement pilot, and it is expected that the first set ofjob placement services will be offered in the next
fiscal year. Draft guidelines for the apprenticeship/work-place based training and job placement
services will be prepared by January 2019 and February 2019, respectively. Focus group discussions
were held during the consultations with a number of job portal and rozgari pasal managers/owners to
understand gaps in the transition of youth from training to employment.
11. Component 2: Project Management, Monitoring and Evaluation: A robust Management
Information System (MIS) was established under the first EVENT Project which continues to be used
under EVENT II. This MIS contains comprehensive and disaggregated information on short-term
training, skills testing and scholarships. To avoid, duplication of training, the PS will explore the option
of using district and citizen number for trainees which will give them a unique identification. The
Implementation Progress Report (IPR) document will be strengthened for clearer reporting on the
ESMF and the Gender Plan. An updated results framework is in Annex 2.
12. Joint monitoring teams comprising members from the PS, the MOEST and the ENSSUREProject (the latter is supported by SDC through a MOU signed between them and GON) have been
systematically conducting the monitoring of short-term training activities according to the monitoringguidelines. Monitoring teams visit all training events at least six times; four times during the training
and two times during employment and income verification. Verification of employment and incometakes place on a representative sample basis. The current MOU with SDC is expiring in March 2019.The EVENT 11 PS will request MOEST for the purpose of extending the MOU with the SDC. The PS
needs to initiate the drafting of terms of reference for and composition of the assessment teams for
quality improvement grants given to selected TSLC and Diploma offering institutions. The MOESThas formed a task force to establish a national TVET MIS which will link with the CTEVT MIS,including the TMIS developed under EVENT I.
13. A nationally representative survey of migrants (current, returnee and repeat migrants) has beencompleted with the objective of identifying their skill and certification needs. Data analysis of the
survey is currently in progress, and findings from the survey will be used to inform the design of training
for and certification of prior skills of migrants. Key preliminary findings were discussed with the PSduring the consultations.
2 Enhanced Skills for Sustainable and Rewarding Employment (ENSSURE)
EVENT II Project, Aide Memoire -4- December 4, 2018
FIDUCIARY COMPLIANCE
14. Procurement Performance: Approved procurement activities should be updated in the first
week of each calendar month by uploading bidding/proposal documents, evaluation reports, contract
documents, and by revising the dates of those activities remains to be initiated and/or with red flags on
STEP. Procurement documents of each activities should be uploaded on STEP irrespective of prior/post
review requirements of the Bank and bids/proposals opening records should be uploaded soon after
completion of such events. For reducing time and effort, procurement activities including selection of
individual consultants can be planned for the required duration rather than repeating procurement
processes for each fiscal year, during the project period. In annual program of project, budget should
be allocated to meet the payment requirements of on-going contracts. The Procurement Plan (PP) should
be prepared as per need to meet result agreements and implement project activities irrespective of
budget allocated in annual program of certain FY. The provisions of the Project Procurement Strategy
for Development (PPSD) should be followed with special attention to procurement caveats provided in
the document. The current PP of the project should be updated by December 7, 2018. Procurement
performance is maintained at Moderately Satisfactory.
15. Financial Management (FM) Performance: The approved budget for FY2018-19 is NPR
1,407.3 mill ion (IDA NPR 1,399.3 million and GON NPR 8.0 million). The expenditure up to the period
ending November 15, 2018 is about NPR 167.66 million (11.91% of the approved budget). The project
has been maintaining books of accounts as required by GON rules and regulations. The Bank team
reviewed payment vouchers on a sample basis, and they were found to be in compliance with financial
regulations. The Project has also maintained required ledgers such as main credit/grant register,
subsidiary credit/grant register, designated accounts. The request for change in authorized signatory
(Project Director) has been made. The internal audit of for FY2017-18 has been completed. There are
no outstanding trimester IPRs/FMRs or audit reports. The Team reminded the Project that the audit
report for FY2017/18 is due on January 15, 2019. Based on the progress made, the FM performance
rating is maintained at Moderately Satisfactory.
16. Disbursements Status: As of November 30, 2018, the Project has disbursed USD 357,171.83
million (SDR 253,994.28) under Category 2 (for actual expenditures incurred up to the second trimester
and advance for the remaining trimester). The Project is expected to disburse US$ 2.26 million in the
next quarter under Category I against achievement of the first year DLIs and US$0.12 million under
Category 2 for actual expenditures incurred up to the third trimester of Year 1. The Project's expected
disbursement for FY 18/19 is US$ 8.3 million.
SAFEGUARD MANAGEMENT
17. Environmental and Social Safeguards: The Bank team noted that environmental and social
safeguard agreed actions of the last review have been completed except for the hiring of an
environmental to support the Project in screening of the proposals, other safeguards activities and
gender related works. The Bank team emphasized the need to expedite the process of recruiting the
specialists whose inputs are required for the screening process to guide and support the beneficiary
institutes in filling and reviewing the checklist during the submission of the proposal. The PS will hire
an environmental specialist by December 31, 2018. The Project shared a sample screening report which
needs to be improved to include specific mitigation measures for the identified safeguard issues.
18. Gender disaggregated data are being collected and reported in the IPR. The Team suggested
that the Project also report against the detailed implementation status of Vulnerable Community
Development Framework, and Gender Development Framework in the IPR. It was noted that the project
Grievance Redress Mechanism is functioning well, and the grievances are recorded and documented on
a monthly basis. It is suggested that the summary of the type and number of grievances received and
how it is being managed is included in the IPR. The environmental and social safeguards performance
is maintained at Moderately Satisfactory.
NEXT REVIEW: The next review of the Project has been tentatively planned for May-June 2019.
EVENT II Project, Aide Memoire -5- December 4, 2018
Table 2: Summary of Agreed Actions
S.N. Activity Responsibility Agreed timeline
Project Activities _6_ecember 3_,_20_8
1. Complete payment of second installment of PS December 31, 2018
scholarship for the remaining 35 students fromYear 1
2. Endorsement of the QA manual by the PIC PS February 28, 2019
3. Selection of 100 institutions for QIG PS May-June 2019
4. Finalization of the list of curricula to be PS, CTEVT March 15, 2019
revised/developed5. Draft guidelines manual for Apprenticeship/Work- PS February 28, 2019
place based training prepared
6. Draft guidelines manual for job placement services PS February 28, 2019preparedEnvironmental and Social Safeuards
7. Hire Safeguards expert to support the PS safeguard PS December 31, 2018
focal person
8. Share sample copy of environmental and social PS January 31, 2019
screening document with the Bank team forfeedback
9. Share a template for reporting on Gender Action PS/WB December 15, 2018
and VCDP to include in the IPR
10. Give continuum to the orientation program/training PS/safeguard expert Continuous
on WB safeguard requirements to all PS staff, jointmonitoring team and beneficiary institutionFinancial Management and Procurement
11. Submit disbursement request through client PS December 30, 2018
connection against achievement of Year 1 DLIs
12. Submit first trimester FMR and IPR ofFY 19 PS December 31, 2018
13. Submit the project audit report of FY 18 PS January 15, 2019
EVENT II Project, Aide Memoire -6- December 4, 2018
Annex IList of Persons Met
Ministry of Education, Science and Technology
1. Mr. Baikuntha Prasad Aryal, Joint Secretary
2. Dr. Dhurba Raj Regmi, Under Secretary
3. Mr. Jaya Acharya, Under Secretary
Ministry of Finance
4, Mr. Churamani Aryal, Section Officer
Enhanced Vocational Education and Training Project II (EVENT II) Project Secretariat
5. Mr. Keshab Prasad Dahal, Project Director
6. Mr. SudarshanMarahatta, Deputy Project Director
7. Mr. Sujan Raj Khanal, Under Secretary
8. Mr. Ram Prasad Adhikari, Under Secretary
9. Mr. Baburam Karakheti, Under Secretary
10. Mr. Chiranjibi Poudel, Under Secretary
11, Mr. Ghanashyam Khanal, Finance Officer
12. Mr. Shobhakar Neupane, Procurement Officer
13. Ms. Sashi Pokharel, Monitoring Officer
14. Mr. Asta Lama, Monitoring Officer
15. Mr. Ganga Sunwar, Monitoring Officer
16. Mr. Netra Narayan Poudel, Monitoring Officer
17. Mr. Krishna Joshi, Technical Assistant
18. Mr. Bishwa Raj Basaula, Procurement Consultant
19. Mr. IndraThapa, Finance Consultant
Council for Technical Education and Vocational Training (CTEVT)
20. Mr. Pushpa Raman Wagle, Member-Secretary
21. Mr. Deepak Poudel, Director, Curriculum Development Division
National Skills Testin2 Board (NSTB)
22. Mr. Binod Badal, Director
23. Mr. Damodar Devkota, Deputy Director
Technical Institute for Technical Instruction (TITI)
24. Ms. Akim Shrestha, Executive Director
25. Mr. Durga Prasad Upadhaya, Director
26. Mr. Kalpa Kumar Basnet, Chief of Administration
27. Mr. Krishna BahadurKhadka, Finance Officer
28. Ms. Mina Kharel
EVENT II Project, Aide Memoire -7- December 4, 2018
Leadership and Management Training Beneficiaries
29. Ms. Lasata Malla, Principal, Green Tara College of Health Science, Bhaisepati, Lalitpur30. Ms. Sumita Shrestha, Principal, Shree Phulchoki Nursing College, Banepa31. Ms. Surnitra Budhathoki, Head of Department, Khowpa Polytechnic Institute, Bhaktapur32. Ms. Radha Acharya, Vice Principal, Kantipur College of Medical Science, Sitapaila,
Kathmandu
Occupational TOT Training Beneficiaries
33. Mr. Yagya Rawat, Instructor, Mandali Secondary School34. Ms. Babita KC, Co-ordinator, Technical Training and Research Institute, Kumaripati
35. Mr. Krishna Lamsal, Instructor, Surkhet Technical Institute
36. Ms. Sunita Duwal, Instructor, Banishwori Secondary School
EVENT H Project, Aide Memoire -8- December 4, 2018
Annex 2Updated Results Framework (as on November 15, 2018)
Indicator Baseline DLI Year 1 Year 2 Year 3 Year 4 Year 5 End Target Data Responsibility(Y/N) Source/Me for Data
thodology CollectionPDO Indicators
Percentage of trainees PMIS; tracer PS; JMTemployed/self-employed studieswithin 6 months of 60 65 65 70 70 70completion of short-termtraining
No target for year 1
Achievement Income verification offirst year trainees inunder-way
Number of Y PIC has endorsed the 100 100 100 100 100 PMIS; PS; SupportedTSLC/Diploma Quality Assurance Administrative institutions;program offering (QA) Manual for Data from the CTEVTinstitutions that have TSLC/Diploma Supportedreceived program offering institutionsperformance based institutions preparedquality improvement by PS; PS has signedgrants MOUs with 100
TSLC/Diplomaprogram offeringinstitutions forreceiving performance-based qualityimprovement grants
Achievement Draft QA manualunder review;Applications receivedfrom 152TSLC/Diplomainstitutions. Selectionsexpected to be
EVENT II Project, Aide Memoire -9- December 4, 2018
Indicator Baseline DLI Year 1 Year 2 Year 3 Year 4 Year 5 End Target Data Responsibility
(Y/N) Source/Me for Datathodology Collection
completed by January2019.
Number of TVET PMIS; PS; TITI;
instructors and/ or Adminstrative NSTB; CTEVT
assessors with enhanced 0 100 440 440 340 340 1660 data submitted
professional by TITI and
competencies NSTB
MOU with
Achievement 76 TITI/NSTBsigned
PMIS; PS; Short-termShare of female and Administrative trainingdisadvantaged youth data submitted providerscompleting market 50 50 55 60 65 65 65 by short-termrelevant short-term trainingtraining programs providers
Achievement 87.18
Intermediate Results Indicators
Component I
Number of heads of PMIS; PS; TITI;institutions who have Y Administrative CTEVTcompleted management 0 40 100 100 100 60 400 data sumbittedtraining program by TITI
Achievement 20 Under_____________________ __________progress
Number of curricula PMIS; PS; CTEVT
revised/developed with Administrative
industry participation to 0 10.00 10.00 10.00 10.00 40.00 data submitted
reflect employer by CTEVT
requirements
EVENT II Project, Aide Memoire -10- December 4, 2018
Indicator Baseline DLI Year 1 Year 2 Year 3 Year 4 Year 5 End Target Data Responsibility
(Y/N) Source/Me for Datathodology Collection
Achievement No target for Year I
Baseline PMIS; PS; supported
Pass rates in quality established Administrative institutions
TSLC/Diploma programs -- -- TBD TBD TBD TBD data submittedt' at the end of
in supported institutions Year 1 by supportedinstitutions
Selection of
Achievement institutions isunderprogress.
Number of disadvantaged PMIS PS
students who have been Administrative
supported through 0 500 2000 2000 2000 0.00 6500 data
scholarships to attendTSLC/Diploma programs
465 students haverecevied twoinstallments of Selection ofscholarships. The students is
Achievement remaining 35 students underwill receive 2 1dinstallment of the progress.
scholarship byDecember 31, 2018
Number of youth, PMIS PS; Short-term
including migrants who N training
have enrolled in market 0 16,000 24750 24750 24750 24750 115000 providers
relevant Projectsupported short-termtraining programs
Achievement 16,087Under18 progress
EVENT I Project, Aide Memoire -11- December 4, 2018
Indicator Baseline DLI Year 1 Year 2 Year 3 Year 4 Year 5 End Target Data Responsibility
(Y/N) Source/Me for Datathodology Collection
Number of youth, PMIS; Ps; NSTB;
including migrants who 0 6000 6000 6000 6000 6000 30000 Administrative CTEVT
have completed the data submitted
NSTB skills test by NSTB
Achievement 6,902 MOU withNSTB signed
Number of youth who PMIS, PS; job
have received job Administrative placement
placement assistance 0 500 500 1000 1000 3000 data submitted service
through Human Resource by service providers
(HR) Service Providers providers
UnderAchievement No target for year 1 preparation
Number of trainees who PMIS; PS; Partner
have successfully Administrative Institutions
completed Project 0 0 500 500 500.00 1500 data submitted
supported apprenticeship by partner
programs institutions
UnderAchievement No target for year I prer
preparation
Component 2: Project Management, Monitoring and Evaluation
Functional Project T Established and Functional Functional Functional Functional Functional
Secretariat ] functional
Achievement Functional
Draft Framework Framework Framework PS PS
completed; and plan and and
-- Consultations held implementat shared with implementa implementatiFramework initiated ion plan GON/stakeho tion plan on plan
initiated Iders completed completed
EVENT II Project, Aide Memoire -12- December 4, 2018
Indicator Baseline DLI Year 1 Year 2 Year 3 Year 4 Year 5 End Target Data Responsibility
(Y/N) Source/Me for Datathodology Collection
Achievement Not yet started
Baseline Sruvey PSsurvey forapprenticeship and jobplacement(Year 2);End-linesurvey for job
End-line placementsurvey for (Year 3);
Baseline apprentices Tracer studyurvey for s Eu e for RPL Tracer hips; of NSTB
Studies/Evaluations -- apprenticeshi job study Tracer certified
p andjob job study study of youth for
placement placement TSLC/Dipl prior skillsoma (Year 4);graduates End-line
survey forapprenticeships (Year 5);Tracer studyofTSLC/Diploma graduate(Year 5)
Achievement No target for year I
First round of Second roundStakeholder of First and TBD TBD
Stakeholder Feedback feedback Stakeholder second round
Survey survey carried feedback of stakeholder
out and survey carried feedback
remedial out and survey carried
EVENT II Project, Aide Memoire -13- December 4, 2018
Indicator Baseline DLI Year 1 Year 2 Year 3 Year 4 Year 5 End Target Data Responsibility(Y/N) Source/Me for Data
thodology Collectionmeasures remedial out in Year 2implemented measures and 4
implemented
Achievement No target for year I
EVENT II Project, A ide Memoire -14- December 4, 2018
Annex 3Status Update on Agreed Actions
S.N. Activity Responsibility Agreed timeline Status onAgreedActions
Overall1. Project Implementation (PIM) Manual PS June 15, 2018 Completed
submitted and endorsed by PICProject Activities
2. Complete occupational training for TSLC TITI, PS July 15, 2018and Diploma instructors. 76 instructors
completedtraining
3. Complete the draft of the operations PS September 30, 2018 Draftmanual for the apprenticeship program. operations
manual for theapprenticeshipprogram hasbeen preparedand is underreview
4. Complete verification process for another PS June 15, 2018 Verification106 disadvantaged youths process has been
completed for 77youth. Theverificationprocess forremaining youthis in progress.
5. Complete data analysis from migration WB June 30, 2018 CompletedsurveyEnvironmental and Social Safeguards
6. Executive summary of ESMF translated in PS June 7, 2018 CompletedNepali and uploaded in EVENT website
7. Orientation on WB safeguard requirements PS (with June 15, 2018 Completedto EVENT II PS Staff and ENSSURE ENSSURE'smonitoring team responsible for the joint- monitoringmonitoring of the short-term training team), WBprograms
8. Hire safeguards expert to support the PS PS July 15, 2018 In the process offocal person hiring safeguards
expert.
Financial Manazement and Procurement
9. Submit revised IUFR (including the PS May 25, 2018 Completedfollowing revisions: repost govt staffsalaries and allowances to GON fund;report I should be by categories as per theFA and not by component; revise theretroactive period; revise the forecasttable)
10. Update PP activities in STEP: PS May 31, 2018 Completed* Drop 4 activities* Upload all necessary documents