PPA, 2007 AS A TOOL FOR ENFORCING TRANSPARENCY
AND ACCOUNTABILITY IN THE NIGERIAN BUILDING &
CONSTRUCTION SECTORBY
ENGR. EMEKA M. EZEH, OFR
DIRECTOR-GENERAL
BUREAU OF PUBLIC PROCUREMENT (BPP)
@
QUANTITY SURVEYORS REGISTRATION BOARD OF NIGERIA THIRD
BUILDING & CONSTRUCTION ROUNDTABLE (BCERT 3)
DATE: THURSDAY MAY 24 2013VENUE: SHEHU MUSA YARDUA CENTRE ABUJA
8/12/2019 Public Procurement Law Tranparency and Accountability
2/32
2
HIGHLIGHTS
Why Transparency and Accountability(TA)?
Challenges for Achieving TA
What is Procurement
PPA, 2007 a to to achieve TABCPs
Conclusions
8/12/2019 Public Procurement Law Tranparency and Accountability
3/32
3
Why Transparency and Accountability in
Building and Construction Projects (TABCPs)?
BCPs make a major contribution toeconomic growth and poverty reduction
Mismanagement and corruption during
the planning and implementation of cangreatly undermine the expected social
and economic benefits.
8/12/2019 Public Procurement Law Tranparency and Accountability
4/32
4
Why TABCPs?
Where procurement officers demand bribes, orcontractors offer bribes to win contracts,
prices may be inflated and competition is impaired.
High prices and poor quality, as well as time delays,
can also arise from mismanagement,
from a poorly prepared specification and inadequate
supervision during the implementation of the project.
8/12/2019 Public Procurement Law Tranparency and Accountability
5/32
5
Why TABCPs
Corruption and mismanagement can leadto unsuitable, defective, and dangerousinfrastructurebuildings that collapse
and roads that break upwhich not onlyraises the costs of maintenance, repair,and replacement but can also result incivil and criminal liability for damages
Transparency helps to expose bothcorruption and mismanagement
8/12/2019 Public Procurement Law Tranparency and Accountability
6/32
6
Challenges for achieving TABCPs
A complex and long project cycle causes for concern throughout the project cycle,
including the feasibility, design, tendering, award
and implementation phases A diverse set of actors
Complex information.
8/12/2019 Public Procurement Law Tranparency and Accountability
7/32
7
Challenges for achieving TABCPs
A diverse set of actors Each phase of a construction project generally
involves different management teams, and requiresthose in charge of each completed phase to hand overto the team undertaking the next phase.
The interrelationships between the actors on aconstruction site are based on historically definedroles for the architect, engineer, quantity surveyor andor builder, with separate responsibilities for planningand designing the structure, estimating the price andconstructing the asset
These create an environment with a diverse set ofactors.
8/12/2019 Public Procurement Law Tranparency and Accountability
8/32
8
Challenges for achieving TABCPs
Complex information. such as contract award price, engineers estimate, or the
number of bidderscan be presented clearly and requiresno further interpretation for the public, informationrelating to changes to cost, time, and quality requiresexpert interpretation.
For example, during contract execution, claims may beartificially inflated, and variation orders and extensions oftimes may be unjustified, but detecting whether this is so
is not easy. Client officials may deliberately embezzle project funds
through fraudulent payments in respect of defective work,equipment, or services not actually supplied
8/12/2019 Public Procurement Law Tranparency and Accountability
9/32
9
PUBLIC PROCUREMENT ACT AS A TOOL FOR
TABCPs
The Public Procurement Act 2007 putsNigeria in the league of countries withlegislation on how Public Funds would
be expended. Prior to now, Nigeria wasamong the few African countrieswithout legislation on PublicProcurement.
8/12/2019 Public Procurement Law Tranparency and Accountability
10/32
10
WHAT IS PROCUREMENT?
Procurement is defined as the overallprocess of acquisition of goods, works and
services at the BEST POSSIBLE TOTAL cost of
ownership, in the Right Quantity and
QUALITY at the RIGHT TIME, in the RIGHT
PLACE for the direct BENEFIT or use of
Government, Corporation or individuals,
generally via a contract.
8/12/2019 Public Procurement Law Tranparency and Accountability
11/32
11
BPP has Regulatory functions to achievethe core objectives:
Probity and Accountability
Transparency and Fairness Economy & Efficiency
CompetitionProviding level playing
ground for all strata of bidders Value for Money
CORE OBJECTIVES BPP
PPA, 2007 Section 4
8/12/2019 Public Procurement Law Tranparency and Accountability
12/32
12
Preparing the needs assessment & evaluation Identifying the goods, works or services
required,
Carry out appropriate market and statistical
survey and on that basis prepare costimplications of proposed procurement.
Aggregating its requirement to obtain economy
of scale & reduce procurement cost
PPA, 2007 SECTION 18 : PROCUREMENT
PLANNING
8/12/2019 Public Procurement Law Tranparency and Accountability
13/32
13
Each MDA must have a PPC to do
the afore-mentionedresponsibilities.
PPA, 2007 SECTION 20 : PROCUREMENT
PLANNINGCOMMITTEE (PPC)
8/12/2019 Public Procurement Law Tranparency and Accountability
14/32
14
Membership
Accounting Officer or its representative to chair.
Procurement Unitto serve as Secretary
Unit directly in requirement of procurement
Financial Unit of the MDA
PRS Department of MDA
Technical personnel of MDA with expertise in the
subject matter for each particular procurement.
Legal Unit of the procuring entity
PPA, 2007 SECTION 20 : PROCUREMENT
PLANNINGCOMMITTEE (PPC)
8/12/2019 Public Procurement Law Tranparency and Accountability
15/32
15
Membership
Accounting Officer or its representative to chair.
Procurement Unitto serve as Secretary
Unit directly in requirement of procurement
Financial Unit of the MDA
PRS Department of MDA
Technical personnel of MDA with expertise in the
subject matter for each particular procurement.
Legal Unit of the procuring entity
PPA, 2007 SECTION 20 : PROCUREMENT
PLANNINGCOMMITTEE (PPC)
8/12/2019 Public Procurement Law Tranparency and Accountability
16/32
16
All public procurement shall be conducted: By open competitive bidding
In Transparent, timely, equitable for ensuringaccountability
With all bidders
Possessing legal capacity
Have fulfilled all its obligations to pay taxes, pension andsocial security
Not in receivership, bankrupt
Criteria stipulated solicitation document forevaluation shall not be changed
STRATEGY TO ENFORCE TRANSPARENCY AND
ACCOUNTABILITY section 16
8/12/2019 Public Procurement Law Tranparency and Accountability
17/32
17
Advertisement for solicitation of bids in NationalNewspapers/Federal Tenders Journal
Observation of everyprocurement process byTWO credible personsa relevant private sector
professional such as NIQS, NSE and non-governmental anti-corruption organization.
Transparent Evaluation Process
Approval by the authority before award.
DEBRIEF the bid losers on request!
STRATEGY TO ENFORCE TRANSPARENCY AND
ACCOUNTABILITY
8/12/2019 Public Procurement Law Tranparency and Accountability
18/32
18
STRATEGY : SUBMISSION OF BIDS
section 27
All bids shall be deposited in secured tamper-
proof bid box.
All procuring entities shall issue receipts
showing the date and time the bid was
delivered.
Any bid received after the deadline for the
submission shall not be opened and must be
returned to the supplier or contractor
STRATEGY OPENING OF BIDS
8/12/2019 Public Procurement Law Tranparency and Accountability
19/32
19
STRATEGY: OPENING OF BIDS
section 30
Bids must be opened in public with bidders inattendance and any interested members of
the public.
Bidders must be permitted to examineenvelopes to ensure bids have not been
tampered with.
Bids must be opened immediately followingthe deadline stipulated for submission
8/12/2019 Public Procurement Law Tranparency and Accountability
20/32
20
Register of names & addresses of all thosepresent at the bid opening indicating the
organization they represent
Call to the hearing of all present and addressof each bidder, the total amount of each bid
and bid currency.
STRATEGY: OPENING OF BIDS (Contd)
8/12/2019 Public Procurement Law Tranparency and Accountability
21/32
21
STRATEGY: BID EVALUATION section
31 &32 Bid Evaluation will generally be preceded by
examination of bids to ensure that the
minimum eligibility requirements stipulated in
the bidding documents are met, that the bid isresponsive and dulyendorsed.
8/12/2019 Public Procurement Law Tranparency and Accountability
22/32
22
PURPOSE OF EVALUATION
To determine and select the lowest evaluated
responsive bid.
No other criteria shall be used except as
stipulated in the solicitation documents.
Prompt notice shall be given to the contractor
of any arithmetic errors that are discovered
during the examination of tenders
8/12/2019 Public Procurement Law Tranparency and Accountability
23/32
23
PURPOSE OF EVALUATION
After Opening of Bids, information relating to
examination, clarification and evaluation of
bids and recommendation, concerning award
shall not be disclosed to bidders or personsnot officially concerned with the evaluation
process until the successful bidder is notified
of the award.
8/12/2019 Public Procurement Law Tranparency and Accountability
24/32
24
No funds shall be disbursed from theTreasury or Federation Account or any
bank of any Procuring Entity for any
procurement unless the cheques,payments or other form of request for
payment is accompanied by a
certificate of No Objection to anaward of contract duly issued by the
Bureau.
STRATEGY: PAYMENT TO CONTRACTORS
8/12/2019 Public Procurement Law Tranparency and Accountability
25/32
25
On provision of UNCONDITIONALBank Guarantee or Insurance Bond
10% Performance Bond to be
provided by successful bidders.
STRATEGY: PAYMENT TO CONTRACTORS
Enforcing Strateg
8/12/2019 Public Procurement Law Tranparency and Accountability
26/32
26
The purpose and objectives of the audit are:- Verification of procurement and contracting
processes followed;
Verification of technical and, physicalcompliance and price competitiveness ofcontracts; and
Review of contract administration and
management.
The procurement audit focuses oncontractimplementation
Enforcing Strategy:
PROCUREMENT AUDIT
8/12/2019 Public Procurement Law Tranparency and Accountability
27/32
27
Bid Riggingre-arrangement ofoffers where winners have been
predetermined
Collusion
Altering procurement documents
Splitting of contracts
Using fake documents like TCC, etc.
Some OFFENCES (section 58)
STRATEGY PENALTY FOR VIOLATORS
8/12/2019 Public Procurement Law Tranparency and Accountability
28/32
28
Sanctions
May recommend for: Suspension of officers concerned.
Replacement of Head of Procurement.
Discipline the Accounting Officer
Temporary transfer of procuring function of theentity to a Third Party .
Nullify the whole or any part of the procurementprocess.
STRATEGY: PENALTY FOR VIOLATORS
SECTION 58
STRATEGY PENALTY FOR VIOLATORS
8/12/2019 Public Procurement Law Tranparency and Accountability
29/32
29
Natural Persons
Jail term for directors of 5 Calendar years but
not more than 10 years without option of fine.
For officers of the Bureau, MDAs
Not less than 5 Calendar years.
Summary Dismissal from Government Service,
STRATEGY: PENALTY FOR VIOLATORS
SECTION 58
STRATEGY PENALTY FOR VIOLATORS
8/12/2019 Public Procurement Law Tranparency and Accountability
30/32
30
For Corporate Bodies Debarment from all public procurement for a
period of not less than 5 Calendar years; plus
Fine equivalent to 25% of the value of theprocurement.
Directors of the company as listed in CAC shall
be liable to a jail term of not less than 3
Calendar years but not exceeding 5 yearswithout option of fine.
STRATEGY: PENALTY FOR VIOLATORS
SECTION 58
8/12/2019 Public Procurement Law Tranparency and Accountability
31/32
31
The Public Procurement Act 2007 providesthe legal and institutional framework for the
enthronement of Transparency,
Accountability, Value for Money and
Efficiency in the procurement of building and
construction projects within the Federal
Ministries Departments and Agencies
PPA 2007 is a tool to enforcing Transparency
and Accountability in Building and
Construction Projects.
CONCLUSION
8/12/2019 Public Procurement Law Tranparency and Accountability
32/32
32
Thank You!