    PPA, 2007 AS A TOOL FOR ENFORCING TRANSPARENCY

    AND ACCOUNTABILITY IN THE NIGERIAN BUILDING &

    CONSTRUCTION SECTORBY

    ENGR. EMEKA M. EZEH, OFR

    DIRECTOR-GENERAL

    BUREAU OF PUBLIC PROCUREMENT (BPP)

    @

    QUANTITY SURVEYORS REGISTRATION BOARD OF NIGERIA THIRD

    BUILDING & CONSTRUCTION ROUNDTABLE (BCERT 3)

    DATE: THURSDAY MAY 24 2013VENUE: SHEHU MUSA YARDUA CENTRE ABUJA

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    2/32

    2

    HIGHLIGHTS

    Why Transparency and Accountability(TA)?

    Challenges for Achieving TA

    What is Procurement

    PPA, 2007 a to to achieve TABCPs

    Conclusions

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    3/32

    3

    Why Transparency and Accountability in

    Building and Construction Projects (TABCPs)?

    BCPs make a major contribution toeconomic growth and poverty reduction

    Mismanagement and corruption during

    the planning and implementation of cangreatly undermine the expected social

    and economic benefits.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    4/32

    4

    Why TABCPs?

    Where procurement officers demand bribes, orcontractors offer bribes to win contracts,

    prices may be inflated and competition is impaired.

    High prices and poor quality, as well as time delays,

    can also arise from mismanagement,

    from a poorly prepared specification and inadequate

    supervision during the implementation of the project.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    5/32

    5

    Why TABCPs

    Corruption and mismanagement can leadto unsuitable, defective, and dangerousinfrastructurebuildings that collapse

    and roads that break upwhich not onlyraises the costs of maintenance, repair,and replacement but can also result incivil and criminal liability for damages

    Transparency helps to expose bothcorruption and mismanagement

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    6/32

    6

    Challenges for achieving TABCPs

    A complex and long project cycle causes for concern throughout the project cycle,

    including the feasibility, design, tendering, award

    and implementation phases A diverse set of actors

    Complex information.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    7/32

    7

    Challenges for achieving TABCPs

    A diverse set of actors Each phase of a construction project generally

    involves different management teams, and requiresthose in charge of each completed phase to hand overto the team undertaking the next phase.

    The interrelationships between the actors on aconstruction site are based on historically definedroles for the architect, engineer, quantity surveyor andor builder, with separate responsibilities for planningand designing the structure, estimating the price andconstructing the asset

    These create an environment with a diverse set ofactors.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    8/32

    8

    Challenges for achieving TABCPs

    Complex information. such as contract award price, engineers estimate, or the

    number of bidderscan be presented clearly and requiresno further interpretation for the public, informationrelating to changes to cost, time, and quality requiresexpert interpretation.

    For example, during contract execution, claims may beartificially inflated, and variation orders and extensions oftimes may be unjustified, but detecting whether this is so

    is not easy. Client officials may deliberately embezzle project funds

    through fraudulent payments in respect of defective work,equipment, or services not actually supplied

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    9/32

    9

    PUBLIC PROCUREMENT ACT AS A TOOL FOR

    TABCPs

    The Public Procurement Act 2007 putsNigeria in the league of countries withlegislation on how Public Funds would

    be expended. Prior to now, Nigeria wasamong the few African countrieswithout legislation on PublicProcurement.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    10/32

    10

    WHAT IS PROCUREMENT?

    Procurement is defined as the overallprocess of acquisition of goods, works and

    services at the BEST POSSIBLE TOTAL cost of

    ownership, in the Right Quantity and

    QUALITY at the RIGHT TIME, in the RIGHT

    PLACE for the direct BENEFIT or use of

    Government, Corporation or individuals,

    generally via a contract.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    11/32

    11

    BPP has Regulatory functions to achievethe core objectives:

    Probity and Accountability

    Transparency and Fairness Economy & Efficiency

    CompetitionProviding level playing

    ground for all strata of bidders Value for Money

    CORE OBJECTIVES BPP

    PPA, 2007 Section 4

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    12/32

    12

    Preparing the needs assessment & evaluation Identifying the goods, works or services

    required,

    Carry out appropriate market and statistical

    survey and on that basis prepare costimplications of proposed procurement.

    Aggregating its requirement to obtain economy

    of scale & reduce procurement cost

    PPA, 2007 SECTION 18 : PROCUREMENT

    PLANNING

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    13/32

    13

    Each MDA must have a PPC to do

    the afore-mentionedresponsibilities.

    PPA, 2007 SECTION 20 : PROCUREMENT

    PLANNINGCOMMITTEE (PPC)

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    14/32

    14

    Membership

    Accounting Officer or its representative to chair.

    Procurement Unitto serve as Secretary

    Unit directly in requirement of procurement

    Financial Unit of the MDA

    PRS Department of MDA

    Technical personnel of MDA with expertise in the

    subject matter for each particular procurement.

    Legal Unit of the procuring entity

    PPA, 2007 SECTION 20 : PROCUREMENT

    PLANNINGCOMMITTEE (PPC)

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    15/32

    15

    Membership

    Accounting Officer or its representative to chair.

    Procurement Unitto serve as Secretary

    Unit directly in requirement of procurement

    Financial Unit of the MDA

    PRS Department of MDA

    Technical personnel of MDA with expertise in the

    subject matter for each particular procurement.

    Legal Unit of the procuring entity

    PPA, 2007 SECTION 20 : PROCUREMENT

    PLANNINGCOMMITTEE (PPC)

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    16/32

    16

    All public procurement shall be conducted: By open competitive bidding

    In Transparent, timely, equitable for ensuringaccountability

    With all bidders

    Possessing legal capacity

    Have fulfilled all its obligations to pay taxes, pension andsocial security

    Not in receivership, bankrupt

    Criteria stipulated solicitation document forevaluation shall not be changed

    STRATEGY TO ENFORCE TRANSPARENCY AND

    ACCOUNTABILITY section 16

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    17/32

    17

    Advertisement for solicitation of bids in NationalNewspapers/Federal Tenders Journal

    Observation of everyprocurement process byTWO credible personsa relevant private sector

    professional such as NIQS, NSE and non-governmental anti-corruption organization.

    Transparent Evaluation Process

    Approval by the authority before award.

    DEBRIEF the bid losers on request!

    STRATEGY TO ENFORCE TRANSPARENCY AND

    ACCOUNTABILITY

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    18/32

    18

    STRATEGY : SUBMISSION OF BIDS

    section 27

    All bids shall be deposited in secured tamper-

    proof bid box.

    All procuring entities shall issue receipts

    showing the date and time the bid was

    delivered.

    Any bid received after the deadline for the

    submission shall not be opened and must be

    returned to the supplier or contractor

    STRATEGY OPENING OF BIDS

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    19/32

    19

    STRATEGY: OPENING OF BIDS

    section 30

    Bids must be opened in public with bidders inattendance and any interested members of

    the public.

    Bidders must be permitted to examineenvelopes to ensure bids have not been

    tampered with.

    Bids must be opened immediately followingthe deadline stipulated for submission

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    20/32

    20

    Register of names & addresses of all thosepresent at the bid opening indicating the

    organization they represent

    Call to the hearing of all present and addressof each bidder, the total amount of each bid

    and bid currency.

    STRATEGY: OPENING OF BIDS (Contd)

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    21/32

    21

    STRATEGY: BID EVALUATION section

    31 &32 Bid Evaluation will generally be preceded by

    examination of bids to ensure that the

    minimum eligibility requirements stipulated in

    the bidding documents are met, that the bid isresponsive and dulyendorsed.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    22/32

    22

    PURPOSE OF EVALUATION

    To determine and select the lowest evaluated

    responsive bid.

    No other criteria shall be used except as

    stipulated in the solicitation documents.

    Prompt notice shall be given to the contractor

    of any arithmetic errors that are discovered

    during the examination of tenders

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    23/32

    23

    PURPOSE OF EVALUATION

    After Opening of Bids, information relating to

    examination, clarification and evaluation of

    bids and recommendation, concerning award

    shall not be disclosed to bidders or personsnot officially concerned with the evaluation

    process until the successful bidder is notified

    of the award.

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    24/32

    24

    No funds shall be disbursed from theTreasury or Federation Account or any

    bank of any Procuring Entity for any

    procurement unless the cheques,payments or other form of request for

    payment is accompanied by a

    certificate of No Objection to anaward of contract duly issued by the

    Bureau.

    STRATEGY: PAYMENT TO CONTRACTORS

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    25/32

    25

    On provision of UNCONDITIONALBank Guarantee or Insurance Bond

    10% Performance Bond to be

    provided by successful bidders.

    STRATEGY: PAYMENT TO CONTRACTORS

    Enforcing Strateg

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    26/32

    26

    The purpose and objectives of the audit are:- Verification of procurement and contracting

    processes followed;

    Verification of technical and, physicalcompliance and price competitiveness ofcontracts; and

    Review of contract administration and

    management.

    The procurement audit focuses oncontractimplementation

    Enforcing Strategy:

    PROCUREMENT AUDIT

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    27/32

    27

    Bid Riggingre-arrangement ofoffers where winners have been

    predetermined

    Collusion

    Altering procurement documents

    Splitting of contracts

    Using fake documents like TCC, etc.

    Some OFFENCES (section 58)

    STRATEGY PENALTY FOR VIOLATORS

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    28/32

    28

    Sanctions

    May recommend for: Suspension of officers concerned.

    Replacement of Head of Procurement.

    Discipline the Accounting Officer

    Temporary transfer of procuring function of theentity to a Third Party .

    Nullify the whole or any part of the procurementprocess.

    STRATEGY: PENALTY FOR VIOLATORS

    SECTION 58

    STRATEGY PENALTY FOR VIOLATORS

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    29/32

    29

    Natural Persons

    Jail term for directors of 5 Calendar years but

    not more than 10 years without option of fine.

    For officers of the Bureau, MDAs

    Not less than 5 Calendar years.

    Summary Dismissal from Government Service,

    STRATEGY: PENALTY FOR VIOLATORS

    SECTION 58

    STRATEGY PENALTY FOR VIOLATORS

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    30/32

    30

    For Corporate Bodies Debarment from all public procurement for a

    period of not less than 5 Calendar years; plus

    Fine equivalent to 25% of the value of theprocurement.

    Directors of the company as listed in CAC shall

    be liable to a jail term of not less than 3

    Calendar years but not exceeding 5 yearswithout option of fine.

    STRATEGY: PENALTY FOR VIOLATORS

    SECTION 58

  • 8/12/2019 Public Procurement Law Tranparency and Accountability

    31/32

    31

    The Public Procurement Act 2007 providesthe legal and institutional framework for the

    enthronement of Transparency,

    Accountability, Value for Money and

    Efficiency in the procurement of building and

    construction projects within the Federal

    Ministries Departments and Agencies

    PPA 2007 is a tool to enforcing Transparency

    and Accountability in Building and

    Construction Projects.

    CONCLUSION